Backlog Management

Author : Daryl Mather


Maintenance Consultant

Few tools are as useful to managing the maintenance workload and effectiveness as the Maintenance Backlog. In many
companies today management of the maintenance backlog has been neglected. As a result they are generally drowning in their
own data. A poorly managed system has a dramatic effect on the entire delivery of maintenance services.
Although the situation may appear random and chaotic, there are several common symptoms of poor backlog management. From
my observations of various maintenance demanding industries, these may include:

Many duplicate works orders. This is one of the main issues causing waste in this area. Particularly if undiscovered they
can result in wasted resources investigating already completed tasks. There are also the effects of re-ordering unrequired
materials and additional planning effort.

Non-standardised free text entries. Affecting future analysis and continuous improvement. This can also lead to
confusion in planning and execution of works.

No indication of forward resource requirements. Giving only best guess indications as to the true manning levels
required.

Poor coding of work orders (No business rules to guide these) Affecting the future analysis and continuous
improvement function. This can contribute to important works being buried among the work order listing.

Little focus on priorities, many unprioritised work orders. This results in corrective actions on the whim either the
supervisor, or section manager. As there is nothing substantial to use as a guide, or give a rating relevant to other backlog
works.

Many tasks not kept in the backlog system. Maintained in lists external to the corporate system. Faith in the backlog
system, and the maintenance delivery systems in general, are eroded.

Unrequired works passing through the work order system, resulting in unnecessary expenditure.

As well as all of these issues, an accurately managed backlog is the precursor to effective planning and scheduling systems,
which is a key driver of labour productivity.
Gaining control of the maintenance backlog is initially a difficult task. Requiring a great deal of effort and process development.
Keeping it under control is the product of correctly targeted systems applied in a disciplined manner by skilled planners,
supervisors and all involved in the work order process.
A correctly maintained backlog system will provide many benefits to the organisation. The system has control over the quality of
tasks to be performed, quality of data used in this execution and the quality of data returning to the system or files for future
analysis or improvement. Maintenance cannot move past the reactive stage without a firm control over this area.

Work Order Life Cycles


A clear-cut work order life cycle needs firstly to be developed. This needs to cover the full life of a works order from its inception to
its later roles in analysis. Points for quality reviews need to be established for both data integrity control, as well as suitability for
execution.
Once the system for this has been established, the process needs to be clearly communicated to all involved in it. Particular
emphasis is needed on the role that the individual holds and any relationships to others in the process.
The following example of a work order life cycle is a process I have seen used or adapted many times, each with an almost
immediate effect. However this system needs to be developed with the goals of each specific corporation in mind. Differences in
creation criteria, forward activity forecasting, and standardisation levels for free text as well as methods for controlling work orders
are common areas of difference.

Creation:
As the foundation of all the system, specific focus can assist greatly here.
Setting of criteria for what constitutes a works order.
Daily reviews by authoriser / planner for conformance to business standards and rules. Eg Classification, Priority, clarity of text,
sufficiency of detail for further works. This can best be accomplished by a request system, using the planner to code and manage
the work order details. The request system does need to contain a strong measure of specific data however.
Integration of the daily work request / work order reports into the morning operations meetings.

Review of Breakdown works orders

Discussion as to other higher priority ones.

Backlog Life
It is advisable to always have at least one weeks planned works ahead. Although the PM schedules can generally be
planned/scheduled out way in advance there is generally not enough for 100% capacity scheduling of labour hours for more than
three - five weeks And with weekly scheduling regimes, and opportune windows, this is a good minimum level.
During this life the work order needs to pass through various controls and processes:

Planning

Resourcing and $cost estimating

Priority reviews

Age by priority reviews

Scheduling of "Planned" works only

Execution and Data capture processes.

Execution and planning analysis and exception reporting

Reliability reporting

All of these are vital steps that need to be explored and organised to create an efficient system. Planning needs to be to a certain
level of information, parts to be within a certain period, documentation prepared, the work executed in a safe and timely fashion
and the data needs to be of high quality for reviewing the system.
By applying controls, accurate processes and of course role-specific training in these areas the backlog becomes a more efficient
tools for use reducing waste of labour hours, parts resources and planning time. Other areas of course need to be focused on but
this will provide the base for later improvements.
Daryl Mather
Email: mather@space.net.au
Copyright 1996-2005, The Plant Maintenance Resource Center . All Rights Reserved.