Professional Documents
Culture Documents
Feasibility Study
Final Report
Volume III Technical Annex
Appendix D
Appendix E
Appendix F
Appendix G
Appendix H
Design calculation
Optimization study
Cost estimate and financial
Analysis
Access road design report
Photographs
October, 2010
Design calculation
Optimization study
Cost estimate and financial
Analysis
Access road design report
Photographs
Quality control
Prepared by:
Signature
Date
Basanta Bagale
Lochan Devkota
Sumin Shrestha
Basanta M. Shrestha
Uttam Dhakal
Checked by:
Approved by:
October, 2010
Report Contents
EXECUTIVE SUMMARY
VOLUME 1
MAIN REPORT
VOLUME 2
INVESTIGATION ANNEX
APPENDIX A HYDROLOGY AND SEDIMENTOLGY
APPENDIX B TOPOGRAPHICAL SURVEY
APPENDIX C SITE INVESTIGATION (GEOLOGY AND
GEOTECHNICAL
VOLUME 3
TECHNICAL ANNEX
APPENDIX D DESIGN CALCULATION
APPENDIX E OPTIMIZATION STUDY
APPENDIX F COST ESTIMATE AND FINANCIAL
ANALYSIS
APPENDIX G ACCESS ROAD DESIGN REPORT
APPENDIX H PHOTOGRAPHS
VOLUME 4
Hydro Consult
APPENDIX D
DESIGN CALCULATION
October, 2010
HYDRAULIC DESIGN
Weir Hydraulics
Orifice Design
Settling Basin Design
Penstock Design
Anchor Block Design
Surge Tank Design
Headloss Calculation Sheet
Power and Output Energy Calculation
HEC RAS Result
Turbine Design Calculation
Tailrace Tunnel Design
Level Determination of Powerhouse and tailrace
Hydro Consult
Weir Hydraulics
NOTE : The design of the Headworks Weir Arrangment has been done on the basis of Hydraulic Model Studies carried out at Hydro Lab Pvt Ltd. The detailed information
about the study result has been compiled on Hydraulic Model Study of the Headworks of Nyadi Hydropower Project.
Weir
26.50
21.00
8.000
10.21
12.000
m3/sec
m
masl
Cd
m
m
m
m
509.00
14.00
1381.50
2.10
26.50
10.21
21.00
57.71
Q = CLH
Head over the crest
m
U/S TEL
masl
Water level elevation U/S of the weir can be determined using the Bernoulli's equation and iteration
6.69
1388.19
m
m
m
1372.90
15.29
14.93
m
m
masl
1387.83
0.87
1388.70
3/ 2
Ec
y1 =
q
2 g ( E o y1 )
1372.9+14.93
Depths of cutoffs
Scour depth U/S and D/S of the floor is determined by Newzealand Formula.
[Equation provided by Bharat Raj Pandey and used in Marsyangdi-III Hydroelectric Project (MHEP-III)]
Discharge intensity
q
m3/s/m
U/S Water Depth
Velocity of Flow
Cross Sectional Area of Flow
Width of Flow
Constant
Y
V
A
B
k
dS
m
m/s
m
m
=k.Y.V.B/A
=1.25 ds
1387.83-7.97
1371.5-1379.86
m
m
m
m
masl
=1.50 ds
1378.07-9.57
m
m
m
m
masl
masl
m
m
Page 1 of 2
36.36
14.93
2.66
209.04
14.00
0.62
6.38
7.97
1379.86
-8.36 Cutoff Not Necessary
8.00 ADOPT
1371.50
1369.00
8.00
6.00
1363.50
1363.00
6.00
masl
masl
m
[Reference: DWPF page no. 74 & 75 (Case 4 and Case 5) and table VII-5 of page no. 100]
Check for Thickness
For 100 yrs flood
U/S portion upto the just below the orifice
Total downstream forces acting (F1) = Weight of water over the concrete + Weight of the concrete
HFL
Low Flow
Assume thickness
2.2 m
2m
Upward force (uplift pressure)
160.20938 KN/m2
122.625 KN/m2
Downward force (weight of concrete +Weight of water)
213.00938 KN/m2
170.625 KN/m2
Factor of saftey
1.400 ok
1.330 ok
U/S portion upto sloping portion starting from just below the orifice
Total downstream forces acting (F1) = Weight of water over the concrete + Weight of the concrete
HFL
Low Flow
Assume thickness
2.2 m
2.6 m
Upward force (uplift pressure)
160.20938 KN/m2
122.625 KN/m2
Downward force (weight of concrete +Weight of water)
213.00938 KN/m2
160.5 KN/m2
Factor of saftey
1.310 ok
1.330 ok
sloping portion
Total downstream forces acting (F1) = Weight of water over the concrete + Weight of the concrete
HFL
Low Flow
Assume thickness
3m
2.8 m
Upward force (uplift pressure)
160 20938 KN/m2
160.20938
139 2272 KN/m2
139.2272
Downward force (weight of concrete +Weight of water)
211.2272 KN/m2
206.4272 KN/m2
Factor of saftey
1.490 ok
1.320 ok
Stilling Basin
Total downstream forces acting (F1) = Weight of water over the concrete + Weight of the concrete
HFL
Low Flow
Assume thickness
3.2 m
3.2 m
Upward force (uplift pressure)
160.20938 KN/m2
160.20938 KN/m2
Downward force (weight of concrete +Weight of water)
216.0272 KN/m2
216.0272 KN/m2
Factor of saftey
note: this thickness can reduced gardually upto 1.5m
1.350 ok
1.350 ok
b
a
=b/d
=
GE per
GE
G E
1+
1+ 2
2
=1/6
h
1
d
Page 2 of 2
9.761
57.710
57.710
97.710
8.143
97.710
8.143
4.602
4.602
0.167
0.167
0.155
0.121
OK
OK
Hydro Consult
ORIFICE DESIGN-1
Date
Job :
Job No:
Calculated by:
Checked by:
Design Considerations/Assumptions
1. The intake opening will be submerged orifice, and may be open during full flushing
2. The orifice will be above river bed level to exclude bigger sediment
3. The top level of the orifice will be just below normal water level so that floatinig debris can be excluded,
4. The design discharge is 11.08 m3/sec
5. Velocity will be limited to 0.5 to 1.1 m/s during normal flow conditions for the exclusion of bed load and floating load to remain at the trash rack (Ref: Emile Mosony 2/A)
6.
7.
8.
9.
