Professional Documents
Culture Documents
Whats Wrong
g With Low PF?
Wastes Power
Overloads Equipment
q p
Costs Money
Uses Up Natural Resources
Power Factor
Active Power (W) is required to
perform useful work.
Reactive power (VAR) is required
for the generation of magnetic field in
inductive loads.
Apparent Power (VA) is the
resultant of above two powers.
Power Factor is the cosine of the
angle between VA and W.
W
All these powers can be represented
with
ith the
th help
h l off power triangle.
ti
l
V
A
R
Complex Power
Apparent Power = S = P + j Q VA
Real Power = P = | V | | I | cos() W
Reactive Power = Q = | V | | I | sin () VAR
Power Factor = PF = cos()
Single
g Phase Power
I = kVA/ kV = kW / (kV PF)
PF)
kVA = kV I
kW = kVA PF
I = kVA/ ( kV 1.732
1 732 )=
) kW / (kV 1.732
1 732 PF)
1.732 II
kVA = kV 1.732
kW = kVA PF
Note: kV is the phase-to-phase voltage
PF Example Correction
Facility
F ilit has
h peakk demand
d
d off 1000 kW Load
L d
Power Factor is 0
0.707
707 lagging
Calculate kVAR.
kVAR
Calculate amount of capacitance in kVAR
needed to correct to a 0.9 PF
How much is capacitance
p
in microfarads?
PF Example Continued
generator efficiencyy
Decreased g
Example: Calculations
1000 KW load
7800 hours per year
415Volt, 3 phase
Assumed System losses = 5%
Existing Power Factor = 0.75
Improved Power Factor = 0
0.95
95
Calculation
Loss Reduction = 1-(PF1/PF2)2
= 1 (0.75/0.95)2 = 0.38
System loss reduction = (loss reduction) x(Sys. Loss)
= 0.38 x 0.05= 0.019
Total kW load will be reduced
= 1000 x 0.019 = 19 kW
kVAR = kW x k-factor
Power
Quality
kVAr = kW x CF
kVAr = 10 x 0.692
kVAr =6
=6.92
92
0.98
Optimum
Location of power-factor
improvement capacitor banks
Induction motors of all types (which from by
far the greatest industrial load on a. c.
mains).
Power thyristor installation (for d.c.
d c motor
control and electro-chemical processes).
Power transformers and voltage regulators
regulators.
Welding machines
Electric-arc and induction furnaces.
g
system.
y
Choke coils and magnetic
Neon sins and fluorescent lighting.
Harmonic values of 5
5, 7,
7 11,
11 and 1 3
should be avoided as they correspond
to the characteristic harmonics of nonlinear loads.
loads
The harmonic value of 3 should also be
avoided as it coincides with harmonics
produced during transformer
energization and/or operation of the
transformer above rated voltage.
Capacitors Switching
1,2,4,4
1,2,2,4,4
FIFO
Reconnect Time
C/K settings
C/
In p
practice,, everyy dielectric excepting
p g vacuum,, has some resistance,,
which allows a small current in phase with the supply voltage pass
through, and consume power, this is known as dielectric loss
When the dielectric of a capacitor is a vacuum,
vacuum no losses take place in
it, and the current taken by a capacitor leads the applied voltage by
exactly 90o, the power being zero.
With any other dielectric, however, there is a loss, known as the
dielectric loss, which has the result that the current does not lead the
g byy the full 90o.
voltage
The phase angle by which the lead falls short 90o is called the loss
angle. If this angle is represented by the sign , then the phase angle
is (90o ) and the power factor of the capacitor is cot
cot. (90
(90- ),
) which
equals tan g.
Because of the small value of the angle g, the loss factor is normally
referred to as tan . The current taken by a capacitor is equal to l = s
CV, and the power absorbed by a capacitor is equal to VI cos .
Source: Rated power factor tests and installation acceptance of emergency and standby power systems
White paper By Jim Iverson, Senior Applications Engineer, Cummins Power Generation
LEA
ADING P
POWER
R FACTO
OR
Advantages
g of Power Factor Improvement
p
Example:
p
If power factor of a 1 MW gas generator running at 80% load
is improved from 0.80 to 0.95,about Rs.500,000 can be
saved per annum.
