You are on page 1of 140

Nyadi Hydropower Project

Feasibility Study
Final Report
Volume III Technical Annex
Appendix D
Appendix E
Appendix F
Appendix G
Appendix H

Design calculation
Optimization study
Cost estimate and financial
Analysis
Access road design report
Photographs
October, 2010

Nyadi Hydropower Limited (NHL)

Nyadi Hydropower Project


Feasibility Study
Final Report
Volume III Technical Annex
Appendix D
Appendix E
Appendix F
Appendix G
Appendix H

Design calculation
Optimization study
Cost estimate and financial
Analysis
Access road design report
Photographs

Quality control
Prepared by:

Signature

Date

Basanta Bagale
Lochan Devkota
Sumin Shrestha
Basanta M. Shrestha
Uttam Dhakal

Checked by:

Saroj Lal Shrestha

Approved by:

Bharat Raj Pandey

October, 2010

Nyadi Hydropower Limited (NHL)

Report Contents
EXECUTIVE SUMMARY
VOLUME 1

MAIN REPORT

VOLUME 2

INVESTIGATION ANNEX
APPENDIX A HYDROLOGY AND SEDIMENTOLGY
APPENDIX B TOPOGRAPHICAL SURVEY
APPENDIX C SITE INVESTIGATION (GEOLOGY AND
GEOTECHNICAL

VOLUME 3

TECHNICAL ANNEX
APPENDIX D DESIGN CALCULATION
APPENDIX E OPTIMIZATION STUDY
APPENDIX F COST ESTIMATE AND FINANCIAL
ANALYSIS
APPENDIX G ACCESS ROAD DESIGN REPORT
APPENDIX H PHOTOGRAPHS

VOLUME 4

MAP AND DRAWINGS


APPENDIX J TOPOGRAPHICAL MAPS
APPENDIX K GEOLOGICAL MAPS
APPENDIX L CIVIL DRAWIGS
APPENDIX M ELECTRICAL DRAWINGS

Hydro Consult

Nyadi Hydropower Project


Feasibility Study Volume III

APPENDIX D
DESIGN CALCULATION

NYADI HYDROPOWER PROJECT


FEASIBILITY STUDY

October, 2010

Nyadi Hydropower Limited

HYDRAULIC DESIGN

Weir Hydraulics
Orifice Design
Settling Basin Design
Penstock Design
Anchor Block Design
Surge Tank Design
Headloss Calculation Sheet
Power and Output Energy Calculation
HEC RAS Result
Turbine Design Calculation
Tailrace Tunnel Design
Level Determination of Powerhouse and tailrace

Hydro Consult

Nyadi Hydropower Project

Weir Hydraulics
NOTE : The design of the Headworks Weir Arrangment has been done on the basis of Hydraulic Model Studies carried out at Hydro Lab Pvt Ltd. The detailed information
about the study result has been compiled on Hydraulic Model Study of the Headworks of Nyadi Hydropower Project.

Weir

26.50

21.00

8.000

10.21
12.000

Calculation of U/S and D/S cutoffs, and Uplift Pressures


Discharge (100 yrs flood)
Length of weir
Weir crest elevation
Coefficient of discharge
Length of U/S floor
Length of sloping glacies
Length of D/S floor (Stilling basin)
Total floor length

m3/sec
m
masl
Cd
m
m
m
m

509.00
14.00
1381.50
2.10
26.50
10.21
21.00
57.71

Q = CLH
Head over the crest
m
U/S TEL
masl
Water level elevation U/S of the weir can be determined using the Bernoulli's equation and iteration

6.69
1388.19

U/S bed level


U/S total energy
Water depth

m
m
m

1372.90
15.29
14.93

m
m
masl

1387.83
0.87
1388.70

3/ 2

Ec
y1 =

q
2 g ( E o y1 )

U/S water level elevation (HGLu)


Free Board
Guide wall Crest Elevation

1372.9+14.93

Depths of cutoffs
Scour depth U/S and D/S of the floor is determined by Newzealand Formula.
[Equation provided by Bharat Raj Pandey and used in Marsyangdi-III Hydroelectric Project (MHEP-III)]
Discharge intensity
q
m3/s/m
U/S Water Depth
Velocity of Flow
Cross Sectional Area of Flow
Width of Flow
Constant

Y
V
A
B
k

Scour Depth measured from HFL

dS

m
m/s
m
m

=k.Y.V.B/A

Depth of U/S cutoff below the U/S HFL

=1.25 ds

Level of bottom of U/S cutoff


Therefore, U/S cutoff depth below U/S floor
Provided U/S cutoff depth

1387.83-7.97
1371.5-1379.86

m
m
m
m

masl

D/S water Elevation


Depth of D/S cutoff below the D/S HFL
Level of bottom of D/S cutoff
Therefore, D/S cutoff depth
Provided D/S cutoff depth
Uplift Pressures

=1.50 ds
1378.07-9.57

U/S floor elevation


D/S floor (basin) elevation
Length of U/S cutoff
Length of D/S cutoff

m
m
m
m

masl
masl
m
m

Page 1 of 2

36.36
14.93
2.66
209.04
14.00
0.62
6.38
7.97
1379.86
-8.36 Cutoff Not Necessary
8.00 ADOPT

Result from HECRAS Analysis 1378.07 WSE at RS 18 (Chainage 0+160)


9.57
1365.46
3.54 Cutoff Required
6.00 ADOPT

1371.50
1369.00
8.00
6.00

U/S Cutoff Elevation


D/S Cutoff Elevation
D/S Curtain Grouting Depth

1363.50
1363.00
6.00

masl
masl
m

[Reference: DWPF page no. 74 & 75 (Case 4 and Case 5) and table VII-5 of page no. 100]
Check for Thickness
For 100 yrs flood
U/S portion upto the just below the orifice
Total downstream forces acting (F1) = Weight of water over the concrete + Weight of the concrete
HFL
Low Flow
Assume thickness
2.2 m
2m
Upward force (uplift pressure)
160.20938 KN/m2
122.625 KN/m2
Downward force (weight of concrete +Weight of water)
213.00938 KN/m2
170.625 KN/m2
Factor of saftey

1.400 ok

1.330 ok

U/S portion upto sloping portion starting from just below the orifice
Total downstream forces acting (F1) = Weight of water over the concrete + Weight of the concrete
HFL
Low Flow
Assume thickness
2.2 m
2.6 m
Upward force (uplift pressure)
160.20938 KN/m2
122.625 KN/m2
Downward force (weight of concrete +Weight of water)
213.00938 KN/m2
160.5 KN/m2
Factor of saftey

1.310 ok

1.330 ok

sloping portion
Total downstream forces acting (F1) = Weight of water over the concrete + Weight of the concrete
HFL
Low Flow
Assume thickness
3m
2.8 m
Upward force (uplift pressure)
160 20938 KN/m2
160.20938
139 2272 KN/m2
139.2272
Downward force (weight of concrete +Weight of water)
211.2272 KN/m2
206.4272 KN/m2
Factor of saftey

1.490 ok

1.320 ok

Stilling Basin
Total downstream forces acting (F1) = Weight of water over the concrete + Weight of the concrete
HFL
Low Flow
Assume thickness
3.2 m
3.2 m
Upward force (uplift pressure)
160.20938 KN/m2
160.20938 KN/m2
Downward force (weight of concrete +Weight of water)
216.0272 KN/m2
216.0272 KN/m2
Factor of saftey
note: this thickness can reduced gardually upto 1.5m

1.350 ok

1.350 ok

Check for exit gradient


Seepage head
Depth of central cutoff (assume)
Intermediate cutoff
length of weir section
Total floor length (creep length)

b
a

=b/d
=

Permissible exit gradient


Exit Gradient

GE per
GE

G E

1+

1+ 2
2

=1/6

h
1
d

For Added Safety


Provide the drainage hole of dia 0.15m at 2.8m C/C throught the section

Page 2 of 2

Normal flow condition


Flood flow condition
12.500

9.761

57.710

57.710

97.710
8.143

97.710
8.143

4.602

4.602

0.167

0.167

0.155

0.121

OK

OK

Hydro Consult

Nyadi Hydropower Project

ORIFICE DESIGN-1
Date
Job :
Job No:
Calculated by:
Checked by:

Design Considerations/Assumptions
1. The intake opening will be submerged orifice, and may be open during full flushing
2. The orifice will be above river bed level to exclude bigger sediment
3. The top level of the orifice will be just below normal water level so that floatinig debris can be excluded,
4. The design discharge is 11.08 m3/sec

5. Velocity will be limited to 0.5 to 1.1 m/s during normal flow conditions for the exclusion of bed load and floating load to remain at the trash rack (Ref: Emile Mosony 2/A)
6.
7.
8.
9.

20% of the design discharge is taken as Flushing discharge at gravel trap and settling basin during the period of continuous flushing
Normal water level 1381.5 m
River bed level at intake is taken as 1371.6
During high flood condition the radial gate will open accordingly

1 Input Data
Percentage Exceedence

~40 %

Design turbine discharge (Q power) =

11.08 m3/sec

Gravel Flushing Discharge (Q SF) =

10%

Sediment Flushing discharge (Q b) =

10%

Set Velocity (V) =


Orifice height/depth (H) = assumed
No of bay
Central pier thickness (t)
Each bar thickness
Spacing of each bar
Width of orifice provided (B)=
Normal Water level (NWL)=
Invert level of orifice

0.60
3.50
3
0.50
0.01
0.25
2.25
1381.5
1376.5

m/s
m
nos
m
m
m
m
m
m

Discharge coffiecient (c) =

0.60 for roughly finished masonary


orifice

Accleration due to gravity (g)=

9 81 m/sec2
9.81

Plan sketch

2 Calculation
2.1 During Normal Flow Condition
3
1.108 m /sec

Gravel Flushing Discharge (Q SF) =


Sediment Flushing discharge (Q b) =

3
1.108 m /sec

Total discharge (Qdesign) =

3
13.30 m /sec

Net area of orifice required


Gross horizontal opening
No of bar in each bay
Net horizontal opening provided

22.16
7.25
8
6.51

Net vertical height of orifice required (H)=

m2
m
Nos
m

3.40 m

OK

22.79 m2
1380.00 m

Net area provided


Top level of orifice opening
Check the discharge in headrace canal by the formula below;
h = (Q/AC)2/2g
h
hh(normal)
Q = A.C. (2g (hr-hh))=
V = Q/A

0.05 m
1381.45 m
3
13.67 m /s

Orifice size is ok

0.60 m/s

Velocity Ok

TRUE

2.2 During Flood Flow Condition


The radial gate will be open accordingly to pass the high flood
h
3 Output
No of orifice =
Orifice Height (H) =
Each Orifice Width (W) =
Clear vertical spacing of bar to bar =
Thickness of central pier =

3
3.50
2.25
0.25
0.50

Nos
m
m
m
m

I:\ED\Jobs\OPEN\751220 Nyadi Implementation\03Reports\Final Review 30 MW as per Damodar Hydrology_23 Nov\VOLUME III - Technical Annex\Appendix D - Design Calculations\2.Orifice self sheet Q=11.08_November 22, 2010.xlsx

Hydro Consult

Nyadi Hydropower Project

Nyadi Hydropower Project


Hydraulic Design Review of Settling Basin
Note: Size review (Ref. Feasibility Study Report March 2000)
3
11.08 m /sec

Design flow (Q T)

3
1.108 m /sec (10% of design flow)

Flushing discharge (Qflush)

Total discharge in basin (Qbasin) =

12.188 m /sec

No of basin

1 nos

first trial

3
12.188 m /sec

Discharge in one basin (Q1 basin) =


Criteria: > 90% settling of

0.2 mm

Fall velocity (w)

0.02 m/sec

1.5 cm/sec

For 0.2 mm particle and 150C temperature

Water temperature
15 0C
Assume inlet transition 1:5 expansions, which gives the performance parameter m = 1/5 (very good performance)
Use Vetter's equation and Hazen's method to calculate Settling basin surface area:
Performance parameter m
1-h = (1+m w Ap/Q) (-1/m)
h = 1 - e - (w*A/Q)
= 0.125
A, m2

A, m2

2200
2190
2180
2170
2160
2150
2140
2130
2120
2110
2100
2090
2080
2070
2060
2050
2040
2030
2020
2010
2000
1990
1980
1970
1960
1950
1940
1930
1920
1910
1900
1890
1880
1870
1860
1850
1840
1830
1820
1810
1800
1790
1780
1770
1760
1750
1740
1730
1720
1710
1700
1690
1680
1670
1660
1650
1640
1630
1620
1610
1600
1590
1580
1570
1560
1550
1540

0.973
0.973
0.972
0.972
0.971
0.971
0.970
0.970
0.969
0.969
0.968
0.968
0.967
0.967
0.966
0.965
0.965
0.964
0.964
0.963
00.962
962
0.962
0.961
0.961
0.960
0.959
0.959
0.958
0.957
0.956
0.956
0.955
0.954
0.954
0.953
0.952
0.951
0.950
0.950
0.949
0.948
0.947
0.946
0.945
0.944
0.943
0.942
0.942
0.941
0.940
0.939
0.938
0.937
0.935
0.934
0.933
0.932
0.931
0.930
0.929
0.928
0.926
0.925
0.924
0.923
0.921
0.920

2500
2480
2460
2440
2420
2400
2380
2360
2340
2320
2300
2280
2260
2240
2220
2200
2180
2160
2140
2120
2100
2 00
2080
2060
2040
2020
2000
1980
1960
1940
1920
1900
1880
1860
1840
1820
1800
1780
1760
1740
1720
1700
1680
1660
1640
1620
1600
1580
1560
1540
1520
1500
1480
1460
1440
1420
1400
1380
1360
1340
1320
1300
1280
1260
1240
1220
1200
1180

93.856%

h
Vetters equation
0.964
0.963
0.962 Hazen's equation
0.961
0.960
0.959
0.958
0.958
0.957
0.956
0.955
0.954
0.953
0.951
0.950
0.949
0.948
0.947
0.946
0.944
0.943
0 943
0.942
0.940
0.939
0.938
0.936
0.935
0.933
0.931
0.930
0.928
0.926
0.925
0.923
0.921
0.919
0.917
0.915
0.913
0.911
0.909
0.906
0.904
0.902
0.899
0.897
0.894
0.891
0.889
0.886
0.883
0.880
0.877
0.874
0.871
0.867
0.864
0.860
0.857
0.853
0.849
0.845
A used
0.841
0.837
0.832
0.828
0.823

= 1 e

wA s

1 = (1 + mwA / Q

Page 1 of 2

1700

)( 1 / m )

Hydro Consult

Nyadi Hydropower Project

1530
1520
1510
1500
1490
1480
1470
1460
1450
1440
1430
1420
1410
1400
1390
1380
1370
1360

0.919
0.917
0.916
0.915
0.913
0.912
0.910
0.909
0.907
0.906
0.904
0.903
0.901
0.899
0.898
0.896
0.894
0.893

1160
1140
1120
1100
1080
1060
1040
1020
1000
980
960
940
920
900
880
860
840
820

Calculate basin width based on Vetter's method:


No of chambers
Flow per chamber, m3/sec
Assumed width, m
Required length for 1700 m2
=assumed (area/ width)
Minimum depth = Q/BV
Maximum flow velocity V = 0.44*SQRT(dlimit)
Where, dlimit = 0.15 mm
V=
0.20 m/s
Adopt two basins width of
Required inlet transition length@1:9 (For

1
12.188
8.000
212.50
7.74

0.819
0.814
0.809
0.804
0.798
0.793
0.787
0.781
0.775
0.769
0.763
0.756
0.749
0.742
0.735
0.727
0.720
0.712

2
3
8.8542
6.094
4.063
13.281
8.000
8.000
13.28 Width and Length ratio OK
106.25
70.83
3.87
2.58
(ref. Civil works guidelines for micro- hydropower in Nepal, page # 73)

Adopt
25

25.00 m (transition from 3 m wide canal to 16

Horizontal transition)

m wide settling basin)

Sediment storage in two chambers:


S = Q*T*C
S - sediment load in kg stored in the basin
Q - Discharge in m3/sec
T - sediment emptying frequency in seconds
C - sediment concentration of the incoming flow in kg/m3, assume
Sediment density
Packing factor of density
Sediment load (S) =
Volume of sediment
Required depth
Total required depth
Water level at settling basin
Bottom level of Beginning of parallel section
Available head for flushing

39.5

28800 (8 hrs)
10,000 ppm
2600
0.5
3510144
2700 1
2700.1
3.08
6.952

10 kg

Kg/m3
Kg
m3
m
m.

7.00 Adopted
1377.50 m
1370.50 m
6.625 m

Checking for flushing of deposition in settling basin

Stable

Stable

particle

particle

size, based size, based


on Shield's on ACI
simplied

h,

b,

m,

a,

p,

R,

n,

h:m

0.40

0.50

1.00

0.20

1.30

0.15

0.015

0.43

0.50

1.00

0.22

1.36

0.16

0.015

0.45

0.50

1.00

0.23

1.40

0.16

0.50

0.50

1.00

0.25

1.50

0.17

s,

1350.1 m3
6.09 m3/sec
4.88 m3/sec

25.00
8.00
93%
2
106.00
3.90
3.08
7.98

m.
m

3
m /s

0.02

2.71

0.54

33.85

305.00

0.02

2.76

0.59

34.78

316.26

0.015

0.02

2.79

0.63

35.36

323.29

0.015

0.02

2.86

0.71

36.67

339.35

Total volume of sediment/No. of chambers


Total basin discharge/No. of chambers
80% of design flow of each chamber of settling basin

nos.
m
m
m
m

Adopted
25.00
8.00
93.00%
2.00
128.00
4.50
3.75
10.30

Page 2 of 2

mm

m/s

the gate is opened fully)


1.67 m3/sec
b*h*0.65*sqrt(2*g*H)
Assuming that the settling basin will not be empitied, only deposition will be flushed out
Vt= Vin + Qin*t-Qflush*t
Accumulated volume in time t = previously stored volume+discharge vol in
t time-outgoing volume due to flushing in t time
t=
-7.0 Min
Drain time
13.5 Min
Recharge time
3.7 Min
Total time required
10.2 Min
Adopted size of settling basin
Inlet transition length =
Width of chamber =
Settling basin efficency =
Nos. of chamber =
Length of parallel section =
Water depth in parallel section =
Required storage depth =
Total depth of settling basin including freeboard =

report

mm

Q,

The present table shows that at any height the deposited sediments will be flushed out.
Flushing time calculation for intermittent flushing of single chamber
Sediment volume in settling basin
Design inflow to settling basin
Inflow to settling basin during flushing
Flushing discharge (when

committee

formula

v,

m.
m
nos.
m
m
m
m

Hydro Consult
CALCULATION FORM
Date:
Job: Nyadi HP

Job no.

Input Datas

Drg. No.

Calc. by

Project Life Period=

30 years

Design Discharge(Q)=

12.19 m3/s

Tunnel Intake Level=

1381.50 m

Tail Race Water Level=

1032.00 m

Gross Head=
Length of headrace Tunnel (L)=

Basanta Bagale

751220 Chkd.

=1.1 times Design discharge

347 m
3955.00 m

Section Type of Head Race tunnel =>


Diameter of Tunnel=

3.20

X-section area of Head Race Tunnel (f) =

9.141 m2

Wetterd Perimeter of Tunnel (Pt)=

11.427 m

Hydraulic Radius of Tunnel (Rt)=

0.8 m

Area of Surge Tank(F)=


Tunnel lining Material=
Manning's Coefficient for Concrete lines Tunnel(n)=
Coefficient of Roughness for tunnel(K)=

19.635 m2
Concrete
0.015
66.667

Is calculated from
Manning's
Strickler Formula
= 1.1*L/(K^2)/(R^(4/3))

Ressistance Factor ()=

1.318059579

Damping Factor(m)=

0.014044698

Diameter of penstock (dp)=


Area of X-section of Penstock(Ap)=
Diameter of pipe after tri-forcation(dtp)=
Orifice Head loss Coefficient(d)=

1.75 m
2.405 m2
1m
1.843

Hydro Consult
CALCULATION FORM

Date:
Job no.

Job: Nyadi HP

Drg. No.

Objective: Calculation for the submergence in the surge tank

hs > 1.5*Vp^2/2/g
where,
hs= Submergence Head
Vp= Velocity in Penstock
g= acceleration due to gravity
Vp =Q/Ap
Where,
At= X-section area of Tunnel
Q= Discharge through Tunnel

12.19 m3/sec

dt= diameter of Tunnel

3.2 m

At=

9.141 m2

Vt=

1.333 m/s

Gordon (1970)

S = kv d
S= submegence (ft.)
k= coefficient 0.3 for symmetrical approach

0.30

0.4 for unsymmetrical approach

0.40
Submergence (S)

1.73 m

Submergence (S)

4.80 m

Submergence (S)

0.14 m

Considered submergence (S)

4.800 m

Prosser (1977)

S = 1.5d

ITDG Manual

v2
S 1.5
2g

Calc. by
751220 Chkd.

Basanta Bagale

Hydro Consult
CALCULATION FORM
Date:
Job: Nyadi HP

Job no.

Summary

Drg. No.

Calc. by

Basant Bagale

751220 Chkd.

Surge Calculated from Finite Difference Method


Upsurge
Surge Level

Downsurge

Max. Surge

Surge Level(m)

Open all Valves from closed stage=


1390.288

Closing All Valves at once=


Absolute Maximum Surge=

Diameter of surge tank=


Free Board for Surge Tank=

1390.288

9.012
9.012

Max. Surge(m)

1367.665

12.485

1376.604

4.672

1367.665

12.485

5m
1.712 m

Submergence head=

4.8 m

So,
Total surge in Surge Shaft=

21.497

Now,
Static Water level=

1381.5 masl

Water level of Highest Upsurge=

1390.288 masl

Level of Lowest Downsurge=

1367.665 masl

Level of the top of ST=

1392.000 masl

Level of Center of Head Race Tunnel=

1360.265 masl

22.623

1392

1.712

Thickness of Surge Shafts


Estimated
Elevation form

Elevation to

Height(m) Thickness(m)

Reinforcement
(t)

Volume of
concrete

Wt. of Concrete

1362.224

1363.224

1.000

0.398879524

orifice

1363.224

1370.046

6.822

0.9

2.285

877.8524706

219.4631176

1370.046

1376.868

6.822

0.7

1.656

823.843969

205.9609922

1376.868

1383.690

6.822

0.5

1.065

771.550023

192.8875057

1383.690

1390.512

6.822

0.3

0.513

720.9706326

180.2426581

3194.217095

798.5542738

Nyadi Penstock Alignment Bend details surface plus vertical shaft


S.

Chainage,

Anchor
Identific-

Hor.

Verical

defln

Angle with

Angle

horizontal

Ver. delection

Easting
X

Northing
Y

m (from
angle degree

PS
TP
VB1
VB2
CB3
VB4
VB5
CB6
VB7

'Degree'
0.00
0.00
0.00
0.00
11.24
0.00
0.00
1.62
0.00

a 'Degree'

1 0.00
2 17.45
3 39.71
4 93.62
5 156.02
6 213.07
7 273.07
8 333.075
9 393.066

0.5

0.83
0.83
6.14
16.97
35.28
22.29
21.36
12.83

0
-0.01
5.31
10.83
18.31
-12.99
-0.93
-6.61
-12.83

541632.30
541632.97
541633.82
541635.89
541638.28
541629.31
541619.88
541610.45
541602.02

3134827.46
3134810.02
3134787.78
3134733.91
3134671.55
3134615.21
3134555.95
3134496.70
3134437.30

10 440.616

VB8

0.00

14.75

-14.75

541595.33

3134390.23

No.

ation/SOP

Anc to anch.
hor distance,

Anc to anch incl


Length at pipe

coordinates) bottom (Leff), m


0.00
0.00
17.45
17.45
22.26
22.26
53.91
54.22
62.40
65.24
57.05
69.89
60.00
64.85
60.00
64.43
59.99
61.53
47.55

Bend angle

Bend angle

Clockwise (downturn bend) +ve

Anticlockwise(upturn) -ve

55.35

Cumulative

Ground

Invert

Level , masl

Level, m

0.00
17.45
39.71
93.93
159.18
229.07
293.92
358.34
419.87

1393.95
1380.24
1362.72
1349.74
1331.08
1290.71
1265.11
1241.64
1227.98

1355.50

475.22

1213.76

Length
of pipe, m

Invert
level diff,
m

Pipe

Groundinvert
height,

Thickness

m
-38.45
-24.99
-7.79
-0.61
-1.00
-1.00
0.00
0.00
0.00

0.00%
-1.46%
-1.44%
-10.76%
-30.52%
-70.76%
-41.00%
-39.11%
-22.77%

10
10
10
10
16
16
22
22

1227.980

0.00
0.25
0.32
5.80
19.04
40.37
24.60
23.47
13.66

1213.320

14.66

-0.44

-26.34%

1355.25
1354.93
1349.125
1330.080
1289.710
1265.111
1241.643

475.22 m
Pipe Summary:
underground

1750

ID Pipe L
1750 ID Pipe L

200.16 m
675.38 m

stock Start, TP = Tunnel Portal, VB= Vertical Bend, CB= Combined bend

5.Penstock Calculation_350MPA_Q=11.08_November 22 2010.xls

Uphill
ground

Gradient

1450

ID

Pipe L
1000

ID

11.00 m

Pipe L
Transition
(1.751.45)

43.23 m

1.2 m

slope, i

Allowable
bearing capacity

22

30
30
30
30
30
25
25
25
25

160
160
160
160
160
160
160
160
160

22

20

160

Nyadi Penstock Calculation


Weir Elevation
Turbine Level
Design flow
Static head
Length of penstock pipe
Youngs' modulus of steel
Yield Stress of steel

Steel Specification
Required Safety Factor
Steel Density
Water Density
Welding efficiency
1 USD
Rate of Steel

1381.5
1034.5
11.08
347.00
675.38
200,000
350
350
350
SAILMA 350
2.5
7850
1000
0.9
71.25
170.5

Qd
Hg
Lp
E
S

SF

Rate of Steel
Nos of turbine units
Number of nozzle in each turbine units
Surge Head
NOTE:

t w = (Pi * d * FOS /( 2 * y * w ) ) + 2

Effective Thickness =

Pi = w * g * H T

V =

<20mm THK
20~40mm THK
>40mm THK

4 * Qd

*d2

kg/m3
kg/m3
Rs
Rs/kg
Surge Head = 0.15 x Static Head
Water Hammer =10 ~15 % of static head (Refer:E. mosonyi, Pg 715 (old))

2.39 USD/kg
3
2
15% Static Head

Penstock permissible velocity for properly settled water with respect to abrassion, v = 3 to 5 m/sec
(Refer: Mosonyi High Head Power Plants Volume Two/A page 330)

Segment #1
Static head
Length of penstock
Diameter, d, mm

m
m
m3/s
m
m
N/mm2
N/mm2
N/mm2
N/mm2

51.42 m
159.22 m

Elevation

1330.08 m

1250

1350

1450

1550

1650

1750

1850

1950

Penstock flow velocity,V m/s


Handling Thickness, mm
Gross thickness, mm

9.03
4.40
8

7.74
4.65
8

6.71
4.90
8

5.87
5.15
8

5.18
5.40
8

4.61
5.65
8

4.12
5.90
8

3.71
6.15
8

Effective thickness, teff mm

4.88

5.11

5.34

5.57

5.80

6.03

6.26

6.49

Internal Pressure, N/Mm^2


Surge Head, Hs m
Total Head, Htot m
Factor of safety
Check
Weight of steel, ton

0.58
7.71
59.13
4.10
OK
41

0.58
7.71
59.13
3.92
OK
45

0.58
7.71
59.13
3.75
OK
48

0.58
7.71
59.13
3.59
OK
51

0.58
7.71
59.13
3.45
OK
55

0.58
7.71
59.13
3.32
OK
58

0.58
7.71
59.13
3.20
OK
61

0.58
7.71
59.13
3.08
OK
65

Segment #2
Static head
Length of penstock
Diameter, d, mm

105.00 m
124.02 m

Elevation

1274.20 m

1250

1350

1450

1550

1650

1750

1850

1950

Penstock flow velocity,V m/s


Gross thickness, mm

9.03
8

7.74
10

6.71
10

5.87
10

5.18
10

4.61
12

4.12
12

3.71
12

Effective thickness, teff mm

7.88

8.35

8.82

9.29

9.76

10.23

10.70

11.17

1.18
15.75
120.75
2.54
OK
32

1.18
15.75
120.75
3.00
OK
44

1.18
15.75
120.75
2.84
OK
47

1.18
15.75
120.75
2.69
OK
50

1.18
15.75
120.75
2.56
OK
53

1.18
15.75
120.75
2.93
OK
68

1.18
15.75
120.75
2.80
OK
72

1.18
15.75
120.75
2.69
OK
76

Internal Pressure, N/Mm^2


Surge Head, Hs m
Total Head, Htot m
Factor of safety
Check
Weight of steel, ton
Segment #3
Static head
Length of penstock
Diameter, d, mm