20% of the design discharge is taken as Flushing discharge at gravel trap and settling basin during the period of continuous flushing
Normal water level 1381.5 m
River bed level at intake is taken as 1371.6
During high flood condition the radial gate will open accordingly
1 Input Data
Percentage Exceedence
~40 %
11.08 m3/sec
10%
10%
0.60
3.50
3
0.50
0.01
0.25
2.25
1381.5
1376.5
m/s
m
nos
m
m
m
m
m
m
9 81 m/sec2
9.81
Plan sketch
2 Calculation
2.1 During Normal Flow Condition
3
1.108 m /sec
3
1.108 m /sec
3
13.30 m /sec
22.16
7.25
8
6.51
m2
m
Nos
m
3.40 m
OK
22.79 m2
1380.00 m
0.05 m
1381.45 m
3
13.67 m /s
Orifice size is ok
0.60 m/s
Velocity Ok
TRUE
3
3.50
2.25
0.25
0.50
Nos
m
m
m
m
I:\ED\Jobs\OPEN\751220 Nyadi Implementation\03Reports\Final Review 30 MW as per Damodar Hydrology_23 Nov\VOLUME III - Technical Annex\Appendix D - Design Calculations\2.Orifice self sheet Q=11.08_November 22, 2010.xlsx
Hydro Consult
Design flow (Q T)
3
1.108 m /sec (10% of design flow)
12.188 m /sec
No of basin
1 nos
first trial
3
12.188 m /sec
0.2 mm
0.02 m/sec
1.5 cm/sec
Water temperature
15 0C
Assume inlet transition 1:5 expansions, which gives the performance parameter m = 1/5 (very good performance)
Use Vetter's equation and Hazen's method to calculate Settling basin surface area:
Performance parameter m
1-h = (1+m w Ap/Q) (-1/m)
h = 1 - e - (w*A/Q)
= 0.125
A, m2
A, m2
2200
2190
2180
2170
2160
2150
2140
2130
2120
2110
2100
2090
2080
2070
2060
2050
2040
2030
2020
2010
2000
1990
1980
1970
1960
1950
1940
1930
1920
1910
1900
1890
1880
1870
1860
1850
1840
1830
1820
1810
1800
1790
1780
1770
1760
1750
1740
1730
1720
1710
1700
1690
1680
1670
1660
1650
1640
1630
1620
1610
1600
1590
1580
1570
1560
1550
1540
0.973
0.973
0.972
0.972
0.971
0.971
0.970
0.970
0.969
0.969
0.968
0.968
0.967
0.967
0.966
0.965
0.965
0.964
0.964
0.963
00.962
962
0.962
0.961
0.961
0.960
0.959
0.959
0.958
0.957
0.956
0.956
0.955
0.954
0.954
0.953
0.952
0.951
0.950
0.950
0.949
0.948
0.947
0.946
0.945
0.944
0.943
0.942
0.942
0.941
0.940
0.939
0.938
0.937
0.935
0.934
0.933
0.932
0.931
0.930
0.929
0.928
0.926
0.925
0.924
0.923
0.921
0.920
2500
2480
2460
2440
2420
2400
2380
2360
2340
2320
2300
2280
2260
2240
2220
2200
2180
2160
2140
2120
2100
2 00
2080
2060
2040
2020
2000
1980
1960
1940
1920
1900
1880
1860
1840
1820
1800
1780
1760
1740
1720
1700
1680
1660
1640
1620
1600
1580
1560
1540
1520
1500
1480
1460
1440
1420
1400
1380
1360
1340
1320
1300
1280
1260
1240
1220
1200
1180
93.856%
h
Vetters equation
0.964
0.963
0.962 Hazen's equation
0.961
0.960
0.959
0.958
0.958
0.957
0.956
0.955
0.954
0.953
0.951
0.950
0.949
0.948
0.947
0.946
0.944
0.943
0 943
0.942
0.940
0.939
0.938
0.936
0.935
0.933
0.931
0.930
0.928
0.926
0.925
0.923
0.921
0.919
0.917
0.915
0.913
0.911
0.909
0.906
0.904
0.902
0.899
0.897
0.894
0.891
0.889
0.886
0.883
0.880
0.877
0.874
0.871
0.867
0.864
0.860
0.857
0.853
0.849
0.845
A used
0.841
0.837
0.832
0.828
0.823
= 1 e
wA s
1 = (1 + mwA / Q
Page 1 of 2
1700
)( 1 / m )
Hydro Consult
1530
1520
1510
1500
1490
1480
1470
1460
1450
1440
1430
1420
1410
1400
1390
1380
1370
1360
0.919
0.917
0.916
0.915
0.913
0.912
0.910
0.909
0.907
0.906
0.904
0.903
0.901
0.899
0.898
0.896
0.894
0.893
1160
1140
1120
1100
1080
1060
1040
1020
1000
980
960
940
920
900
880
860
840
820
1
12.188
8.000
212.50
7.74
0.819
0.814
0.809
0.804
0.798
0.793
0.787
0.781
0.775
0.769
0.763
0.756
0.749
0.742
0.735
0.727
0.720
0.712
2
3
8.8542
6.094
4.063
13.281
8.000
8.000
13.28 Width and Length ratio OK
106.25
70.83
3.87
2.58
(ref. Civil works guidelines for micro- hydropower in Nepal, page # 73)
Adopt
25
Horizontal transition)
39.5
28800 (8 hrs)
10,000 ppm
2600
0.5
3510144
2700 1
2700.1
3.08
6.952
10 kg
Kg/m3
Kg
m3
m
m.
7.00 Adopted
1377.50 m
1370.50 m
6.625 m
Stable
Stable
particle
particle
h,
b,
m,
a,
p,
R,
n,
h:m
0.40
0.50
1.00
0.20
1.30
0.15
0.015
0.43
0.50
1.00
0.22
1.36
0.16
0.015
0.45
0.50
1.00
0.23
1.40
0.16
0.50
0.50
1.00
0.25
1.50
0.17
s,
1350.1 m3
6.09 m3/sec
4.88 m3/sec
25.00
8.00
93%
2
106.00
3.90
3.08
7.98
m.
m
3
m /s
0.02
2.71
0.54
33.85
305.00
0.02
2.76
0.59
34.78
316.26
0.015
0.02
2.79
0.63
35.36
323.29
0.015
0.02
2.86
0.71
36.67
339.35
nos.
m
m
m
m
Adopted
25.00
8.00
93.00%
2.00
128.00
4.50
3.75
10.30
Page 2 of 2
mm
m/s
report
mm
Q,
The present table shows that at any height the deposited sediments will be flushed out.
Flushing time calculation for intermittent flushing of single chamber
Sediment volume in settling basin
Design inflow to settling basin
Inflow to settling basin during flushing
Flushing discharge (when
committee
formula
v,
m.
m
nos.
m
m
m
m
Hydro Consult
CALCULATION FORM
Date:
Job: Nyadi HP
Job no.
Input Datas
Drg. No.
Calc. by
30 years
Design Discharge(Q)=
12.19 m3/s
1381.50 m
1032.00 m
Gross Head=
Length of headrace Tunnel (L)=
Basanta Bagale
751220 Chkd.
347 m
3955.00 m
3.20
9.141 m2
11.427 m
0.8 m
19.635 m2
Concrete
0.015
66.667
Is calculated from
Manning's
Strickler Formula
= 1.1*L/(K^2)/(R^(4/3))
1.318059579
Damping Factor(m)=
0.014044698
1.75 m
2.405 m2
1m
1.843
Hydro Consult
CALCULATION FORM
Date:
Job no.
Job: Nyadi HP
Drg. No.
hs > 1.5*Vp^2/2/g
where,
hs= Submergence Head
Vp= Velocity in Penstock
g= acceleration due to gravity
Vp =Q/Ap
Where,
At= X-section area of Tunnel
Q= Discharge through Tunnel
12.19 m3/sec
3.2 m
At=
9.141 m2
Vt=
1.333 m/s
Gordon (1970)
S = kv d
S= submegence (ft.)
k= coefficient 0.3 for symmetrical approach
0.30
0.40
Submergence (S)
1.73 m
Submergence (S)
4.80 m
Submergence (S)
0.14 m
4.800 m
Prosser (1977)
S = 1.5d
ITDG Manual
v2
S 1.5
2g
Calc. by
751220 Chkd.
Basanta Bagale
Hydro Consult
CALCULATION FORM
Date:
Job: Nyadi HP
Job no.
Summary
Drg. No.
