NJC Hydropower Limited

EIA study for Nyamjangchhu


Hydroelectric Project

CHAPTER - 9
CONSTRUCTION METHODOLOGY
9.1

GENERAL

The project envisages construction of barrage, a head regulator, Feeder


Channel, desilting chamber, collection pool & intake, Head race tunnel, surge
shaft, pressure shaft, underground power house, tail race tunnel and all
infrastructure works. The construction methodology and equipment planning
for various works is based on the site conditions prevailing in the project area.
Construction activities are planned in such a way that the project will be
completed in the shortest possible time period. The following assumptions
have been made for construction methodology and equipment planning of the
project.
All the pre-construction activities like land acquisition, infrastructure works
and government approvals are completed before the start of construction
works on main components of the project. All civil, hydro-mechanical and
electro-mechanical works are executed in following main packages :

WAPCOS Limited

CIVIL WORKS
Package I
Package II

:
:

Barrage and Desilting works


Head Race Tunnel from RD-0.00m to
RD-8,400.00m
Package III
:
Head Race Tunnel from RD-8,400.00m
to RD-16,875.00m
Package IV
:
Head Race Tunnel from RD16,875.00m to RD-23,450.00 m
Package V
:
Civil works for Surge Shaft and
Pressure Shaft
Package VI
:
Civil works for Power House,
Transformer Cavern, Tail Race Tunnel
and Switch Yard.
HYDRO-MECHANICAL WORKS
Package VII
:
Hydro Mechanical works comprising of
gates, hoists and Pressure Shafts steel
liner
Electro-Mechanical Works
Package VIII
:
Generating Units (Turbine &
Generator), Cooling Water System,
Drainage/ Dewatering System, Unit
Control & Automation, Bus duct.
Package IX
:
Valves-MIV& BFV
Package X
:
EOT Crane,
Package XI
:
Air Conditioning, Ventilation etc.
Package XII
:
Fire Fighting,
Package XIII
:
Transformers(Generator Transformer),

9-1

NJC Hydropower Limited

9.2

EIA study for Nyamjangchhu


Hydroelectric Project

Package
Package
Package
Package
Package
Package
Package

XIV
XV
XVI
XVII
XVIII
XIX
XX

Package XXI

:
:
:
:
:
:
:
:

415 V Switchgear & 11 kV Switchgear


Illumination
DG sets (construction power)
Cable &Cable Trays
Switchyard & Protection metering
Transformer (Dry Type UAT SST),
DC System (Battery & Battery
Charger), UPS
Miscellaneous and finishing works

BASIC ASESSMENT OF CONSTRUCTION METHODOLGY

The project involves execution of large quantities of excavation and concreting


for surface and underground structures. Considering the magnitude and nature
of construction activity, mechanized construction has been considered for all
type of construction job so as to achieve consistent quality at a faster rate for
timely completion of the project. Special attention has been paid to the
equipment planning for underground works as the restricted work space and
constraints of geology make this exercise very critical.
The construction of the project will involve simultaneous works on all the
packages for civil, hydro-mechanical and electro-mechanical works for various
project components. Tunneling in Head race Tunnel & underground excavation
for power house and transformer cum GIS-Cavern is one of the most critical
activities for the project and accordingly, the work is assumed to continue
uninterrupted till its completion.
9.3

PRE CONSTRUCTION ACTIVITIES

The activities proposed to be undertaken during Pre-construction work include


the following:

WAPCOS Limited

Detailed Topographical Survey and marking the Layout at site,


Pre- construction geotechnical investigation
Clearance from Government agencies like Pollution control
board, Public health, Irrigation and Forest Clearance
Acquisition of Land
Financial closure
Detailed design and preparation of tender documents for Civil,
Electro-mechanical, Hydro mechanical works
Award of Contracts
Setting up of Site office
Arranging of construction power
Construction of approach roads/ paths
Route survey of Transmission line
Mining Licence for construction materials
Formation of project team