157.00 m
176.63 m

Elevation

1222.20 m

1250

1350

1450

1550

1650

1750

1850

1950

9.03
12

7.74
12

6.71
14

5.87
14

5.18
14

4.61
16

4.12
16

3.71
16

Effective thickness, teff mm

10.79

11.49

12.19

12.89

13.60

14.30

15.00

15.71

Internal Pressure, N/Mm^2


Surge Head, Hs m
Total Head, Htot m
Factor of safety
Check
Weight of steel, ton

1.77
23.55
180.55
2.78
OK
69

1.77
23.55
180.55
2.61
OK
75

1.77
23.55
180.55
2.87
OK
94

1.77
23.55
180.55
2.71
OK
100

1.77
23.55
180.55
2.57
OK
107

1.77
23.55
180.55
2.80
OK
129

1.77
23.55
180.55
2.67
OK
137

1.77
23.55
180.55
2.55
OK
144

Penstock flow velocity,V m/s


Gross thickness, mm

Segment #4
Static head
Length of penstock
Diameter, d, mm
Penstock flow velocity,V m/s
Gross thickness, mm

232.75 m
75.75 m

Elevation

1156.20

1250

1350

1450

1550

1650

1750

1850

1950

9.03
16

7.74
18

6.71
18

5.87
20

5.18
20

4.61
22

4.12
22

3.71
25

Page 2of 3

Effective thickness, teff mm

15.02

16.07

17.11

18.15

19.19

20.23

21.28

22.32

Internal Pressure, N/Mm^2


Surge Head, Hs m
Total Head, Htot m
Factor of safety
Check
Weight of steel, ton

2.63
34.91
267.66
2.66
OK
40

2.63
34.91
267.66
2.80
OK
48

2.63
34.91
267.66
2.63
OK
52

2.63
34.91
267.66
2.75
OK
62

2.63
34.91
267.66
2.61
OK
66

2.63
34.91
267.66
2.72
OK
76

2.63
34.91
267.66
2.59
OK
81

2.63
34.91
267.66
2.80
OK
97

Segment #5
Static head
Length of penstock
Diameter, d, mm
Penstock flow velocity,V m/s
Gross thickness, mm

1250
9.03
18

Effective thickness, teff mm

16.98

Internal Pressure, N/Mm^2


Surge Head, Hs m
Total Head, Htot m
Factor of safety
Check
Weight of steel, ton

3.02
40.16
307.91
2.65
OK
21

Segment #6
Static head
Length of penstock
Diameter, d, mm
Penstock flow velocity,V m/s
Gross thickness, mm

1250
9.03
20

Effective thickness, teff mm

18.94

Internal Pressure, N/Mm^2


Surge Head, Hs m
Total Head, Htot m
Factor of safety
Check
Weight of steel, ton

3.42
45.41
348.16
2.64
OK
23

267.75 m
35.00 m
1350
7.74
20

Diameter, d, mm
Penstock flow velocity,V m/s
Internal Pressure, N/Mm^2
Gross thickness, mm
Effective thickness, teff mm
Surge Head, Hs m
Total Head, Htot m
Factor of safety
Check
Weight of steel, ton
weight of steel
weight of steel with Wastage (5%)
Cost of steel, USD

Selected Diameter =
Section
Length of penstock of section, m
Static Head, m
Surge Head, m
Total Head, m
Pipe Thickness. mm
Pipe weight. Ton

Penstock pipe
Expansion Joints
Stifners, saddle, wear plate
Weight of 1.45 m dia pipe
Weight of 1 m dia pipe
Total weight of Steel
Total Cost of steel, USD

1121.20

1450
6.71
20

1550
5.87
22

1650
5.18
22

1750
4.61
25

1850
4.12
25

1950
3.71
28

18.18

19.38

20.58

21.78

22.98

24.18

25.37

3.02
40.16
307.91
2.75
OK
25

3.02
40.16
307.91
2.58
OK
27

3.02
40.16
307.91
2.67
OK
31

3.02
40.16
307.91
2.53
OK
33

3.02
40.16
307.91
2.72
OK
40

3.02
40.16
307.91
2.59
OK
42

3.02
40.16
307.91
2.76
OK
50

302.75 m
35.00 m
1350
7.74
22

Segment #7
Static head
Length of penstock

Elevation

Elevation

1086.20

1450
6.71
22

1550
5.87
25

1650
5.18
25

1750
4.61
28

1850
4.12
28

1950
3.71
30

20.30

21.65

23.01

24.36

25.72

27.07

28.43

3.42
45.41
348.16
2.71
OK
27

3.42
45.41
348.16
2.54
OK
29

3.42
45.41
348.16
2.72
OK
36

3.42
45.41
348.16
2.57
OK
38

3.42
45.41
348.16
2.72
OK
45

3.42
45.41
348.16
2.59
OK
48

3.42
45.41
348.16
2.64
OK
54

351.45 m
69.76 m

Elevation

1030.05

1250

1350

1450

1550

1650

1750

1850

1950

9.03
3.96
22

7.74
3.96
25

6.71
3.96
25

5.87
3.96
28

5.18
3.96
28

4.61
3.96
30

4.12
3.96
32

3.71
3.96
36

21.67

23.24

24.81

26.39

27.96

29.53

31.11

32.68

52.72
404.17
2.54
OK
51

52.72
404.17
2.69
OK
62

52.72
404.17
2.52
OK
67

52.72
404.17
2.65
OK
80

52.72
404.17
2.50
OK
85

52.72
404.17
2.54
OK
96

52.72
404.17
2.57
OK
109

52.72
404.17
2.75
OK
129

277
305
730218

326
369
882081

363
402
961225

410
455
1089938

436
503
1203093

513
539
1289963

549
640
1530931

614
722
1727929

1750 mm
Segment#1

Segment#2

159.22
51.4
7.7
59.13
8
58

539
16
15
5.10
8.74

124.02
105.0
15.8
120.75
12
68

Segment#3
176.63
157.0
23.6
180.55
16
129

Segment#4

Segment#5

75.75
232.8
34.9
267.66
22
76

Ton
Ton
Ton
Ton
Ton

584 Ton
1,397,277.11

Page 3of 3

35.00
267.8
40.2
307.91
25
40

Segment#6
35.00
302.75
45.4
348.16
28
45

Segment#7
69.76
351.45
52.72
404.17
30
96

Hydro Consult
CALCULATION SHEET
Job Nyadi Hydropower Project (NHP)
Subject Anchor Block Design
Calculated By:
Date
Checked By:
ANCHOR BLOCKChainage:
Length of Penstock
Weir Level
Anchor Block Level
Ground Level
Young's Modulus ,E
Design Discharge, Q
Nominal wall thicknesss, t
Pipe internal diameter,d
Pressure wave velocity, a
Velocity in Penstock, v
Critical time, Tc
Closure time, T
Nos of turbine units
Number of nozzle in each turbine units

E
Q
t
d
a
v
Tc
T

CB3
0+156.02
675.38
1381.50
1330.08
1331.08
200000
11.08
16.00
1750
976.236
4.61
1.38
6
3
2
30

m
masl
masl
masl
N/mm2
m3/sec
mm
mm
m/s
m/s
sec
sec

Angle of internal friction

Unitweight
g of concrete

gconcrete

3
24.00 kN/m

Unitweight of steel

gsteel

3
78.50 kN/m

Unitweight of soil

gsoil

3
18.00 kN/m

Friction coeff
Coefficien of friction of soli

f
m

0.25
0.50

for steel to rusty plates movement, ITDG, Pg 7-9


RESULTS:

Allowable bearing capacity

2
160.00 kN/m

Deflection angle in horz bend


Deflection angle in vert bend u/s
Deflection angle in vert bend d/s

11.241
16.97
35.28

D
a
b
1/2 the distance betn u/s pier to anchor block L1u

for boulder mixed soil

Expansion
Safe When Check against overturning
Safe When Check on bearing capacity
Safe When Check against sliding

Contraction
Safe When Check against overturning
Safe When Check on bearing capacity
Safe When Check against sliding

4.00 m

1/2 the distancebetn d/s pier to anchor block L1d


Distance between two consecutive support

4.00 m

piers

L2u

8.00 m

Distance to upstream expansion joint

L4u

65.89 m

Distance to d/s expansion joint

L4d

5.65 m

7
6

Distance between consecutive anchor blocks

65.24 m

Penstock clear cover by anchor at uphill face

1.00
6.00
7.30
6.00
9.00
4.00
2.00
0.00
1.000

As exp joints is just 2.0m d/s from anchor block face

4
3
2

Asume width of block


Length of block
Assume height of block at upstream end
Number of support pier
Assume height of block at downstream end
Assume depth of burried at upstream
Increase the downstream depth by factor
Buried depth of block at d/s face

B
L
hu
hd
h1
h2

m
m
m
m

0.010
Base width
Base thickness

7.50
1.00

0
-1.00

14.6 4.866667
29.2 48.6666667
0.4 4.055556 4.866667

m
m
Projection Depth =

Page 1of 2

1.00

3.00

5.00

7.00

9.00

Surge head
Gross head

hs
hgross

51.420 m

76.40 m

7.30

2.433

6.00

Total head

htotal

127.823 m

7.30

4.00

3.397

0.667

3.397

0.667

Assume centre of bend at 1/3 of 7.3m from upstream


Volume of block

Notes : Surge head for Pelton turbine

2.433

6.00

3
215.393 m

2.433 m

= 1X7.3/3
V = B(L/3*hu+0.5*2L/3*(hu-hd)+(PD+hd)*2/3L)-pi ((d+t

6.00

5169.44 kN

WB = 215.393429762801X24

0.01

WP = 3.142X1.766X0.016X78.5

WW = 3.142X1.75^2*9.8/4

7.30

F1u = (23.57+6.97)X4XCOS(3.142X16.9720801281178/

Weight of block

V
WB

Weight of pipe

WP

6.97 kN/m

Weight of water

WW

23.57 kN/m

1.Weight of pipe and water perp to the pipe

F1u

116.84 kN

7.30

F1d

99.72 kN

F1d = (23.57+6.97)X4XCOS(3.142X35.281999258953/1 2.433333

F2u

58.42 kN

F2u = 0.25X(6.97+23.57)X8XCOS(16.9720801281178X 2.433333

2. Frictional force per support pier


Total frictional force
3. Hydrostatic pressure in vertical bend
Hydrostatic pressure in horz bend

525.78 kN

= 58.42X9

F3 v

959.75 kN

F3 = 2gX3.142X127.822646281088X1.75^2/4XSIN(3.142X(35.281999258953-16.9720801281178)X0.5/180)

F3 H

590.780 kN

F4u

134.060 kN

F4d

76.920 kN

6. Frictional force in expansion joint

F6

175.000 kN

7. Hydrostatic force on exposed joint

F7u

95.120 kN

F7d

111.970 kN

F8

16.240 kN

F8H

9.990 kN

F8 = 2X200000^2/[3.142X0.016^2/4)XSIN((11.241)/2X3.142/180]

9. Force due to reduction in pipe

F9

0.000 kN

For no reduction of pipe

10 U hill ground
10.Uphill
d slope
l

i
Ka
F10

4. Force parallel to pipe


Force parallel to pipe

8. Dynamic force at bend(vertical)


Dynamic force at bend(horizontal)

F4u =6.97X65.892515510314XSIN(16.9720801281178X3.142/180)
F4d =23.57X5.65XSIN(35.281999258953X3.142/180)
F6 = 100X1.75
F7u = gX3.142X[127.822646281088-65.892515510314XSIN(16.9720801281178X3.142/180)]X(1.75+0.016)X0.016
F7d = gX3.142X127.822646281088X(1.75+0.016)X0.016
F8 = 2X11.08^2/[3.142X1.75^2/4)XSIN((35.281999258953-16.9720801281178)/2X3.142/180]

30.000
30 000
0.000

Ka should be calculated when 2-1 is greater than unity

0.00 kN

F10 = 18X2^2/2XCOS(30X3.142/180)X0X6

The force acts on 1/3 of 2 from botom of the block


0.667 m
Force components
X direction +ve right
Y direction +ve down
Forces
Expansion Contraction
Expansion
Contraction

Check against overturning

F1u =116.84

-34.110

-34.110

111.750

Allowable eccentricity eallowable

F1d =99.72
F2u =525.78
F3 v =959.75
F3 H =590.78
F4u =134.06
F4d =76.92
F6 =175
F7u =95.12

-57.600
502.890
422.640
57.870
128.230
62.800
24.530
90.980

-57.600
-502.880
422.640
57.870
128.230
62.800
-24.522
90.980

81.400
153.480
-861.680
-587.940
39.133
44.429
49.997
27.766

F7d =111.97

-91.410

-91.410

-64.670

F8 =16.24
F8H =9.99
F9 =0
F10 =0
WB =5169.44
Total force
Force at the bend

7.160
0.980
0.000
0.000
1114.960
1114.960
Ai
Xi

Centre of gravity from the u/s of the block


Thus the weight of block WB acts 3.397 from left most point

7.160
0.980
0.000
0.000
60.138
60.138
14.600
1.217
3.397 m

-14.580
-9.940
0.000
5169.440
4138.585
-1030.855
4.867
4.056

111.750

1.217 m

Expansion
81.400
Cases
18394.612
-153.480
Moment about left mo
4.445
-861.680 ver bend Center of force
-587.940 horz bend
0.795
39.133
Eccentricity
44.429
Safe
-49.997
27.766
Check on bearing capacity
Abase
-64.670
Area of base
43.800
-14.580 ver bend
-9.940 horz bend
Force at base
0.000
5169.440
Check against sliding
3731.631
Sum of vertical forces
-1437.809
Sum of horizontal forc
19.467
38.933
4.867

Page 2of 2

eallowable = 7.3/6
contraction
14239.892
3.816
0.166
Safe

156.203
Safe

96.821
Safe

4138.585
1114.960
Safe

3731.631
60.138
Safe

NYADI HYDROELECTRIC PROJECT


TURBINE DESIGN CALCULATION

Tunnel intake Level

1381.50 m

Generator Effeciency

97.00%

Transfermer efficiency

99.00%

Gross head, m
Dry season outage
Synchronous Speed

Turbine units

Turbine axis level

89.00%

347.50 m

Overall efficiency

85.47%

4%

Wet season outage

473 rpm
3 No

Length of tunnel

3950.00 m

Manning's coefficient

3.20 m

Height to the stringer

1.60 m

Number of nozzle

nj

50 Hz
2 No
650 m

Friction coeficient

0.0200 For shotcrete

Penstock Diameter

2
9.14 m

Sectional Area of tunnel

4%

Frequency

Length of penstock

0.014 For concrete

Tunnel Diameter

Probability excedence, %

1034.00 m

Turbine Efficiency

1.750 m

Tunnel Perimeter

11.427 m

40.00%
3
11.08 m /s

Design flow, m3/s

3
0.308 m /s

D/s release m3/s

Rated power Calculation


Gross head

Hg

347.500 m

Gross head = Turbine axis level - Tunnel intake level

Net head

339.370 m

Net Head = Gross head - Total head loss

Net power in kW

30000.00 kW

Net power in MW

PMW

30.00 MW

In MW Net power = 30000/1000

Net power in horse power

Php

40215 Hp

In Horse power Net power = 30000/0.746

Net power = Unit wt. of water x Overall efficiency x Design discharge x Net head

Page 1 of 3

NYADI HYDROELECTRIC PROJECT


TURBINE DESIGN CALCULATION
Synchronous Speed
Specific Speed for single Jet (assume)

20.00

Ref: High head power plants E. Mosonyi Vol 2/B; Pg 859, eqn 28/101

jet diameter

dj

0.172 m

Ref: High head power plants E. Mosonyi Vol 2/B; Pg 854, eqn 6/101

pitch circle diameter

1.862 m

Synchronous Speed

Ns

Synchronous Speed for multiple jets

Ns

397 rpm
561 rpm

no of pole pair

5.35

Take no of pole pair

6 Pairs

Calculated Synchronous Speed

473 rpm

Calculated Specific Speed (of runner with 2 jet)

37.6

Ns

Discharge in each unit, Qd/n

Ref: High head power plants E. Mosonyi Vol 2/B; Pg 856, eqn 16/101
Ref: High head power plants E. Mosonyi Vol 2/B; Pg 856, eqn 16/101

3
3 693 m /s
3.693

Qt

Ref: Water Power Engineering M.M Dandekar; Pg 310, eqn 13.3

Ref: Water Power Engineering M.M Dandekar; Pg 310, eqn 13.3


Ref: Water Power Engineering M.M Dandekar; Pg 310, eqn 13.4

Discharge per unit = 11.08/3

The actual velocity of jet at nozzle is given by

= K

Ref: High head power plants E. Mosonyi Vol 2/B; Pg 854, eqn 2/101
v

2 gH

Vj

Where Kv Varies from 0.96 to 0.99

79.151 m/s

Kv

Nozzle Velocity = KvXSQRT(2X9.81Xnet head)

0.97

The speed ratio Ku varies frpom 0.43 to 0.47

Ku

Bucket velocity = KuVj

34.827 m/s

1.406 m

1.500 m

Qj

3
1.847 m /s

0.44

Ref: Hydraulics and Fluid Mechanics P.N. Modi & S. M. Seth; Pg 1017
Bucket velocity = 0.44X79.151 m/s

Mean Diameter of the Pelton Wheel (pitch diameter) is

D =

Ref: Hydraulics and Fluid Mechanics P.N. Modi & S. M. Seth; Pg 1017

60 u
N
Adopt

Pitch Diameter = (60X34.827)/(3.142X)

Calculation of Nozzle Diameter Method 1


Nozzle Discharge Qt/nj
Diameter of Nozzle, D/m
Adopt Nozzle, diameter

Here, actual specific speed for single jet


Nozzle Area

a 90

Discharge per unit = 3.694/2 m3/s

0.172 m

Nozzle Diameter = SQRT(1.84666666666667X4)/(3.142X79.151)

0.180 m

This should be equal to or greater than calculated nozzle diameter

26.040 rpm

Ref: High head power plants E. Mosonyi Vol 2/B; Pg 856, eqn 16/101

2
0.0254 m

Nozzle area =3.142X(0.18X0.18)/4 m2

Calculated jet ratio

m
H

Number of buckets

8.33
20 No

Calculated jet ratio = 1.5/0.18


Number of buckets = 0.5X8.33333333333333+15

Page 2 of 3

NYADI HYDROELECTRIC PROJECT


TURBINE DESIGN CALCULATION
Calculation of Nozzle Diameter Method 2
Total Area of nozzle required for the discharge in unit

2
0.047 m

Adopt jet ratio

11

Total nozzle area = 3.693/79.151 m2


Varies from 11 to 14

Diameter of Nozzle, D/m

0.136 m

Adopt Nozzle, diameter

0.140 m

Nozzle Area

2
0.0146 m

Number of nozzle

nj

3.195 No

Number of nozzle (adopt)

nj

3 No

Calculated jet ratio

11

Number of buckets

20 No

Nozzle Discharge Qt/nj

Qj

Nozzle Diameter = 1.5/11 m

Nozzle area =3.142X(0.14X0.14)/4 m2


Required number of nozzle = 0.047/0.015

Calculated jet ratio = 1.5/0.14


Number of buckets = 0.5X10.714+15

3
1.231 m /s

Discharge per unit = 3.694/3 m3/s

Bucket Dimensions in meter


Parameters

Method 1

Method 2

Low

High

Low

High

B = (4 to 5)dj

Width

0.720

0.900

0.720

0.900

L = (2.4 to 3.2)dj

Length

0.432

0.576

0.432

0.576

C = (0.81 to 1.05)dj

Depth

0.146

0.189

0.146

0.189

l = (1.2 to 1.9)dj

0.216

0.342

0.216

0.342

M= (1.1 to 1.25)dj

0.198

0.225

0.198

0.225

1.932

2.076

1.932

2.076

4.760

5.057

4.760

5.057

Setting Parameters
Outer Diameter of the bucket, Do

D+L

Housing diameter (0.78+2.06Do)


Setting height (0.5 to 1 +Do-B/2)

hs

2.072

2.626

2.072

2.626

Free height (hs-B/2)

hf

1.712

2.176

1.712

2.176

Maximum water depth

1+Do

2.932

3.076

2.932

3.076

Ref: High head power plants E. Mosonyi Vol 2/B; Pg 971


Turbine Axis level from Maximum TWL hsp

hf+Do/2

2.678

3.21

2.678

3.214

Ref: High head power plants E. Mosonyi Vol 2/B; Pg 878


width of the tailwater flume, Bt

1.5+.75Do

2.949

3.057

2.949

3.057

Ref: High head power plants E. Mosonyi Vol 2/B; Pg 969


Maximum Tailwater Level, MTWL
Minimum Turbine Axis Level required
Turbine axis level provided
Turbine Axis level from max TWL, h sp provided

1030.200 m
hsp+MTWL

1033.414 m

Turbine Axis = 1030.2+3.214

1034.000 m
3.800

Page 3 of 3

2.004

Hydro Consult

Nyadi Hydropower Project

Nyadi Hydropower Project (NHP)


Subject: Tailrace tunnel
Data
Q design

3
11.08 m /sec

Q in each tunnel

3
11.08 m /sec

Let assume size B

3.60 m

Height of tunnel H

3.60

water depth D

H-B/2

1.90 m

slope sn

0.0013

1.80
750

0.020

Height of water at tunnel top dome (D-(H-B/2))

0.10 m

Angle subtended

0.0556 radian

Calculation

for D<(H-B/2)

for D>(H-B/2)

Wetted Area

6.84

Wetted Perimeter

7.40

Hydraulic Radius

0.92

Velocity limit

velocity normal

1.75

v =

1
R
n

2
3

1
2

3
11.85 m /sec

OK

Velocity

1.73 m/sec

Ok

Shield dn = 11RS

0.01 mm

Discharge

Summary
Breadth, B

3.60 m

Design Discharge Depth, H

1.90 m

D shape tunnel top curve depth

1.8 m

Total Height of Tunnel

3.60 m

Slope

1:750

Page 1 of 1

Hydro Consult

Nyadi Hydropower Project

Nyadi Hydropower Project (NHP)


Subject: Tailrace canal below turbine
Data
3
11.08 m /sec

Q design
Q in each canal
Assume size B
Height of tunnel H
water depth D
slope sn
n
Height of water at tunnel top dome
Angle subtended

3.693
2.00
2.00
1.30
0.001
0.014
0.30
0.304692654

Calculation
Area
Perimeter
Hydraulic Radius
Velocity limit

velocity normal

m3/sec
m
m
1000
m
radian

for D<(H-B/2) for D>(H-B/2)


2.59
4.61
0.56
3

v =

1
R
n

2
3

1
2

3.99 m3/sec OK
1.54 m/sec Ok
0.01 mm

Discharge
Velocity
Shield dn = 11RS
Summary
Breadth, B
Design Discharge Depth, H
D shape tunnel top curve depth
Total Height of Tunnel
Slope

2.00
1.30
1
2.00
1:1000

Page 1 of 1

m
m
m
m

Hydro Consult

Nyadi Hydropower Project

Nyadi Hydropower Project (NHP)


Fixing the level of powerhouse and tailrace
3
11.08 m /sec

Q design
1000 year flood level at Tailrace exit
Invert level of Tailrace tunnel outlet
Length of Main Tailrace

1027.00 m
1028.00 m
356.50 m

Slope of Tailrace (1 in)


Invert Level at 3.6m width Tailrace Start
Design discharge Tailrace water depth
Tailwater level
Calculated Height from turbine axis to tailrace WL
Turbine axis level calculated
Adopt Turbine Axis level

750.00
1028.48
1.90
1030.38
3.67
1034.05
1034.00

Adopted Height from turbine axis to tailrace WL


Provided floor level of PH

m
m
m
m
m
m
m

3.62 m
1032.50 m

Design discharge Tailrace water depth below turbine


Invert Level below Turbine

1.30
1029.08 m

Page 1 of 1

HEC-RAS Plan: Plan 01 River: Nyadi Reach: Nyadi PH site


Reach

Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site

River Sta

Profile

30
29
28
27
26
25
24
23
22
21
20
19
18
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1

Q100
Q100
Q100
Q100
Q100
Q100
Q100
Q100
Q100
Q100
Q100
Q100
Q100
Q100
Q100
Q100
Q100
Q100
Q100
Q100
Q100
Q100
Q100
Q100
Q100
Q100
Q100
Q100
Q100
Q100

Profile: Q100

Q Total

Min Ch El

W.S. Elev

Crit W.S.