Calc. by
Basant Bagale
751220 Chkd.
Downsurge
Max. Surge
Surge Level(m)
1390.288
9.012
9.012
Max. Surge(m)
1367.665
12.485
1376.604
4.672
1367.665
12.485
5m
1.712 m
Submergence head=
4.8 m
So,
Total surge in Surge Shaft=
21.497
Now,
Static Water level=
1381.5 masl
1390.288 masl
1367.665 masl
1392.000 masl
1360.265 masl
22.623
1392
1.712
Elevation to
Height(m) Thickness(m)
Reinforcement
(t)
Volume of
concrete
Wt. of Concrete
1362.224
1363.224
1.000
0.398879524
orifice
1363.224
1370.046
6.822
0.9
2.285
877.8524706
219.4631176
1370.046
1376.868
6.822
0.7
1.656
823.843969
205.9609922
1376.868
1383.690
6.822
0.5
1.065
771.550023
192.8875057
1383.690
1390.512
6.822
0.3
0.513
720.9706326
180.2426581
3194.217095
798.5542738
Chainage,
Anchor
Identific-
Hor.
Verical
defln
Angle with
Angle
horizontal
Ver. delection
Easting
X
Northing
Y
m (from
angle degree
PS
TP
VB1
VB2
CB3
VB4
VB5
CB6
VB7
'Degree'
0.00
0.00
0.00
0.00
11.24
0.00
0.00
1.62
0.00
a 'Degree'
1 0.00
2 17.45
3 39.71
4 93.62
5 156.02
6 213.07
7 273.07
8 333.075
9 393.066
0.5
0.83
0.83
6.14
16.97
35.28
22.29
21.36
12.83
0
-0.01
5.31
10.83
18.31
-12.99
-0.93
-6.61
-12.83
541632.30
541632.97
541633.82
541635.89
541638.28
541629.31
541619.88
541610.45
541602.02
3134827.46
3134810.02
3134787.78
3134733.91
3134671.55
3134615.21
3134555.95
3134496.70
3134437.30
10 440.616
VB8
0.00
14.75
-14.75
541595.33
3134390.23
No.
ation/SOP
Anc to anch.
hor distance,
Bend angle
Bend angle
Anticlockwise(upturn) -ve
55.35
Cumulative
Ground
Invert
Level , masl
Level, m
0.00
17.45
39.71
93.93
159.18
229.07
293.92
358.34
419.87
1393.95
1380.24
1362.72
1349.74
1331.08
1290.71
1265.11
1241.64
1227.98
1355.50
475.22
1213.76
Length
of pipe, m
Invert
level diff,
m
Pipe
Groundinvert
height,
Thickness
m
-38.45
-24.99
-7.79
-0.61
-1.00
-1.00
0.00
0.00
0.00
0.00%
-1.46%
-1.44%
-10.76%
-30.52%
-70.76%
-41.00%
-39.11%
-22.77%
10
10
10
10
16
16
22
22
1227.980
0.00
0.25
0.32
5.80
19.04
40.37
24.60
23.47
13.66
1213.320
14.66
-0.44
-26.34%
1355.25
1354.93
1349.125
1330.080
1289.710
1265.111
1241.643
475.22 m
Pipe Summary:
underground
1750
ID Pipe L
1750 ID Pipe L
200.16 m
675.38 m
stock Start, TP = Tunnel Portal, VB= Vertical Bend, CB= Combined bend
Uphill
ground
Gradient
1450
ID
Pipe L
1000
ID
11.00 m
Pipe L
Transition
(1.751.45)
43.23 m
1.2 m
slope, i
Allowable
bearing capacity
22
30
30
30
30
30
25
25
25
25
160
160
160
160
160
160
160
160
160
22
20
160
Steel Specification
Required Safety Factor
Steel Density
Water Density
Welding efficiency
1 USD
Rate of Steel
1381.5
1034.5
11.08
347.00
675.38
200,000
350
350
350
SAILMA 350
2.5
7850
1000
0.9
71.25
170.5
Qd
Hg
Lp
E
S
SF
Rate of Steel
Nos of turbine units
Number of nozzle in each turbine units
Surge Head
NOTE:
t w = (Pi * d * FOS /( 2 * y * w ) ) + 2
Effective Thickness =
Pi = w * g * H T
V =
<20mm THK
20~40mm THK
>40mm THK
4 * Qd
*d2
kg/m3
kg/m3
Rs
Rs/kg
Surge Head = 0.15 x Static Head
Water Hammer =10 ~15 % of static head (Refer:E. mosonyi, Pg 715 (old))
2.39 USD/kg
3
2
15% Static Head
Penstock permissible velocity for properly settled water with respect to abrassion, v = 3 to 5 m/sec
(Refer: Mosonyi High Head Power Plants Volume Two/A page 330)
Segment #1
Static head
Length of penstock
Diameter, d, mm
m
m
m3/s
m
m
N/mm2
N/mm2
N/mm2
N/mm2
51.42 m
159.22 m
Elevation
1330.08 m
1250
1350
1450
1550
1650
1750
1850
1950
9.03
4.40
8
7.74
4.65
8
6.71
4.90
8
5.87
5.15
8
5.18
5.40
8
4.61
5.65
8
4.12
5.90
8
3.71
6.15
8
4.88
5.11
5.34
5.57
5.80
6.03
6.26
6.49
0.58
7.71
59.13
4.10
OK
41
0.58
7.71
59.13
3.92
OK
45
0.58
7.71
59.13
3.75
OK
48
0.58
7.71
59.13
3.59
OK
51
0.58
7.71
59.13
3.45
OK
55
0.58
7.71
59.13
3.32
OK
58
0.58
7.71
59.13
3.20
OK
61
0.58
7.71
59.13
3.08
OK
65
Segment #2
Static head
Length of penstock
Diameter, d, mm
105.00 m
124.02 m
Elevation
1274.20 m
1250
1350
1450
1550
1650
1750
1850
1950
9.03
8
7.74
10
6.71
10
5.87
10
5.18
10
4.61
12
4.12
12
3.71
12
7.88
8.35
8.82
9.29
9.76
10.23
10.70
11.17
1.18
15.75
120.75
2.54
OK
32
1.18
15.75
120.75
3.00
OK
44
1.18
15.75
120.75
2.84
OK
47
1.18
15.75
120.75
2.69
OK
50
1.18
15.75
120.75
2.56
OK
53
1.18
15.75
120.75
2.93
OK
68
1.18
15.75
120.75
2.80
OK
72
1.18
15.75
120.75
2.69
OK
76
157.00 m
176.63 m
Elevation
1222.20 m
1250
1350
1450
1550
1650
1750
1850
1950
9.03
12
7.74
12
6.71
14
5.87
14
5.18
14
4.61
16
4.12
16
3.71
16
10.79
11.49
12.19
12.89
13.60
14.30
15.00
15.71
1.77
23.55
180.55
2.78
OK
69
1.77
23.55
180.55
2.61
OK
75
1.77
23.55
180.55
2.87
OK
94
1.77
23.55
180.55
2.71
OK
100
1.77
23.55
180.55
2.57
OK
107
1.77
23.55
180.55
2.80
OK
129
1.77
23.55
180.55
2.67
OK
137
1.77
23.55
180.55
2.55
OK
144
Segment #4
Static head
Length of penstock
Diameter, d, mm
Penstock flow velocity,V m/s
Gross thickness, mm
232.75 m
75.75 m
Elevation
1156.20
1250
1350
1450
1550
1650
1750
1850
1950
9.03
16
7.74
18
6.71
18
5.87
20
5.18
20
4.61
22
4.12
22
3.71
25
Page 2of 3
15.02
16.07
17.11
18.15
19.19
20.23
21.28
22.32
2.63
34.91
267.66
2.66
OK
40
2.63
34.91
267.66
2.80
OK
48
2.63
34.91
267.66
2.63
OK
52
2.63
34.91
267.66
2.75
OK
62
2.63
34.91
267.66
2.61
OK
66
2.63
34.91
267.66
2.72
OK
76
2.63
34.91
267.66
2.59
OK
81
2.63
34.91
267.66
2.80
OK
97
Segment #5
Static head
Length of penstock