Payback period is about 5 months.
months
kWh
Month
Month
Dec.09
Jan.10
Feb.10
M 10
Mar.10
Apr.10
May.10
Jun.10
Jul 10
Jul.10
Aug.10
Sep.10
MDI
Penalty
Total Bill
Amount
14,769
Rs./
kWh
P.F
18.01
0.79
Peak
Off Peak
Peak
Jan.10
Off Peak
780
40
14
Low P.F
PF
1,036.1
Feb.10
1,340
16
1,324.1
21,411
15.98
0.77
Mar.10
1,580
18
667.8
23,558
14.91
0.84
May.10
1,640
20
3,176.3
27,823
16.97
0.65
Jun.10
2,020
19
3,203.6
30,956
15.32
0.63
Aug.10
1,800
40
19
4,793.7
33,417
18.16
0.57
Sep.10
1,800
20
17
4,725.7
30,886
16.97
0.49
18,927.1
182,820
16.62
kWh
Off Peak
360
961
1,498
2 273
2,273
1,360
949
1,350
1 000
1,000
2,220
1,300
Peak
20
7
23
12
40
43
20
30
120
70
MDI
Off Peak
Peak
15
0
18
0
25
0
10
1
16
1
13
1
15
1
12
1
16
2
16
3
Penalty
Low P.F
2,721
2,048
2,090
1 279
1,279
2,790
2,404
2,289
1 962
1,962
2,563
2,712
22,859
Bill
Amount
12,500
18,213
25,825
25 731
25,731
23,493
18,560
22,059
16 893
16,893
32,649
24,915
22,084
Rs./
kWh
32.89
18.82
16.98
11 26
11.26
16.78
18.71
16.1
16 4
16.4
13.95
18.19
18.01
PF
P.F
0.61
0.72
0.77
07
0.7
0.64
0.63
0.67
0 66
0.66
0.7
0.67
Power
Quality
Power
Quality
Faulty
F
lt Capacitors
C
it
b k draw
banks
d
more kW power and
d the
th loss
l
t
turn
out to be more as compared to the savings they provide.
Check the kW drawn by the capacitor banks periodically.
If it draws more power, then its replacement with new one
i beneficial.
is
b
fi i l
Check the kW and kVAR meter readings on weekly basis and
calculate the power factor to avoid the LPF penalty at the
end of the month, in case of capacitor banks failure.
This check will help you the timely replacement of faulty
capacitor banks.
Power
Quality
Bank
Capacitor
415v
5kVAr
7A 50HZ
7A,
15 kVAr
10 kVAr
Volts
Amp.
406 6736
406.6736
Power
Factor
Measured
kW
kVAr
71
7.1
0 12
0.12
1 62
1.62
417.7584
1.69
400 092
400.092
1 59
1.59
394.90
395.59
399 75
399.75
407.37
406.33
405 29
405.29
20.7
15.8
15 4
15.4
8.1
8
0
0.07
0.64
0 58
0.58
2.76
2.7
-
Status
OK
Replace it.
1- leg off
Extra loss
Capacitor
Bank #
01
02
03
04
05
06
07
Phase
Volts
R
Y
B
234.00
234.70
231.30
R
Y
B
234.10
234.20
231.70
R
Y
B
234.20
234.40
231.60
R
Y
B
234.00
234 30
234.30
231.40
R
Y
B
233.90
234 70
234.70
231.20
R
Y
B
234.00
234 50
234.50
231.30
R
Y
B
233.90
234 30
234.30
231.70
PFI, Panel #
Measured Measured
Ampare
kW
kVAr
74.40
0.01
16.29
74.60
0.08
16.42
73.20
0.07
15.99
0.16
48.70
57.90
0.09
12.74
49.80
1.05
11.03
48.60
0.90
10.64
2.04
34.41
51.20
2.04
11.00
58.20
1.08
12.86
41.20
0.99
9.00
4.11
32.86
76.70
0.00
16.82
71 00
71.00
0 49
0.49
15 71
15.71
71.40
0.36
15.58
0.85
48.11
54.50
1.50
11.88
50 10
50.10
0 95
0.95
11 03
11.03
61.40
0.47
13.46
2.92
36.37
58.90
0.02
12.90
57 20
57.20
0 24
0.24
12 69
12.69
55.80
0.15
12.22
0.41
37.81
53.30
0.45
11.71
53 30
53.30
0 48
0.48
11 80
11.80
49.10
0.00
10.74
0.93
34.25
Rated
kVAr
50.00
50.00
50.00
50 00
50.00
50 00
50.00
50 00
50.00
50 00
50.00
Hik E
Hike
Energy C
Center
t
----------------------------------------------------------------------------Office 11,
11 2nd Floor China Tower Model Town Link Road Lahore Pakistan
e-mail: hikenergy@live.com , info@hec.net.pk http://www.hec.net.pk
Please consider your environmental responsibility before printing this document