E.G. Elev

E.G. Slope

Vel Chnl

(m3/s)

(m)

(m)

(m)

(m)

(m/m)

(m/s)

(m2)

(m)

475
475
475
475
475
475
475
475
475
475
475
475
475
475
475
475
475
475
475
475
475
475
475
475
475
475
475
475
475
475

1019.93
1018.68
1018.24
1017.93
1017.78
1017.06
1016.19
1015.3
1015.08
1014.3
1013.85
1013.96
1013.88
1013.29
1012.26
1012.03
1011.72
1010.92
1010.41
1010.13
1009.76
1008.59
1007.25
1007.24
1006.29
1006.23
1005.39
1004.23
1003.82
1003.44

1023.92
1022.47
1022.12
1021.54
1021.17
1021.18
1020.39
1018.82
1018.58
1017.86
1017.53
1017.15
1016.69
1015.94
1015.44
1014.41
1014.15
1013.94
1013.99
1013.48
1013.06
1011.6
1010.97
1010.32
1009.09
1008.46
1008.12
1007.47
1007.04
1006.56

1023.92
1022.47
1022.12
1021.54
1021.17
1021.18
1020.39
1018.82
1018.58
1017.86
1017.53
1017.15
1016.69
1015.94
1015.44
1014.41
1014.15

1025.33
1023.86
1023.47
1023.02
1022.66
1022.41
1021.46
1020.22
1019.65
1018.92
1018.55
1018.2
1017.53
1016.83
1016.35
1015.42
1015.1
1014.72
1014.6
1014.51
1014.1
1012.65
1012.12
1011.35
1010.01
1009.35
1009.07
1008.79
1008.26
1007.82

0.009748
0.010482
0.009608
0.011018
0.010554
0.008716
0.00907
0.010923
0.008574
0.008137
0.008146
0.00894
0.009325
0.010002
0.009353
0.009798
0.008896
0.008473
0.005705
0.009287
0.009768
0.00983
0.008714
0.010029
0.01038
0.01159
0.011264
0.013995
0.010915
0.010731

5.51
5.35
5.38
5.71
5.69
5.31
4.89
5.47
4.82
4.81
4.73
4.92
4.49
4.64
4.82
4.18
4.15
4.52
4.02
5.15
5.11
4.97
5.06
4.83
4.59
4.22
4.45
5.19
4.96
5.04

92.59
92.92
95.2
91.07
91
101.37
107.21
93.16
108.86
110.8
113.34
109.43
121.46
118.36
116.59
109.65
112.68
123.72
140.79
112.05
109.54
108.27
105.45
109.63
114.81
114.8
111.24
94.84
98.91
97.73

33.32
34.45
36.09
34.37
33.59
39.75
48.76
37.08
49.75
52.14
56.06
51.41
70.64
70.25
62.54
55.08
60.31
64.12
61.96
54.32
52.48
51.97
46.99
54.8
62.8
66.02
59.55
45.13
41.95
39.9

1013.58
1013.48
1013.06
1011.6
1010.97
1010.32
1009.09
1008.46
1008.12
1007.47
1007.04
1006.56

Page 1 of 2

Flow Area Top Width Froude # Chl Water depth


(m)

0.95
0.98
0.95
1.02
1
0.91
0.89
0.99
0.88
0.86
0.86
0.9
0.9
0.93
0.92
0.9
0.87
0.85
0.71
0.91
0.94
0.94
0.9
0.94
0.94
0.96
0.96
1.08
0.98
0.97

3.99
3.79
3.88
3.61
3.39
4.12
4.2
3.52
3.5
3.56
3.68
3.19
2.81
2.65
3.18
2.38
2.43
3.02
3.58
3.35
3.3
3.01
3.72
3.08
2.8
2.23
2.73
3.24
3.22
3.12

Tailrace

HEC-RAS Plan: Plan 01 River: Nyadi Reach: Nyadi PH site


Reach

Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site

River Sta

Profile

30
29
28
27
26
25
24
23
22
21
20
19
18
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1

Q2
Q2
Q2
Q2
Q2
Q2
Q2
Q2
Q2
Q2
Q2
Q2
Q2
Q2
Q2
Q2
Q2
Q2
Q2
Q2
Q2
Q2
Q2
Q2
Q2
Q2
Q2
Q2
Q2
Q2

Profile: Q2: 2 year return period flow

Q Total Min Ch El W.S. Elev Crit W.S. E.G. Elev


(m3/s)
200
200
200
200
200
200
200
200
200
200
200
200
200
200
200
200
200
200
200
200
200
200
200
200
200
200
200
200
200
200

(m)
1019.93
1018.68
1018.24
1017.93
1017.78
1017.06
1016.19
1015.3
1015.08
1014.3
1013.85
1013.96
1013.88
1013.29
1012.26
1012.03
1011.72
1010.92
1010.41
1010.13
1009.76
1008.59
1007.25
1007.24
1006.29
1006.23
1005.39
1004.23
1003.82
1003.44

(m)
1022.46
1021.16
1020.76
1020.21
1020.2
1019.77
1019.17
1017.61
1017.3
1016.5
1016.21
1016.01
1015.8
1015.05
1014.36
1013.4
1012.95
1012.76
1012.71
1012.43
1012.01
1010.54
1009.71
1009.27
1008.17
1007.62
1007.21
1006.54
1005.91
1005.37

(m)
1022.46
1021.16
1020.76
1020.21
1019.77
1019.17
1017.61
1017.3
1016.5
1016.21
1016.01
1015.8
1015.05
1014.36
1013.4
1012.95
1012.76
1012.43
1012.01
1010.54
1009.71
1009.27
1008.17
1007.62
1007.21
1006.54
1005.91
1005.37

(m)
1023.36
1021.99
1021.61
1021.07
1020.76
1020.65
1019.96
1018.41
1018.08
1017.35
1016.99
1016.76
1016.4
1015.6
1015.01
1014.04
1013.65
1013.39
1013.17
1013.09
1012.67
1011.21
1010.49
1009.93
1008.76
1008.16
1007.8
1007.23
1006.63
1006.12

Page 2 of 2

E.G. Slope

Vel Chnl

(m/m)
0.012536
0.012946
0.011859
0.01262
0.006111
0.011552
0.012188
0.011709
0.012149
0.012552
0.012148
0.011079
0.011736
0.011083
0.011414
0.010217
0.009434
0.012028
0.007771
0.009379
0.010431
0.011186
0.010734
0.011499
0.011979
0.014094
0.014116
0.013559
0.013406
0.013474

(m/s)
4.33
4.09
4.19
4.28
3.43
4.3
4.03
4.06
3.99
4.1
3.98
3.99
3.79
3.67
3.86
2.82
2.66
3.77
3.39
3.99
3.96
3.88
4.03
3.74
3.6
3.21
3.48
3.71
3.78
3.87

Flow

Top

Froude #

Area

Width

Chl

(m2)
48.04
50.07
50.31
49.3
61.44
49.2
51.44
51.57
51.92
49.59
52.29
54.55
61.03
63.19
57.83
58.88
56.94
57.8
68.25
60.24
58.77
57
52.86
57.49
61.04
61.94
59.22
54.94
53.61
52.48

(m)
27.48
31.07
30.71
29.26
29.06
29.75
35.63
32.41
34.17
31.47
35.79
38.93
56.1
56.25
46.12
45.39
38.72
47.32
47.08
45.02
44.39
43.09
36.42
44.73
53.15
59.42
52.88
40.45
38.09
35.78

0.98
0.99
0.96
1
0.72
0.96
0.95
0.95
0.96
0.98
0.96
0.93
0.94
0.91
0.93
0.83
0.79
0.93
0.76
0.86
0.91
0.93
0.92
0.93
0.93
0.97
0.98
0.98
0.99
0.99

Water depth
(m)

2.53
2.48
2.52
2.28
2.42
2.71
2.98
2.31
2.22
2.2
2.36
2.05
1.92
1.76
2.1
1.37
1.23
1.84
2.3
2.3
2.25
1.95
2.46
2.03
1.88
1.39
1.82
2.31
2.09
1.93

Tailrace

Hydro Consult
Headloss Calculation

Nyadi Hydropower Project


January 6, 2011
Sn

Description

Reference

Unit

Value

Turbine Discharge

Qt

Symbol

m3/sec

11.080

Orifice Discharge

Qo

m3/sec

15.512

m
m
m

1381.500
1034.000
1030.830

Wo

7.500

Ho

3.000

Normal water level at weir crest


Turbine Axis level
Normal Tail water level
1

Orifice
Width of the Orifice
Height of the Orifice

Coarse Trashrack
Trashrack coefficient

Ktr

thickness of the bar

2.420
m

clear spacing between the bars

angle with horizontal, a

0.010
0.150
30.000

Gravel trap
Length

Lg

3.000

Width

Wg

3.000

Height

hg

1.000

angle of bend

degree

0.000

radius of bend

rc

100.000

Bend

Fine Trashrack
thickness of the bar

0.010

clear spacing between the bars

0.050

angle with horizontal, a

72.000

trashrack coefficient

Ktr

2.420

Approach tunnel
Length

Lac

55.500

Width/ dia

Wac

3.000

tunnel height

hac

3.000

Slope

1 in 500

0.0020

SB Bifurcation
Length

Lac

60.000

Width/ dia

Wac

3.000

tunnel height

hac

3.000

Slope

1 in 100

0.0100

128.000

Settling basin
No of bay

Length

Lsb

Inlet transition length

Ltr

25.000

Cross section area

m2

31.000

Perimeter

22.500

Average width

Wtr

8.000

Average depth

htr

10.000

3.200

Lt

3937.000

Tunnel Intake
Intake (Bellmouth)
Diameter

Tunnel
Length

Page 1 of 7

Hydro Consult
Headloss Calculation

Nyadi Hydropower Project


January 6, 2011
Sn

Description

Reference

Symbol

Unit

Value
3.200

Diameter

Dt

Total height

Ht

3.200

Concrete lined length

Lcon

1200.000

Slope

St

1 in 500

0.0020

Bend 1
radius

equivalent circular diameter

10.000
3.100

Bend angle in degrees

angle

22.000

radius

10.000

equivalent circular diameter

3.000

Bend angle in degrees

angle

38.000

Bend 2

10 Penstock
Length

Lp

675.380

Diameter

Dp

1.750

11 Branching and Valve Losses


Length of the branching (Total)

Lbr

42.500

Diameter 1

Dp1

1.750

Diameter 2

Dp2

1.550

Diameter 3

Dp3

1.100

Branch bend angle


surface roughness

friction factor

From Moody's Chart


From Moody's Chart

mm

0.015

f
12.500

f
Lbr
Kv

Length of the branch of dia 3


Valve loss coefficient
12

60.000

Lbr

Length of the branch of dia 2


friction factor

degree

30.000
0.300

Monthly Flow
Jan

3.57

Poush

(m3/s)

Feb

3.23

Magh

(m3/s)

3.75
3.38

Mar

3.21

Falgun

(m3/s)

3.08

Apr

3.86

Chaitra

(m3/s)

3.34

May

6.85

Baishakh

(m3/s)

4.38

Jun

17.13

Jestha

(m3/s)

9.31

Jul

32.54

Ashar

(m3/s)

24.95

Aug

37.73

Shravan

(m3/s)

40.12

Sep

28.39

Bhadra

(m3/s)

35.34

Oct

15.69

Ashoj

(m3/s)

21.44

Nov

7.70

Kartik

(m3/s)

9.94

4.60

Mangsir

(m3/s)

5.45

Dec

Page 2 of 7

Hydro Consult
Headloss Calculation

Nyadi Hydropower Project


January 6, 2011
SN

Description

Formula

Symbol

Unit

Design Value

Baishakh
40.00%

Jestha
40.00%

Ashar
40.00%

Shravan
40.00%

Bhadra
40.00%

Asoj
40.00%

Kartik
40.00%

Mangsir
40.00%

Poush
40.00%

Magh
40.00%

Falgun
40.00%

Chaitra
40.00%

Turbine Discharge

Qt

m3/sec

11.080

4.708

10.404

11.080

11.080

11.080

11.080

11.036

6.462

4.442

3.818

3.313

Orifice Discharge

Qo

m3/sec

15.512

6.591

14.566

15.512

15.512

15.512

15.512

15.451

9.047

6.219

5.345

4.638

4.782

m
m
m

1381.500
1034.000
1030.830

1381.500
1034.000
1030.830

1381.500
1034.000
1030.830

1381.500
1034.000
1030.830

1381.500
1034.000
1030.830

1381.500
1034.000
1030.830

1381.500
1034.000
1030.830

1381.500
1034.000
1030.830

1381.500
1034.000
1030.830

1381.500
1034.000
1030.830

1381.500
1034.000
1030.830

1381.500
1034.000
1030.830

1381.500
1034.000
1030.830

7.500

Normal water level at weir crest


Turbine Axis level
Normal Tail water level

3.415

1 Orifice
Width of the Orifice

Wo

7.500

7.500

7.500

7.500

7.500

7.500

7.500

7.500

7.500

7.500

7.500

7.500

Height of the Orifice

Ho

3.000

3.000

3.000

3.000

3.000

3.000

3.000

3.000

3.000

3.000

3.000

3.000

3.000

Ao

m2

22.500

22.500

22.500

22.500

22.500

22.500

22.500

22.500

22.500

22.500

22.500

22.500

22.500

Vo

m/sec

0.689

0.293

0.647

0.689

0.689

0.689

0.689

0.687

0.402

0.276

0.238

0.206

0.213

ho

0.067

0.012

0.059

0.067

0.067

0.067

0.067

0.067

0.023

0.011

0.008

0.006

0.006

0.067

0.012

0.059

0.067

0.067

0.067

0.067

0.067

0.023

0.011

0.008

0.006

0.006

2.420

2.420

2.420

2.420

2.420

2.420

2.420

2.420

2.420

2.420

2.420

2.420

2.420
0.010

Area of the Orifice

Ao=Wo x Ho

Velocity through the orifice


Difference in river water and canal

a.

water elevation at orifice


Headloss

=(Vo^2)/(0.6^2*2*9.81)

TH1

Total Energy Level

1381.433

2 Coarse Trashrack
Ktr

Trashrack coefficient
[GDHIP pg 67 & 68]

a.

thickness of the bar

0.010

0.010

0.010

0.010

0.010

0.010

0.010

0.010

0.010

0.010

0.010

0.010

clear spacing between the bars

0.150

0.150

0.150

0.150

0.150

0.150

0.150

0.150

0.150

0.150

0.150

0.150

0.150

0.500

0.500

0.500

0.500

0.500

0.500

0.500

0.500

0.500

0.500

0.500

0.500

0.500

0.00079

0.00014

0.00070

0.00079

0.00079

0.00079

0.00079

0.00079

0.00027

0.00013

0.00009

0.00007

0.00008

0.735

0.312

0.691

0.735

0.735

0.735

0.735

0.732

0.429

0.295

0.253

0.220

0.227

0.001

0.000

0.001

0.001

0.001

0.001

0.001

0.001

0.000

0.000

0.000

0.000

0.000

Sin(ao)

angle with horizontal, a

ao=83

Trashrack Loss

=Ktr*(t/b)^(4/3)*SIN(ao)*(Vo^2)/(2*9.81) Losstr

Velocity at trashrack

m
m/sec

Headloss

TH2

Total Energy Level

1381.432

5 Gravel trap

a.

Length

Lg

3.000

3.000

3.000

3.000

3.000

3.000

3.000

3.000

3.000

3.000

3.000

3.000

3.000

Width

Wg

3.000

3.000

3.000

3.000

3.000

3.000

3.000

3.000

3.000

3.000

3.000

3.000

3.000

Height

hg

1.000

1.000

1.000

1.000

1.000

1.000

1.000

1.000

1.000

1.000

1.000

1.000

1.000

Manning's Coefficient

0.014

0.014

0.014

0.014

0.014

0.014

0.014

0.014

0.014

0.014

0.014

0.014

0.014

Average Sectional area at gravel trap

Ag

m2

2.035

2.035

2.035

2.035

2.035

2.035

2.035

2.035

2.035

2.035

2.035

2.035

2.035

Velocity inside the gravel trap

Vg

m/sec

9.911

3.008

6.647

7.079

7.079

7.079

7.079

7.051

4.129

2.838

2.439

2.117

2.182

Wetted Perimeter

Pg

6.713

6.713

6.713

6.713

6.713

6.713

6.713

6.713

6.713

6.713

6.713

6.713

6.713

Hydraulic Radius

Rg

0.303

0.303

0.303

0.303

0.303

0.303

0.303

0.303

0.303

0.303

0.303

0.303

0.303

Lossfr

0.16784

0.03030

0.14799

0.16784

0.16784

0.16784

0.16784

0.16652

0.05709

0.02697

0.01993

0.01501

0.01595

0.150

0.150

0.150

0.150

0.150

0.150

0.150

0.150

0.150

0.150

0.150

0.150

0.150

0.018

0.003

0.016

0.018

0.018

0.018

0.018

0.017

0.006

0.003

0.002

0.002

0.002

Friction loss

=(((Qo*n)/(Ag*Rg^(2/3)))^2)*Lg

Transition
Kc

Contraction coefficient
[GDHIP pg.58]

b.

Contraction Loss

=Kc*Vac^2/(2*9.81)

Losscon

radian

rc

Bend
angle of bend

q=50.5 o

radius of bend

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

100.000

100.000

100.000

100.000

100.000

100.000

100.000

100.000

100.000

100.000

100.000

100.000

100.000

Chezy's coefficient

C=(R^1/6)/n

58.542

58.542

58.542

58.542

58.542

58.542

58.542

58.542

58.542

58.542

58.542

58.542

58.542

Bend Coefficient

K=24(hq/r c)[sqrt(g)/C+2.5g/c 2]

Kb

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

=Kb*(Vg^2)/(2*9.81)

Lossbend

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.185

0.033

0.164

0.185

0.185

0.185

0.185

0.184

0.063

0.030

0.022

0.017

0.018

0.010

[Flow through open channels, KG Rangaraju, Pg. no 267]

c.

Bend Loss
Headloss

TH5

Total Energy Level

1381.246

4 Fine Trashrack
[GDHIP pg 67 & 68]

thickness of the bar

0.010

0.010

0.010

0.010

0.010

0.010

0.010

0.010

0.010

0.010

0.010

0.010

clear spacing between the bars

0.050

0.050

0.050

0.050

0.050

0.050

0.050

0.050

0.050

0.050

0.050

0.050

0.050

0.951

0.951

0.951

0.951

0.951

0.951

0.951

0.951

0.951

0.951

0.951

0.951

0.951

angle with horizontal, a


trashrack coefficient
a.

Trashrack loss
Velocity at trashrack

ao=72

Sin(ao)
Ktr

=Ktr*(t/b)^(4/3)*Sin(ao)*(G41^2)/(2*9.81) Lossftr

2.420

1.830

1.830

1.830

1.830

1.830

1.830

1.830

1.830

1.830

1.830

1.830

1.830

1.348

0.094

0.458

0.520

0.520

0.520

0.520

0.516

0.177

0.084

0.062

0.046

0.049

m/sec

5.762

2.448

5.410

5.762

5.762

5.762

5.762

5.739

3.360

2.310

1.985

1.723

1.776

Page 3 of 7

I:\ED\Jobs\OPEN\751220 Nyadi Implementation\03Reports\Final Review 30 MW as per Damodar Hydrology_23 Nov\VOLUME III - Technical Annex\Appendix D - Design Calculations\8.Energy calculation - Q=11.08 _40%.xlsx

Hydro Consult
Headloss Calculation

Nyadi Hydropower Project


January 6, 2011
SN

Description

Formula

Headloss

Symbol

Unit

TH4

Design Value

Baishakh
40.00%

1.348

Total Energy Level

0.094

Jestha
40.00%
0.458

Ashar
40.00%
0.520

Shravan
40.00%
0.520

Bhadra
40.00%
0.520

Asoj
40.00%
0.520

Kartik
40.00%
0.516

Mangsir
40.00%
0.177

Poush
40.00%
0.084

Magh
40.00%
0.062

Falgun
40.00%
0.046

Chaitra
40.00%
0.049

1379.899

6 Approach tunnel

a.

Approach tunnel Discharge

Qtunnel

m3/sec

12.188

5.179

11.445

12.188

12.188

12.188

12.188

12.140

7.108

4.886

4.200

3.644

3.757

Length

Lac

55.500

55.500

55.500

55.500

55.500

55.500

55.500

55.500

55.500

55.500

55.500

55.500

55.500

Width/ dia

Wac

3.000

3.000

3.000

3.000

3.000

3.000

3.000

3.000

3.000

3.000

3.000

3.000

3.000

tunnel height

hac

3.000

3.000

3.000

3.000

3.000

3.000

3.000

3.000

3.000

3.000

3.000

3.000

3.000

Slope

1 in 100

0.002

0.0020

0.0020

0.0020

0.0020

0.0020

0.0020

0.0020

0.0020

0.0020

0.0020

0.0020

0.0020

Manning's Coefficient

0.015

0.015

0.015

0.015

0.015

0.015

0.015

0.015

0.015

0.015

0.015

0.015

0.015

Sectional Area of flow

Aac

m2

8.035

8.035

8.035

8.035

8.035

8.035

8.035

8.035

8.035

8.035

8.035

8.035

8.035

Wetted Perimeter

Wac

10.713

10.713

10.713

10.713

10.713

10.713

10.713

10.713

10.713

10.713

10.713

10.713

10.713

Hydraulic Radius

Rac

0.750

0.750

0.750

0.750

0.750

0.750

0.750

0.750

0.750

0.750

0.750

0.750

0.750

Velocity of flow

Vac

m/sec

1.517

0.645

1.424

1.517

1.517

1.517

1.517

1.511

0.885

0.608

0.523

0.454

0.468

Lossfr

0.042

0.008

0.037

0.042

0.042

0.042

0.042

0.042

0.014

0.007

0.005

0.004

0.004

0.042

0.008

0.037

0.042

0.042

0.042

0.042

0.042

0.014

0.007

0.005

0.004

0.004

Friction loss

=Lac*((Qtunnel*n)/(Aac*Rac^(2/3)))^2

Headloss

TH6

Total Energy Level

1379.857

6 SETTLING BASIN bifurcation

a.

Approach tunnel Discharge

Qtunnel

m3/sec

6.094

2.662

2.662

2.662

2.662

2.662

2.662

2.662

2.662

2.662

2.662

2.662

2.662

Length

Lac

60.000

55.500

55.500

55.500

55.500

55.500

55.500

55.500

55.500

55.500

55.500

55.500

55.500

Width/ dia

Wac

3.000

3.000

3.000

3.000

3.000

3.000

3.000

3.000

3.000

3.000

3.000

3.000

3.000

tunnel height

hac

3.000

3.000

3.000

3.000

3.000

3.000

3.000

3.000

3.000

3.000

3.000

3.000

3.000

Slope

1 in 100

0.010

0.0020

0.0020

0.0020

0.0020

0.0020

0.0020

0.0020

0.0020

0.0020

0.0020

0.0020

0.0020

Manning's Coefficient

0.015

0.015

0.015

0.015

0.015

0.015

0.015

0.015

0.015

0.015

0.015

0.015

0.015

Sectional Area of flow

Aac

m2

8.035

8.035

8.035

8.035

8.035

8.035

8.035

8.035

8.035

8.035

8.035

8.035

8.035

Wetted Perimeter

Wac

10.713

10.713

10.713

10.713

10.713

10.713

10.713

10.713

10.713

10.713

10.713

10.713

10.713

Hydraulic Radius

Rac

0.750

0.750

0.750

0.750

0.750

0.750

0.750

0.750

0.750

0.750

0.750

0.750

0.750

Velocity of flow

Vac

m/sec

1.517

0.331

0.331

0.331

0.331

0.331

0.331

0.331

0.331

0.331

0.331

0.331

0.331

Lossfr

0.011

0.002

0.002

0.002

0.002

0.002

0.002

0.002

0.002

0.002

0.002

0.002

0.002

0.011

0.002

0.002

0.002

0.002

0.002

0.002

0.002

0.002

0.002

0.002

0.002

0.002

Friction loss

=Lac*((Qtunnel*n)/(Aac*Rac^(2/3)))^2

Headloss

TH6

Total Energy Level

1379.845

7 Settling basin
No of bay

Discharge per bay

m3/sec

Length

Lsb

6.094

2.589

5.722

6.094

6.094

6.094

6.094

6.070

3.554

2.443

2.100

1.822

1.878

128.000

128.000

128.000

128.000

128.000

128.000

128.000

128.000

128.000

128.000

128.000

128.000

128.000

25.000

25.000

25.000

25.000

25.000

25.000

25.000

25.000

25.000

25.000

25.000

25.000

25.000

0.015

0.015

0.015

0.015

0.015

0.015

0.015

0.015

0.015

0.015

0.015

0.015

0.015

Inlet transition length

Ltr

Manning's coefficient

Sectional Area of flow

Asb

m2

31.000

31.000

31.000

31.000

31.000

31.000

31.000

31.000

31.000

31.000

31.000

31.000

31.000

Wetted perimeter

Psb

22.500

22.500

22.500

22.500

22.500

22.500

22.500

22.500

22.500

22.500

22.500

22.500

22.500

Hydraulic Radius

Rsb

1.378

1.378

1.378

1.378

1.378

1.378

1.378

1.378

1.378

1.378

1.378

1.378

1.378

Velocity of flow

Vsb

m/sec

0.197

0.084

0.185

0.197

0.197

0.197

0.197

0.196

0.115

0.079

0.068

0.059

0.061

0.300

0.300

0.300

0.300

0.300

0.300

0.300

0.300

0.300

0.300

0.300

0.300

0.300
0.003

Inlet transition
Ktr

Transition coefficients
[GDHIP pg 58]

a.

Lossit

0.035

0.006

0.031

0.035

0.035

0.035

0.035

0.034

0.012

0.006

0.004

0.003

Average width

Wtr

8.000

8.000

8.000

8.000

8.000

8.000

8.000

8.000

8.000

8.000

8.000

8.000

8.000

Average depth

htr

10.000

10.000

10.000

10.000

10.000

10.000

10.000

10.000

10.000

10.000

10.000

10.000

10.000

Average area

Atr

m2

80.000

80.000

80.000

80.000

80.000

80.000

80.000

80.000

80.000

80.000

80.000

80.000

80.000

Hydraulic radius

Rtr

2.222

2.222

2.222

2.222

2.222

2.222

2.222

2.222

2.222

2.222

2.222

2.222

2.222

Transition loss

=Ktr*(Vac^2-Vsb^2)/(2*9.81)

b.

Friction loss within transition

=Lac*((Qtunnel*n)/(Aac*Rac^(2/3)))^2

Losstr

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

0.0000

c.

Friction loss

=Lsb*((Q*n)/(Asb*Rsb^(2/3)))^2

Lossfr

0.00073

0.00013

0.00064

0.00073

0.00073

0.00073

0.00073

0.00072

0.00025

0.00012

0.00009

0.00006

0.00007

0.150

0.150

0.150

0.150

0.150

0.150

0.150

0.150

0.150

0.150

0.150

0.150

0.150

0.006

0.001

0.005

0.006

0.006

0.006

0.006

0.006

0.002

0.001

0.001

0.001

0.001

0.041

0.007

0.036

0.041

0.041

0.041

0.041

0.041

0.014

0.007

0.005

0.004

0.004

[Friction loss calculation is done considering only one bay]

Outlet transition
Kc

Contraction coefficients
[GDHIP pg 58, for cylindrical quadrant contraction]

d.

Contraction loss
Headloss

=Kc*v^2/(2*9.81)

Losscon
TH7

Page 4 of 7

I:\ED\Jobs\OPEN\751220 Nyadi Implementation\03Reports\Final Review 30 MW as per Damodar Hydrology_23 Nov\VOLUME III - Technical Annex\Appendix D - Design Calculations\8.Energy calculation - Q=11.08 _40%.xlsx

Hydro Consult
Headloss Calculation

Nyadi Hydropower Project


January 6, 2011
SN

Description

Formula

Symbol

Unit

Design Value

Total Water Level

Baishakh
40.00%

Jestha
40.00%

Ashar
40.00%

Shravan
40.00%

Bhadra
40.00%

Asoj
40.00%

Kartik
40.00%

Mangsir
40.00%

Poush
40.00%

Magh
40.00%

Falgun
40.00%

Chaitra
40.00%

1379.815

8 Tunnel Intake
Intake (Bellmouth)

a.

Diameter

4.000

4.000

4.000

4.000

4.000

4.000

4.000

4.000

4.000

4.000

4.000

4.000

4.000

C/s area

m2

12.566

12.566

12.566

12.566

12.566

12.566

12.566

12.566

12.566

12.566

12.566

12.566

12.566

Velocity of flow

m/sec

Coefficient for well rounded bellmouth

C
Lossin

Intake loss
Headloss

TH8

0.882

0.375

0.828

0.882

0.882

0.882

0.882

0.878

0.514

0.353

0.304

0.264

0.272

0.100

0.100

0.100

0.100

0.100

0.100

0.100

0.100

0.100

0.100

0.100

0.100

0.100

0.004

0.001

0.003

0.004

0.004

0.004

0.004

0.004

0.001

0.001

0.000

0.000

0.000

0.004

0.001

0.003

0.004

0.004

0.004

0.004

0.004

0.001

0.001

0.000

0.000

0.000

Total Energy Level

1379.811

9 Tunnel
Length

Lt

3937.000

3937.000

3937.000

3937.000

3937.000

3937.000

3937.000

3937.000

3937.000

3937.000

3937.000

3937.000

3937.000

Diameter

Dt

3.200

3.200

3.200

3.200

3.200

3.200

3.200

3.200

3.200

3.200

3.200

3.200

3.200

Total height

Ht

3.200

3.200

3.200

3.200

3.200

3.200

3.200

3.200

3.200

3.200

3.200

3.200

3.200

Concrete lined length

Lcon

1200.000

1200.000

1200.000

1200.000

1200.000

1200.000

1200.000

1200.000

1200.000

1200.000

1200.000

1200.000

1200.000

Slope

St

1 in 500

0.002

0.002

0.002

0.002

0.002

0.002

0.002

0.002

0.002

0.002

0.002

0.002

0.002

Manning's coefficient for concrete lining

nl

0.015

0.015

0.015

0.015

0.015

0.015

0.015

0.015

0.015

0.015

0.015

0.015

0.015

Manning's coefficient for unlined tunnel

nu

0.022

0.022

0.022

0.022

0.022

0.022

0.022

0.022

0.022

0.022

0.022

0.022

0.022

Sectional Area

At

m2

9.141

9.141

9.141

9.141

9.141

9.141

9.141

9.141

9.141

9.141

9.141

9.141

9.141

Wetted Perimeter

Pt

11.427

11.427

11.427

11.427

11.427

11.427

11.427

11.427

11.427

11.427

11.427

11.427

11.427

Hydraulic Radius

Rt

0.800

0.800

0.800

0.800

0.800

0.800

0.800

0.800

0.800

0.800

0.800

0.800

0.800

Velocity of flow

Vt

m2/sec

1.212

0.515

1.138

1.212

1.212

1.212

1.212

1.207

0.707

0.486

0.418

0.362

0.374

a.