Diameter, d, mm
Penstock flow velocity,V m/s
Gross thickness, mm
1250
9.03
18
16.98
3.02
40.16
307.91
2.65
OK
21
Segment #6
Static head
Length of penstock
Diameter, d, mm
Penstock flow velocity,V m/s
Gross thickness, mm
1250
9.03
20
18.94
3.42
45.41
348.16
2.64
OK
23
267.75 m
35.00 m
1350
7.74
20
Diameter, d, mm
Penstock flow velocity,V m/s
Internal Pressure, N/Mm^2
Gross thickness, mm
Effective thickness, teff mm
Surge Head, Hs m
Total Head, Htot m
Factor of safety
Check
Weight of steel, ton
weight of steel
weight of steel with Wastage (5%)
Cost of steel, USD
Selected Diameter =
Section
Length of penstock of section, m
Static Head, m
Surge Head, m
Total Head, m
Pipe Thickness. mm
Pipe weight. Ton
Penstock pipe
Expansion Joints
Stifners, saddle, wear plate
Weight of 1.45 m dia pipe
Weight of 1 m dia pipe
Total weight of Steel
Total Cost of steel, USD
1121.20
1450
6.71
20
1550
5.87
22
1650
5.18
22
1750
4.61
25
1850
4.12
25
1950
3.71
28
18.18
19.38
20.58
21.78
22.98
24.18
25.37
3.02
40.16
307.91
2.75
OK
25
3.02
40.16
307.91
2.58
OK
27
3.02
40.16
307.91
2.67
OK
31
3.02
40.16
307.91
2.53
OK
33
3.02
40.16
307.91
2.72
OK
40
3.02
40.16
307.91
2.59
OK
42
3.02
40.16
307.91
2.76
OK
50
302.75 m
35.00 m
1350
7.74
22
Segment #7
Static head
Length of penstock
Elevation
Elevation
1086.20
1450
6.71
22
1550
5.87
25
1650
5.18
25
1750
4.61
28
1850
4.12
28
1950
3.71
30
20.30
21.65
23.01
24.36
25.72
27.07
28.43
3.42
45.41
348.16
2.71
OK
27
3.42
45.41
348.16
2.54
OK
29
3.42
45.41
348.16
2.72
OK
36
3.42
45.41
348.16
2.57
OK
38
3.42
45.41
348.16
2.72
OK
45
3.42
45.41
348.16
2.59
OK
48
3.42
45.41
348.16
2.64
OK
54
351.45 m
69.76 m
Elevation
1030.05
1250
1350
1450
1550
1650
1750
1850
1950
9.03
3.96
22
7.74
3.96
25
6.71
3.96
25
5.87
3.96
28
5.18
3.96
28
4.61
3.96
30
4.12
3.96
32
3.71
3.96
36
21.67
23.24
24.81
26.39
27.96
29.53
31.11
32.68
52.72
404.17
2.54
OK
51
52.72
404.17
2.69
OK
62
52.72
404.17
2.52
OK
67
52.72
404.17
2.65
OK
80
52.72
404.17
2.50
OK
85
52.72
404.17
2.54
OK
96
52.72
404.17
2.57
OK
109
52.72
404.17
2.75
OK
129
277
305
730218
326
369
882081
363
402
961225
410
455
1089938
436
503
1203093
513
539
1289963
549
640
1530931
614
722
1727929
1750 mm
Segment#1
Segment#2
159.22
51.4
7.7
59.13
8
58
539
16
15
5.10
8.74
124.02
105.0
15.8
120.75
12
68
Segment#3
176.63
157.0
23.6
180.55
16
129
Segment#4
Segment#5
75.75
232.8
34.9
267.66
22
76
Ton
Ton
Ton
Ton
Ton
584 Ton
1,397,277.11
Page 3of 3
35.00
267.8
40.2
307.91
25
40
Segment#6
35.00
302.75
45.4
348.16
28
45
Segment#7
69.76
351.45
52.72
404.17
30
96
Hydro Consult
CALCULATION SHEET
Job Nyadi Hydropower Project (NHP)
Subject Anchor Block Design
Calculated By:
Date
Checked By:
ANCHOR BLOCKChainage:
Length of Penstock
Weir Level
Anchor Block Level
Ground Level
Young's Modulus ,E
Design Discharge, Q
Nominal wall thicknesss, t
Pipe internal diameter,d
Pressure wave velocity, a
Velocity in Penstock, v
Critical time, Tc
Closure time, T
Nos of turbine units
Number of nozzle in each turbine units
E
Q
t
d
a
v
Tc
T
CB3
0+156.02
675.38
1381.50
1330.08
1331.08
200000
11.08
16.00
1750
976.236
4.61
1.38
6
3
2
30
m
masl
masl
masl
N/mm2
m3/sec
mm
mm
m/s
m/s
sec
sec
Unitweight
g of concrete
gconcrete
3
24.00 kN/m
Unitweight of steel
gsteel
3
78.50 kN/m
Unitweight of soil
gsoil
3
18.00 kN/m
Friction coeff
Coefficien of friction of soli
f
m
0.25
0.50
2
160.00 kN/m
11.241
16.97
35.28
D
a
b
1/2 the distance betn u/s pier to anchor block L1u
Expansion
Safe When Check against overturning
Safe When Check on bearing capacity
Safe When Check against sliding
Contraction
Safe When Check against overturning
Safe When Check on bearing capacity
Safe When Check against sliding
4.00 m
4.00 m
piers
L2u
8.00 m
L4u
65.89 m
L4d
5.65 m
7
6
65.24 m
1.00
6.00
7.30
6.00
9.00
4.00
2.00
0.00
1.000
4
3
2
B
L
hu
hd
h1
h2
m
m
m
m
0.010
Base width
Base thickness
7.50
1.00
0
-1.00
14.6 4.866667
29.2 48.6666667
0.4 4.055556 4.866667
m
m
Projection Depth =
Page 1of 2
1.00
3.00
5.00
7.00
9.00
Surge head
Gross head
hs
hgross
51.420 m
76.40 m
7.30
2.433
6.00
Total head
htotal
127.823 m
7.30
4.00
3.397
0.667
3.397
0.667
2.433
6.00
3
215.393 m
2.433 m
= 1X7.3/3
V = B(L/3*hu+0.5*2L/3*(hu-hd)+(PD+hd)*2/3L)-pi ((d+t
6.00
5169.44 kN
WB = 215.393429762801X24
0.01
WP = 3.142X1.766X0.016X78.5
WW = 3.142X1.75^2*9.8/4
7.30
F1u = (23.57+6.97)X4XCOS(3.142X16.9720801281178/
Weight of block
V
WB
Weight of pipe
WP
6.97 kN/m
Weight of water
WW
23.57 kN/m
F1u
116.84 kN
7.30
F1d
99.72 kN
F2u
58.42 kN
525.78 kN
= 58.42X9
F3 v
959.75 kN
F3 = 2gX3.142X127.822646281088X1.75^2/4XSIN(3.142X(35.281999258953-16.9720801281178)X0.5/180)
F3 H
590.780 kN
F4u
134.060 kN
F4d
76.920 kN
F6
175.000 kN
F7u
95.120 kN
F7d
111.970 kN
F8
16.240 kN
F8H
9.990 kN
F8 = 2X200000^2/[3.142X0.016^2/4)XSIN((11.241)/2X3.142/180]
F9
0.000 kN
10 U hill ground
10.Uphill
d slope
l
i
Ka
F10
F4u =6.97X65.892515510314XSIN(16.9720801281178X3.142/180)
F4d =23.57X5.65XSIN(35.281999258953X3.142/180)
F6 = 100X1.75
F7u = gX3.142X[127.822646281088-65.892515510314XSIN(16.9720801281178X3.142/180)]X(1.75+0.016)X0.016
F7d = gX3.142X127.822646281088X(1.75+0.016)X0.016
F8 = 2X11.08^2/[3.142X1.75^2/4)XSIN((35.281999258953-16.9720801281178)/2X3.142/180]
30.000
30 000
0.000