9-2

NJC Hydropower Limited

9.4

EIA study for Nyamjangchhu


Hydroelectric Project

APPROACH ROADS AND BRIDGE

Transportation of heavy machines and equipments will be required for


construction purpose. Construction of new access roads and bridges, widening
of existing roads and improvement in grade of existing roads shall be
undertaken before starting construction of main project components. These
roads would be connected through an extensive network of project roads to
various colonies, workshop, quarries etc.
9.5

BASIC CONSIDERATIONS

Construction methodology and equipment planning has been carried out


separately

for execution of all project components. The types and sizes of

equipment to be used have also been indicated while describing the


construction methodology for each of the components under relevant subhead.
The number of Machines/Equipment required for construction of each
component has been worked out and their size and capacity has been arrived
at after drawing the deployment schedule matching with the construction
schedule.
Most of the construction work shall be executed through contractors. The
requirement of equipment as marked out herein has been utilized for analysis
of rates and Cost Estimates. The prices of construction equipment are based
on the prevalent market prices in India as on May, 2010.
The project area is situated in a region where extensive rainfall occurs during
monsoon. The working season is, therefore, limited to 9 months, beginning
from October to June for open works. The underground works being critical are
proposed to be carried out in two shifts of 20 hours/day.
9.6

DETAILED DESIGN AND CONSTRUCTION DRAWINGS

The detailed design will be done in parallel with the Pre-construction works. It
is envisaged that the design will be started soon after the preliminary works
are completed.

During Tender engineering, detailed design work will be

started and construction drawings will be available by the time contracts are
awarded.
9.7

BASIC ASSUMPTIONS FOR EQUIPMENT PLANNING

Guidelines for preparation of Detailed Project Reports of Irrigation and


multipurpose Projects issued by Central water Commission have been used

WAPCOS Limited

9-3

NJC Hydropower Limited

EIA study for Nyamjangchhu


Hydroelectric Project

for the planning of equipments. Basic assumptions made for the planning of
equipment for various construction activities are enumerated below:
9.7.1

Working hours of equipment

All works are proposed to be done in two shifts and the scheduled working
hours have been taken as 20 hours per day. 26 days/month have been
considered on an average in a month.
9.7.2

Densities of Materials

The calculations have been based on capacity of hauling units without


considering the densities of different types of materials for excavation and the
fill material.
9.7.3

Earth Volume conversion factor

Suitable standard norms have been adopted for conversion of volumes in


natural, loose and compacted state.
9.7.4

Operating Efficiency

The operating efficiency of different types of equipment has been taken as 50


min per hour.
9.7.5

Muck Dumping Lead

A lead of 15 km has been considered for dumping of muck that would be


generated from Head Race Tunnel and a lead of 5 km is assumed for the
dumping of muck that would be generated from Power House, TRT,
Transformer Cavern, Barrage, Feeder Channel, Desilting Chamber and
Collection Pool works. A lead of 10 km is assumed for the muck dumping of the
material generated from Surge Shaft and Pressure Shaft works.
9.7.6

Concreting Lead

A lead of 10 km is considered for the concrete works in Head Race Tunnel and
5 km is assumed for the concrete works in Power House, TRT, Transformer
Cavern, Barrage, Feeder Channel, Desilting Chamber, Collection Pool, Surge
Shaft and Pressure Shaft works.

WAPCOS Limited

9-4

NJC Hydropower Limited

9.8

EIA study for Nyamjangchhu


Hydroelectric Project

METHODOLOGY OF CONSTRUCTION FOR VARIOUS ACTIVITIES

9.8.1

River diversion during construction

River diversion works has been planned for construction of Barrage and Head
Regulator. The construction of Barrage has to be taken up during non monsoon
months of relatively low flow. The river will be diverted along one side of the
river by construction of temporary cofferdams for the construction of the
upstream works. The cofferdam will be made of river bed material properly
compacted to the required level to prevent overtopping. An impervious layer
of geo-membrane will be provided to prevent seepage through the body of the
dam.