Friction loss in lined portion

=Lcon*((Qt*nl)/(At*Rt^(2/3)))^2

Lossfr

0.534

0.096

0.471

0.534

0.534

0.534

0.534

0.530

0.182

0.086

0.063

0.048

0.051

b.

Friction loss in unlined portion

=(Lt-Lcon)*((Qt*nu)/(At*Rt^(2/3)))^2

Lossfr

2.621

0.473

2.311

2.621

2.621

2.621

2.621

2.600

0.891

0.421

0.311

0.234

0.249

10.000

Bend 1
[GDHIP pg 62 & 63]

c.

radius

10.000

10.000

10.000

10.000

10.000

10.000

10.000

10.000

10.000

10.000

10.000

10.000

equivalent circular diameter

3.100

3.100

3.100

3.100

3.100

3.100

3.100

3.100

3.100

3.100

3.100

3.100

3.100

radius/ diameter ratio

r/d

3.226

3.226

3.226

3.226

3.226

3.226

3.226

3.226

3.226

3.226

3.226

3.226

3.226

First coefficient

k1

0.0910

0.0910

0.0910

0.0910

0.0910

0.0910

0.0910

0.0910

0.0910

0.0910

0.0910

0.0910

0.0910

Bend angle in degrees

angle

22.000

22.000

22.000

22.000

22.000

22.000

22.000

22.000

22.000

22.000

22.000

22.000

22.000

Second coefficient

k2

0.388

0.388

0.388

0.388

0.388

0.388

0.388

0.388

0.388

0.388

0.388

0.388

0.388

Bend coefficient

Kb

0.035

0.035

0.035

0.035

0.035

0.035

0.035

0.035

0.035

0.035

0.035

0.035

0.035

0.003

0.000

0.002

0.003

0.003

0.003

0.003

0.003

0.001

0.000

0.000

0.000

0.000

10.000

Bend loss

=Kb*Vt^2/(2*9.81)

Lossbend

Bend 2
[GDHIP pg 62 & 63]

d.

radius

10.000

10.000

10.000

10.000

10.000

10.000

10.000

10.000

10.000

10.000

10.000

10.000

equivalent circular diameter

3.000

3.100

3.100

3.100

3.100

3.100

3.100

3.100

3.100

3.100

3.100

3.100

3.100

radius/ diameter ratio

r/d

3.333

3.226

3.226

3.226

3.226

3.226

3.226

3.226

3.226

3.226

3.226

3.226

3.226

First coefficient

k1

0.0867

0.0910

0.0910

0.0910

0.0910

0.0910

0.0910

0.0910

0.0910

0.0910

0.0910

0.0910

0.0910

Bend angle in degrees

angle

38.000

38.000

38.000

38.000

38.000

38.000

38.000

38.000

38.000

38.000

38.000

38.000

38.000

Second coefficient

k2

0.604

0.604

0.604

0.604

0.604

0.604

0.604

0.604

0.604

0.604

0.604

0.604

0.604

Bend coefficient

Kb

0.052

0.055

0.055

0.055

0.055

0.055

0.055

0.055

0.055

0.055

0.055

0.055

0.055

0.004

0.001

0.004

0.004

0.004

0.004

0.004

0.004

0.001

0.001

0.000

0.000

0.000

0.571

2.788

3.162

3.162

3.162

3.162

3.137

1.075

0.508

0.375

0.283

0.300

Bend loss

=Kb*Vt^2/(2*9.81)

Headloss

Lossbend

TH9

3.161

Total Energy Level

1376.650

10 Penstock
Length

Lp

675.380

675.380

675.380

675.380

675.380

675.380

675.380

675.380

675.380

675.380

675.380

675.380

675.380

Diameter

Dp

1.750

1.750

1.750

1.750

1.750

1.750

1.750

1.750

1.750

1.750

1.750

1.750

1.750

Sectional area

Ap

m2

2.405

2.405

2.405

2.405

2.405

2.405

2.405

2.405

2.405

2.405

2.405

2.405

2.405

Wetted Perimeter

Pp

5.498

5.498

5.498

5.498

5.498

5.498

5.498

5.498

5.498

5.498

5.498

5.498

5.498

Hydraulic Radius

Rp

0.438

0.438

0.438

0.438

0.438

0.438

0.438

0.438

0.438

0.438

0.438

0.438

0.438

Velocity of flow

Vp

m/sec

4.607

1.957

4.326

4.607

4.607

4.607

4.607

4.588

2.687

1.847

1.587

1.377

1.420

0.100

0.100

0.100

0.100

0.100

0.100

0.100

0.100

0.100

0.100

0.100

0.100

0.100

0.108

0.020

0.095

0.108

0.108

0.108

0.108

0.107

0.037

0.017

0.013

0.010

0.010

Well rounded entrance


Ke

Entrance coefficient
a.

Entrance loss

=Ke*(Vp^2)/(2*9.81)

Lossent

Page 5 of 7

I:\ED\Jobs\OPEN\751220 Nyadi Implementation\03Reports\Final Review 30 MW as per Damodar Hydrology_23 Nov\VOLUME III - Technical Annex\Appendix D - Design Calculations\8.Energy calculation - Q=11.08 _40%.xlsx

Hydro Consult
Headloss Calculation

Nyadi Hydropower Project


January 6, 2011
SN

Description

Formula

Symbol

No of bend

nos
Kb

Total Bend coefficient


b.

Bend loss

Unit

=Kb*(Vp^2)/(2*9.81)

Lossbend

=(f*Lp*Vp^2)/(2*9.81*Dp)

Lossfr

Design Value

Baishakh
40.00%

Jestha
40.00%

Ashar
40.00%

Shravan
40.00%

Bhadra
40.00%

Asoj
40.00%

Kartik
40.00%

Mangsir
40.00%

Poush
40.00%

Magh
40.00%

Falgun
40.00%

Chaitra
40.00%

7
0.415

0.415

0.415

0.415

0.415

0.415

0.415

0.415

0.415

0.415

0.415

0.415

0.415

0.449

0.081

0.396

0.449

0.449

0.449

0.449

0.445

0.153

0.072

0.053

0.040

0.043

0.01230

0.0123

0.0123

0.0123

0.0123

0.0123

0.0123

0.0123

0.0123

0.0123

0.0123

0.0123

0.0123

5.134

0.927

4.527

5.134

5.134

5.134

5.134

5.094

1.746

0.825

0.610

0.459

0.488

5.691

1.027

5.018

5.691

5.691

5.691

5.691

5.646

1.936

0.915

0.676

0.509

0.541

Wall friction
Friction factor
c.

Friction loss

Headloss

TH10

Total Energy Level

1370.959

11 Branching and Valve Losses


Length of the branching

Lbr

42.500

42.500

42.500

42.500

42.500

42.500

42.500

42.500

42.500

42.500

42.500

42.500

42.500

Diameter 1

Dp1

1.750

1.750

1.750

1.750

1.750

1.750

1.750

1.750

1.750

1.750

1.750

1.750

1.750

Diameter 2

Dp2

1.550

1.550

1.550

1.550

1.550

1.550

1.550

1.550

1.550

1.550

1.550

1.550

1.550

Veloctiy in the branch-2

Vbr

3.657

1.957

4.326

4.607

4.607

4.607

4.607

4.588

2.687

1.847

1.587

1.377

1.420

Veloctiy in the branche-3

Vbr

3.630

First contraction [D1 to D2]


a.

Contraction coefficient

=0.42*(1-(Dp2/Dp1)^2)

Kbr

Branch contraction loss

=Kbr*Vbr^2/(2*9.81)

Lossbr

0.091

0.091

0.091

0.091

0.091

0.091

0.091

0.091

0.091

0.091

0.091

0.091

0.091

0.098

0.018

0.086

0.098

0.098

0.098

0.098

0.097

0.033

0.016

0.012

0.009

0.009

[Hydropower Development 8, hydraulic design (Lysne) pg no. 99]

Branch bend angle

c.

60.000

60.000

60.000

60.000

60.000

60.000

60.000

60.000

60.000

60.000

60.000

60.000

60.000

Radius to Diameter ratio

r/d

2.000

2.000

2.000

2.000

2.000

2.000

2.000

2.000

2.000

2.000

2.000

2.000

2.000

Branch bend loss coefficient

Kbb

0.109

0.109

0.109

0.109

0.109

0.109

0.109

0.109

0.109

0.109

0.109

0.109

0.109

0.075

0.021

0.104

0.118

0.118

0.118

0.118

0.117

0.040

0.019

0.014

0.011

0.011

Branch bend loss

=Kbb*Vbr^2/(2*9.81)

Lossbb

friction factor

From Moody's Chart

0.0123

0.0123

0.0123

0.0123

0.0123

0.0123

0.0123

0.0123

0.0123

0.0123

0.0123

0.0123

0.0123

Lbr

12.500

12.500

12.500

12.500

12.500

12.500

12.500

12.500

12.500

12.500

12.500

12.500

12.500

0.068

0.019

0.095

0.107

0.107

0.107

0.107

0.106

0.036

0.017

0.013

0.010

0.010

Length of the branch


d.

friction loss in first section


friction factor

=f*Lbr*Vbr^2/(2*9.81*Dp2)

Lossfr

From Moody's Chart

0.0123

0.0123

0.0123

0.0123

0.0123

0.0123

0.0123

0.0123

0.0123

0.0123

0.0123

0.0123

0.0123

Lbr

30.000

30.000

30.000

30.000

30.000

30.000

30.000

30.000

30.000

30.000

30.000

30.000

30.000

0.248

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

Length of the branch


e.

friction loss in second section

f.

Valve loss

=f*Vbr*Lbr^2/(2*9.81*Dp3)

Lossfr
Kv

Valve loss coefficient


=Kv*Vbr^2/(2*9.81)

Lossv

0.300

0.300

0.300

0.300

0.300

0.300

0.300

0.300

0.300

0.300

0.300

0.300

0.300

0.204

0.059

0.286

0.324

0.324

0.324

0.324

0.322

0.110

0.052

0.039

0.029

0.031

0.117

0.571

0.648

0.648

0.648

0.648

0.643

0.220

0.104

0.077

0.058

0.062

[GDHIP pg no. 64 for Butterfly valves]

Headloss

TH11

0.692

Total Energy Level

1370.267

Headloss in headworks

Hh

1.685

0.155

0.756

0.857

0.857

0.857

0.857

0.850

0.291

0.138

0.102

0.077

0.081

Headloss in tunnel

Ht

3.165

0.571

2.791

3.165

3.165

3.165

3.165

3.141

1.077

0.509

0.376

0.283

0.301

Headloss in penstock and branching

Hp

6.383

1.144

5.589

6.339

6.339

6.339

6.339

6.289

2.156

1.019

0.753

0.567

0.602

11.233

1.871

9.136

10.361

10.361

10.361

10.361

10.280

3.525

1.665

1.230

0.926

0.985

Total Headloss

Check on power generation


Gross head
Net head
Percentage headloss
Power generated

m
m
KW

347.500
336.267
3.23%
32127.840

347.500
345.629
0.54%
14031.026

Page 6 of 7

347.500
338.364
2.63%
30356.693

347.500
337.139
2.98%
32211.146

347.500
337.139
2.98%
32211.146

347.500
337.139
2.98%
32211.146

347.500
337.139
2.98%
32211.146

347.500
337.220
2.96%
32091.702

347.500
343.975
1.01%
19167.723

347.500
345.835
0.48%
13245.991

347.500
346.270
0.35%
11400.255

347.500
346.574
0.27%
9900.726

347.500
346.515
0.28%
10205.280

I:\ED\Jobs\OPEN\751220 Nyadi Implementation\03Reports\Final Review 30 MW as per Damodar Hydrology_23 Nov\VOLUME III - Technical Annex\Appendix D - Design Calculations\8.Energy calculation - Q=11.08 _40%.xlsx

NYADI HYDROPOWER PROJECT, FEASIBILITY STUDY


POWER AND OUTPUT ENERGY CALCULATION
Gross head, m

347.50 m

Overall efficiency

85.47%

Dry season outage

4%

Wet season outage

4%

D/s release m3/s

0.31 m3/s

Length of tunnel

3937.0 m

Turbine

Gen.

Transformer

Overall

Shotcreted tunnel

2737.0 m

90.50%

97.00%

99.50%

87.35%

Concrte lined tunnel

1200.0 m

89.00%

97.00%

99.00%

85.47%

Generation

Dry season

Wet season

capacity

energy

energy

(kW)

(kWh)

(kWh)

Length of penstock

675.4 m

Manning's coefficient

0.015 For concrete

Friction coeficient

0.022 For shotcrete

Tunnel Diameter

3.20

Area

Height to the stringer

1.60

Perimeter

Adopt

9.14 m2
11.43 m

Probability excedence, %

40.00%

Design flow, m /s

11.08

Penstock Diameter, m

1.75
Flow

Month
(Nepali)

Nyadi

Available

Intake Flow flow in Siuri

available in

Available

Operating

Siuri

Flow

days

Design flow

Headloss

Headloss

Headloss

Total

HW

HRT

Penstok

Headloss

Net head

Tailrace
(m3/s)

Baishakh
Jestha
Ashar
Shravan
Bhadra
Ashoj
Kartik
Mangsir
Poush
Magh
Falgun
Chaitra

(m3/sec)

4.38
9.31
24.94
40.12
35.34
21.44
9.94
5.45
3.75
3.38
3.08
3.34

(m3/s)

(m3/s)

(m3/s)

0.68

0.64

4.71

31

4.71

0.155

0.571

1.144

1.871

345.63

13642.61

9,744,099

1.62

1.40

10.40

31

10.40

0.756

2.791

5.589

9.136

338.36

29516.00

21,081,508

3.87

1.40

26.04

32

11.08

0.857

3.165

6.339

10.361

337.14

30000.00

22,118,400

7.46

1.40

41.21

31

11.08

0.857

3.165

6.339

10.361

337.14

30000.00

21,427,200

7.83

1.40

36.43

31

11.08

0.857

3.165

6.339

10.361

337.14

30000.00

21,427,200

4.62

1.40

22.54

31

11.08

0.857

3.165

6.339

10.361

337.14

30000.00

21,427,200

2.28

1.40

11.04

30

11.04

0.850

3.141

6.289

10.280

337.22

30000.00

20,736,000

1.36

1.32

6.46

29

6.46

0.291

1.077

2.156

3.525

343.98

18637.11

1.04

1.00

4.44

30

4.44

0.138

0.509

1.019

1.665

345.83

12879.31

8,902,178

0.79

0.75

3.82

29

3.82

0.102

0.376

0.753

1.230

346.27

11084.67

7,406,330

0.58

0.54

3.31

30

3.31

0.077

0.283

0.567

0.926

346.57

9626.65

6,653,939

0.43

0.39

3.42

30

3.42

0.081

0.301

0.602

0.985

346.52

9922.77

6,858,620

12,452,572

Maximum Power Generation, kW

30,000.00

Total seasonal Energy, kWh

29,821,067

Annual generation, GWh

29.82

Total energy, GWh

150,414,178
150.41
180.24

Ratio of wet season energy with dry season energy

5.04

Page 7 of 7

GEOTECHNICAL DESIGN
OF
UNDERGROUND STRUCTURES

Hydro Consult

Nyadi Hydropower Project


Feasibility Study Volume III

APPENDIX E
OPTIMIZATION STUDY

NYADI HYDROPOWER PROJECT


FEASIBILITY STUDY

October, 2010

Nyadi Hydropower Limited

Hydro Consult

Nyadi Hydropower Project


Feasibility Study Volume III

Tables of Contents
1. plant capacity optimization ..................................................................................................... 2
1.1

Introduction ..................................................................................................................... 2

1.2

Objectives ........................................................................................................................ 2

1.3

Approach and Methodology ............................................................................................... 2

1.4

Hydrology ........................................................................................................................ 3

1.5

Plant Capacity Ranges ........................................................................................................ 3

1.6

Conceptual Layout ............................................................................................................ 4

1.7

Energy Production............................................................................................................. 6

1.8

Cost Estimate ................................................................................................................... 6

1.9

Benefit Cost Analysis for Various Installed Capacities........................................................... 7

1.10

Result of Benefit Cost Analysis ........................................................................................... 8

1.11

Conclusion and Recommendation ...................................................................................... 8

List of table and Figures


Table 1.1 Intake site average monthly flows in m3/s ........................................................................... 3
Table 1.2 Plant Capacity Ranges ............................................................................................... 3
Table 1.3 Project Structures Details ................................................................................................. 5
Table 1.4 Energy Production........................................................................................................... 6
Table 1.5 Comparison of the base project costs for various installed Capacities .................................. 7
Table 1.6 Financial Indicators for various installed capacities ............................................................. 8
Figure 3-1-1 Optimization Curves EIRR Vs percentage exceedance ..................................................... 8

Hydro Consult

Nyadi Hydropower Project


Feasibility Study Volume III

1. PLANT CAPACITY OPTIMIZATION


1.1 Introduction
The plant capacity is dependent primarily on the discharge in the river if other factors are pre-assumed
to be constant. Discharge of varying exceedance is required for determining the size of structures which
ultimately impact on the associated costs and benefits. Thus this optimization chapter deals with the
study of comparative costs and benefits of various discharges of varying exceedance flows in order to
determine the most economical installed capacity of the plant.

1.2 Objectives
The main objective of optimization is to determine the optimum plant capacity at which the discharge
will produce maximum benefit. The benefit is revenue from sales of the generated energy of the power
plant. It is a comprehensive analysis of cost benefits analysis and fixing the optimum capacity of project.

1.3 Approach and Methodology


The selection of the optimum plant capacity is determined from the economic and financial indicators
such internal rate of return, benefit cost ratio and optimum utilisation of natural resources.
The Nyadi Khola is a steep River with perennial discharge and gross head available within the study area
is sufficient to produce power ranging from 18.50 MW to 50.10 MW. From the flow duration curve as
discussed in section 2.3, it has been determined that the discharges available to divert at the intake vary
from 6.74 m3/sec to 18.50 m3/sec (including the tailrace water of Siuri Hydroelectric Project) for the
optimization purpose which would produce plant capacities from 18.50 MW to 50.10 MW respectively.
In general practice, more discharge is diverted than design discharge for flushing, which will not consider
for optimization purposes. It was assumed that plant capacity below and above these discharges would
yield relatively lower returns, therefore the optimization study was limited to the above range.
The procedure followed for each option during the optimization is described below:
1. Determination of conceptual layout of the scheme.
2. Determination of discharge options (as explained above) based on hydrology of the river at
headworks and additional flow available from Siuri tailrace.
3. Determination of gross head of the scheme.
4. Preliminary design of the structures like weir with orifice type frontal intake and bottom sluice
with two radial gates, gravel trap, intake tunnel, settling basin with flushing arrangement, surge
shaft, underground powerhouse with access tunnel and tailrace tunnel and Provision of tapping
Siuri tailrace flow.
5. Determination of optimum size of headrace tunnel and penstock pipe.
6. Determination of head loss and computation of energy based on the diversion discharge.
7. Determination of the cost of individual structure and the total cost of the project.
8. Computation of benefit-cost analysis and determination of financial indicators for each option.

Hydro Consult

Nyadi Hydropower Project


Feasibility Study Volume III

1.4 Hydrology
Hydrology is the prime factor on which energy and revenue are based. The main purpose of the
optimization is to determine the optimum discharge from techno-economic point of view. The
optimization has been carried out based on mean daily flow available in the river. Long-term average
monthly flow of Nyadi intake is calculated by correlating with flow data (DHM) of Seti River, gauge
reading data of Nyadi HP and available flow data in Siuri tailrace (as per feasibility report of Siuri SHP),
which are presented in Table 1.1.
Table 1.1 Intake site average monthly flows in m3/s
Nyadi at intake
(m3/sec)

Siuri Tailrace
(m3/sec)

Combined discharge
(m3/sec)

Baishakh

4.38

0.64

5.02

Jestha

9.31

1.40

10.71

Ashar

24.95

1.40

26.35

Shravan

40.12

1.40

41.52

Bhadra

35.34

1.40

36.74

Asoj

21.44

1.40

22.84

Kartik

9.94

1.40

11.34

Mangsir

5.45

1.32

6.77

Poush

3.75

1.00

4.75

Magh

3.38

0.75

4.13

Falgun

3.08

0.54

3.62

Chaitra

3.34

0.39

3.73

Month

There will be downstream riparian release of 10% of the minimum mean monthly flow for fish and
aquatic life which is equivalent to 0.31 m3/sec.

1.5 Plant Capacity Ranges


For optimization, different options are determined for probability of exceedance flow ranging from 30%
to 50%. It is obvious that lower the probability of exceedance, the higher will be the plant capacity and
hence higher energy generation. It is however not mandatory that the highest plant capacity will be most
optimum scheme. Thus, the ranges of plant capacities were determined by the design discharge at
various probabilities of exceedance, the corresponding net head and overall efficiency (85.47%). The
plant capacity for different probability of exceedance have been presented and listed in Table 1.2.
Table 1.2 Plant Capacity Ranges
Plant
capacity(MW)
18.50
22.40
30
36.30
50.10

Rated Discharge
(m3/s)
6.74
8.16
11.08
13.26

Probability of
exceedance (%)
50
45
40
35

18.50

30

Gross Head
(m)
333.90
333.90
333.90
333.90
333.90

Head loss
(m)
5.76
5.63
10.36
7.351

Net Head
(m)
328.13
328.27
323.54
326.59

10.66

323.24

Hydro Consult

Nyadi Hydropower Project


Feasibility Study Volume III

1.6 Conceptual Layout


The concept of the project layout is proposed to maximize the discharge and head within the project
boundary. The headworks area lies at upstream of the confluence of Nyadi and Siuri Khola. Tailrace
water of Siuri Khola Hydropower Project is also used in this project along the left bank of the Nyadi
River via pumping mechanism.
The headworks structures will comprise of concrete diversion weir with bottom sluice and two radial
gates, frontal intake with orifices, gravel trap and intake tunnel. All of these structures lie on the right
bank of the Nyadi Khola. There will be two bifurcating tunnels to feed the diverted water to
underground settling basins with flushing arrangement. Then, discharge will be passed through 3,937m
long headrace tunnel following the ridge of the hill Sangla and Nana village. A surge shaft with surge shaft
adit will be provisioned at the end of Headrace tunnel near Nana village. Steel penstock pipe with
surface penstock and drop shaft will connect the headrace tunnel with underground powerhouse
located inside the hill on the right bank near Thulobeshi village. The powerhouse comprises of three
units of horizontal axis pelton turbines, generators, transformers and other necessary accessories. A
switchyard located at foot of the hill on the right bank close to powerhouse will connect to 132 kV
Transmission lines of length of about 7km which will evacuate the generated electricity to the proposed
NEA Hub at Tunikharka.
A 10.50 km long access road is required to connect the headworks with powerhouse and existing
Besishahar- Chame road at Thakanbeshi at the right bank of the Marsyangdi River. Additionally, 3 km
link road will be required to connect surge adit outlet from the road to Headworks. Besides, a 52 m
long bridge has been proposed to connect the two sides of the Marsyangdi River along the road
alignment at Thakanbeshi. The details of structures for each of the options are presented in Table 3.3.

Hydro Consult

Nyadi Hydropower Project


Feasibility Study Volume III

Table 1.3 Project Structures Details


Description

18.50 MW

22.40 MW

30.00 MW

36.30 MW

50.10 MW

Weir Crest Level


Weir Crest Length
Weir Type
Bottom Sluice Unit
Intake

1381.50 masl
14 m
Concrete Weir
Two
Frontal with
orifice
2
2.25m*3.50m
57m*2.4m*2.4m

1381.50 masl
14 m
Concrete Weir
Two
Frontal with
orifice
3
2.25m*3.50m
57m*2.6m*2.6m

1381.50 masl
14 m
Concrete Weir
Two
Frontal with
orifice
3
2.25m*3.50m
57m*3m*3m

1381.50 masl
14 m
Concrete Weir
Two
Frontal with
orifice
4
2.25m*3.50m
57m*3.4m*3.4m

1381.50 masl
14 m
Concrete Weir
Two
Frontal with
orifice
4
2.25m*4.50m
57m*4m*4m

84m*8m*8.50m

101m*8m*9m

128m*8m*10.3m

165m*8m*11.3m

230m*8m*12.8m

3981 m

3964 m

3937m

3900 m

3835m

3.2m

3.2m

3.2 m

3.5 m

3.8m

26.26m
5m

27.63 m
5m

29.66m
5m

32.08 m
5m

32.64m
5m

476 m
200m

476 m
200m

476 m
200m

476 m
200m

476m
200m

1550mm

1750mm

1750mm

2150mm

2250mm

19.00 mm
U/G
Horizontal Axis
Pelton Turbine
3 nos.

19.00mm
U/G
Horizontal Axis
Pelton Turbine
3nos.

19.00mm
U/G
Horizontal Axis
Pelton Turbine
3nos.

22.00mm
U/G
Horizontal Axis
Pelton Turbine
4nos.

22.00mm
U/G
Horizontal Axis
Pelton Turbine
4nos.

12m*53 m
225.85m*3.2m*3
.2 m
13.5 KM
52m

14m*53 m
225.85m*3.4m*3
.4m
13.5 KM
52m

14m*53 m
225.85m*3.6m*
3.6m
13.5 KM
52m

15m*64 m
225.85m*
3.8m*3.8m
13.5 KM
52m

225.85m*
4.2m*4.2m
13.5 KM
52m

132kV, 7 KM,
NEA Hub

132kV, 7 KM,
NEA Hub

132kV, 7 KM,
NEA Hub

132kV, 7 KM,
NEA Hub

132kV, 7 KM,
NEA Hub

No. of Orifice
Orifice Size
Intake Tunnel
Settling Basin
Cavern
Headrace Tunnel
Length
Headrace Tunnel
Diameter
Surge Shaft Height
Surge Shaft
Diameter
Surface Penstock
Drop Shaft and
Horizontal parts
Diameter
Average Thickness
Powerhouse
Turbine Type
No of Units
Powerhouse
Cavern Size (B*L)
Tailrace Tunnel
(L*B*H)
Access road
Bridge Over
Marsyangdi River
Transmission Line

15m*64 m

Hydro Consult

Nyadi Hydropower Project


Feasibility Study Volume III

1.7 Energy Production


Based on the net head, turbine discharge and overall efficiency of the plant, the energy production in a
year has been calculated. An outage of 4% has been estimated for transmission loss, self consumption
and plant shut down during maintenance periods. Estimated power consumption for rural electrification
in project affected area is 0.09 GWh in dry season and 0.18 GWh in wet season. Estimated power
consumption for pumping of Siuri tailrace water is 0.99 GWh in dry season and 0.79 GWh in wet
season. After deduction of total energy for rural electrification and pumping of Siuri tailrace water, net
energy available for sale has been calculated and tabulated below.
Table 1.4 Energy Production
Plant Capacity

18.50 MW

22.40 MW

30MW

36.30 MW

50.10 MW

Total Energy generation


(GWh) after deduction of 4%
outage

128.97

145.97

177.30

192.40

223.01

Energy for rural


electrification (GWh)

0.27

0.27

0.27

0.27

0.27

Energy for pumping (GWh)

1.78

1.78

1.78

1.78

1.78

Net Energy available for sale


(GWh)

126.92

143.92

175.25

194.45

234.06

1.8 Cost Estimate


The cost components for various capacities on varying exceedance flow are estimated as per the
feasibility level design. The size and crest elevation of weir structures remains same in the various
discharge, but nos. and size of intake orifice opening is changed as per the design discharges of various
exceedance flows. The size of gravel trap, intake tunnel and underground settling basin change with
discharges of different option, which have significant impact on the total project cost of various options.
From the recent technological development and practices, the tunnel with diameter of around 3.2 m can
be mechanically constructed with proper working space and ventilation. Therefore, same size of tunnel
is adopted for discharge with the exceedance 40% to 50%. But headrace tunnel size is found optimum
for higher discharge based on cost and revenue loss. The size of surge shaft increases with discharge of
various capacities and cost of each capacity estimated separately.
Penstock diameter increases with increase of discharge and has significant impact on the total project
cost. Although an increase in penstock pipe diameter raises initial cost, the energy output will be
increased due to reduction of headloss. So, the penstock is optimized for most cost effective
combination of the penstock diameter and thickness. Penstock pipe was adopted for corresponding
discharges and associated costs. The thickness of each penstock pipe has been estimated. The cost of
anchor blocks and support piers are slightly affected by change in discharge and diameter of the
penstock which is estimated accordingly.
Other hydro-mechanical costs like radial gates, bulk head gates, stoplogs, and trashrack etc have been
estimated as per the prevailing market rate.