0.00 kN
F10 = 18X2^2/2XCOS(30X3.142/180)X0X6
F1u =116.84
-34.110
-34.110
111.750
F1d =99.72
F2u =525.78
F3 v =959.75
F3 H =590.78
F4u =134.06
F4d =76.92
F6 =175
F7u =95.12
-57.600
502.890
422.640
57.870
128.230
62.800
24.530
90.980
-57.600
-502.880
422.640
57.870
128.230
62.800
-24.522
90.980
81.400
153.480
-861.680
-587.940
39.133
44.429
49.997
27.766
F7d =111.97
-91.410
-91.410
-64.670
F8 =16.24
F8H =9.99
F9 =0
F10 =0
WB =5169.44
Total force
Force at the bend
7.160
0.980
0.000
0.000
1114.960
1114.960
Ai
Xi
7.160
0.980
0.000
0.000
60.138
60.138
14.600
1.217
3.397 m
-14.580
-9.940
0.000
5169.440
4138.585
-1030.855
4.867
4.056
111.750
1.217 m
Expansion
81.400
Cases
18394.612
-153.480
Moment about left mo
4.445
-861.680 ver bend Center of force
-587.940 horz bend
0.795
39.133
Eccentricity
44.429
Safe
-49.997
27.766
Check on bearing capacity
Abase
-64.670
Area of base
43.800
-14.580 ver bend
-9.940 horz bend
Force at base
0.000
5169.440
Check against sliding
3731.631
Sum of vertical forces
-1437.809
Sum of horizontal forc
19.467
38.933
4.867
Page 2of 2
eallowable = 7.3/6
contraction
14239.892
3.816
0.166
Safe
156.203
Safe
96.821
Safe
4138.585
1114.960
Safe
3731.631
60.138
Safe
1381.50 m
Generator Effeciency
97.00%
Transfermer efficiency
99.00%
Gross head, m
Dry season outage
Synchronous Speed
Turbine units
89.00%
347.50 m
Overall efficiency
85.47%
4%
473 rpm
3 No
Length of tunnel
3950.00 m
Manning's coefficient
3.20 m
1.60 m
Number of nozzle
nj
50 Hz
2 No
650 m
Friction coeficient
Penstock Diameter
2
9.14 m
4%
Frequency
Length of penstock
Tunnel Diameter
Probability excedence, %
1034.00 m
Turbine Efficiency
1.750 m
Tunnel Perimeter
11.427 m
40.00%
3
11.08 m /s
3
0.308 m /s
Hg
347.500 m
Net head
339.370 m
Net power in kW
30000.00 kW
Net power in MW
PMW
30.00 MW
Php
40215 Hp
Net power = Unit wt. of water x Overall efficiency x Design discharge x Net head
Page 1 of 3
20.00
Ref: High head power plants E. Mosonyi Vol 2/B; Pg 859, eqn 28/101
jet diameter
dj
0.172 m
Ref: High head power plants E. Mosonyi Vol 2/B; Pg 854, eqn 6/101
1.862 m
Synchronous Speed
Ns
Ns
397 rpm
561 rpm
no of pole pair
5.35
6 Pairs
473 rpm
37.6
Ns
Ref: High head power plants E. Mosonyi Vol 2/B; Pg 856, eqn 16/101
Ref: High head power plants E. Mosonyi Vol 2/B; Pg 856, eqn 16/101
3
3 693 m /s
3.693
Qt
= K
Ref: High head power plants E. Mosonyi Vol 2/B; Pg 854, eqn 2/101
v
2 gH
Vj
79.151 m/s
Kv
0.97
Ku
34.827 m/s
1.406 m
1.500 m
Qj
3
1.847 m /s
0.44
Ref: Hydraulics and Fluid Mechanics P.N. Modi & S. M. Seth; Pg 1017
Bucket velocity = 0.44X79.151 m/s
D =
Ref: Hydraulics and Fluid Mechanics P.N. Modi & S. M. Seth; Pg 1017
60 u
N
Adopt
a 90
0.172 m
0.180 m
26.040 rpm
Ref: High head power plants E. Mosonyi Vol 2/B; Pg 856, eqn 16/101
2
0.0254 m
m
H
Number of buckets
8.33
20 No
Page 2 of 3
2
0.047 m
11
0.136 m
0.140 m
Nozzle Area
2
0.0146 m
Number of nozzle
nj
3.195 No
nj
3 No
11
Number of buckets
20 No
Qj
3
1.231 m /s
Method 1
Method 2
Low
High
Low
High
B = (4 to 5)dj
Width
0.720
0.900
0.720
0.900
L = (2.4 to 3.2)dj
Length
0.432
0.576
0.432
0.576
C = (0.81 to 1.05)dj
Depth
0.146
0.189
0.146
0.189
l = (1.2 to 1.9)dj
0.216
0.342
0.216
0.342
M= (1.1 to 1.25)dj
0.198
0.225
0.198
0.225
1.932
2.076
1.932
2.076
4.760
5.057
4.760
5.057
Setting Parameters
Outer Diameter of the bucket, Do
D+L
hs
2.072
2.626
2.072
2.626
hf
1.712
2.176
1.712
2.176
1+Do
2.932
3.076
2.932
3.076
hf+Do/2
2.678
3.21
2.678
3.214
1.5+.75Do
2.949
3.057
2.949
3.057
1030.200 m
hsp+MTWL
1033.414 m
1034.000 m
3.800
Page 3 of 3
2.004
Hydro Consult
3
11.08 m /sec
Q in each tunnel
3
11.08 m /sec
3.60 m
Height of tunnel H
3.60
water depth D
H-B/2
1.90 m
slope sn
0.0013
1.80
750
0.020
0.10 m
Angle subtended
0.0556 radian
Calculation
for D<(H-B/2)
for D>(H-B/2)
Wetted Area
6.84
Wetted Perimeter
7.40
Hydraulic Radius
0.92
Velocity limit
velocity normal
1.75
v =
1
R
n
2
3
1
2
3
11.85 m /sec
OK
Velocity
1.73 m/sec
Ok
Shield dn = 11RS
0.01 mm
Discharge
Summary
Breadth, B
3.60 m
1.90 m
1.8 m
3.60 m
Slope
1:750
Page 1 of 1
Hydro Consult
Q design
Q in each canal
Assume size B
Height of tunnel H
water depth D
slope sn
n
Height of water at tunnel top dome
Angle subtended
3.693
2.00
2.00
1.30
0.001
0.014
0.30
0.304692654
Calculation
Area
Perimeter
Hydraulic Radius
Velocity limit
velocity normal
m3/sec
m
m
1000
m
radian
v =
1
R
n
2
3
1
2
3.99 m3/sec OK
1.54 m/sec Ok
0.01 mm
Discharge
Velocity
Shield dn = 11RS
Summary
Breadth, B
Design Discharge Depth, H
D shape tunnel top curve depth
Total Height of Tunnel
Slope
2.00
1.30
1
2.00
1:1000
Page 1 of 1
m
m
m
m
Hydro Consult
Q design
1000 year flood level at Tailrace exit
Invert level of Tailrace tunnel outlet
Length of Main Tailrace
1027.00 m
1028.00 m
356.50 m
750.00
1028.48
1.90
1030.38
3.67
1034.05
1034.00
m
m
m
m
m
m
m
3.62 m
1032.50 m
1.30
1029.08 m
Page 1 of 1
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
River Sta
Profile
30
29
28
27
26
25
24
23
22
21
20
19
18
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
Q100
Q100
Q100
Q100
Q100
Q100
Q100
Q100
Q100
Q100
Q100
Q100
Q100
Q100
Q100
Q100
Q100
Q100
Q100
Q100
Q100
Q100
Q100
Q100
Q100
Q100
Q100
Q100
Q100
Q100
Profile: Q100
Q Total
Min Ch El
W.S. Elev
Crit W.S.