To avoid puncturing, fine materials are placed below and over the

impermeable layer. Rip rap protections will be provided on the river side to
prevent scouring of the dam. It is expected that the cofferdam will be
damaged during the monsoon season which will be repaired for the dry
season.
The construction of Barrage structures will be done in two stages and
cofferdam will be provided accordingly.

In the first stage, the river will be

diverted towards the right bank. During the period, construction work on the
left bank will be done. The work includes construction of Spillway (5 bays),
Undersluice, Head Regulator, Feeder Channel, Desilting Chamber, Reservoir,
intake structures and flood walls, upstream and downstream aprons and
stilling basins. Likewise, the remaining bays of spillway and Earthen Dam that
are on the right bank will be constructed during the second phase. During the
period, the river will be diverted through the Undersluice and gated Spillway.
The cofferdam will create the dry space in the right bank during this period.
9.8.2

Civil works

Upstream works
The deposits on the river bank shall be removed to have enough space for
construction activities. The deposit will be used for the river diversion work
and for rip rap protection works. The construction of cofferdam will be taken
up parallel with the removal of deposits. The construction of Coffer dam would
be taken up with 2 Nos of Dozers (200 HP), 2 Nos of Hydraulic Excavators of
1.5 cum bucket capacity, 2 Nos of Vibratory Rollers and sufficient number of
20/25 T Dumpers. The Coffer Dam is planned to be completed in three
months.

WAPCOS Limited

9-5

NJC Hydropower Limited

EIA study for Nyamjangchhu


Hydroelectric Project

Phase-I
Construction of 5 bays of Spillway, Undersluice and Head Regulator will be
taken up in the first phase of Barrage works. Total of 3.0 lacs cum of
earthwork is involved in these structures and by providing 3 Nos of Hydraulic
Excavators of 1.5 m3 capacity working round the clock (with stand bye
equipment) and fleet of dumpers, daily progress of 3,000 m3 is expected.
Therefore, the excavation gets completed in 4 months. Adequate dewatering
arrangements would be made during the excavation in foundation at Barrage
complex. Dynamic compaction will commence immediately after the necessary
excavation at Barrage site. The excavation for cut-off wall will commence
immediately after dynamic compaction/compacted backfill at Barrage site. The
deep excavation for cut-off wall will be done with Hydraulic Excavator

BC-

30. Bentonite solution will be used during excavation of cut-off wall so as to


avoid the side wall collapses. The excavation of cut-off wall up to the required
level will be done and plastic concrete will be poured in the excavated trench
by using a tremmie. The concrete work for Barrage base slab and other
superstructure works will commence immediately after the completion of
plastic concrete in cut-off walls. Concreting in the river bed, pertaining to
under sluice, 5 bays of spillway and head regulator and adjacent structures will
be taken up on priority in full swing by 2 nos. 30 m3 Batching plant and 2
Stationery 1 m3 Capacity Mixers, placement of concrete is planned by Transit
mixers and Cranes with suitable Concrete Buckets. The concreting of under
sluice, 5 bays of spillway and head regulator up to sill level will be completed
in 2 months before onset of monsoon. The superstructure works of these
structures will commence immediately after the concreting of the base slab.
The Hydro-Mechanical works for these structures will be executed in parallel to
the civil works of these components. All civil and hydro mechanical works for
these components will get completed in 27 months after the start of work at
Barrage site.

WAPCOS Limited

9-6

NJC Hydropower Limited

EIA study for Nyamjangchhu


Hydroelectric Project

During planning it is assumed that all the structures on the left bank that will
be affected by the river flow will be completed in two seasons. Structures like
floodwalls and the intake will be completed within the first eight months. The
upstream and downstream apron, stilling basin and the rip rap protections will
be completed within 27 months. After completing the First Phase works on the
left bank, the river will be diverted through under sluice and the construction
for Phase-II Barrage works will be taken up.
Phase-II
Construction of Earthen Dam and 6 bays Spillway will be taken up in this phase
of Barrage works. 1.2 lacs cum of earthwork is involved in these structures and
by providing 2 Nos. of Hydraulic Excavators of 1.5 cum capacity working round
the clock (with stand bye equipment) and fleet of dumpers, daily progress of
2,000 m3 is expected. Therefore, the excavation gets completed in 3 months.
Adequate dewatering arrangements would be made during the excavation in
foundation

at

Barrage

complex.