Hydro Consult

Nyadi Hydropower Project


Feasibility Study Volume III

Based on design discharge and rated head, the type and size of turbine are calculated. Sizes of
powerhouse caverns are determined accordingly. Then the cost estimate of powerhouse of each option
is estimated accordingly. The cost of electro-mechanical parts including turbine, governor, generator,
transformers, etc. are estimated based on prevailing practice and market prices.
The estimated base costs of project include transportation, installation and custom duties as well as
other applicable taxes. Similarly the cost of transmission line has been estimated based on per kilometre
cost of construction of 132kV transmission line and it also includes interconnection arrangement at
delivery location. Other cost like tapping of tailrace water of Siuri SHP, access road, environmental
mitigation, land acquisition, infrastructures, owner development cost and contingencies have been
proportionately increased for the respective plant capacities
Table 1.5 Comparison of the base project costs for various installed Capacities
Amout in US$ Milion
Summary of project contract costs for various installed capacities

50.10 MW

36.30 MW

30.00 MW

22.40 MW

18.50 MW

Civil works

34.94

26.70

23.87

21.53

21.05

Electromechanical works

19.16

14.15

10.33

8.95

7.75

Penstock and Hydromechanical works

3.86

3.66

3.26

3.15

2.88

Transmission line works

1.35

1.35

1.35

1.35

1.35

Marsyangdi Bridge and Access Road

2.47

2.47

2.47

2.47

2.47

Siuri Tailrace Flow Diversion

1.41

1.41

1.41

1.41

1.41

Socio-environmental mitigation costs

0.91

0.68

0.45

0.45

0.45

Infrastructure development costs

1.79

1.23

1.02

1.02

1.02

Land acquisition and direct costs

0.54

0.54

0.54

0.54

0.54

Rural Electrification Costs

0.37

0.37

0.37

0.37

0.37

66.80

52.56

45.06

41.24

39.30

Engineering fees

5.34

4.20

3.61

3.30

3.14

1.5 % insurance,tax and 10% VAT

7.48

5.92

5.22

4.81

4.66

Owner's development cost

3.08

2.82

2.15

2.15

2.15

Total Project cost for year 2010

82.70

65.50

56.04

51.50

49.25

Total Project cost for year 2011 based on price escalation @ 5 p.a.

86.84

68.77

58.84

54.08

51.71

Total contact cost

1.9 Benefit Cost Analysis for Various Installed Capacities


The different options with various plant capacities and their corresponding construction costs and
benefits are compared by financial analysis based on discounted cash flow. Financial analysis has been
performed to find the capacity at which the benefits are maximized. The analysis is carried out in
Nepalese Rupees (NRs.) as the price for the energy that will be sold from this project to the bulk power

Hydro Consult

Nyadi Hydropower Project


Feasibility Study Volume III

purchaser after finalizing the power purchase agreement (PPA). The relevant specific parameters applied
for the financial analysis in this study are adapted as given in section 15.2.

1.10 Result of Benefit Cost Analysis


Financial indicators such as IRR on equity and IRR on Project for various installed capacities are shown
in Table 1.6 . IRR on equity versus percentage exceedance are shown in figure 3-1.
Table 1.6 Financial Indicators for various installed capacities
Descriptions

18.50 MW

22.40 MW

30MW

36.30 MW

50.10 MW

IRR on Equity

11.28%

13.63%

17.13%

15.47%

14.12%

IRR on Project

13.67%

15.04%

16.995

16.08%

15.32%

EIRRVsPercentageExceedance
18.00%
17.13%

17.00%
16.00%
15.47%

EIRR

15.00%
14.12%

14.00%

13.63%

13.00%
12.00%
11.28%

11.00%
10.00%
25

30

35

40

45

50

55

PERCENTAGEEXCEEDANCE(%)

Figure 3-1-1 Optimization Curves EIRR Vs percentage exceedance

1.11 Conclusion and Recommendation


Based on the financial analysis of all the options corresponding to different exceedance flow, the project
has been found to be optimized at 30 MW corresponding to 40% exceedance.
Thus project engineering works (design and drawings), quantity estimation, costing and financial analysis
have been carried out for 30 MW.

Hydro Consult

Nyadi Hydropower Project


Feasibility Study Volume III

APPENDIX F
COST ESTIMATE AND
FINANCIAL ANALYSIS

NYADI HYDROPOWER PROJECT


FEASIBILITY STUDY

October, 2010

Nyadi Hydropower Limited

Hydro Consult

Nyadi Hydropower Project


Feasibility Study volume III

TABLES OF CONTENTS
F. COST ESTIMATE AND FINANCIAL ANALYSIS ................................................................ 2
F.1
Cost estimate....................................................................................................................................................... 2
F.1.1
Preliminary site works ................................................................................................................................ 2
F.1.2
Main civil works............................................................................................................................................ 2
F.1.3
Mechanical and electrical ........................................................................................................................... 2
F.1.4
132 kV transmission line ............................................................................................................................ 3
F.2
Engineering fees .................................................................................................................................................... 3
F.3
VAT and taxes ...................................................................................................................................................... 3
F.4
Contingency sums ................................................................................................................................................ 3
F.5
Benefit Calculation ............................................................................................................................................... 3
List of Tables
Table F 1. Project cost summary ...................................................................................................................................... 4
Table F 2. Owners direct cost .......................................................................................................................................... 5
Table F 3. Land acquisition cost ........................................................................................................................................ 6
Table F 4. Access road and Marsyangdi Bridge cost .................................................................................................... 7
Table F 5. Infrastructure development costs ................................................................................................................. 8
Table F 6. Civil Works Cost .............................................................................................................................................. 9
Table F 7. Hydro mechanical cost .................................................................................................................................. 15
Table F 8. Electromechanical cost .................................................................................................................................. 16
Table F 9. Transmission line and intergrid connection cost ..................................................................................... 17
Table F 10. Environmental monitoring and mitigation cost ...................................................................................... 18
Table F 11. New rate summary ....................................................................................................................................... 19
Table F 12. Rate summary of Miscellaneous Item....................................................................................................... 23
Table F 13. Tunnel Excavation Rate ............................................................................................................................... 24
Table F 14. Energy Calculation Sheet of NHP ............................................................................................................. 25
Table F15. Benefit Calculation sheet of NHP.....................................................................................................................26

Nyadi Hydropower Limited

Hydro Consult

Nyadi Hydropower Project


Feasibility Study volume III

F. COST ESTIMATE AND FINANCIAL ANALYSIS


Cost estimate

F.1

The total project cost for year 2011 is presented in Table F1.The detailed cost estimate for different packages
are presented in Tables F 2 to F 10. New rate summary is given in Table F 11. Other assumptions on which
the estimate is based are indicated below.
The cost estimate has been split into five cost packages. The packages are as follows:
Contract C1

Preliminary site works

Land Acquisition

Access road

Bridge over Marsyangdi

Temporary and permanent Housing

Contract C2

Main civil works

Contract C3

Elect mechanical

Contract C4

Penstock and Hydro-mechanical

Contract C5

132 kV transmission line

Preliminary site works

F.1.1

This contract contains the items necessary to expedite the work in the initial stage which is preliminary civil
works including the permanent access road, preparation of construction areas, housing for this phase, offices,
water supplies, sewage disposal. The program critical path items are Bridge over Marshyangdi and the access
road.

Main civil works

F.1.2

Contract C2 comprises the main civil works including the Headworks, waterway including surge shaft and
vertical shaft, underground powerhouse, tailrace tunnel, access tunnel and switchyard.
The following assumptions have been made:

The average tunnelling rate for the headrace tunnel is minimum 15 m to maximum 25 m per week
The unit rates are developed based on the experience of other similar projects in Nepal.

Water supply
Total daily volumes of water demands are based on experience at Khimti Hydropower Project. Water supply
costs allow for chlorinating at each major site and have a nominal allowance for simple water treatment (e.g.
roughing filter). Water supply costs are order of cost only and would need to be verified after further design.
Sewerage
The cost allows for sewer collection system, septic tank and soaks away trenches. At the Headworks
however, given the steep and rocky ground, septic effluent disposal by conventional trenches is considered
problematic. Therefore an allowance for a package treatment plant to treat septic tank effluent is included.
F.1.3

Mechanical and electrical

The cost includes supply and installation of all the mechanical and electrical equipment from the powerhouse
to the outdoor switchyard.

Nyadi Hydropower Limited

Hydro Consult

Nyadi Hydropower Project


Feasibility Study volume III

Steel penstock
Costs are based on budget cost advice from Nepal Hydro Electric (NHE) in Butwal.

132 kV transmission line

F.1.4

This cost package includes the erection of the switchyard electrical items and the 132 kV line and
commissioning of the line.
The following assumptions have been made:

F.2

There will be no NEA charge for connecting the 132 kV line into the grid at proposed NEAs Hub
at Tunikharka.
Steel Type towers are used in the cost estimate

Engineering fees

The 8% engineering fees are assumed to cover the additional studies described in Section 13.4, Volume 1,
main report, the hydraulic model study , all detailed design and including construction supervision by a local
Consultant.

F.3

VAT and taxes

The amount of VAT payable has been based on assumed Nepal currency expenditure percentages of total
contract values. This is indicated in Table F.1. VAT is assumed to 13%. Tax deducted at source is assumed
payable on engineering fees at 5%.

F.4

Contingency sums

A general sum of 10% has been included on contract C1, C2 and C4 and 8% has been included in C3 and C5.
A higher sum of 10% has been included on the C2 main civil works contract to cover the higher risk of the
underground works. However, 5% contingencies sums are taken in preliminary site works.

F.5

Benefit Calculation

The basis for the benefit calculation is the adopted hydrological parameters and possible tariff rates of the
energy which could be agreed while reaching PPA.
Annual dry and wet energy production in a normal year are calculated based on the adopted hydrological data.
Allowance is made for downstream release (10 % of the driest mean monthly flow) while estimating the
energy production. Planned and forced outages are considered as 4 % for both wet and dry seasons. The
monthly energy estimate is carried out based on average monthly flow. The estimated monthly energy
production in a normal year after deducting energy for rural electrification and pumping for the base case is
summarized in Table F 14.
While calculating the energy benefit in terms of money, the flat tariff rates (base case) of 6.30 NRs/kWh have
been assumed for both dry and wet energy with 6 % escalations per annum up to 10 years period after
commissioning date of the project. Details of the benefit calculations based on project base cost for year 2011
are presented in Table F15.

Nyadi Hydropower Limited

Hydro Consult

Nyadi Hydropower Project


Feasibility Study volume III

Table F 1. Project cost


summary
Nyadi Hydropower Project (NHP)
PROJECT COST ESTIMATE
Exchange Rate (US$)

Installed capacity
SUMMARY OF DIFFERENT
%

CONTRACT COSTS
Civil works
Contingency sum

NRs
337,075,604
33,707,560

10

US$

NRs Total

370,783,164

Electromechanical works
Contingency sum

109,701,337
10,970,134

10

35,272,100
2,821,768

134,441,099
13,444,110

10

Siuri Tailrace Flow Diversion


Contingency sum

16,225,634
1,622,563

10

81%

1,449,929,510

42.59%

10,325,112

8%

61,950,673

18.42%

120,671,471

1,646,725

44%

106,216,494

5.81%

38,093,868

842,833

100%

101,306,375

2.41%

147,885,209

494,460

100%

184,969,677

4.40%

17,848,197

1,172,351

56%

59,233,723

2.52%

100%

33,940,200

0.81%

100%

76,860,923

1.83%

40,337,701

0%

0.96%

28,000,000

0%

0.67%

100%

270,382,806

6.43%

780,401
62,432

449,509
44,951

1,065,773
106,577

Sub - Total
Socio-environmental mitigation costs
Contingency sum
Sub - Total

Infrastructure development costs


Contingency sum
Sub - Total

Land acquisition and direct costs


Contingency sum
Sub - Total

Item
Allocations

1,497,023
149,702

Sub - Total
Marsyangdi Bridge and Access Road
Contingency sum
Sub - Total

VAT complying
NRs equivalent

18,923,377

Sub - Total

Transmission line works


Contingency sum

VAT
complying

9,560,289
764,823

Penstock and Hydromechanical works


Contingency sum
Sub - Total

US$ Total

17,203,070
1,720,307

Sub - Total

32,324,000
1,616,200
33,940,200
41,730,729
2,086,536

419,602
20,980
43,817,266

440,582

38,416,858
1,920,843

Rural Electrification Costs

28,000,000

841,377,075 33,845,440

TOTAL CONTRACT COSTS SEPARATE

45,063,801

TOTAL CONTRACT COSTS US$


ENGINEERING FEES

75

30.0 MW

3,605,104

TOTAL CONTRACTS & ENGINEERING COST US$

48,668,905

1.5 % INSURANCE COST


Sub- Total (A)

730,034
49,398,939

0.015

TOTAL VAT COMPLYING US$ EQUIVALENT


VAT
13
TDS on Engineering fees
1.5

2,344,790,381

4,064,303
54,077

Total Taxes (1% custom duty & 0.1%


godown charge )
1.1
TOTAL TAX AND VAT (B)
TOTAL CONTRACTS & ENGINEERING COST INC. VAT & TDS
Owner's development costs

372,300
4,490,680
53,889,618
2,149,590

TOTAL PROJECT COST (Nearest $1000) for 2010

56,040,000

Cost escalation@5% p.a.

2,802,000

5%

58,842,000
TOTAL PROJECT COST (Nearest $1000) for 2011
Notes:
Unit rates are based at the site local to construction.
Unit Cost US$
1,961
Unit rates include cost of labour plant and materials
Contingency sum cover forseen and unforseen risks. It does not cover cost overrun.
Risks - ground conditions, strikes, material shortage, political instability, delay in license, manpower shortage

Nyadi Hydropower Limited

per KW

Hydro Consult

Nyadi Hydropower Project


Feasibility Study volume III

Table F 2. Owners direct cost


Nyadi Hydropower Project
Owner's Direct cost
Rate for US$/NRs
75
S.N.
1
2
2
2.1
2.2
2.2.1
2.2.2
2.2.3
2.2.4
2.2.5
2.2.6
2.2.7
2.2.8
3
4
5
6

Description of Items
Feasibility Study
Detail design including tender doc
preparation
Office Setup
Office building rent
Salary for personnel
Project Director
Resident Project Manager
Planning,Account/Admin, Contract Manager
Engineers/geologist/mitigation officer
Peons
Guard
Secretary
Drivers
Vehicle
Office furniture
Owner's Overhead
Site Security
Officers
Assistants
Housing and facilities

Nos.

Quantity

Rate
(US$)

Amount
(US$)

L.S.

106,670.00

106,670.00

L.S.

400,000.00

400,000.00

months

48

270.00

12,960.00

months
months
Months
months
months
months
months
months
Nos.

1
1
3
8
5
4
2
6
6

48
48
48
48
48
48
48
48
1
L.S.
L.S.

3,500.00
1,800.00
1,500.00
1,000.00
250.00
250.00
250.00
245.00
50,000.00
50,000.00

168,000.00
86,400.00
216,000.00
384,000.00
60,000.00
48,000.00
24,000.00
70,560.00
300,000.00
30,000.00
50,000.00

40
40
L.S.

200
125.00
45,000.00

48,000.00
100,000.00
45,000.00

Units

months
months

6
20

Total Cost

Nyadi Hydropower Limited

2,149,590.00

Hydro Consult

Nyadi Hydropower Project


Feasibility Study volume III

Table F 3. Land acquisition cost

Nyadi Hydropower Project (NHP)


LAND ACQUISITION AND COMPENSATION COST

Description

Unit

Quantity

Amount
(NRs)

Land purchased

Upto 27 July,2010

Access road

Ropani

130

7,373,356.00

Hydropower components

Ropani

308

19,651,728.00

Total

27,025,084.00

Remaining Land to be purchased


Require private land for access road
Required land for Powerhouse, Tailrace
Switchyard
Staff housing area at powerhouse site
Vertical tunnel, penstock alignment, surge
shaft, Road for surge shaft, spoil tip area of
surge adit area

Ropani

16

814,052.80

671,601.00

116,913.00

1,689,207.00

Ropani
Ropani

Ropani

Staff housing area at intake site

Ropani

20

2,900,000.00

Required land for Adit tunnel in Naiche

Ropani

10

1,450,000.00

Transmission line

Ropani

25

3,750,000.00

Total
Total Amount

Nyadi Hydropower Limited

Remarks

11,391,773.80
38,416,857.80

Hydro Consult

Nyadi Hydropower Project


Feasibility Study volume III

Table F 4. Access road and Marshyangdi Bridge cost

Nyadi Hydropower Project


Bailey Bridge and Access Road Cost
Description

Unit

Quantity

Rate(US$)

Rate (Nrs)

Amount
(US$)

1 US$

75 NRs.

Amount (Nrs)

Remarks
Reference from contract
to be signed

Marsyangdi
Bridge
Civil works
Bailey Bridge with
Complete fitting

2,517,784.00

992,000.00

137,027.20
20% contribution by Siuri
SHP

Sub Total
Access road
Total Length

Km

13.500

28,933.473

12,215,121.73

312,481.51

131,923,315

449,508.71

134,441,098.67

Sub Total
Total

Nyadi Hydropower Limited

Reference from Boq of


Access road
20% contribution by Siuri
SHP

Hydro Consult

Nyadi Hydropower Project


Feasibility Study volume III

Table F 5. Infrastructure development costs

Nyadi Hydropower Limited

Hydro Consult

Nyadi Hydropower Project


Feasibility Study volume III

Table F 6. Civil Works Cost

Nyadi Hydropower Project


Cost of Civil Works
Exchange Rate 1 US$ =

S.N.

1
1.1
2
2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
2.9
2.10
2.11
3
3.1
3.2
3.3
3.4
3.5

Item Descriptions
GENERAL ITEMS
Insurances
Mobilization
Demobilization
Specified
requirements
Testing of materials;
aggregates, cement,
concrete, shotcrete
cores, density tests
construction power cost
(Desiel Generator) with
11 KV line
Sub-total
General, Headworks
Site Clearence
Sub-total
Diversion tunnel and
fish ladder
Surface rock excavation
with blasting
Tunnel excavation
(Underground)
Inlet pipe Dia 0.5m (8
mm thickness)
Reinforced Cement
Concrete (C25)
Reinforcement
Shotcrete (5cm steel fibre
reinforced)
Rockbolt (2m long, 25mm
dia grouted)
Formwork
Trimming and
preparation
Water control in tunnel,
25 lps
Grouting
Sub-total
Coffer Dam
Filling with rock in 45 cm
thick layer in compaction
PVC sheet 1 mm thick
Hard stone lining ( 0.4m
thick)
Removal of coffer dam
Water control in coffer
dam(25-50 lps)

Unit

Quantity

Rate ,
USD

Amount
USD

sum
sum
sum
sum

30,000

sum

919,127.83
949,127.83

m2

Amount
NRs

1,500,000
1,000,000

4000.00

90.02

608,171.84
3,108,171.84
360088.00
360088.00

m3
m3

600.00

22.67

300.00

13600.00

180000.00

1400.00

56.67

750.00

79333.33

1050000.00

2.00

2393.00

170500.00

2878.42

136723.73

5.70
0.45

121.33
1360.00

4900.00
18000.00

691.60
608.53

27930.00
8054.10

57.00

566.67

7500.00

32299.66

427495.50

320.00
38.00

34.00

450.00
1000.00

10880.00
0.00

144000.00
38000.00

90.00

0.00

10800.00

11.25

150.00
5865.94
146307.48

0.00
77637.40
2100640.73

ton
m3
ton
m3
No
m2
m2
Day
kg

m3
m2
m2
No
Day

120.00
15.00
6901.10

10.00
0.85

1680.00
640.00

0.33
12.50

1106.02

553.16
8000.00

1858118.77
0.00

80.00
2.00

34.25

7706.25
100000.00

2740.00

616500.00
200000.00

10.00

10.00

100.00
11393.16

0.00
2674618.77

Sub-total
Nyadi Hydropower Limited

Rate,
NRs

NRs 75.00

Remarks

Hydro Consult

S.N.
4
4.1
4.2
4.3
4.4
4.5
4.6
4.7
4.8
4.9
4.10
4.11
4.12
4.13
4.14
4.15
4.16
4.17
4.18
4.19
6
6.1
6.2
6.3
6.4
7
7.1
7.2
7.3
7.4
7.5
7.6
7.7
7.8
7.9
7.10
7.11
7.12
8
8.1

Item Descriptions
Weir and Bottom
Sluice
Surface rock excavation
with blasting
Boulder mixed soil
excavation on river bed
Earthwork in backfilling
Blinding concrete (C15)
Reinforced Cement
Concrete (C35)
Reinforced Cement
Concrete (C25)
Reinforcement
Geotextile
Hard stone lining (0.4m
thick)
Water control in weir
Laying 300 mm thick filter
layer
Boulder lining
Formwork
Expansion Joints
Seleant
Hydro cell
Water bars
Curtain grouting
GI Pipes (50mm dia)
Sub-total
Gravel Trap
Tunnel excavation
(Underground)
Reinforced Cement
Concrete (C35)
Reinforcement
Formwork
Sub-total
Intake Tunnel
Tunnel excavation
(Underground)
Reinforced Cement
Concrete (C25)
Reinforcement
Formwork
Shotcrete (5 cm steel
fibre reinforced)
Rockbolt (1.5m long,
25mm dia grouted)
Water control in tunnel
(25 lps)
Expansion Joints
Seleant
Hydro cell
Water bars
Grouting
Sub-total
Settling Basin
Tunnel excavation

Nyadi Hydropower Limited

Nyadi Hydropower Project


Feasibility Study volume III

Unit

Quantity

Rate ,
USD

Rate,
NRs

Amount
USD

Amount
NRs

m3
6362.13

22.67

300.00

144208.28

1908639.00

6362.13
5211.22
1353.00

3.18
65.00

39.94
85.00
2625.00

20211.69
0.00
87945.00

254132.30
442953.70
3551625.00

2887.84

143.00

5775.00

412961.12

16677276.00

4331.77
850.11
1485.00

121.33
1246.67
1.49

4900.00
16500.00
308.66

525588.09
1059802.65
2213.16

21225673.00
14026799.78
458360.10

330.40

34.25
20.00

7706.25
1500.00

0.00

m2
m2
m
m
m
m
kg
m

1865.50
1025.00
5344.60
14.00
14.00
14.00
14.00
57.30
135.00

19.95
11.67
21.25
23.80
16.15
16.15
0.85
4.00

1496.39
2625.00
670.00
30.00
315.00
213.75
213.75
11.25
200.00

37220.19
11958.33
0.00
297.50
333.20
226.10
226.10
48.71
540.00
2305280.12

2791514.05
2690625.00
3580882.00
420.00
4410.00
2992.50
2992.50
644.63
27000.00
67646939.56

m3

630.00

56.67

750.00

35700.00

472500.00

m3

98.25

143.00

5775.00

14049.75

567393.75

ton
m2

7.71
135.00

1246.67

16500.00
670.00

9615.07
59364.82

127258.31
90450.00
1257602.06

m3
m3
m3
m3
m3
ton
m2
m3
Day
m3

75.00

m3

677.25

56.67

750.00

38377.50

507937.50

m3

185.85

121.33

4900.00

22549.80

910665.00

ton
m2
m3

14.59
323.93
323.95

1360.00
566.67

18000.00
1000.00
7500.00

19841.35
0.00
183569.40

262606.05
323925.00
2429595.00

No

105.00

28.33

375.00

2975.00

39375.00

Day

25.00

10.00

250.00

0.00

m
m
m
m
kg

5.00
5.00
5.00
5.00
2490.43

21.25
23.80
16.15
16.15
0.85

30.00
315.00
213.75
213.75
11.25

106.25
119.00
80.75
80.75
2116.87
270066.66

150.00
1575.00
1068.75
1068.75
28017.38
4505983.43

m3

29263.34

56.67

750.00

1658255.93

21947505.00

10

Remarks

Hydro Consult

S.N.
8.2
8.3
8.4
8.5
8.6
8.7
8.8
8.9
8.11
8.12
8.13
8.14
8.15
8.16
81.8
9
9.1
9.2
10
10.1
10.2
10.3
10.4
10.5
10.6
10.7
10.8
10.9
10.10
10.11
10.12
10.13
10.14
10.15

Item Descriptions
(Underground)
Reinforced Cement
Concrete (C25)
Reinforcement
Formwork
Shotcrete (10cm steel
fibre reinforced)
Shotcrete (5cm steel fibre
reinforced)
Rockbolt (1.5m long,
25mm dia grouted)
Rockbolt (2 m long,
25mm dia grouted)
Rockbolt (3.5 m long,
25mm dia grouted)
Water control in tunnel,
50 lps
Expansion Joints
Seleant
Hydro cell
Water bars
1:4 Stone masonry
S4 System including
automatic gates
Sub-total
River Protection
Earthwork in excavation
Gabion works
Sub-total
Headrace tunnel
Rock Excavation
Blinding Concrete (C15)
Structural Concrete
(C25)
Rebar
Formworks
Subase Preparation
50 mm of unreinforced
shotcrete
50 mm steel fibre
reinforced shotcrete
100 mm steel fibre
reinforced shotcrete
150 mm steel fibre
reinforced shotcrete
200 mm steel fibre
reinforced shotcrete
2 m long 25 mm dia.
Grouted rock bolts at
1.5m*1.5m c/c
Spot bolting , 2m long
25mm dia grouted rock
bolts
2m long 25mm dia
grouted rock bolts at
1.3m*1.3m c/c spacing
2m long 25mm dia

Nyadi Hydropower Limited

Nyadi Hydropower Project


Feasibility Study volume III

Unit
m3
ton
m2
m3

Rate ,
USD

Rate,
NRs

3137.28
246.28
5480.52

121.33
1360.00

4900.00
18000.00
1000.00

380656.64
334936.01

15372672.00
4432976.64
5480520.00

934.13

453.33

6000.00

423473.17

5604792.00

280.16

566.67

7500.00

1875.00

28.33

375.00

53125.00

703125.00

1092.00

34.00

450.00

37128.00

491400.00

4140.00

51.00

675.00

211140.00

2794500.00

130.00
27.00
27.00
27.00
27.00
1986.86

20.00
21.25
23.80
16.15
16.15
55.00

30.00
315.00
213.75
213.75
3300.00

2600.00
573.75
642.60
436.05
436.05
109277.30

0.00
810.00
8505.00
5771.25
5771.25
6556638.00

Quantity

m3
No
No
No
Day
m
m
m
m
m3
sum

Amount
USD

Amount
NRs

2101192.50

Andhikhol
a

454092.00
3666772.51

65506178.64

m3
m3

1315.60
965.00

3.18
11.67

39.94
2625.00

4179.50
11258.33
15437.83

52551.03
2533125.00
2585676.03

m3
m3
m3

62557.22
1120.62
3417.12

56.67
78.00
121.33

750.00
3150.00
4900.00

3544909.13
87408.36
414610.56

46917915.00
3529953.00
16743888.00

ton
m2
m2
m3

268.24
11412.00
14941.60
424.15

1360.00

453.33

18000.00
1000.00
90.00
6000.00

364811.73
0.00
0.00
192279.52

4828390.56
11412000.00
1344744.00
2544876.00

m3

119.88

566.67

7500.00

67929.17

899062.50

m3

496.99

453.33

6000.00

225299.87

2981910.00

m3

233.90

396.67

5250.00

92781.33

1227988.13

m3

141.34

396.67

5250.00

56066.45

742056.00

no

3568.00

34.00

450.00

121312.00

1605600.00

no

5178.00

34.00

450.00

176052.00

2330100.00

no

4110.00

34.00

450.00

139740.00

1849500.00

no

1295.00

34.00

450.00

44030.00

582750.00

11

Remarks

Hydro Consult

S.N.