E.G. Elev
E.G. Slope
Vel Chnl
(m3/s)
(m)
(m)
(m)
(m)
(m/m)
(m/s)
(m2)
(m)
475
475
475
475
475
475
475
475
475
475
475
475
475
475
475
475
475
475
475
475
475
475
475
475
475
475
475
475
475
475
1019.93
1018.68
1018.24
1017.93
1017.78
1017.06
1016.19
1015.3
1015.08
1014.3
1013.85
1013.96
1013.88
1013.29
1012.26
1012.03
1011.72
1010.92
1010.41
1010.13
1009.76
1008.59
1007.25
1007.24
1006.29
1006.23
1005.39
1004.23
1003.82
1003.44
1023.92
1022.47
1022.12
1021.54
1021.17
1021.18
1020.39
1018.82
1018.58
1017.86
1017.53
1017.15
1016.69
1015.94
1015.44
1014.41
1014.15
1013.94
1013.99
1013.48
1013.06
1011.6
1010.97
1010.32
1009.09
1008.46
1008.12
1007.47
1007.04
1006.56
1023.92
1022.47
1022.12
1021.54
1021.17
1021.18
1020.39
1018.82
1018.58
1017.86
1017.53
1017.15
1016.69
1015.94
1015.44
1014.41
1014.15
1025.33
1023.86
1023.47
1023.02
1022.66
1022.41
1021.46
1020.22
1019.65
1018.92
1018.55
1018.2
1017.53
1016.83
1016.35
1015.42
1015.1
1014.72
1014.6
1014.51
1014.1
1012.65
1012.12
1011.35
1010.01
1009.35
1009.07
1008.79
1008.26
1007.82
0.009748
0.010482
0.009608
0.011018
0.010554
0.008716
0.00907
0.010923
0.008574
0.008137
0.008146
0.00894
0.009325
0.010002
0.009353
0.009798
0.008896
0.008473
0.005705
0.009287
0.009768
0.00983
0.008714
0.010029
0.01038
0.01159
0.011264
0.013995
0.010915
0.010731
5.51
5.35
5.38
5.71
5.69
5.31
4.89
5.47
4.82
4.81
4.73
4.92
4.49
4.64
4.82
4.18
4.15
4.52
4.02
5.15
5.11
4.97
5.06
4.83
4.59
4.22
4.45
5.19
4.96
5.04
92.59
92.92
95.2
91.07
91
101.37
107.21
93.16
108.86
110.8
113.34
109.43
121.46
118.36
116.59
109.65
112.68
123.72
140.79
112.05
109.54
108.27
105.45
109.63
114.81
114.8
111.24
94.84
98.91
97.73
33.32
34.45
36.09
34.37
33.59
39.75
48.76
37.08
49.75
52.14
56.06
51.41
70.64
70.25
62.54
55.08
60.31
64.12
61.96
54.32
52.48
51.97
46.99
54.8
62.8
66.02
59.55
45.13
41.95
39.9
1013.58
1013.48
1013.06
1011.6
1010.97
1010.32
1009.09
1008.46
1008.12
1007.47
1007.04
1006.56
Page 1 of 2
0.95
0.98
0.95
1.02
1
0.91
0.89
0.99
0.88
0.86
0.86
0.9
0.9
0.93
0.92
0.9
0.87
0.85
0.71
0.91
0.94
0.94
0.9
0.94
0.94
0.96
0.96
1.08
0.98
0.97
3.99
3.79
3.88
3.61
3.39
4.12
4.2
3.52
3.5
3.56
3.68
3.19
2.81
2.65
3.18
2.38
2.43
3.02
3.58
3.35
3.3
3.01
3.72
3.08
2.8
2.23
2.73
3.24
3.22
3.12
Tailrace
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
Nyadi PH site
River Sta
Profile
30
29
28
27
26
25
24
23
22
21
20
19
18
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
Q2
Q2
Q2
Q2
Q2
Q2
Q2
Q2
Q2
Q2
Q2
Q2
Q2
Q2
Q2
Q2
Q2
Q2
Q2
Q2
Q2
Q2
Q2
Q2
Q2
Q2
Q2
Q2
Q2
Q2
(m)
1019.93
1018.68
1018.24
1017.93
1017.78
1017.06
1016.19
1015.3
1015.08
1014.3
1013.85
1013.96
1013.88
1013.29
1012.26
1012.03
1011.72
1010.92
1010.41
1010.13
1009.76
1008.59
1007.25
1007.24
1006.29
1006.23
1005.39
1004.23
1003.82
1003.44
(m)
1022.46
1021.16
1020.76
1020.21
1020.2
1019.77
1019.17
1017.61
1017.3
1016.5
1016.21
1016.01
1015.8
1015.05
1014.36
1013.4
1012.95
1012.76
1012.71
1012.43
1012.01
1010.54
1009.71
1009.27
1008.17
1007.62
1007.21
1006.54
1005.91
1005.37
(m)
1022.46
1021.16
1020.76
1020.21
1019.77
1019.17
1017.61
1017.3
1016.5
1016.21
1016.01
1015.8
1015.05
1014.36
1013.4
1012.95
1012.76
1012.43
1012.01
1010.54
1009.71
1009.27
1008.17
1007.62
1007.21
1006.54
1005.91
1005.37
(m)
1023.36
1021.99
1021.61
1021.07
1020.76
1020.65
1019.96
1018.41
1018.08
1017.35
1016.99
1016.76
1016.4
1015.6
1015.01
1014.04
1013.65
1013.39
1013.17
1013.09
1012.67
1011.21
1010.49
1009.93
1008.76
1008.16
1007.8
1007.23
1006.63
1006.12
Page 2 of 2
E.G. Slope
Vel Chnl
(m/m)
0.012536
0.012946
0.011859
0.01262
0.006111
0.011552
0.012188
0.011709
0.012149
0.012552
0.012148
0.011079
0.011736
0.011083
0.011414
0.010217
0.009434
0.012028
0.007771
0.009379
0.010431
0.011186
0.010734
0.011499
0.011979
0.014094
0.014116
0.013559
0.013406
0.013474
(m/s)
4.33
4.09
4.19
4.28
3.43
4.3
4.03
4.06
3.99
4.1
3.98
3.99
3.79
3.67
3.86
2.82
2.66
3.77
3.39
3.99
3.96
3.88
4.03
3.74
3.6
3.21
3.48
3.71
3.78
3.87
Flow
Top
Froude #
Area
Width
Chl
(m2)
48.04