Dynamic

compaction

will

commence

immediately after the necessary excavation at this phase of Barrage


construction. The excavation for cut-off wall will commence immediately after
dynamic compaction/compacted backfilling at this front. The deep excavation
for cut-off wall will be done with a Hydraulic Excavator BC-30 and Bentonite
solution will be used during excavation of cut-off wall so as to avoid the side
wall collapses. The excavation of cut-off wall up to the required level will be
done and plastic concrete will be poured in the excavated trench by using a
tremmie. The concrete / earth filling work for this phase will commence
immediately after the completion of plastic concrete in cut-off walls. Concreting
in the river bed, pertaining to remaining bays of spillway will be taken up after
necessary excavation / dynamic compaction. The concreting of remaining bays
of spillway up to sill level will be completed in 2 months. The superstructure
work of this structure will commence immediately after the concreting of the
base slab. All civil works for these components will get completed in 18
months.

WAPCOS Limited

9-7

NJC Hydropower Limited

EIA study for Nyamjangchhu


Hydroelectric Project

The structures like Desilting Basin and Feeder channel can be constructed
throughout the year.

The excavation of the Desilting Basin will commence

after the completion of flood wall beside the Desilting Basin. Work at Reservoir
just downstream of Desilting Basin would be taken up simultaneously with the
Desilting Basin.

Excavation and backfilling at Desilting Basin, Reservoir and

Feeder Channel would be taken up with 4 Nos. of Hydraulic excavators of 5.0


lacs cum bucket capacity and sufficient nos of 20/25 T Dumpers. Therefore,
total earthwork of 5 lacs cum involved in these structures is planned to be
completed in 6 months. Adequate dewatering arrangements would be made
during the excavation at these fronts. The concrete work will commence
immediately after the completion of excavation/backfilling work at these
fronts. Concreting of the structures will be taken up on priority in full swing by
2 nos. 30 m3 Batching plant and 2 Stationery 1 m3 Capacity Mixers,
placement of concrete is planned by Transit mixers and Cranes with suitable
Concrete Buckets. The superstructure civil works for these structures will be
carried in parallel to hydro mechanical works. All civil and hydro mechanical
works for these components will get completed in 30 months after the start of
work at these fronts.
Equipments required for the construction of Coffer Dam, Earthen Dam,
Spillway, Under Sluice, Head Regulator, Feeder Channel, Desilting Chambers
and Collection Pool are shown in Annexure-14.1.
Headrace tunnel
6.2 m dia. Circular shaped, 23.450 km long Head Race Tunnel has been
proposed at the end of Collection pool for carrying water to the pressure
shafts. 300 mm thick concrete lining has been proposed all along the length of
the tunnel.
The headrace tunnel will be started from the thirteen faces as shown in Fig9.1. All the adits shall be completed before the start of excavation of headrace
tunnel. Construction of HRT Face-1 and Face-2 will be taken up from Adit-1 to
HRT. Similarly Face-3/Face-4, Face-5/Face-6, Face-7/Face-8, Face-9/Face-10,
Face-11/Face-12, and Face-13 will be taken up from Adit-2, Adit-3, Adit-4,
Adit-5, Adit-6, and Adit-7 respectively. The critical reach of HRT is about
5000m between Face-8 and Face-9, so special attention in terms of resources
is required at this front for completion of work in time schedule.

WAPCOS Limited

9-8

NJC Hydropower Limited

EIA study for Nyamjangchhu


Hydroelectric Project

Figure-9.1
The tunnel will be excavated by conventional drill and blast method using
mechanised equipment.