10.16
10.17
10.18
10.19
10.20
11
11.1
11.2
11.3
11.4
11.5
11.6
11.7
11.8
11.9
11.10
11.11
11.12
12
12.1
12.2
12.3
12.4
12.5
12.6
12.7
12.8
12.9
12.10
12.11
12.12
12.13
12.14
12.15
12.16
13

Item Descriptions

Nyadi Hydropower Project


Feasibility Study volume III

Unit

Quantity

Rate ,
USD

Rate,
NRs

Amount
USD

Amount
NRs

grouted rock bolts at


1.2m*1.2m c/c spacing
2m long 25mm dia
no
1120.00
34.00
450.00
38080.00
504000.00
grouted rock bolts at
1m*1m c/c spacing
4 m long spilling
no
185.00
62.33
825.00
11531.67
152625.00
Grouting
kg
288454.32
0.85
11.25
245186.17
3245111.10
Ribs
kg
22275.00
3.00
50.00
66825.00
1113750.00
Water control tunnel
Day
400.00
10.00
4000.00
0.00
(25-50 lps)
Sub-total
5892852.95 104556219.29
Naije Adit
Landscaping spoil tip
m2
20800.00
0.50
10400.00
Rock Excavation
m3
2243.41
56.67
750.00
127126.78
1682560.35
2m long 25mm dia
no
680.00
34.00
450.00
23120.00
306000.00
grouted rock bolts at
1.5m*1.5m c/c spacing
50 mm unreinforced
m3
80.84
453.33
6000.00
36645.20
485010.00
shotcrete
Gravel fill
m3
58.56
30.94
389.03
1811.85
22781.30
Subbase preparation
m2
30.00
1000.00
30000.00
C15 Blinding Concrete
m3
2.07
78.00
3150.00
161.82
6535.23
C25 Concrete
m3
68.52
121.33
4900.00
8314.31
335770.30
Formworks
m2
53.27
1000.00
53272.00
Rebar
ton
5.38 1360.00
18000.00
7315.68
96825.19
1:4 stone masonry works
m3
540.00
55.00
3300.00
29700.00
1782000.00
Grouting
kg
9811.00
0.85
11.25
8339.35
Sub-total
252935.00
4800754.36
Surge adit , Surge Shaft and Ventillation adit , Gravel Trap with flushing and spoil tips
Boulder mix soil
m3
2311.35
2.76
39.94
6385.10
92325.79
excavation
Surface Rock Excavation
m3
3374.65
79.33
1050.00
267722.14
3543381.29
Blinding Concrete (C15)
m3
49.36
78.00
3150.00
3849.77
155471.40
Structural Concrete
m3
636.89
121.33
4900.00
77276.14
3120767.27
(C25)
Rebar
ton
60.20 1360.00 18000.00
81871.11
1083588.28
Formworks
m2
1504.61
1000.00
1504613.10
Subase Preparation
m2
679.01
90.00
61111.26
50 mm of steel reinforced
m2
58.63
566.67
7500.00
33226.01
439756.05
shotcrete
100 mm of steel
m2
62.84
453.33
6000.00
28487.47
377040.00
reinforced shotcrete
2 m long 25 mm dia.
no
481.12
34.00
450.00
16358.08
216504.00
Grouted rock bolts at
1.5m*1.5m c/c
3 m long 25 mm dia.
no
294.00
45.33
600.00
13328.00
176400.00
Grouted rock bolts at
1.5m*1.5m c/c
Landscaping spoil tip
m2
6500.00
0.50
3250.00
1:4 Stone masonry wall
m3
663.40
55.00
3300.00
36487.00
2189220.00
75mm HDP Pipes for
weep holes
Ge--textile
Filter materials
Sub-total
Anchor blocks/

Nyadi Hydropower Limited

360.00

4.30

m2
m3

120.00
60.00

1.49
19.95

12

1548.00
308.66
244.38

178.84
1197.11
571164.78

37039.20
14662.50
13011880.14

Remarks

Hydro Consult

S.N.
13.1
13.2
13.3
13.4
13.5
13.5
13.6
13.7
13.8
13
13.1
13.2
13.3
13.4
13.5
13.6
15
15.1
15.2
15.3
15.4
15.5
15.6
15.7
15.8
15.9
15.10
15.11
15.12
15.13
15.14
16
16.1
16.2
16.3
16.4
16.5
16.6
16.7
16.8

Item Descriptions
Support piers
Rock Excavation
Boulder mix soil
excavation
Blinding Concrete (C15)
C20 with 40% plum
concrete
C25 Concrete
Rebar
Formworks
Back Filling
Subase Preparation
Sub-total
Vertical Shaft
Rock Excavation
Structural Concrete
(C25)
Rebar
70 mm of steel reinforced
shotcrete
2 m long 25 mm dia.
Grouted rock bolts at
1.5m*1.5m c/c
Double grouting
Sub-total
Powerhouse Main
Building
Rock Excavation
200mm thick Shotcrete
25mm dia 4m long rock
bolts @1.2m C/C
Shotcrete ribs
Rebar in Shotcrete ribs
Water control in cavern
50-70 l/s
Cement grout
Concrete (C25)
Reinforcement
Formwork
Steelwork
CGI sheets 20 gauge
CGI sheet ceiling
accessories
Finishes
Sub-total
Powerhouse Control
building
Rock Excavation
120mm thick Shotcrete
25mm dia 4m long rock
bolts @1.2m C/C
Cement grout
C25 Concrete
Rebar
Formwork
Finishes

Nyadi Hydropower Limited

Nyadi Hydropower Project


Feasibility Study volume III

Unit

Quantity

Rate ,
USD

Rate,
NRs

Amount
USD

Amount
NRs

m3
m3

432.88
8947.39

22.67
0.24

300.00
600.88

9811.95
2150.51

129864.00
5376263.89

m3
m3

70.44
2414.70

78.00
60.67

1050.00
2450.00

5494.55
146491.96

73965.15
5916021.31

m3
ton
m2
m3
m2

685.28
119.46
1885.54
3728.67
875.24

104.00
1360.00

4200.00
18000.00
670.00
11.81
90.00

71268.92
162460.78

399448.02

2878167.87
2150216.24
1263309.12
44032.29
78771.60
17910611.47

0.47

1769.35

m3
m3

1627.72
682.53

90.67
130.00

1200.00
5250.00

147579.49
88728.64

1953258.00
3583272.00

ton
m3

53.58
136.83

1360.00
510.00

18000.00
6750.00

72866.69
69781.01

964412.06
923572.13

no

830.00

30.50

383.47

25313.34

318278.03

kg

52659.68

0.85

11.25

44760.73
449029.90

592421.45
8335213.66

m3
m3
no.

10415.74
336.00
1260.00

56.67
396.67
62.33

750.00
5250.00
825.00

590225.27
133280.00
78540.00

7811805.00
1764000.00
1039500.00

m3
ton
day

264.00
14.98
180.00

396.67
1360.00
20.00

5250.00
18000.00

104720.00
20378.03
3600.00

1386000.00
269709.26
0.00

kg
m3
ton
m2
ton

9056.12
298.93
19.52
1048.53
23.52

0.85
121.33
1360.00
2392.98

7697.71
36270.02
26541.25
0.00
33769.77

101881.40
1464750.96
351281.24
1048525.12
1604064.00

m2
m2

575.00
575.00

11.21
10.68

11.25
4900.00
18000.00
1000.00
170500.0
0
119.03
129.95

6446.01
6143.38

68439.38
74721.25

LS

1.00

7500.00

7500.00
1055111.44

0.00
16984677.60

m3
m3
no.

1119.38
29.81
264.00

56.67
396.67
62.33

750.00
5250.00
825.00

63431.25
11825.63
16456.00

839531.25
156515.63
217800.00

kg
m3
ton
m2
LS

1707.01
105.89
8.31
690.94
1.00

0.85
121.33
1360.00

11.25
4900.00
18000.00
1000.00

1450.96
12848.47
11305.24
0.00
5000.00

19203.83
518880.60
149628.22
690940.00
0.00

5000.00

13

Remarks

Hydro Consult

Nyadi Hydropower Project


Feasibility Study volume III

S.N.

Item Descriptions

Unit

16.9
16.10
16.11

Doors and windows


Plumbing & pipework
Miscellaneous steelwork;
covers, handrails
Sub-total
Access Tunnel
Portal excavation and
support
Water control in adit on
incline 25-25 l/s
Rock Excavation
120mm thick Shotcrete
25mm dia 2.4m long rock
bolts @1.5m C/C
Cement grout
C25 Concrete in floor
Rebar for C25 Concrete
in floor
Rock bolts for cable rack
Sub-total
TAILRACE TUNNEL
Rock excavation
100 mm shotcrete
25mm dia 2m long rock
bolts @1.2m C/C
C15 Concrete
Steel works
Water control in tailrace
tunnel 20-25 l/s
Sub-total
Switchyard and River
Training works
Soil excavation for gabion
mattress and stone
masonry
Gravel filling
Gabion mattress as
launching apron
Backfilling
Rip rap
1:4 C/S Stone Masonry
C15 Concrete Blinding
C20 Concrete Slab
C25 concrete for
machine foundation
Formworks
Reinforcement
Sub-total

m2
LS
LS

17
17.1
17.2
17.3
17.4
17.5
17.6
17.7
17.8
17.9
18
18.1
18.2
18.3
18.5
18.6
18.7
19
19.1
19.2
19.3
19.4
19.5
19.6
19.7
19.8
19.9
19.10
19.11

Quantity
31.33
1.00
1.00

Rate ,
USD
4.03
3000.00
3000.00

Rate,
NRs
3318.14

Amount
NRs
103957.37
0.00
0.00

128443.79

2696456.90

15000.00

0.00

500.00

0.00

LS

1.00

Day

50.00

10.00

m3
m3
no.

3640.00
226.20
968.00

56.67
396.67
41.93

750.00
5250.00
527.27

206266.67
89726.00
40592.84

2730000.00
1187550.00
510395.24

Kg
m3
ton

7267.26
125.30
9.84

0.85
121.33
1360.00

11.25
4900.00
18000.00

6177.17
15203.07
13377.03

81756.68
613970.00
177048.90

no

383.00

28.33

375.00

10851.67
397694.44

143625.00
5444345.82

m3
m2
no.

4792.35
356.64
2799.00

56.67
453.33
34.00

750.00
6000.00
450.00

271566.50
161676.80
95166.00

3594262.50
2139840.00
1259550.00

m3
ton
day

7.00
1.03
60.00

78.00
1360.00
10.00

3150.00
18000.00

546.00
1400.80
600.00

22050.00
18540.00
0.00

530956.10

7034242.50

m3

150.30

0.17

437.00

26.27

65681.10

m3
m3

414.00
150.00

19.95
32.67

1496.39
1050.00

8260.07
4900.00

619505.13
157500.00

m3
m2
m3
m3
m3
m3

7901.50
900.00
601.50
14.44
7.00
127.47

0.47
11.67
55.00
65.00
86.67
104.00

11.81
2625.00
3300.00
2625.00
3500.00
4200.00

3749.47
10500.00
33082.50
938.44
606.67
13257.09

93309.76
2362500.00
1984950.00
37898.44
24500.00
535382.66

m2
ton

387.08
21.15

1246.67

670.00
16500.00

0.00
26362.58
101683.09
17203069.92

259345.28
348916.55
6489488.92
337009789.71

Total

Nyadi Hydropower Limited

Amount
USD
126.24
3000.00
3000.00

14

Remarks

Hydro Consult

Nyadi Hydropower Project


Feasibility Study volume III

Table F 7. Hydro mechanical cost

Nyadi Hydropower Limited

15

Hydro Consult

Nyadi Hydropower Project


Feasibility Study volume III

Table F 8. Electromechanical cost

Nyadi Hydropower Limited

16

Hydro Consult

Nyadi Hydropower Project


Feasibility Study volume III

Table F 9. Transmission line and intergrid connection cost

Nyadi Hydropower Limited

17

Hydro Consult

Nyadi Hydropower Project


Feasibility Study volume III

Table F 10. Environmental monitoring and mitigation cost


Nyadi Hydropower Project
Summary of Environmental Monitoring & Mitigation Cost
Reference cost interpolated from NHP Mitigation Reports
Item / Description
Mitigation and enhancement measures cost
Cost for baseline monitoring
Cost for environmental monitoring during construction phase
Environmental monitoring during operation phase
Internal environmental auditing cost
Total (Rs.)

Nyadi Hydropower Limited

Total Cost (Rs)


16464000
963750
11795000
2255000
846250
32,324,000.00

18

Hydro Consult

Nyadi Hydropower Project


Feasibility Study volume III

Table F 11. New rate summary

S No
A
1
2
3
4
5
6
7
8
9

B
1
2
3

C
1

3
4

6
7

Item description

Unit

Item Unit Rate


in NRs

Item Unit Rate


in USD

0.07

163.88

0.09

218.50

0.24

600.88

Earthwork Excavation
Excavation on soft clay &silty soils including disposal
(up to 10 m lead & 1.5 m lift).
Excavation of Hard soil, Gravel/Boulder Mixed Soil
including disposal (up to 10 m lead & 1.5 m lift).
Excavation of Soft Rock without blasting, disposal (up
to 10 m lead & 1.5 m lift)
Excavation of hard rocks with blasting (Manual Drill),
disposal (up to 10 m lead & 1.5 m lift)
Excavation of hard rocks without blasting, disposal (up
to 10 m lead & 1.5 m lift) with chisel
Ditch cutting in hard soils, disposal (up to 10 m lead
and 1.5 m lift).
Excavation for foundation in all types of soil including
disposal up to 20 m and relevant lift (Depth upto
1.5m)
Excavation for foundation work including disposal up
to 20 m and relevant lift,soft moorum rocks.
Excavation for foundation work including disposal up
to 20 m and relevant lift, Medium hard rocks (without
blasting).

m3
m3
m3
m3

3.56

796.95

m3

1.05

2,622.00

m3

0.13

327.75

0.17

437.00

0.24

600.88

1.05

2,622.00

0.47

11.81

0.33

1,106.02

0.14

1,150.00

143.00

5,775.00

104.00

4,200.00

65.00

2,625.00

99.99

11,271.15

86.49

9,988.44

64.64

7,327.92

57.37

6,637.80

m3
m3
m3

Filling work
Filling with suitable (excavated) material in 15 cm thick
layer compaction using machinery, (haulage distance
10 m )With sprinkling water
Filling with rocks in 45 cm thick layer compaction,
sprinkling water and haulage distance 10 m.
Filling soils in pipe line trenches in 20 cm thick layers
including hand and water sprinkling. Filling by stones in
the foundation and levelling incl. Haulage dist. Up to
30 m

m3
m3
m3

Concrete Work
Machine Mixed Concreting Works(of super
structures, deck slabs, beams including supply of
materials and haulage dist up to 30 m) Concrete grade
C35
Machine Mixed Concreting Works(of super
structures,deck slabs, beams including supply of
materials and haulage dist up to 30 m) Concrete grade
C25
Machine Mixed Concrete grade C15 (Supply of
materials & haulage dist up to 30 m) in Foundation,
Footing etc
Manual Mixed Concreting Works(of super structures,
deck slabs, beams including supply of materials and
haulage dist up to 30 m) Concrete grade C35
Manual
Mixed
Concreting
Works(of
super
structures,deck slabs, beams including supply of
materials and haulage dist up to 30 m) Concrete grade
C25
Manual Mixed Concrete grade C15 (Supply of
materials & haulage dist up to 30 m) in Foundation,
Footing etc
Plum Concrete grade C15 (1:3:6) (Supply of materials
& haulage dist up to 30 m) (30% Plum)

Nyadi Hydropower Limited

m3

m3

m3
m3
m3

m3
m3

19

Hydro Consult

S No
8

Nyadi Hydropower Project


Feasibility Study volume III

Item description
Machine Mixed Concrete grade C20 (Supply of
materials & haulage dist up to 30 m) in Foundation,
Footing etc
Machine Mixed Concrete grade c20 with 40% Plum

Steel Work

Reinforced Bar cutting, bending, placing in position and


binding of M.S rod for R.C.C works including a lead of
30 m for 1 MT

Formwork

F
1

Making wooden form including supply and selection of


material, fixing nailing according to drawings, placing
separators, dismanteling form and hauling up to 30 m
distance.
a. Flooring and slab work
b. Vertical faces , wall etc (Upto 3 m high)
c. Vertical surface, wall etc (3-6m high)
d. Vertical surface, wall etc (6-9 m high)
e. Vertical surface, wall etc (More than 9 m high)
Erection, adjustment and nailing of forms for column
including dismantle, removal and hauling up to30 m .
a. Upto 3 m High
b. 3 - 6 m High
c. 6 - 9 m High
d. above 9 m
Making form for structural beam including selection of
material,fixing,nailing, oiling ,dismantle, removal and
hauling up to 30 m distance .

Rubble masonry works including supply of hard stone


blocks, preparing cement mortar, and const. of wall
(up to 5 m highand lead up to 30 m ) using Machine
a. Cement mortar 1:3
b. Cement mortar 1:4
c. Cement mortar 1:6
Rubble masonry works including supply of hard stone
blocks, preparing cement mortar, and const. Of wall
(up to 5 m high (lead up to 30 m ) (Manually)
a. Cement mortar 1:3
b. Cement mortar 1:4
c. Cement mortar 1:6
Providing & Laying dry stone masonry (0-5 m)
including dressing etc all complete (haulage upto 30 m)

Cement Plaster Work

1
2

86.67

3,500.00

m3

60.67

2,450.00

MT

1,246.67

16,500.00

m2
m2
m2
m2
m2

611.84
366.37
447.91
549.40
-

m2
m2
m2
m2
m2

452.20
539.85
670.00
-

744.47

m3
m3
m3

32.99
55.00
23.87

3,211.11
3,300.00
2,651.54

m3
m3
m3
m3

31.81
28.13
22.69

3,394.30
3,168.00
2,834.73

6.48

1,226.33

50.13

7,885.20

m3

Brick Work

4
5
6

Item Unit Rate


in USD

Stone Masonry

Brick work in 1:3 cement sand mortar (Machine


Mixed)
Brick work in 1:4 cement sand mortar (Machine
Mixed)
Brick work in 1:6 cement sand mortar (Machine
Mixed)
Brick work in 1:3 cement sand mortar (Manual Mixed)
Brick work in 1:4 cement sand mortar (Manual Mixed)
Brick work in 1:6 cement sand mortar (Manual Mixed)

Item Unit Rate


in NRs

Unit

Plastering 12.5 mm thick


mortar
Plastering 12.5 mm thick

Nyadi Hydropower Limited

m3
m3

48.06

7,596.37

m3

46.08

7,320.99

m3
m3
m3

49.12
47.04
45.07

7,943.44
7,654.61
7,379.23

1.29

119.54

1.15

117.75

thick 1:3 cement sand

m2

thick 1:4 cement sand

m2

20

Hydro Consult

S No

Nyadi Hydropower Project


Feasibility Study volume III

Item description

4
5
6
7

mortar
Plastering 12.5 mm thick thick 1:6 cement sand
mortar
Plastering 20 mm thick thick 1:3 cement sand mortar
Plastering 20 mm thick thick 1:4 cement sand mortar
Plastering 20 mm thick thick 1:6 cement sand mortar
3 mm thick Cement Punning

Wood works

1
2
3
4
5
6

Making salwood frame and fixing of door size 900 x


2100 mm (75mmX100mm)
Making Shutter in 38 mm thick salwood frame (shutter
size 1.07m x 1.982 m)
Making and fitting 3mm glazed shutter in 38 x 75 mm
salwood frame
Making and fitting 24 gauge mosquito proof wire mesh
shutter in 38mm thick salwood frame with shutter size
1.07 x 1.982 m
Making and fixing eves board with 25 mm thick sal
wood
Fixing 3 mm thick commercial plywood in frame using
timber beads

3
4

Painting Works

Two coats of white washing


First and second coat of cement paint on plasterd
surface
Two coats of enamel painting on one coat lining

Fencing works

Barbed wire fencing works with five rows and two


diagonal barbed wires and column at 3m spacing ,size
of timber column is 75 mm * 100 mm * 2100 mm

Gabion Work

M
1

Item Unit Rate


in USD

0.89

114.21

1.97
1.73
1.32
0.96

144.76
141.58
136.11
66.70

67.91

59,093.11

4.03

3,318.14

2.67

2,578.57

2.45

2,499.74

2.33

1,037.78

0.33

163.73

m2

11.21

119.03

m2

10.68

129.95

kg
kg

1.71
1.55

31.03
20.77

m2
m2

0.12

10.01

0.35

136.56

m2

0.93

68.08

4.14

25.30

18.57
19.41
21.62
11.25
32.67

69.69
71.13
77.59
244.38
1,050.00

19.95

1,496.39

11.67

2,625.00

m2
m2
m2
m2
m2

m3
m2
m2
m2
m2
m2

Roofing Works
CGI Sheet roofing works with supply of materials
complete
Making ridge of CGI plain sheets and fitting with supply
of materials complete
Fixing and supply of steel tubular truss
Fixing and supply of steel tubular pipe for purlins

Item Unit Rate


in NRs

Unit

Making gabion including cutting wire , netting, placing


in position, tying gabion by tightening wire and closing
from the top etc complete hexagonal mesh size 100
mm
x
120
mm.
Mesh
wire10
SWG
Selvedge-8
SWG
Tying wire- 12 Swg
a. Box size (3 m x 1 m x 1 m)
b. Box size (2 m x 1 m x 1 m)
c. Box size (1.5 m x 1 m x 1 m)
Filling stones/ boulders in the gabion boxes
Gabion Works

m3
m3
m3
m3

Filter material laying


Laying 300 mm thick filter layer of 75mm to 6mm
stone aggregates in canal bed including haulage up to
10m distance.
Boulder Riprap

Nyadi Hydropower Limited

m3
m2

21

Hydro Consult

S No

Nyadi Hydropower Project


Feasibility Study volume III

Item description

N
1

Geotextile
Supply and Laying of geotextile materials

Site preparation

a Uprooting trees & disposal 15 m far from the


construction site. (12 -30 cm dia)
b Cutting thick vegetation, grubing their roots &
disposal 25 m far from the const. Site. (the vegetation
dia.<= 30 cm & density >15 nr/2100 m2
c Cutting thin vegetation, grubing their roots &
disposal 25 m far from the const. Site. (the vegetation
dia.<= 30 cm & density<=15 nr/2100 m2
d Cutting, uprooting & disposal of bamboo (measure
volume of excavation)
e Spreading top soils at the required slope.
f Dressing nicely the spreaded top soils in slope
including levelling & light compaction.

Nyadi Hydropower Limited

Unit

m2

each
m2
m2
m3
m3
m2

22

Item Unit Rate


in NRs

Item Unit Rate


in USD

1.49

308.66

90.02

13.50

9.23

630.15

9.00

105.78

Hydro Consult

Nyadi Hydropower Project


Feasibility Study volume III

Table F 12. Rate summary of Miscellaneous Item

1
USD
Item
no.

Description

Unit

75
US$

Increment

12%

Remarks

NRs.
Rate
in
US$

Current
Rate in
US$

Current
Rate in
NRs.

25.00

21.25

30.00

0
1

Expansion Joints

Seleant

24.53

28.00

23.80

315.00

Hydrocell

16.10

19.00

16.15

213.75

Water bars

16.60

19.00

16.15

213.75

3.00

1.80

90.00

Metal works for walkway and Railings

KG

Curtain Grouting

kg

Hard stone lining

Steel lining (20 mm thick)

Railings

1.00

0.85

11.25

m3

121.50

137.00

34.25

7,706.25

m2

334.00

375.00

225.00

11,250.00

rm

12.50

14.00

8.40

420.00

4.30

5.00

4.00

70.00

14.00

16.00

10

HDPE pipe of 75mm

11

Sub-Base Laying (15m. Thick)

rm
m3

12

Sub-Grade Preparation

m2

13

Backfilling by compaction

Nyadi Hydropower Limited

1,200.00
90.00
85.00

23

Hydro Consult

Nyadi Hydropower Project


Feasibility Study volume III

Table F 13. Tunnel Excavation Rate

Nyadi Hydropower Limited

24

Hydro Consult

Nyadi Hydropower Project


Feasibility Study volume III

Table F 14. Energy Calculation Sheet of NHP

NYADI HYDROPOWER PROJECT, FEASIBILITY STUDY


POWER AND OUTPUT ENERGY CALCULATION
Gross head, m

333.90 m

Overall efficiency

85.47%

Dry season outage

4%

Wet season outage

4%

D/s release m3/s

0.31 m3/s

Length of tunnel

3937.0 m

Turbine

Generator

Transformer

Overall

Shotcreted tunnel

2737.0 m

90.50%

97.00%

99.50%

87.35%

Concrte lined tunnel

1200.0 m

89.00%

97.00%

99.00%

85.47%

Length of penstock

675.4 m

Manning's coefficient

0.015 For concrete

Friction coeficient

0.022 For shotcrete

Tunnel Diameter

3.20

Area

Height to the stringer

1.60

Perimeter

9.14 m2
11.43 m
40.00%

Probability excedence, %
Design flow, m3/s

11.08

Penstock Diameter, m

1.75
Flow

Month
(Nepali)

Nyadi

Available

Intake Flow flow in Siuri

available in

Available

Operating

Siuri

Flow

days

Design flow

Headloss

Headloss

Headloss

Total

HW

HRT

Penstok

Headloss

Net head

Generation
capacity

Tailrace
(m3/s)

Baishakh
Jestha
Ashar
Shravan
Bhadra
Ashoj
Kartik
Mangsir
Poush
Magh
Falgun
Chaitra

Adopt

(m3/sec)

4.38
9.31
24.94
40.12
35.34
21.44
9.94
5.45
3.75
3.38
3.08
3.34

(m3/s)

(m3/s)

(m3/s)

(kW)

Energy for
Rural
Electrification
(kWh)

Energy for
Pumping

(kWh)

Dry season

Wet season

energy (after

energy (After

deduction

deduction

outage, RE and

outage,RE and

Pumping)
(kWh)

Pumping))
(kWh)

0.68

0.64

4.71

31

4.71

0.155

0.571

1.144

1.871

332.03

13105.79

22,500.00

148333.50

9,189,849

1.62

1.40

10.40

31

10.40

0.756

2.791

5.589

9.136

324.76

28329.98

22,500.00

296667.00

19,915,237

3.87

1.40

26.04

32

11.08

0.857

3.165

6.339

10.361

323.54

30000.00

22,500.00

0.00

22,095,900

7.46

1.40

41.21

31

11.08

0.857

3.165

6.339

10.361

323.54

30000.00

22,500.00

0.00

21,404,700

7.83

1.40

36.43

31

11.08

0.857

3.165

6.339

10.361

323.54

30000.00

22,500.00

0.00

21,404,700

4.62

1.40

22.54

31

11.08

0.857

3.165

6.339

10.361

323.54

30000.00

22,500.00

0.00

21,404,700

2.28

1.40

11.04

30

11.04

0.850

3.141

6.289

10.280

323.62

29944.90

22,500.00

296667.00

20,378,747

1.36

1.32

6.46

29

6.46

0.291

1.077

2.156

3.525

330.38

17900.24

22,500.00

296667.00

1.04

1.00

4.44

30

4.44

0.138

0.509

1.019

1.665

332.23

12372.83

22,500.00

296667.00

8,232,931

0.79

0.75

3.82

29

3.82

0.102

0.376

0.753

1.230

332.67

10649.31

22,500.00

148333.50

6,944,608

0.58

0.54

3.31

30

3.31

0.077

0.283

0.567

0.926

332.97

9248.89

22,500.00

148333.50

6,221,996

0.43

0.39

3.42

30

3.42

0.081

0.301

0.602

0.985

332.92

9533.32

22,500.00

148333.50

6,418,600

11,641,058

Maximum Power Generation, kW

30,000.00

Total seasonal Energy, kWh

27,818,136

Annual generation, GWh

27.82

Total energy, GWh

147.43
175.25

Ratio of wet season energy with dry season energy

Nyadi Hydropower Limited

147,434,892

5.30

25

Table F15. Benefit calculation sheet of NHP


Nyadi Hydropower Project
Major Assumptions:

(USD in '000)
Typical Disbursement percentage

Capacity

MW

Exchange Rate (US$)

NRs.

