Professional Documents
Culture Documents
Management, Pune.
SCBA
Submitted by
Submitted to;
P91107 Anoop Nimkande
Date
P91119 Vijaydatta Patil
15th Dec 2014
Prof. V.
Date:
POSCO alternatives
o Stop at iron ore mining stage
Depletion premium
$ 10.18 for a steel producer located within Orissa
operation
( investment
value of quantity of ou
o
AIEC
o
o
o
AIEC is the average price needed per tonne for the project
to earn 12 % EIRR
Test Discount Rate = Economic Opportunity Cost of capital
of crude steel
Finer Process
= $308 per tonne lest cost
Blast Furnace Process
= $345 per tonne
Forecasted steel slab price post 2006 =
$450
per
tonne
competitiveness of Indian steel
Sensitivity Analysis
o EIRR of POSCO project calculated to be 16.6%
o Even if sales falls 10% short of expected, EIRR would be 13.9%,
higher than the hurdle rate of 12%
o Economic impact is calculated to be $2.5bn at test discount rate of
12%
Infrastructure development proposed
o Roads proposed
6.7- km coastal road from Paradip to POSCO-Indias SEZ site
11-km access roads from the SEZ to NH-5A andSH-12.
o Make power receiving equipment like towers, cables and
transmission hardware in the DTA.
o Indian township and Korean township to house all employees
Cumulative tax revenue
= Rs 174,970 Cr
o The Government of Orissa share
=Rs 77,870 Cr
Opportunity Cost = Tax revenue assuming project in DTA Tax Revenue
from project in SEZ
o Rs.3689 Cr or $0.8bn
o 33% of social benefits
2. How were the Social Costs & Benefits of the project identified and
quantified?
Time saving is a potentially important factor in most transport projects. once time saved
has been estimated
it must be valued and its monetary value must be included in cost savings. The benefits
of transport facility improvements are defined in terms of cost savings. For road projects,
these are VOC savings plus time savings and savings for non-motorized transport. For
rail, they will be savings on the rail network. For road projects, the main elements of cost
savings for vehicles will be fuel and oil, depreciation, tires, and spare parts. Time savings,
which are part of the generalized cost savings, include that of the crew for commercial
freight, and of drivers and passengers for private cars and commercial buses. For nonmotorized transport (such as bicycles, carts, and pedestrian walking time), the main cost
savings will be in time and possibly some savings in depreciation due to less wear and
tear. VOC savings will vary considerably by vehicle typeand good practice requires at a
minimum a distinction between cars, trucks, buses, and motorcycleswith, if possible, a
further distinction by engine size. VOC savings by vehicle type will vary with factors like
road surface, gradient, speed of travel, and quality of maintenance.
The effects of air pollution arising from particulate matter and other chemicals, such as
nitrogen oxides and sulphur dioxide, will vary with factors like location, population in the
areas affected, prevailing wind direction, as well as the nature of the transport activity
and the height of the emission source. Considerable work has been done in the European
Union on costing these pollutants in terms of health damage costs, using the cost-ofillness, human capital, and stated preference survey approaches.
(taken to be 0.75 for all types of work time and 1 for leisure) and zero for
transfers.
The breakdown of VOC savings and road maintenance expenditure savings into
various primary input categories is shown in Table 7.12.
of health damage costs, using the cost-of-illness, human capital, and stated
preference survey approaches.
II.
III.
The shadow exchange rate is 11% above the market rate which is taken to
be due to trade taxes.
IV.
Government loses direct tax revenue due to reduced VOC, but on the
other hand, there is extra foreign exchange expenditure as a result of the
project.
These results indicate that a rise in capital cost of 54% above the base case
estimate is needed to render the project marginal. As fuel price is a significant
element in VOC, the level of project benefits rises with the fuel price; however,
only when the assumed fuel price falls by 29% will the project become marginal.
The present value of benefits from generated traffic is $33.26 million, which
represents a 17.8% reduction from the base case value of $40.45 million. The
resulting NPV of $57.72 million and EIRR of 16.6% indicate that the project is still
acceptable, which is expected since the sensitivity analysis has shown that the
project can be justified on the grounds of cost savings for normal traffic alone.
Risk analysis incorporates simultaneous changes in all key variables. The project is
tested for risk by varying key parameters simultaneously within what are considered to
be a reasonable range. Table 7.19 gives the parameters that are varied and the range
within which they vary. Modest variation of capital cost and much higher variation of the
fuel price are allowed for, as well as changes in income growth and price elasticity of
demand. The key result is the probability of project failure, defined by a negative NPV.
This probability is about 10% and while there is no unique cut-off rate for acceptable risk
levels (although 25% is sometimes used as a rule of thumb), the project appears to be
low risk.
1. What was the context of study? Why was the study conducted?
The case study is based on the
1,000-MW Nam Theun 2 (NT2)
hydroelectric project located in the Lao PDR and selling most of the
generated electricity (around 97%) to Thailand.
The NT2 project was developed by a private company, Nam Theun 2
Power Company (NTPC)
The project construction period was around 5 years, commencing in 2005,
with predevelopment costs starting in 2004. Project commissioning was
expected in 2010.
From the perspective of Lao PDR, the projects objective is to develop
hydroelectric power as a key source of foreign exchange and, secondly, to
devote a small part of the output to domestic consumers as a low-cost
source of supply.
The advantages put forward for private sector undertaking the project
were:
I.
I.
II.
III.
II.
III.
IV.
The evaluation found that NT2 was the cheapest alternative among all
available options.
2. How were the Social Costs & Benefits of the project identified and
quantified?
II.
Construction costs
III.
IV.
Costs are allocated into traded goods, non- traded goods, foreign skilled
labor, local skilled labor, local unskilled labor, fuel, and transfer
payments, and are adjusted by the appropriate conversion factors.
to
project
sales
to
Capital cost
II.
III.
IV.
500