At each Adit, 3-Boom Drill Jumbo will be used for

drilling holes and robotic shotcrete machine will be used for temporary rock
support. After blasting, fresh air will be supplied at excavated face to remove
gas and dust produced during blasting by a duct. The excavated muck will be
loaded through one 1.5 cum bucket capacity hydraulic excavator and
transported by dump trucks of 20/25 T capacity to muck dumping area. After
excavation scaling will be done followed by the rock bolting and shotcreting.
Pre-splitting or smooth blasting technique shall also be adopted to avoid over
break. The proposed cycle time for the excavation and rock support of HRT
along with equipment planning is enclosed as Annexure-14.2.
Overt Lining
For overt lining it is proposed to take up more than half of upper portion of the
tunnel. The concrete will be placed in the overt by using 6m long shutter form.
Transit mixer of 6 cum capacity will be used for transportation of concrete from
batching plant to concreting site. Pouring of concrete in the overt will be done
through with 38 cum capacity truck mounted concrete pumps fitted with
hydraulically operated placing boom. With this arrangement and suitable
manipulation of boom, the concrete will be delivered from the pump.
Invert Lining
Invert lining will be taken up after the completion of overt lining of HRT in
various reaches. A progress of 300 m/month on average is assumed for this
activity.

WAPCOS Limited

9-9

NJC Hydropower Limited

EIA study for Nyamjangchhu


Hydroelectric Project

Surge shaft
Construction of approach road to Adit to Surge Shaft bottom is planned to be
completed during pre-construction works. The construction of Adit to Surge Shaft
bottom would be taken up immediately after the start of Civil works. This Adit is
planned to be completed in 4 months. Thereafter, a pilot shaft (235m deep & 4m
dia.) would be constructed from bottom of Surge Shaft using Alimack Raise
Climber with sufficient nos. of jack hammers, one Dozer of 200 HP, one Hydraulic
Excavator of 1.5 cum capacity and sufficient nos. of 20/25 T Dumpers. This
activity is planned to be completed in 5 months time while excavation of horizontal
Pressure Shaft at EL-1940m would be in progress simultaneously. Once pilot shaft
is made through, slashing of Surge Shaft can be done from the top to bottom.

Pressure Shaft
Two number 3.3 m dia circular steel lined pressure shafts each bifurcating into
unit penstock of 2.0 m dia circular steel lined pressure shaft have been
provided for taking the water to six pelton machines in underground power
house. Each pressure shaft consists of horizontal and inclined portions. Adits to
Horizontal Pressure Shafts at EL-1571.4m, EL-1271.4m and EL-1051.4m would
be completed before the start of excavation work in Pressure Shafts. The
construction of horizontal pressure shafts at elevation of 1900.0 m shall be
taken up by full face drilling and blasting method. The adit used for reaching
the bottom of Surge Shaft will be used for construction of this portion of
pressure shaft. The excavation shall be taken up with one 3Boom Drill Jumbo,
one hydraulic excavator, one dozer (200HP) and sufficient nos of 10T/20T
dumpers.
Similarly the horizontal pressure shafts at El-1571.4m and EL-1271.4m shall
be taken up individually with separate set of equipments as deployed at upper
horizontal pressure shafts. Construction of horizontal pressure shaft at
elevation of El 1051.4 m

will be undertaken from branch tunnel from Main

Access Tunnel to Power House.