50.07
50.31
49.3
61.44
49.2
51.44
51.57
51.92
49.59
52.29
54.55
61.03
63.19
57.83
58.88
56.94
57.8
68.25
60.24
58.77
57
52.86
57.49
61.04
61.94
59.22
54.94
53.61
52.48
(m)
27.48
31.07
30.71
29.26
29.06
29.75
35.63
32.41
34.17
31.47
35.79
38.93
56.1
56.25
46.12
45.39
38.72
47.32
47.08
45.02
44.39
43.09
36.42
44.73
53.15
59.42
52.88
40.45
38.09
35.78
0.98
0.99
0.96
1
0.72
0.96
0.95
0.95
0.96
0.98
0.96
0.93
0.94
0.91
0.93
0.83
0.79
0.93
0.76
0.86
0.91
0.93
0.92
0.93
0.93
0.97
0.98
0.98
0.99
0.99
Water depth
(m)
2.53
2.48
2.52
2.28
2.42
2.71
2.98
2.31
2.22
2.2
2.36
2.05
1.92
1.76
2.1
1.37
1.23
1.84
2.3
2.3
2.25
1.95
2.46
2.03
1.88
1.39
1.82
2.31
2.09
1.93
Tailrace
Hydro Consult
Headloss Calculation
Description
Reference
Unit
Value
Turbine Discharge
Qt
Symbol
m3/sec
11.080
Orifice Discharge
Qo
m3/sec
15.512
m
m
m
1381.500
1034.000
1030.830
Wo
7.500
Ho
3.000
Orifice
Width of the Orifice
Height of the Orifice
Coarse Trashrack
Trashrack coefficient
Ktr
2.420
m
0.010
0.150
30.000
Gravel trap
Length
Lg
3.000
Width
Wg
3.000
Height
hg
1.000
angle of bend
degree
0.000
radius of bend
rc
100.000
Bend
Fine Trashrack
thickness of the bar
0.010
0.050
72.000
trashrack coefficient
Ktr
2.420
Approach tunnel
Length
Lac
55.500
Width/ dia
Wac
3.000
tunnel height
hac
3.000
Slope
1 in 500
0.0020
SB Bifurcation
Length
Lac
60.000
Width/ dia
Wac
3.000
tunnel height
hac
3.000
Slope
1 in 100
0.0100
128.000
Settling basin
No of bay
Length
Lsb
Ltr
25.000
m2
31.000
Perimeter
22.500
Average width
Wtr
8.000
Average depth
htr
10.000
3.200
Lt
3937.000
Tunnel Intake
Intake (Bellmouth)
Diameter
Tunnel
Length
Page 1 of 7
Hydro Consult
Headloss Calculation
Description
Reference
Symbol
Unit
Value
3.200
Diameter
Dt
Total height
Ht
3.200
Lcon
1200.000
Slope
St
1 in 500
0.0020
Bend 1
radius
10.000
3.100
angle
22.000
radius
10.000
3.000
angle
38.000
Bend 2
10 Penstock
Length
Lp
675.380
Diameter
Dp
1.750
Lbr
42.500
Diameter 1
Dp1
1.750
Diameter 2
Dp2
1.550
Diameter 3
Dp3
1.100
friction factor
mm
0.015
f
12.500
f
Lbr
Kv
60.000
Lbr
degree
30.000
0.300
Monthly Flow
Jan
3.57
Poush
(m3/s)
Feb
3.23
Magh
(m3/s)
3.75
3.38
Mar
3.21
Falgun
(m3/s)
3.08
Apr
3.86
Chaitra
(m3/s)
3.34
May
6.85
Baishakh
(m3/s)
4.38
Jun
17.13
Jestha
(m3/s)
9.31
Jul
32.54
Ashar
(m3/s)
24.95
Aug
37.73
Shravan
(m3/s)
40.12
Sep
28.39
Bhadra
(m3/s)
35.34
Oct
15.69
Ashoj
(m3/s)
21.44
Nov
7.70
Kartik
(m3/s)
9.94
4.60
Mangsir
(m3/s)
5.45
Dec
Page 2 of 7
Hydro Consult
Headloss Calculation
Description
Formula
Symbol
Unit
Design Value
Baishakh
40.00%
Jestha
40.00%
Ashar
40.00%
Shravan
40.00%
Bhadra
40.00%
Asoj
40.00%
Kartik
40.00%
Mangsir
40.00%
Poush
40.00%
Magh
40.00%
Falgun
40.00%
Chaitra
40.00%
Turbine Discharge
Qt
m3/sec
11.080
4.708
10.404
11.080
11.080
11.080
11.080
11.036
6.462
4.442
3.818
3.313
Orifice Discharge
Qo
m3/sec
15.512
6.591
14.566
15.512
15.512
15.512
15.512
15.451
9.047
6.219
5.345
4.638
4.782
m
m
m
1381.500
1034.000
1030.830
1381.500
1034.000
1030.830
1381.500
1034.000
1030.830
1381.500
1034.000
1030.830
1381.500
1034.000
1030.830
1381.500
1034.000
1030.830
1381.500
1034.000
1030.830
1381.500
1034.000
1030.830
1381.500
1034.000
1030.830
1381.500
1034.000
1030.830
1381.500
1034.000
1030.830
1381.500
1034.000
1030.830
1381.500
1034.000
1030.830
7.500
3.415
1 Orifice
Width of the Orifice
Wo
7.500
7.500
7.500
7.500
7.500
7.500
7.500
7.500
7.500
7.500
7.500
7.500
Ho
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
Ao
m2
22.500
22.500
22.500
22.500
22.500
22.500
22.500
22.500
22.500
22.500
22.500
22.500
22.500
Vo
m/sec
0.689
0.293
0.647
0.689
0.689
0.689
0.689
0.687
0.402
0.276
0.238
0.206
0.213
ho
0.067
0.012
0.059
0.067
0.067
0.067
0.067
0.067
0.023
0.011
0.008
0.006
0.006
0.067
0.012
0.059
0.067
0.067
0.067
0.067
0.067
0.023
0.011
0.008
0.006
0.006
2.420
2.420
2.420
2.420
2.420
2.420
2.420
2.420
2.420
2.420
2.420
2.420
2.420
0.010
Ao=Wo x Ho
a.
=(Vo^2)/(0.6^2*2*9.81)
TH1
1381.433
2 Coarse Trashrack
Ktr
Trashrack coefficient
[GDHIP pg 67 & 68]
a.