Base Project Cost


Cost Overrun
Financing Cost
Construction Insurance Cost

US$
0%
2%

30.00

Total Project Cost

US$

60,019

30%

18,006

Debt Portion

70%

42,013

Interest Rate

After Capitalization

58,842
1,177 of Project Cost
of Project Cost

Equity Portion

Loan Payback Period

Construction P Year 1

75

14%

Per Annum

10

Years

74218

37.84%

22265

Year 2

Year 3

Year 4

Year 5

Year 6

Year 7

100.0%

0.0%

0.0%

0.0%

0.0%

0.0%

0.0%

2
3
4
5

60.0%
30.0%
20.0%
20.0%

40.0%
40.0%
20.0%
20.0%

0.0%
30.0%
30.0%
20.0%

0.0%
0.0%
30.0%
20.0%

0.0%
0.0%
0.0%
20.0%

0.0%
0.0%
0.0%
0.0%

0.0%
0.0%
0.0%
0.0%

15.0%

15.0%

15.0%

15.0%

25.0%

15.0%

0.0%

15.0%

12.0%

13.0%

15.0%

15.0%

15.0%

15.0%

51953
Actual Project Cost (USD'000)

64279

TRUE
Construction Period Years
Total Project Cost

Investment Outlays

4
0th year

Cost %

1st Year
1.5%

Amount (USD '000)

2nd Year

18.5%
964

3rd Year

20.0%

11,892

4th Year

30.0%

5th Year

30.0%

12,856

6th Year

0.0%

SUM Check

7th Year

0.0%
-

0.0%
-

TRUE

19,284

19,284

20.0%
8,403

30.0%
12,604

30.0%
12,604

0.0%
-

0.0%
-

0.0%
-

TRUE

20.00%
4,453

30.00%
6,680

30.00%
6,680

0.00%
-

0.00%
-

0.00%
-

TRUE

Debt
Debt %
Amount (USD '000)

0.0%
-

20.0%
8,403
Equity

20.00%
964

Equity %
Amount (USD '000)

3,489

O&M Cost

2.00%

of Project Cost

Corporate Overhead and Insurance


Replacement Cost (USD '000) (% of Total E/M Cost)

1.50%
2625

of Project Cost

Inflation Rate per year

20 th year

at 350 per KW EM cost

5%
Other Important Input Factors

Royalty:

BPC's S/H
2%

1 - 15 Years

100.00%

Employee Bonus
1.33 USD/KW installed

2%

Salvage Value of Assets

Working Capital

30

Dividend Payout

95%

% of PAT

10%

16 - 50 Years

13.33 USD/KW installed

Discount Rate
Income Tax

Days

14.0%
21.5%
Total
Energy Production ( GWh)

Dry
175.25

Outage and Station Use % of Total Energy


Outage Energy (GWh)

0.00%
0.00

Tariffs as per PPA

Total

Wet
27.82

147.43

Dry

Wet

Interest Factor

Tariff Rate (NRs/KWh)

6.30

6.30

6.30

Tariff Rate (USD/KWh)

0.0840

0.0840

0.0840

Escalation on Tariff per year from day of PPA

6%
0%

Depreciation Year

25

Depreciation %/Year

of FCFs

for Project CF

10 for Yrs
onwards

4.00%

Financial Analysis Worksheet


Fiscal Years

(USD in '000)
Construction Periods

Develop
2067/68
2011

Years #
Year of Operation
Total Energy (GWh) Produced
Dry
Wet
Energy for Outages (GWh)
Tariffs (USD/KWh)
Dry
Wet
Total Revenue from Energy Sale

Cost of Energy production (USD/KWh)


Costs
Development
Construction Cost
Running Cost
O&M Cost
Corporate Overhead and Insurance
M&E Replacement Cost
Royalty
Working Capital
Total Cost
Operating Income
Depreciation
Interest
Earning before Tax
Tax
EBIT
Total Cost including Tax
Profit After Tax (PAT)

2012
1

2013
2

2014
3

Commercial Operation Starts

2015
4

2016
5

2017
6

2018
7

2019
8

1
175.25
27.82
147.43
0.084
0.084
0.084
14,721

2
175.25
27.82
147.43
0.089
0.089
0.089
15,604

3
175.25
27.82
147.43
0.094
0.094
0.094
16,488

0.0077

0.0075

0.0073

11,892

12,856

19,284

19,284

964
(964)
(964)

11,892
(11,892)
(11,892)

12,856
(12,856)
(12,856)

106
19,389
(19,389)
(19,389)

1,430
1,073
334
2,838
11,883
2,571
8,034
1,278

1,502
1,126
352
2,981
12,624
2,571
7,619
2,434

1,577
1,183
370
3,130
13,358
2,571
7,145
3,641

964
-

11,892
-

12,856
-

19,284
(19,284)
(19,284)
19,284
-

(0)
19,389
-

9,312
2,838
1,278

10,053
2,981
2,434

10,787
3,130
3,641

964

11,892

12,856

19,284

2020
9

4
175.25
27.82
147.43
0.00
0.099
0.099
0.099
17371

2021
10

5
175.25
27.82
147.43
0.00
0.104
0.104
0.104
18254

2022
11

6
175.25
27.82
147.43
0.00
0.109
0.109
0.109
19137

2023
12

7
175.25
27.82
147.43
0.00
0.114
0.114
0.114
20021

2024
13

8
175.25
27.82
147.43
0.00
0.119
0.119
0.119
20904

2025
14

9
175.25
27.82
147.43
0.00
0.124
0.124
0.124
21787

2026
15

10
175.25
27.82
147.43
0.00
0.129
0.129
0.129
22670

2027
16

11
175.25
27.82
147.43
0.00
0.134
0.134
0.134
23554

2028
17

12
175.25
27.82
147.43
0.00
0.134
0.134
0.134
23554

2029
18

13
175.25
27.82
147.43
0.00
0.134
0.134
0.134
23554

2030
19

14
175.25
27.82
147.43
0.00
0.134
0.134
0.134
23554

2031
20

15
175.25
27.82
147.43
0.00
0.134
0.134
0.134
23554

2032
21

16
175.25
27.82
147.43
0.00
0.134
0.134
0.134
23554

2033
22

17
175.25
27.82
147.43
0.00
0.134
0.134
0.134
23554

2034
23

18
175.25
27.82
147.43
0.00
0.134
0.134
0.134
23554

2035
24

19
175.25
27.82
147.43
0.00
0.134
0.134
0.134
23554

2036
25

20
175.25
27.82
147.43
0.00
0.134
0.134
0.134
23554

2037
26

21
175.25
27.82
147.43
0.00
0.134
0.134
0.134
23554

2038
27

22
175.25
27.82
147.43
0.00
0.134
0.134
0.134
23554

2039
28

23
175.25
27.82
147.43
0.00
0.134
0.134
0.134
23554

2040
29

24
175.25
27.82
147.43
0.00
0.134
0.134
0.134
23554

2041
30

25
175.25
27.82
147.43
0.00
0.134
0.134
0.134
23554

2042
31

26
175.25
27.82
147.43
0.00
0.134
0.134
0.134
23554

2043
32

27
175.25
27.82
147.43
0.00
0.134
0.134
0.134
23554

28
175.25
27.82
147.43
0.000
0.134
0.134
0.134
23554

2044
33
29
175.25
27.82
147.43
0.000
0.134
0.134
0.134
23554

0.0071

0.0069

0.0065

0.0068

0.0064

0.0061

0.0065

0.0061

0.0062

0.0063

0.0064

0.0065

0.0076

0.0077

0.0078

0.0080

0.0119

0.0083

0.0084

0.0086

0.0087

0.0089

0.0079

0.0081

0.0083

0.0085

1,656
1,242
387

1,739
1,304
405

1,826
1,369
423

1,917
1,438
440

2,013
1,510
458

2,113
1,585
476

2,219
1,664
493

2,330
1,748
511

2,447
1,835
511

2,569
1,927
511

2,697
2,023
511

2,832
2,124
511

2,974
2,230
2,755

3,123
2,342
2,755

3,279
2,459
2,755

3,443
2,582
2,755

3,615
2,711
8,466
2,755

3,795
2,847
2,755

3,985
2,989
2,755

4,184
3,138
2,755

4,394
3,295
2,755

4,613
3,460
2,755

4,844
3,633
2,755

5,086
3,815
2,755

5,341
4,005
2,755

5,608
4,206
2,755

3,285
14,085
2,571
6,605
4,909

3,448
14,806
2,571
5,990
6,245

3,618
15,520
2,571
5,288
7,660

11,514
3,285
4,909

12,235
3,448
6,245

12,948
3,618
7,660

3,795
16,225
2,571
4,488
9,166
985
13,654
4,780
8,181

3,980
16,923
2,571
3,576
10,776
1,158
14,352
5,139
9,618

4,174
17,613
2,571
2,536
12,505
1,344
15,042
5,519
11,161

4,377
18,293
2,571
1,351
14,371
3,090
15,722
7,467
11,281

4,589
18,965
2,571
16,394
3,525
16,394
8,113
12,869

4,793
18,761
2,571
16,190
3,481
16,190
8,273
12,709

5,007
18,547
2,571
15,976
3,435
15,976
8,441
12,541

5,231
18,322
2,571
15,751
3,386
15,751
8,618
12,365

5,467
18,086
2,571
15,515
3,336
15,515
8,803
12,179

7,960
15,594
2,571
13,023
2,800
13,023
10,759
10,223

8,220
15,334
2,571
12,763
2,744
12,763
10,964
10,019

8,493
15,061
2,571
12,489
2,685
12,489
11,178
9,804

8,780
14,774
2,571
12,203
2,624
12,203
11,403
9,579

17,547
6,007
2,571
3,435
739
3,435
18,286
2,697

9,397
14,156
2,571
11,585
2,491
11,585
11,888
9,094

9,729
13,824
2,571
11,253
2,419
11,253
12,149
8,834

10,078
13,475
2,571
10,904
2,344
10,904
12,423
8,560

10,444
13,109
2,571
10,538
2,266
10,538
12,710
8,272

10,829
12,725
2,571
10,154
2,183
10,154
13,012
7,971

11,232
12,321
12,321
2,649
12,321
13,881
9,672

11,656
11,897
11,897
2,558
11,897
14,214
9,339

12,101
11,452
11,452
2,462
11,452
14,564
8,990

12,569
10,985
10,985
2,362
10,985
14,930
8,623

10,647

9,672

9,339

8,990

8,623

964

19,389

Net Benefit to the Project

11,883

12,624

13,358

14,085

14,806

15,520

15,240

15,765

16,269

15,204

15,440

15,280

15,112

14,936

14,750

12,794

12,590

12,375

12,150

5,268

11,665

11,405

11,131

10,844

Salvage Value of Assets


Salvage Value of Working Capital

Net Cost to The Project

106

(11,892)

(12,856)

(19,284)

(19,389)

11,883

12,624

13,358

14,085

14,806

15520

15240

15765

16269

15204

15440

15280

15112

14936

14750

12794

12590

12375

12150

5268

11665

11405

11131

10844

10647

9672

9339

8990

8623

19137
3618

20021
4780

20904
5139

21787
5519

22670
7467

23554
8113

23554
8273

23554
8441

23554
8618

23554
8803

23554
10759

23554
10964

23554
11178

23554
11403

23554
18286

23554
11888

23554
12149

23554
12423

23554
12710

23554
13012

23554
13881

23554
14214

23554
14564

23554
14930

5268
54

9672
193

9339
187

8990
180

8623
172

(964)

Net Cash Flow to the Project


FINANCIAL ANALYSIS FOR THE PROJECT
NPV Benefits (USD 000)
NPV Cost (USD 000)
NPV Benefits-Cost (USD 000)

Benefit Cost Ratio


IRR on the Project
FINANCING COSTS
Equity
Loans
Balance of Loan
Interest During Construction
Balance of Loan after Capitalization
Income
Total Costs including Tax

50019
40161
9858
1.25

16.99%
Year 0
964
-

Year 1
3,489
8,403
8,403
1,176
9,579

Year 2
4,453
8,403
17,982
2,517
20,499

Year 3
6,680
12,604
33,103
4,634
37,737

Year 4
6,680
12,604
50,341
7,048
57,389

Year 5
-

Year 6
-

Year 7
-

11,892

12,856

19,284

19,389

14,721
2,838

15,604
2,981

16,488
3,130

57389
11002

57389

57,389

1
11,002
8,034
2,968
54,421

2
11,002
7,619
3,383
51,038

3
11,002
7,145
3,857
47,181

Cash Inflow to the Project


Bonus
Debt Servicing
Deposits for Electromechanical Replacement
Withdrawl for Electromechanical Replacement
Cash Inflow for Equity Holders
Cash Outflow for Equity Holders

11,883
26

12,624
49

13,358
73

11,002
0

11,002
0

11,002
0

Net Cash Flow to Equity after Repayments


FINANCIAL ANALYSIS FOR THE SHAREHOLDERS
NPV Benefits (USD 000)
NPV Cost (USD 000)
NPV Benefits-Cost (USD 000)
Benefit Cost Ratio

17371
3285

18254
3448

Years

Capital and Interest Repayments


Total Loan Including IDC
Yearly Equal Payment
Interest Repayment
Principal Repayment
Balance of Loans (after Repayment)

51283

964

0
964
(964)

3489

4453

6680

(3,489)

(4,453)

(6,680)

6,680
(6,680)

855
855

1,573

2,283

1,573

2,283

4
11,002
6,605
4,397
42,784

5
11,002
5,990
5,012
37,772

6
11,002
5,288
5,714
32,058

7
11,002
4,488
6,514
25,543

8
11,002
3,576
7,426
18,117

10

11,002
2,536
8,466
9,651

11,002
1,351
9,651
-

11

12

13

14085
98

14806
125

15520
153

15240
164

15765
192

16269
223

15204
226

15440
257

15280
254

15112
251

14936
247

14750
244

12794
204

12590
200

12375
196

12150
192

11665
182

11405
177

11131
171

10844
165

10647
159

11002

11002

11,002
0

11,002
0

11,002
0

11,002
0

11,002
0

5,214

11,484

11,228

10,960

10,678

10,488

9,479

9,153

8,810

8,451

5,214

11,484

11,228

10,960

10,678

10,488

9,479

9,153

8,810

8,451

2,985

3,679

4,364

4,074

4,570

5,043

3,976

15,183

15,026

14,861

14,688

14,507

12,590

12,389

12,179

0.00
11,959

2,985

3,679

4,364

4,074

4,570

5,043

3,976

15,183

15,026

14,861

14,688

14,507

12,590

12,389

12,179

11,959

19722
13960
5762
1.41

26

Hydro Consult

Nyadi Hydropower Project


Feasibility Study Volume III

APPENDIX G
ACCESS ROAD AND BRIDGE
DESIGN REPORT

NYADI HYDROPOWER PROJECT


FEASIBILITY STUDY

October, 2010

Nyadi Hydropower Limited

Hydro Consult

Nyadi Hydropower Project


Access Road Design Report

Table of contents
Page no.
SUMMARY ................................................................................................................................... I
1. INTRODUCTION ................................................................................................................ 1
1.1
1.2
1.3
1.4
1.5

Background ...............................................................................................................................................1
Geomorphology and Geology ..............................................................................................................2
Climatic Condition ..................................................................................................................................2
Vegetation .................................................................................................................................................2
Hydrology and Meteorology .................................................................................................................3

2. ALIGNMENT SURVEY ....................................................................................................... 4


2.1
2.2
2.3
2.4
2.5
2.6

Introduction ..............................................................................................................................................4
Survey Procedure ....................................................................................................................................4
Discarded Road Alignment ...................................................................................................................4
Proposed Alignment Description ........................................................................................................4
Material survey .........................................................................................................................................5
Longitudinal Section and Cross Section .............................................................................................5

3. GEOMETRIC DESIGN STANDARDS ............................................................................... 6


3.1
3.2
3.3

3.4
3.5

3.6
3.7
3.8
3.9
3.10
3.11
3.12
3.13
3.14
3.15

Road Classification: Traffic and Loading .............................................................................................6


Design speed.............................................................................................................................................6
Horizontal Alignment .............................................................................................................................6
3.3.1
3.3.2
3.3.3

Horizontal Curvature............................................................................................................................... 6
Minimum radius of curvature ................................................................................................................. 7
Extra widening ........................................................................................................................................... 8

3.5.1
3.5.2
3.5.3

Vertical curve ............................................................................................................................................. 9


Summit Curve ............................................................................................................................................ 9
Valley Curve ............................................................................................................................................... 9

Super Elevation.........................................................................................................................................8
Vertical alignment ....................................................................................................................................9

Stopping Sight distance ........................................................................................................................ 10


Hair-Pin Bends....................................................................................................................................... 10
Drainage .................................................................................................................................................. 11
Pavement Design .................................................................................................................................. 11
Retaining structures ............................................................................................................................. 12
Cut/ Fill batter Slope............................................................................................................................ 13
Lateral clearance ................................................................................................................................... 13
Vertical clearance ................................................................................................................................. 13
Right of way ........................................................................................................................................... 13
Sign posts and Safety devices ............................................................................................................. 13

4. MEASURES FOR ENVIRONMENTAL PROTECTION ................................................. 14


4.1
4.2

Recommended species for bioengineering in the road sections ............................................... 14


Conclusions and recommendations ................................................................................................. 15

Nyadi Hydropower Limited

Hydro Consult

Nyadi Hydropower Project


Access Road Design Report

5. ACCESS ROAD COST...................................................................................................... 16


6. MARSYANGDI BRIDGE ................................................................................................... 17
7. CONCLUSION AND RECOMMENDATIONS .............................................................. 18
8. REFERENCES..................................................................................................................... 19
LIST OF TABLES

Page no.

Table 1-1 Salient feature of the access road..........................................................................................................1


Table 3-1 Widening of curve ..................................................................................................................................8
Table 3-2 Super Elevation .........................................................................................................................................9
Table 3-3 Sight distance .......................................................................................................................................... 10

Nyadi Hydropower Limited

ii

Hydro Consult

Nyadi Hydropower Project


Access Road Design Report

List of abbreviations
BH

Borehole

BPC

Butwal Power Company Ltd.

DHM

Department of Hydrology and Meteorology

DoR

Department of Roads

DoS

Department of Survey

km

Kilometer

Meter

m2

Square meter

MCT

Main Central Thrust

US $

United States Dollars

VDC

Village Development Committee

GON

Government of Nepal

NHP

Nyadi Hydropower Project

NHL

Nyadi Hydropower Limited

Nyadi Hydropower Limited

iii

Hydro Consult

Nyadi Hydropower Project


Access Road Design Report

SUMMARY
Background
The access road to the site of Nyadi Hydropower Project is designed as a district level road located
in Lamjung District. This road links Beshishar - Chame road at Thakanbeshi near Nyadi Bazaar to
Powerhouse site, Surge Shaft and headworks area of Nyadi Hydropower Project. Among two
alternatives studied, the proposed one proves to be better alignment for Access Road in terms of
geometric standard and cost effectiveness.
The length of the proposed access road will be about 9KM from its roadhead at Thakanbeshi
(Besishashar Chame road) at the right bank of Marsyangdi River near Nyadi Bazaar to Naiche
Village. Around 2KM road is also considered for access from Naiche Village to Headworks area for
the construction of the project. A 52.0m long major bridge will be constructed for crossing
Marsyangdi River at Thakanbeshi. In order to provide access to surge shaft location, additional 2.4KM
of road from Thulobeshi village to Surge Adit is considered as well. The access to the powerhouse
site can be provided by the construction of access tunnel with its starting point at Ch. 4+500 near
the proposed switchyard location.
Hence, the total length of the whole access road for the project will be about 13.45KM starting from
the existing Besisahar-Chame road.
Geometric Design Standards
This access road for Nyadi Hydropower Project falls under District Road Class A type according to
NRS 2045 and DoLIDAR 1998. This road as being the hill road is so designed by considering
minimum radius of curve of 12.5m, carriage way width 3.0m, formation width 4.50m and design speed
is 20kmph. The Right Of Way (ROW) of the access road is taken as 10m on each side of the road
centreline at most of the stetches except around those areas where the ROW can be reduced
depending upon field condition and design requirement. It is assumed that for design, the transport
unit has been taken less than 400 per day in this road and maximum axle wheel load is 14.4 tons.
Alignment Survey
First of all, Reconnaissance survey was done for fixing the alignment. After the completion of
reconnaissance survey, the tentative fixing of alignment was done using Abney level and tape. After
fixing tentative alignment, a traverse was run along the road corridor of specified width by using total
station instrument. In general, the alignment passes through steep slopes, forests and cultivated lands
while the few stretches have to pass through hard cliff.
Design
The design has been done according to Nepal Road Standard (First Revision 2045). Horizontal and
vertical curve has been provided as per necessity. Since the road is considered as hill road, some
hair-pin bends have been introduced as well to maintain the required gradient. The side slope of
filling and cutting of the road was so chosen to ensure the stability of the road in a balanced way.
Proper drainage system has been provided in order to prevent the road formation from further
damage due to monsoon flow. The side drains, both lined and unlined depending upon flow and
catchment area are kept along the route and drain out to the near-by natural water course or into
the meeting of cross-drainage structures. Gravel has been considered as the pavement material to be
used in Sub-base layer with no other layers considered. The use of retaining walls and structures has
been minimized as far as possible from viewpoint of economy and construction simplicity with some
stone masonry and gabion walls provided at unavoidable areas.

Nyadi Hydropower Limited

S-i

Hydro Consult

Nyadi Hydropower Project


Access Road Design Report

Measures for Environmental Protection


Mitigation measures are recommended to reduce, avoid or offset potential adverse environmental
consequences from implementing the project. The objective of mitigation measures is to maximize
project benefits and minimize the undesirable impacts. Bio engineering is one of the measures
commonly adopted. to ensuring ground stability as well as improving the environmental condition.
Access Road Cost
The cost of the access road has been obtained from the quantity surveying based on design works
and the rate analysis based on the standard norms of Nepal Road Standard. The estimated cost of the
whole access road (excluding VAT and Contingencies) is about NRs. 211,052,331.00. This is
subjected to change since the actual cost of construction may vary depending upon the modifications
made in design as per site condition during construction.
Conclusion and Recommendations
From all the informations provided in this report, it can be concluded that the selected alignment for
the access road is the most suitable and cost effective one from the viewpoint of topographic
stability, engineering and geological features of the project area, the road design parameters provided
and the overall economy. The environmental protection measures are considered to be satisfactory
in terms of its effectiveness. No such problem that may be imposed by this road seems to be
significant as compared to its usefulness. So, It is strongly recommended to effectively implement the
design during construction so that the road can successfully meet the objective for which it is made
and serve with its full capacity to its users for a long period of time.
It is worthy to mention here that during construction, the design may be altered depending upon
actual site condition. However, the variations in design and hence the quantity may require the
approval of Site Engineer to ensure quality control.

Nyadi Hydropower Limited

S-ii

Hydro Consult

Nyadi Hydropower Project


Access Road Design Report

1. INTRODUCTION
1.1 Background
Construction of Nyadi Hydropower Project requires an access road which provides an access to the
powerhouse site at Thulobesi of Bahundada VDC and reaches the headworks site of the same VDC.
At present, there is no motorable road except around 10 km long foot trail access from Nyadi
Bazaar.
The alignment of the road runs mostly along the river valley of the rain fed catchments of Nyadi
khola. The proposed access road starts from Besishar Chame road at Thakanbeshi and reaches up
to headworks site of NHP at Bahundada VDC. The primary objective of this road is to facilitate the
construction of NHP in time by making project accessible to the main road at Nyadi Bazaar. Further,
it will facilitate the people of Bahundada VDC of Lamjung district by making the area accessible using
vehicle from the existing motorable road. The access road project area is located on hilly areas of
Western Development Region of Nepal and it has been designed on the basis of Green (Agricultural)
Road concept with the flexibility in construction technique by the use of both man and machine so as
to reduce cost.
Table 1-1 Salient feature of the access road
S.N.
1.
2

4
5

6
6.1
6.2
6.3
6.4

6.5
6.6
7
8
9

Parameters
Name of the Project
Geographical location
Region
Zone
District
Geographical feature:
Climate
Geology
Hydrology
Meteorology
Classification:
Length of road
Starting point
End point
Total length of road
Design Criteria:
Design speed
Stopping Sight Distance
Gradient
Maximum gradient
Minimum gradient
Cross section
Right of way
Formation width
Carriage way
Shoulder
Side drain
Minimum horizontal curve radius
Pavement
Cross Drainage Structure
Bridge 52.0m span
0.6m dia Pipe Culvert
Retaining Structure
Gabion

Nyadi Hydropower Limited

Description
Nyadi Hydropower Project
Western Region
Gandaki
Lamjung
Sub-Tropical.
Mountainous.
Rain fed catchment of Nyadi khola
Unevenly distributed precipitation controlled by monsoon
District Rural Road Class 'A'
Upstream of Nyadi Bazaar at Thakanbeshi (Right Bank of
Marsyangdi River)
Proposed Headworks Site.
13.50KM
20 kmph.
20 m.
12.0%
0.5% to facilitate better drainage.
10 m from the road centerline on either side.
4.5 m.
3.0 m.
0.75 m.
Earthen Tick/ Trapezoidal Dry Stone/ Stone Masonry Drain
12.5m
Gravel (15 cm Thick)
1 no. (Proposed)
23 nos. (Proposed)
610m3

Hydro Consult

Nyadi Hydropower Project


Access Road Design Report

1.2 Geomorphology and Geology


The NHP lies within the Higher Himalayan Topographic Zone to the north of the Main Central
Thrust (MCT), which lies near the proposed surface powerhouse. The project area consists of
medium - to high - grade metamorphic rocks of the Lesser Himalaya and Higher Himalaya of
Precambrian age. The main rock types are gneisses, schist, and quartzite.
The Nyadi area is a narrow V- shaped valley, which was formed by vertical rock cliff at right bank and
steeply dipping colluviums and rock at left bank. Colluviums and alluvial deposits were located along
and side of the Khola at left bank and foothill. At some places, the Nyadi has made deep gorges by
cutting into bedrock and alluvial deposits, which reflect the rise of the Himalaya.

1.3 Climatic Condition


The climate of this area is monsoonal in character with a marked rainy season between June and
September. The annual rainfall in or around Nyadi catchment varies between 665 mm and 4436 mm
depending upon elevation.
Temperatures vary with altitude and slope facing. On ridge tops at an altitude of 3000 m, monthly
means temperature may vary from 15oC in January to 24oC in June. Valley bottoms are generally
warmer for very much longer periods and enjoy a sub-tropical warm temperate climate.
Local variations in climate have a significant influence on land use, and to a certain extent on
engineering works. North facing slopes are generally colder and retain more water in summer.
When uncultivated they support strong, forest vegetation which tends to stabilize slopes. South
facing slopes on the other hand are warmer and drier in summer and the combined effect of forest
clearance and cultivation makes them more susceptible to erosion. Many of the largest landslides are
located on south or south-east facing slopes. It is reported that many of these have been initiated by
continuous heavy rainfall during the monsoon.

1.4 Vegetation
The overall natural vegetation cover within the study area has been categorized as forests, shrub and
bushy land and agricultural land. Forests have been disrupted by fuel wood, fodder, timber collection
and extensive cultivation.
The vegetation along the Access Road consists of mixed forest. The different types of vegetation
along the road alignment are listed below.

Uttis (Alnus nepalensis)

Chilaune (Schima wallichi)

Kaphal (Myrica nagi)

Siris (Albizzia stipulata)

Katus (Castanopsis indica)

Gayo (Bridelia retusa)

Kyamun (Syzygium cerasoides)

Kutmiro (Litsea monopetala)

Sindhure (Mallaotus phillippinensis)

Gurans (Rhododendrun sps.)