WAPCOS Limited

9-10

NJC Hydropower Limited

EIA study for Nyamjangchhu


Hydroelectric Project

After the excavation in these horizontal Pressure Shafts, the excavation of


inclined portion for a length of about 450 m will be taken up bottom upward by
2 Nos. of double motor diesel Raise climber. The excavation of inclined
Pressure Shafts to required excavated diameter will be excavated in single
phase. Firstly the 2 Nos of Raise Climbers will be mobilized at inclined Pressure
Shafts between EL-1891.4m to EL-1571.4m. The excavation of these shafts
will be completed in 9 months. Similarly the excavation of inclined Pressure
Shafts at EL-1051.4m to EL-1271.4m (6 Nos) and at EL-1271.4m to EL1571.4m (2 Nos) will be taken after the completion of inclined Pressure Shafts
between EL-1891.4m to EL-1571.4m. The time taken to complete the
excavation of the inclined Pressure Shaft at EL-1051.4m to EL-1271.4m (6
Nos) and at EL-1271.4m to EL-1571.4m (2 Nos) will be 12 months and 8
months respectively. The excavation and mucking will be taken by sufficient
nos of Jack hammers, one Dozer (200 HP), one hydraulic excavator of 1.5 cum
capacity and sufficient no of 10T/20T dumpers.
Steel lining of pressure shafts will be undertaken after excavation is complete.
Ferrules of 2.5m length shall be fabricated in the workshop outside and shall
be transported on trailers to the pressure shafts for lowering. Inside the
tunnels, ferrules shall be transported on trolleys travelling on rails and pulled
by winch. For upper horizontal and inclined portion, steel lining shall proceed
from bottom to top first and there after horizontal portion shall be taken. The
concrete backfilling of these ferrules will immediately follow after the erection
and welding of ferrules inside the shaft. The concrete shall be poured after
welding 5 pieces of 2.5m ferrules. A progress of 40m/month (erection and
backfilling) per shaft is planned for these inclined Pressure Shafts. The time
taken to complete the ferrule erection/backfilling of the inclined Pressure Shaft
at EL-1051.4m to EL-1271.4m (6 Nos), EL-1271.4m to EL-1571.4m (2 Nos)
and at EL-1571.4m to EL-1891.4m (2 Nos) will be 15 months, 11 months and
12 months respectively. The ferrule erection/backfilling in horizontal pressure
shafts

at

various

benches

will

be

followed

only

after

the

ferrule

erection/backfilling in respective inclined pressure shafts. Equipment required


for the construction of Pressure Shaft is shown in Annexure-14.1.

WAPCOS Limited

9-11

NJC Hydropower Limited

EIA study for Nyamjangchhu


Hydroelectric Project

Powerhouse
An underground Power House has been proposed on the left bank of Nyamjang
Chhu River with the installed capacity of 780 MW comprising 6 units of 130
MW each. An underground excavation of 1.2 lacs cum is assessed in Power
House and is expected to be completed in 25 months with two shifts operating.
The construction of powerhouse involves co-ordination of civil works and
electromechanical works. The main civil works in the powerhouse consists of
excavation, rock support and concreting works.
The excavation of Power House would be taken up after the excavation of the
Adit to Power House Crown branching off from Main Access Tunnel to Service
Bay in the Power House. This Adit would be extended through the length of the
Power House and expanded sideways to the size of 20m x 7m. Power House
excavation would be carried out by constructing suitable ramps for benching
down. Movement of equipment would be carried through ramps. For
excavation from EL-1084.202m to EL-1077.20m mucking would be done
through adit to the crown of Power House including ramp removal. For
excavation from EL-1077.20m to EL-1070.20m mucking would be carried out
through Main Access Tunnel to Power House including Bus Duct Tunnels.
Mucking of Power House below Service Bay level would be carried out through
Main Access Tunnel as well as construction adit to Pressure Shaft and Tail Race
Tunnel. Benching down of Power House from EL-1070.20m to EL-1059.40m
would be carried out in two stages by making suitable ramps in each stage. For
excavation from EL-1059.40m to EL-1054.50 m mucking would be carried out
through pressure shaft Tunnels. The bottom of the Power House will be
excavated through Tail Race Tunnels.
The equipment required for underground excavation of power house are 3
boom drill jumbo, 1.5 cum hydraulic excavator, 20/25T dumpers, wagon
drills/crawler drills, jack hammers, shotcrete machine, grout pump, concrete
pump, vibrator, transit mixers etc. Batching and mixing plant (90 cum/hr), 180
TPH aggregate processing plant would meet the concreting requirement of
Power House. The installation of electromechanical equipment will be done in
close coordination with the civil contractor. Almost all of the civil structures
including the installation of overhead crane will be completed before the
installation of electromechanical equipment.

