Professional Documents
Culture Documents
301
The Protocol recommends that, in deciding entitlement to EOT, the adjudicator, judge or arbitrator should as far as is practicable put him/herself in the
position of the CA at the time the Employer Risk Event occurred. He/she
should use the Updated Schedule to establish the status of the works at that
time. He/she should then determine what (if any) EOT entitlement could or
should have been recognised by the CA at the time.
This application seems to suggest that the blindsight approach should be adopted
and that the analyst should only take into account, when modelling the delaying
event, what was known at the time. For instance, where a work activity is extended
due to an increase in quantity, a reasonable assumption, at the time, would be that
the activity duration should be extended in proportion to the original scope of
work. Contemporaneous records may provide evidence of what, at the time, the
management team thought the effects of the delaying event might be. This
approach has led to criticism when dealing with delays retrospectively why look
into the crystal ball, when you can read the book.5 When dealing with delays
retrospectively, the analyst will have data and evidence of the actual duration and
sequences that resulted from the delaying event. Using this information, the hindsight approach will lead to a more realistic and accurate response of the schedule
and reduces the speculative and subjective assumptions.
The data required when undertaking a basic time impact analysis are:
Attributed to Aneurin Bevan (18971960) but used more recently in Beware the Dark Arts, p. 5.
Section IV
Progress records and as-built data whether collected from diaries, weekly reports
or progress meeting minutes should be cross-checked and verified against other
records such as photographs, quality records, time sheets and so on to verify their
accuracy. The method depends on updating the schedule to the point just prior
tothe delaying event occurring. Most probably, progress and as-built data for a
particular date, if it is not on the date of a specific progress report, will not be
available; therefore, it will be necessary to interpolate the specific data between
the records for two known dates.
The stages in undertaking time impact analysis are:
302
4.
5.
6.
Section IV
7.
303
The starting point for the analysis is the networked (linked) as-planned programme as shown previously in Figure15.2.
The first delaying event is identified and the date that it took place. Progress at
that date is identified. In this case, the design approval took longer than
expected so progress is measured up to the end of week 2 as shown in
Figure15.3a. The dropline shows that activity 8, Clear site and RL excavation, is 1 week behind schedule.
When the schedule is reanalysed (the critical path recalculated), the position or
status of the project at the time of the delaying event is established. The slow
progress of activity 8 results in the critical path being extended, and the milestone 17 Handover Key Date 1 is delayed until 2 July, 1 week later than the
original as-planned date of 25 June, as shown in Figure15.3b. This is considered to be the effect (or likely effect) on completion due to the thus far slow
progress of clearing the site and reduced level excavation; this would usually be
considered to be a culpable delay on behalf of the contractor.
The first delaying event is then modelled in the progress updated schedule.
Aspreviously, the design approval took 4 weeks as shown in Figure15.3c.
When the schedule is reanalysed, the critical path is further extended and the
handover date is delayed until 9 July, 1 week more than the previous date of
2 July and 2 weeks later than the original as-planned date of 25 June(see
Figure15.3d). The additional 1 week is said to be the effect (or likely effect) on
completion of the delay to the drawing approval period beyond the delay
already apparent due to the slow progress of activity 8.
Progress just prior to the second delaying event is input to the delay schedule,
and the schedule reanalysed. Figure15.3e shows the effect of progress and the
likely effect on the completion of the project. The analysis shows that a further
week has been lost; the additional lost week appears to be due to the extended
period taken to manufacture and deliver the steelwork (activity 6). Usually, this
would be considered a culpable delay, the responsibility of the contractor.
The next delaying event, the stoppage of the steelwork erection whilst the
wind-bracing calculations are checked, is modelled on the previously impacted
schedule as shown in Figure15.3f.
When the schedule is reanalysed, the critical path is not extended any further,
and the delay to completion remains at 3 weeks, as shown in Figure 15.3g.
Thereis no effect (or likely effect) on the completion date as a result of the
steelwork erection.
Progress just prior to the third delaying event is input to the delay schedule and
the schedule reanalysed. Figure 15.3h shows the effect of progress and the
likely effect on the completion of the project; there is no effect (or likely effect)
on the completion date.
The third delaying event, the additional racking, is then modelled on the schedule previously impacted by the second delaying event as shown in Figure15.3i.
When the schedule is reanalysed, the critical path is not extended any further
and the handover date remains at 16 July(see Figure15.3j). There is no effect
(or likely effect) on the completion date as a result of the installation of the
additional racking.
Section IV
Section IV
Section IV
Section IV
Section IV
Section IV
Section IV
Section IV
Section IV