Angeri (Pieris ovalifolia)

Mauwa (Bassia latifolia)

Simal (Bomex cebia),

Nyadi Hydropower Limited

Hydro Consult

Nyadi Hydropower Project


Access Road Design Report

Lapsi (Choerospondias axillaris)

The ground cover consists of Nigalo (Arundinaria sp), Chutro (Berberis aristata), Ainselu (Rubus
elipticus), Banmara (Eupatorium adenophorum), Titepati (Artimisia vulgaris), Ghodtapre (Centella
asiatica), etc.

1.5 Hydrology and Meteorology


A field visit was carried out for hydrological investigation of the Kholsa crossing of the proposed
road. It passes through a stretch of land of similar topographical and geological features, and
therefore, the hydrological characteristics of the cross drainage are quite similar. The catchment area
of such Kholsa crossing on the road is quite small. Most of the cross drainage are of seasonal type,
and there are flash flood during rainy seasons only.
The hydrology of the road corridor is strongly affected by the monsoon climate which makes the
rainfall pattern and its distribution the important features for the stability of terrain.

Nyadi Hydropower Limited

Hydro Consult

2.

Nyadi Hydropower Project


Access Road Design Report

ALIGNMENT SURVEY

2.1 Introduction
The access road under this design study is totally a new construction with only foot trails available in
the project area. This chapter deals with all the necessary survey works related to the design and
construction of the road.

2.2 Survey Procedure


Review of reports available before site investigation for road survey and the study of related
topographical map sheets was carried out so as to ensure the collection of all required information.
At first, a reconnaissance survey was done before fixing the alignment. After completion of
reconnaissance survey, the tentative fixing of alignment was done using Abney level and tape. After
fixing tentative alignment, detail engineering survey was done including traverse (Base line) survey
along the road corridor of specified width using total station. The base line was so set up that the
center line of the road would coincide with the traverse line. During survey, Total Station was used
to get all the necessary data and information to generate contour map of the proposed access road.
The base line system of the road has been connected to the grid system of Nyadi Hydropower
Project as the road runs through the project area.
For vertical control, benchmarks were provided on permanent structures at approximately 1000m
interval. Concrete pegs were driven at the places where permanent structures were not available.

2.3 Discarded Road Alignment


Marsyangdi River Bank Route
One of the options considered was the route to the proposed Marsyangdi bridge along the right
bank of Marsyangdi river by the use of Hair-Pin bends just after the starting point of the road. This
option is considered to be unsafe from flood hazard point of view in case of high flood in Marsyangdi
river, which may require river training structures to prevent the road from floods and may also be
longer than the proposed option. Hence, this option was discarded.
Route to Naiche along upper mid hills
Another option considered was the route to Naiche along upper mid hills from powerhouse area.
This option is regarded as unsuitable as it requires excessive excavation of hard and soft rocks by the
use of blasting technique As compared to this alternative, the proposed route along the left bank of
Nyadi River requires less rock excavation with minimum risk of flood damage. Hence, this route
along upper mid hills to Naiche is discarded.

2.4 Proposed Alignment Description


The road survey and design starts from Thakanbeshi at upper side of Nyadi Bazaar and meets the
proposed Headworks site at Bahundada VDC. The proposed road alignment mostly follows the
existing trail passing through the sloping areas having thin forest and cultivated lands and along the
right bank of Nyadi river as well keeping in mind that the length will be the shortest one. In order to
maintain the slope of formation level of access road within the permissible value, several hair pin
bends have been provided along the road alignment.

Nyadi Hydropower Limited

Hydro Consult

Nyadi Hydropower Project


Access Road Design Report

2.5 Material survey


Based on the investigation during the field trip, all the required materials like cement, reinforcement
bar, gabion-wire etc should be transported from Besishar, Lamjung. Gravel, sand, boulder and
aggregate are available at the Nyadi Khola and Marsyangdi River. In some areas, boulders are locally
available as well.

2.6 Longitudinal Section and Cross Section


For longitudinal section, field survey should include reduced levels of ground at regular intervals of
road centerline. Similarly, for cross-section, ground information at either side of at least right of way
of road centerline has been obtained from survey. As per Scope of Works, cross sections at 20m
interval were assessed from the topographical survey. All the required details of longitudinal section
and cross section has been shown in drawings provided in Annex D.

Nyadi Hydropower Limited

Hydro Consult

Nyadi Hydropower Project


Access Road Design Report

3. GEOMETRIC DESIGN STANDARDS


3.1 Road Classification: Traffic and Loading
According to the Nepal Road Standard (NRS)-2045, roads can be classified as follows:
1.
2.
3.
4.
5.

National Highway
Feeder Roads
District Roads
City Roads
Village Roads (According to revised NRS)

The access road for Nyadi Hydropower project falls under District Road according to NRS (First
Revision-2045). For the purpose of movement of heavy laden vehicles, the carriage way and
formation width (total width of the road) were taken as 3.0 m and 4.5 m respectively. It is assumed
that for design, transport unit has been taken less than 400 per day in this type of road. The
maximum axle load standard is 14.4 tons for the design of pavement.

3.2 Design speed


The design speed is the most important factor for controlling the geometric design elements of
highways. It is one of the deciding factors as per the overall requirement of the road. In Nepal,
different speed standards have been assigned according to the class of road and the topography of
the area. From design standards, the design speed of vehicle in this type of District road is 20 kmph.

3.3 Horizontal Alignment


3.3.1 Horizontal Curvature
The alignment was chosen and surveyed following the existing trails as far as possible. Horizontal
curves are designed as circular curves according to the alignment data taken during field survey. The
curves are designed as a. The design procedures of simple circular curves are given below:
Where,
I. P.

= Intersection point

T1

= Commencement of tangent

T2

= Point of tangency

BC

= Beginning of Curve

EC

= End of Curve

Ax

= Apex distance from I. P.

R.

= Radius of curvature

= Deflection angle

Nyadi Hydropower Limited

Hydro Consult

Nyadi Hydropower Project


Access Road Design Report

The various parameters of curves were calculated by taking appropriate value of Radius of curvature
and Deflection Angle, which are obtained actually noted from the field work.
Then,

Tangent length = R.tan


2


Apex distance = R. sec 1
2
Curve length =

R
180 0

Now,
a)

Chainage of commencement of tangent = Chainage of I. P. - Tangent length

b)

Chainage of termination of tangent = Chainage of commencement of tangent + curve


length

c)

Chainage of apex point = Chainage of commencement of tangent + 0.5 x curve length

d)

Chainage of supporting I. P.= Chainage of termination of preceding I. P. + I. P. to I.P


distance - Tangent length of preceding I. P.

When centerline of the road deviates from its original position, the horizontal curve is introduced to
facilitate the safe and smooth movement of vehicles.
3.3.2 Minimum radius of curvature
Empirical Formula has been given for obtaining the minimum radius of horizontal curve as below:
R = V2/(127*(e+f)
Where,
R = Radius in m,
V = Design Speed in kmph,
e = superelevation in m per m,
Nyadi Hydropower Limited

Hydro Consult

Nyadi Hydropower Project


Access Road Design Report

f = frictional coefficient taken as 0.15.


Since the road lies in steep mountainous area, minimum radius of horizontal curves adopted is 12.5
m as referred to the prevailing design practice of hill roads in Nepal.
3.3.3 Extra widening
The extra widening of road should be provided for safe and comfortable turning of vehicles at curves.
Widening includes mechanical and psychological widening. The widening can be calculated using the
following empirical formula
We

= (nL2/ 2R) + V/(9.5R)

Where, We= extra widening


N= number of traffic lanes
L= length of wheel base (6.1 m)
V= design speed (40 km/h)
R= radius of curve
The empirical formula has been modified into tabular form using adopted values for varying radius
with reference to the design trend for the sake of design simplicity, which is presented in Table 3-1.
Table 3-1 Widening of curve
Radius of inner edge of carriage
way(m)
From

Widening on curves in m.
No. of lanes

To

Soft verges

Hard verges

>1.5m

<1.5m

12.5

2.0

2.0

12.6

20

1.5

1.5

21

40

1.2

1.2

41

60

0.8

0.8

61

80

0.5

0.5

81

100

0.3

0.3

101

1000

0.0

0.0

Full width of the adopted extra widening of the road has been applied for the whole part of the
corresponding horizontal curve. The transition has been provided at the rate of 0.1m per m along
the straight portions as there is no provision made for transition curve.

3.4 Super Elevation


Super Elevation is required at places where the alignment passes through horizontal curves in order
to counteract the centrifugal force that will be produced while vehicle encounters those curves. The
pavement is raised at a particular rate of super elevation depending upon the radius of curve and the
design speed. Super elevation can be calculated by using the following empirical formula:

e = V2/(127*R)-f
Nyadi Hydropower Limited

Hydro Consult

Nyadi Hydropower Project


Access Road Design Report

Where,
e = superelevation in m per m,
V = Design Speed in kmph,
R = Radius in m,
f = frictional coefficient taken as 0.15.
This empirical formula has been modified in tabular form for compatibility in design as presented in
Table 3-2.
Table 3-2 Super Elevation

Radius (m)
From
To
0.0
20.0
20.0
35.0
35.0
55.0
55.0
80.0
80.0
1000.0

SE (%)
7.0
6.0
5.0
4.0
3.0

The maximum super elevation of 7% has been adopted while


the minimum value should be equal to the road camber of 3% as per design trend.

3.5 Vertical alignment


The average road grade along the vertical alignment has been kept under ruling ie. 8%-9% while for
maximum road grades which is 12%, relax grade of 7% - 8% has been provided as per standard.
3.5.1 Vertical curve
When the gradient changes abruptly, the vertical curves have been introduced in order to provide
smooth movement of the vehicle. All the vertical curves are parabolic in nature and they have been
avoided in the areas of horizontal curves as far as possible while at unavoidable cases, the grade
compensation has been made.
The design of vertical curves is done considering the sight distance available. The criterion to be
adopted is that the minimum sight distance shall be equal to the stopping sight distance laid down.
Vertical curve may be either summit curve or valley curve and the length of the curve can be
calculated as below:
3.5.2 Summit Curve
The length of summit curve which depends upon stopping sight distance can be calculated as below:
1. When L > S, L = AS2 / 4.4
2. When L < S, L = 2S - 4.4/ A
3.5.3 Valley Curve
The length of summit curve should be such that for night travel, the headlight beam distance is equal
to the stopping sight distance. Based on this criterion, the length of curve can be calculated as below:
Nyadi Hydropower Limited

Hydro Consult

Nyadi Hydropower Project


Access Road Design Report

1. When L > S, L = AS2 / (1.5+0.035S)


2. When L < S, L = 2S - (1.5+0.035S)/ A
Where, L = Length of vertical curves in m
S = Stopping Sight distance in m
A = deviation angle ie. algebraic difference between approaching road grades
Ht. of eye = 1.0 meter
Ht. of lowest object visible = 0.10 meter
Headlight height = 0.75m

3.6 Stopping Sight distance


The stopping sight distance is the clear distance needed by a driver to bring his vehicle to stop before
collision. This is calculated as the sum of braking distance required by the vehicle during perception
and brake reaction time.
Minimum stopping sight distances shall be as presented in Table 3-3.
Table 3-3 Sight distance
Design speed kmph

Minimum stopping sight distance meter


200
145
110
85
65
45
30
20

120
100
80
60
50
40
30
20

3.7 Hair-Pin Bends


Hair-pin bends have been provided at various places to keep the road grade under ruling and to keep
the alignment in track. It consists of either circular curves with transition curves at each end or
compound circular curves. The latter case has been considered in this design.
Following design criteria has been adopted in the design of Hair-pin bend:
a) Minimum design speed: 20kmph
b) Minimum road width: 6.5m
c) Minimum radius for inner curve: 12.5m
d) Gradient: 7% - 8%
e) Superelevation: 7%

Nyadi Hydropower Limited

10

Hydro Consult

Nyadi Hydropower Project


Access Road Design Report

The inner and the outer edges of the roadway should be concentric with respect to the
centreline of the road.
A minimum intervening length of 60m has been provided as far as possible between two
successive bends to enable the driver for smooth vehicle manoeuvre.

3.8 Drainage
The drainage system has been designed in order to drain out the surface run off along the pavement
to the nearest natural water course. Following empirical formulae have been applied in the design of
Side drains and Cross drainage structures:
Rational method of Rainfall-Runoff:
Q=0.28*C*I*A
Where, Q= discharge in cumecs.
C= run-off coefficient.
I= Rainfall intensity in mm/hr.
A= Catchment area in sq. km.
Mannings formula: Q= A*(1/n)*R^(2/3)*S^(1/2)
Where, Q= discharge in cumecs.
A= Cross-sectional area of flow in sqm.
n= roughness coefficient.
R= Hydraulic Radius in m.
S= Bed slope.
The nature of hydrology is almost similar in majority of the sections of the road alignment The side
drains, the size and shape of which has been fixed from design using above formulae are kept along
the route. The flow coming from side drains has been designed to discharge properly to the near-by
natural water course or into the meeting cross-drainage structures using drop structures of standard
design at suitable places.
With regard to cross drainage structures, pipe culvert using NP3 0.6m dia hume pipe has been
considered in most of the cases to control the surface drainage due to existing waterways. This
minimum size has been selected in view of easy handling and transportation, maintenance ease during
choking and economy as well.

3.9 Pavement Design


Gravel road has been considered as the pavement surface of the access road. Hence, the design of
pavement includes determination of the thickness of gravel sub base. CBR (California Bearing Ratio)
method has been adopted for design in which the pavement thickness is governed by the number of
commercial vehicles per day and the CBR value of the natural sub-grade, assumed to be 400 and 15%
respectively. The graph below illustrates the determination of pavement thickness using CBR
method.

Nyadi Hydropower Limited

11

Hydro Consult

Nyadi Hydropower Project


Access Road Design Report

3.10 Retaining structures


Retaining structures also referred as retaining walls have been designed in order to protect the road
components above them from possible damage because of the applied thrust. The size and type of
retaining walls depend upon the nature of ground and the materials to be used. The walls should be
strong enough to withstand the lateral earth pressure. Following formula has been widely applied in
the design of retaining walls:
Rankines formula:
P=w/2*(h2)*(1-sinF)/ (1+sinF) where, P=lateral earth pressure per meter of wall.
w=unit weight of soil.
h=height of wall
F=angle of repose of soil.
The height of retaining wall in the valley side is governed by the level difference between the
pavement edge and the natural ground below it. The wall height has been provided in such a way to
maintain as far as possible the horizontal and vertical exposure of 1m and 0.5m respectively. The
base width of retaining wall should be kept about 0.6 times the height. Other wall details has been
provided as such to withstand the lateral earth pressure imposed below the road. during design,
mostly gabion retaining walls and dry stone walls in some cases have been used the details of which
are provided in drawings attached in separate access road design report.

Nyadi Hydropower Limited

12

Hydro Consult

Nyadi Hydropower Project


Access Road Design Report

3.11 Cut/ Fill batter Slope


Cut/fill slope designs are normally based on geo-technical parameters, such as soil and rock
properties, terrain slope, water tables and height of cut slope. However, for simplicity, the following
roadside slopes as indicated in the design manual have been used in this design:

Cut slope for hard rock 1H : 6V

Cut slope for soft rock 1H : 4.5V

Cut slope for Boulder and Gravel Mixed Soil 1H : 3V

Cut slope for soft soil 1H : 2V

Normal embankment slope in filling 1.5H : 1V

Maximum embankment slope in filling 1 : 1 with plantation

3.12 Lateral clearance


For culverts, the full roadway width shall be carried through including the width of the shoulders.
For minor and medium bridges, minimum width between kerbs shall be one meter greater than the
approaching pavement width.

3.13 Vertical clearance


Minimum vertical clearance for through structures shall be 4.75 meters. Overhead wires, poles etc.
shall be at least 7.0 meters above the road surface.

3.14 Right of way


For rural road, the minimum right of way and distance between building lines will be 20 m (10 m on
either side of the road center line).

3.15 Sign posts and Safety devices


The standard design for kilometer stones and traffic signs issued separately by the Department of
Roads has been followed which is necessary for providing useful information to the road users and
ensuring safe and smooth flow of the vehicles in the road.
Similarly, Safety devices are devices that are required at various places on the road to provide safety
and reduce accidents while driving. Delineators, Guard blocks using gabion baskets or concrete
barriers, barbed wire fences etc. are commonly used safety devices that should be provided at the
places of high risk of accidents.

Nyadi Hydropower Limited

13

Hydro Consult

Nyadi Hydropower Project


Access Road Design Report

4. MEASURES FOR ENVIRONMENTAL PROTECTION


Mitigation measures are recommended to reduce, avoid or offset potential adverse environmental
consequences during and after implementation of the projects. The objective of mitigation measures
is to maximize project benefits and minimize undesirable impacts. The following prescribed mitigation
measures will be useful to mitigate the adverse impacts due to the implementation of the proposed
projects.

Check dams and retaining wall to control the soil erosion,

Bioengineering methods in landslide prone areas,

Blasting activities not to be allowed in fragile areas,

Cutting of trees in landslide prone areas to be avoided,

Cultivation and grazing in the sloping area and illegal cutting of trees to be strictly
prohibited,

Haphazard disposal of construction materials to be controlled, the construction materials


to be piled up in barren land as far as possible to protect the ground vegetation,

Major portion of excavated muck to be utilized in cut and fill operation and the remaining
muck to be used for backfilling of quarry and burrow pits and for land reclamation,

The excavated muck to be levelled and surface runoff by monsoon rain to be properly
drained out ,

Excavated muck not to be placed at steep sloping areas,

The forest clearance to be minimized by cutting trees of formation width only as far as
possible,

As a compensatory measures, plantation to be done around the road alignment

Nursery to be established as one of the compensatory measures,

Awareness campaign on forest conservation and management to be conducted to


improve the forest condition of the road and surrounding environment.

4.1 Recommended species for bioengineering in the road sections


GRASSES

Phurke (Arynduella nepalensis)

Khar (Cymbopogon microtheca)

Napier (Pennisetum paniceum)

Amliso (Thysanolaena maxima)

SHRUBS

Chutro (Berberis aristata)

Ainselu (Rubus elipticus)

Areli (Acacia pennata)

Nyadi Hydropower Limited

14

Hydro Consult

Nyadi Hydropower Project


Access Road Design Report

TREES

Chilaune (Schima wallichi)

Jamun (Syzygium cumini)

Kutmiro (Litsea monopetala)

Rato siris (Albizia julibrissin)

The plants that should never be used for bioengineering are listed below

Banmara (Eupatorium adenophorum)

Tite Pate (Artemisia vulgaris)

Patula salla (Pinus patula)

Sagawan/teak (Tectona grandis)

4.2 Conclusions and recommendations


Every road project can have several impacts upon the economical, biological, physical and social
environment. Road construction especially in hills has become serious problem from bio-engineering
point of view. Therefore, special attention should be given for slope stability, soil erosion and
siltation problems.
The following recommendations are proposed to minimize the adverse environmental impacts in the
vicinity of the road.
i.

Effective maintenance program to minimize clay run-off from road surface.

ii.

Establishment of nurseries along the road side.

iii.

Periodical reforestation on and off roadside for soil conservation.

Nyadi Hydropower Limited

15

Hydro Consult

Nyadi Hydropower Project


Access Road Design Report

5. ACCESS ROAD COST


The quantity surveying work like the volume calculation of earthwork, retaining structures, side
drains, cross drainage structures and pavement materials has been done as per the design of the
access road based on Nepal Road Standard. The unit rates of different items of work have been
obtained from the rate analysis based on the norms of Road department of Nepal. The total project
cost of the access road has been computed from the quantity and rate analysis works and found to
be about NRs. 131,923,314.67 excluding VAT and Contingencies with per KM average cost of about
NRs. 9,772,097.38. The details of quantity and cost calculation of the access road have been provided
in access road design report separately. Though, this figure may subject to change since the actual
cost of construction may vary depending upon the modifications made in design as per site condition
during construction. Hence, the actual cost of road can be obtained only after measuring the quantity
of the completed construction works.

Nyadi Hydropower Limited

16

Hydro Consult

Nyadi Hydropower Project


Access Road Design Report

6. MARSYANGDI BRIDGE
In order to link the project area with the existing road head, the access road has to cross Marsyangdi
river. Hence, a bridge has been proposed to fulfill the accessibility requirement of the project having
its location at about 1.1KM upstream of the Marsyangdi-Nyadi confluence. The proposed bridge not
only provides access to the project area but also connects several villages like Thulobeshi and Naiche
of Bahundanda VDC to the existing motorable road. Hence, this bridge should be given utmost
importance and be made an integral part of access road for overall development of the surrounding
area of the project.
The bridge has been designed as bailey bridge with its length of about 52.0m. The estimated cost of
the bridge as obtained from design comes out to be NRs. 25,517,784.00. The details of technical
aspects regarding the bridge design have been provided in the bridge design report separately.

Nyadi Hydropower Limited

17

Hydro Consult

Nyadi Hydropower Project


Access Road Design Report

7. CONCLUSION AND RECOMMENDATIONS


From all those included in this report, it can be concluded that the selected alignment for the access
road is the most suitable and cost effective one from the viewpoint of topographic stability,
engineering and geological features of the project area, the road design parameters provided and the
overall economy. The environmental protection measures are considered to be satisfactory in terms
of its effectiveness.
As far as design is concerned, the effort has been made in route selection to follow the existing trails
as much as possible. This result in the reduction of the project cost and allows the users to take
maximum benefit from the road.
With regard to cross drainage structures, they have been proposed entirely to protect the road
from water related problems like surface run off as well as ground water movement. Besides, the
selected road alignment does not possess major hydrological problems because of the provision of
well designed drainage system.
In general, the proposed access road and the bridge is not only important in facilitating the
construction works of the project but also in bringing social, cultural, economical transformation by
providing access to the nearest market area and consequently increasing the professional activity of
the local people under the catchment area. No such problem that may be imposed by this road
seems to be significant as compared to its usefulness.
With due considerations to all the things mentioned above, It is strongly recommended to effectively
implement the design during construction so that the road can successfully meet the objective for
which it is made and serve with its full capacity to its users for a long period of time.
It is worthy to mention here that during construction, the design may be altered depending upon
actual site condition. However, the variations in design and hence the quantity and cost should be
submitted for the approval of Site Engineer for effective quality control.

Nyadi Hydropower Limited

18

Hydro Consult

Nyadi Hydropower Project


Access Road Design Report

8. REFERENCES
IRC

Various books of IRC publications with revisions.

DHM:

Climatologic records of Nepal.

Lamjung District

District Rate

DoLIDar, 1998

Technical Specifications for Agricultural and Rural Roads. Ministry of Local


Development, Transport Division. 1999

DoLIDar, 1998

Work Norms for Agricultural and Rural Roads. Ministry of Local Development,
Transport Division. 1999

DoLIDar, 1999

The Approach for the Development of Rural and Agricultural Roads. Ministry of
Local Development, Transport Division. 1998

DOR

A Hand Book of Roadside Bio- Engineering

DOR

A Reference Manual of Roadside Bio-Engineering

DOR

Nepal Road Standard (NRS) - 2045 Government of Nepal (GoN), Ministry of


Works and Transport, Department of Road (DOR)

GON1:50000 & 1: 25000


Topographical Maps. Government of Nepal (GON), Department of
Survey
GON

Standard design;
Design Section Government of Nepal (GON), Ministry of
Works and Transport, Department of Road (DOR)

ICIMOD

Mountain Risk Engineering. International Centre for Integrated Mountain


Development, Kathmandu, Nepal.

Khanna, S. K & Justo,

C. E. G. Highway Engineering. Seventeenth Edition, 1991. Nem Chand &


Bros., Civil Lines, Roorkee 1971

NRA District Profile


Vazirani

Highway Engineering.

19

Hydro Consult

Nyadi Hydropower Project


Feasibility Study Volume III

APPENDIX H
PHOTOGRAPHS

NYADI HYDROPOWER PROJECT


FEASIBILITY STUDY

October, 2010

Nyadi Hydropower Limited

Hydro Consult

Nyadi Hydropower Project


Feasibility Study Volume III

LIST OF PHTOGRAPHSPAGE NO.


PHOTO H. 1 PROPOSED NHP WEIR AXIS AND INTAKE SITES..................................................................................................1
PHOTO H. 2 PROPOSED NYADI HEADWORK SITES .....................................................................................................................1
PHOTO H.3 UPSTREAM OF HEADWORKS SITES .............................................................................................................................2
PHOTO H. 4 GAUGING STATION AND INTAKE SITES.................................................................................................................2
PHOTO H.5 PROPOSED NAIJE PORTAL AREA ..................................................................................................................................3
PHOTO H. 6 HILL THROUGH WHICH TUNNEL PASSES ..............................................................................................................3
PHOTO H. 7 HILL THROUGH WHICH TUNNEL PASSES ..............................................................................................................4
PHOTO H. 8 TUNNEL PORTAL AND SURGE ADIT AREA ............................................................................................................4
PHOTO H. 9 PENSTOCK ALIGNMENT AREA ....................................................................................................................................5
PHOTO H.10 STEEP SECTION OF PENSTOCK AREA (SURFACE OPTION) ...........................................................................5
PHOTO H. 11 SURFACE POWERHOUSE AREA .................................................................................................................................6
PHOTO H. 12 SURFACE POWER AREA DOWNSTREAM OPTION ..........................................................................................6
PHOTO H. 13 SURFACE POWER AREA DOWNSTREAM OPTION ..........................................................................................7
PHOTO H. 14: SURFACE POWERHOUSE AREA UPSTREAM OPTION ....................................................................................7
PHOTO H. 15 UNDERGROUND POWERHOUSE LOCATION....................................................................................................8
PHOTO H. 16 SWITCYARD LOCATION .............................................................................................................................................8

Nyadi Hydropower Limited

H-i

Hydro Consult

Nyadi Hydropower Project


Feasibility Study Volume III

PHOTO H. 1 PROPOSED NHP WEIR AXIS AND INTAKE SITES

PHOTO H. 2 PROPOSED NYADI HEADWORK SITES

Nyadi Hydropower Limited

H-1

Hydro Consult

Nyadi Hydropower Project


Feasibility Study Volume III

PHOTO H.3 UPSTREAM OF HEADWORKS SITES

PHOTO H. 4 GAUGING STATION AND INTAKE SITES

Nyadi Hydropower Limited

H-2

Hydro Consult

Nyadi Hydropower Project


Feasibility Study Volume III

PHOTO H.5 PROPOSED NAIJE PORTAL AREA

PHOTO H. 6 HILL THROUGH WHICH TUNNEL PASSES

Nyadi Hydropower Limited

H-3

Hydro Consult

Nyadi Hydropower Project


Feasibility Study Volume III

Nana

Tunnel level

PHOTO H. 7 HILL THROUGH WHICH TUNNEL PASSES

PHOTO H. 8 TUNNEL PORTAL AND SURGE ADIT AREA

Nyadi Hydropower Limited

H-4

Hydro Consult

Nyadi Hydropower Project


Feasibility Study Volume III

PHOTO H. 9 PENSTOCK ALIGNMENT AREA

PHOTO H.10 STEEP SECTION OF PENSTOCK AREA (SURFACE OPTION)

Nyadi Hydropower Limited

H-5

Hydro Consult

Nyadi Hydropower Project


Feasibility Study Volume III

PHOTO H. 11 SURFACE POWERHOUSE AREA

PHOTO H. 12 SURFACE POWER AREA DOWNSTREAM OPTION

Nyadi Hydropower Limited

H-6

Hydro Consult

Nyadi Hydropower Project


Feasibility Study Volume III

PHOTO H. 13 SURFACE POWER AREA DOWNSTREAM OPTION

PHOTO H. 14: SURFACE POWERHOUSE AREA UPSTREAM OPTION

Nyadi Hydropower Limited

H-7

Hydro Consult

Nyadi Hydropower Project


Feasibility Study Volume III

PHOTO H. 15 UNDERGROUND POWERHOUSE LOCATION

PHOTO H. 16 SWITCYARD LOCATION

Nyadi Hydropower Limited

H-8

You might also like