WAPCOS Limited

9-12

NJC Hydropower Limited

EIA study for Nyamjangchhu


Hydroelectric Project

Transformer Cavern
The excavation Work for Transformer Cavern of size 173mx16.3mx23m
located on downstream of Power House Cavern will generate about 70,000
cum of excavated muck. The crown of this cavern would be accessed through
100 m long Adit branching off from adit to crown of Power House cavern. The
construction adit to Transformer Cavern crown would be extended to full
length of the Transformer Cavern. Thereafter, it would be enlarged sideways to
the full width of the Transformer Cavern. Transformer Cavern excavation
would be carried out by constructing suitable ramps for benching down.
Movement of equipment would be carried through ramps. For excavation from
EL-1085.675m to EL-1076.80m mucking would be carried out through adit to
crown of Transformer Cavern including ramp removal. Mucking of Transformer
Cavern at EL-1076.80m to EL-1070.20m

would be carried out through the

access tunnel branching off from Main Access Tunnel.


The equipment required for this purpose are 3 boom drill jumbo.1.5 cum
hydraulic excavator, 20/25T multi axle rear dumpers, wagon drills/crawler
drills, jack hammers, shotcrete machine, grout pump, concrete pump, vibrator,
transit mixers etc. Batching and mixing plant (90 cum/hr), 180 TPH aggregate
processing plant would meet the concreting requirement of Transformer
Cavern.
Tailrace
7m dia. Circular shape, 1.965 km long Tail Race Tunnel has been proposed
from power house to discharge the water back to river. TRT will be concrete
lined. The construction of Tail Race tunnel will be done from outlet face of TRT
and from junction of the Main Access Tunnel with TRT. The tunnel will be
excavated by drill and blast method using mechanised equipment.

3-Boom

Drill Jumbo will be used for drill holes and robotic shotcrete machine will be
used for temporary lining.

An advance of 95 m/month from each face is

proposed for the excavation of TRT.


Concrete Lining of TRT will commence immediately after the completion of
excavation work at respective faces. The lining of the tunnel is proposed to be
done in two stages i.e. overt concrete will be done firstly followed by invert
concrete lining. Two gantry shutters of 6m length are proposed to be used in
TRT so as to achieve a progress of 6m/day and 150m/month in this reach.

WAPCOS Limited

9-13

NJC Hydropower Limited

EIA study for Nyamjangchhu


Hydroelectric Project

Bus Duct Tunnel and Switchyard


The XLPE cables from Transformer cavern to surface Switch Yard will be taken
through a 7m dia and 23m deep shaft and then through a Bus Bar Tunnel of
7.6m (H), 5.1m (W) and 769m length. The Bus Bar tunnel will be excavated
from the Portal side @ 100m/month. Work at Switch Yard will be taken up
after completing Power House excavation and filling the muck at Switch Yard
area. Concrete/Building works will immediately commence after the completion
of necessary excavation/muck filling and foundation treatment works. The
completion however, should be finished before the completion of installation of
electromechanical equipment in the powerhouse. Equipment required for the
construction of GIB Tunnel and Switch Yard is shown in Annexure-14.1.
Hydro Mechanical Equipment
The fabrication of Barrage gates shall be done partly in manufacturers
workshop and partly at site.

The civil contractors will co-ordinate with the

agencies supplying such equipment and provide them all necessary support at
site. Block outs and first stage anchor plates shall be provided in various
structures during first stage concreting.

The second stage embedded parts

comprising of sill beams, tracks, seal seats & guides etc. shall be erected in
these block outs before undertaking second stage concreting.
The supply and installation of all Hydro mechanical equipment required at
different locations shall be ensured to be completed in time so that the works
related to components can be completed in scheduled time.
9.9

EQUIPMENT PLANNIING

The list of equipment to be used is given in Table-9.1.


TABLE-9.1
List of Equipments
S.
No.

1
2
3
4
5
6

Equipment

Raise Climber
(Double motor)
3 Boom Drill
Jumbo
Tippers (20/25T))
Tippers (5.0m)
Excavators
(1.5m)
J CB

WAPCOS Limited

Package
-I
(Barrag
e and
Desilting
works)

Package
-II
(HRT RD
0 TO
8400.0
m)

PackageIII (HRT
RD 8400.0
m TO
16875.0
m)

PackageIV (HRT
RD
16875.0 m
to
23450.0
m)

Package-V
(Pressure
Shaft and
Surge
Shaft)

Packag
e-VI
(Power
House
and
allied
works)

3
3

28

34

50

50

9-14

Total

3
4

18

30

24

216

18

10

58

10

38

22

NJC Hydropower Limited

S.
No.

Equipment

Compressors
(500cfm/600cfm)
DG Set (250KVA)

DG Set (500KVA)

10

Welding Set
Ventilation Blower
(80 HP)
Dewatering
Pumps
Shotcrete Machine
(30m3/hr)
Concrete Placer
Concrete Pump
(38m3/hr)
Grouting Pump
Transit Mixer
(6.0m)
Batching Plant
(90m3/hr)
Batching Plant
(30m3/hr)
D-8 Dozer
(200HP)

11
12
13
14
15
16
17
18
19
20
21

Vibrators

22

Jack Hammers

EIA study for Nyamjangchhu


Hydroelectric Project

Package
-I
(Barrag
e and
Desilting
works)

Package
-II
(HRT RD
0 TO
8400.0
m)

PackageIII (HRT
RD 8400.0
m TO
16875.0
m)

PackageIV (HRT
RD
16875.0 m
to
23450.0
m)

Package-V
(Pressure
Shaft and
Surge
Shaft)

Packag
e-VI
(Power
House
and
allied
works)

Total

14

10

43

15

13

As per
Req

18

21

15

71

10

33

As per
Req

As per Req

As per Req

As per Req

21

18

27

22

15

17

17

11

12

90

As per
Req
As per
Req

As per
Req
As per
Req

24

As per Req

As per Req

As per Req

As per Req

As per Req

As per Req

22

16

19

21

16

As per
Req
As per
Req

36

Mobile Crane
(10T)
Crushing Plant
(180TPH)
Water Tanker
(11000ltrs)
Crawler Drill
Concrete Mixers
(14/10)
Rock Bolter
Truck Mounted
Scissor Platform
Vibratory
Compactor
Road Roller
Electric Winch
(5T)
EOT Crane (25T)
Shutter (CIFA) 7m
dia (6m Long)
Shutter (CIFA)
6.7m dia (6m
Long)
Crane 100T

37

Excavator BC-30

38

Explosive Van

39

Ambulance

40

Bus/Mini Bus

12

41

Workshop

LS

LS

LS

LS

LS

LS

23
24
25
26
27
28
29
30
31
32
33
34
35

WAPCOS Limited

5
1

1
5

1
4 sets

8 Sets

10 Sets

8 set

26 sets

2
2

9-15

NJC Hydropower Limited

S.
No.

Equipment

EIA study for Nyamjangchhu


Hydroelectric Project

Package
-I
(Barrag
e and
Desilting
works)

Package
-II
(HRT RD
0 TO
8400.0
m)

PackageIII (HRT
RD 8400.0
m TO
16875.0
m)

PackageIV (HRT
RD
16875.0 m
to
23450.0
m)

Package-V
(Pressure
Shaft and
Surge
Shaft)

Packag
e-VI
(Power
House
and
allied
works)

Total

LS

LS

LS

LS

LS

LS

14

13

Equipment
42
43
44
45

Ventilation
Ducting
Diesel Tanker
7000ltrs
Petrol Tanker
7000ltrs
Water Sprinkler
10000ltrs

WAPCOS Limited

9-16