0.010
0.010
0.010
0.010
0.010
0.010
0.010
0.010
0.010
0.010
0.010
0.010
0.150
0.150
0.150
0.150
0.150
0.150
0.150
0.150
0.150
0.150
0.150
0.150
0.150
0.500
0.500
0.500
0.500
0.500
0.500
0.500
0.500
0.500
0.500
0.500
0.500
0.500
0.00079
0.00014
0.00070
0.00079
0.00079
0.00079
0.00079
0.00079
0.00027
0.00013
0.00009
0.00007
0.00008
0.735
0.312
0.691
0.735
0.735
0.735
0.735
0.732
0.429
0.295
0.253
0.220
0.227
0.001
0.000
0.001
0.001
0.001
0.001
0.001
0.001
0.000
0.000
0.000
0.000
0.000
Sin(ao)
ao=83
Trashrack Loss
=Ktr*(t/b)^(4/3)*SIN(ao)*(Vo^2)/(2*9.81) Losstr
Velocity at trashrack
m
m/sec
Headloss
TH2
1381.432
5 Gravel trap
a.
Length
Lg
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
Width
Wg
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
Height
hg
1.000
1.000
1.000
1.000
1.000
1.000
1.000
1.000
1.000
1.000
1.000
1.000
1.000
Manning's Coefficient
0.014
0.014
0.014
0.014
0.014
0.014
0.014
0.014
0.014
0.014
0.014
0.014
0.014
Ag
m2
2.035
2.035
2.035
2.035
2.035
2.035
2.035
2.035
2.035
2.035
2.035
2.035
2.035
Vg
m/sec
9.911
3.008
6.647
7.079
7.079
7.079
7.079
7.051
4.129
2.838
2.439
2.117
2.182
Wetted Perimeter
Pg
6.713
6.713
6.713
6.713
6.713
6.713
6.713
6.713
6.713
6.713
6.713
6.713
6.713
Hydraulic Radius
Rg
0.303
0.303
0.303
0.303
0.303
0.303
0.303
0.303
0.303
0.303
0.303
0.303
0.303
Lossfr
0.16784
0.03030
0.14799
0.16784
0.16784
0.16784
0.16784
0.16652
0.05709
0.02697
0.01993
0.01501
0.01595
0.150
0.150
0.150
0.150
0.150
0.150
0.150
0.150
0.150
0.150
0.150
0.150
0.150
0.018
0.003
0.016
0.018
0.018
0.018
0.018
0.017
0.006
0.003
0.002
0.002
0.002
Friction loss
=(((Qo*n)/(Ag*Rg^(2/3)))^2)*Lg
Transition
Kc
Contraction coefficient
[GDHIP pg.58]
b.
Contraction Loss
=Kc*Vac^2/(2*9.81)
Losscon
radian
rc
Bend
angle of bend
q=50.5 o
radius of bend
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
100.000
100.000
100.000
100.000
100.000
100.000
100.000
100.000
100.000
100.000
100.000
100.000
100.000
Chezy's coefficient
C=(R^1/6)/n
58.542
58.542
58.542
58.542
58.542
58.542
58.542
58.542
58.542
58.542
58.542
58.542
58.542
Bend Coefficient
K=24(hq/r c)[sqrt(g)/C+2.5g/c 2]
Kb
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
=Kb*(Vg^2)/(2*9.81)
Lossbend
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.185
0.033
0.164
0.185
0.185
0.185
0.185
0.184
0.063
0.030
0.022
0.017
0.018
0.010
c.
Bend Loss
Headloss
TH5
1381.246
4 Fine Trashrack
[GDHIP pg 67 & 68]
0.010
0.010
0.010
0.010
0.010
0.010
0.010
0.010
0.010
0.010
0.010
0.010
0.050
0.050
0.050
0.050
0.050
0.050
0.050
0.050
0.050
0.050
0.050
0.050
0.050
0.951
0.951
0.951
0.951
0.951
0.951
0.951
0.951
0.951
0.951
0.951
0.951
0.951
Trashrack loss
Velocity at trashrack
ao=72
Sin(ao)
Ktr
=Ktr*(t/b)^(4/3)*Sin(ao)*(G41^2)/(2*9.81) Lossftr
2.420
1.830
1.830
1.830
1.830
1.830
1.830
1.830
1.830
1.830
1.830
1.830
1.830
1.348
0.094
0.458
0.520
0.520
0.520
0.520
0.516
0.177
0.084
0.062
0.046
0.049
m/sec
5.762
2.448
5.410
5.762
5.762
5.762
5.762
5.739
3.360
2.310
1.985
1.723
1.776
Page 3 of 7
I:\ED\Jobs\OPEN\751220 Nyadi Implementation\03Reports\Final Review 30 MW as per Damodar Hydrology_23 Nov\VOLUME III - Technical Annex\Appendix D - Design Calculations\8.Energy calculation - Q=11.08 _40%.xlsx
Hydro Consult
Headloss Calculation
Description
Formula
Headloss
Symbol
Unit
TH4
Design Value
Baishakh
40.00%
1.348
0.094
Jestha
40.00%
0.458
Ashar
40.00%
0.520
Shravan
40.00%
0.520
Bhadra
40.00%
0.520
Asoj
40.00%
0.520
Kartik
40.00%
0.516
Mangsir
40.00%
0.177
Poush
40.00%
0.084
Magh
40.00%
0.062
Falgun
40.00%
0.046
Chaitra
40.00%
0.049
1379.899
6 Approach tunnel
a.
Qtunnel
m3/sec
12.188
5.179
11.445
12.188
12.188
12.188
12.188
12.140
7.108
4.886
4.200
3.644
3.757
Length
Lac
55.500
55.500
55.500
55.500
55.500
55.500
55.500
55.500
55.500
55.500
55.500
55.500
55.500
Width/ dia
Wac
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
tunnel height
hac
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
Slope
1 in 100
0.002
0.0020
0.0020
0.0020
0.0020
0.0020
0.0020
0.0020
0.0020
0.0020
0.0020
0.0020
0.0020
Manning's Coefficient
0.015
0.015
0.015
0.015
0.015
0.015
0.015
0.015
0.015
0.015
0.015
0.015
0.015
Aac
m2
8.035
8.035
8.035
8.035
8.035
8.035
8.035
8.035
8.035
8.035
8.035
8.035
8.035
Wetted Perimeter
Wac
10.713
10.713
10.713
10.713
10.713
10.713
10.713
10.713
10.713
10.713
10.713
10.713
10.713
Hydraulic Radius
Rac
0.750
0.750
0.750
0.750
0.750
0.750
0.750
0.750
0.750
0.750
0.750
0.750
0.750
Velocity of flow
Vac
m/sec
1.517
0.645
1.424
1.517
1.517
1.517
1.517
1.511
0.885
0.608
0.523
0.454
0.468
Lossfr
0.042
0.008
0.037
0.042
0.042
0.042
0.042
0.042
0.014
0.007
0.005
0.004
0.004
0.042
0.008
0.037
0.042
0.042
0.042
0.042
0.042
0.014
0.007
0.005
0.004
0.004
Friction loss
=Lac*((Qtunnel*n)/(Aac*Rac^(2/3)))^2
Headloss
TH6
1379.857
a.
Qtunnel
m3/sec
6.094
2.662
2.662
2.662
2.662
2.662
2.662
2.662
2.662
2.662
2.662
2.662
2.662
Length
Lac
60.000
55.500
55.500
55.500
55.500
55.500
55.500
55.500
55.500
55.500
55.500
55.500
55.500
Width/ dia
Wac
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
tunnel height
hac
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
3.000
Slope
1 in 100
0.010
0.0020
0.0020
0.0020
0.0020
0.0020
0.0020
0.0020
0.0020
0.0020
0.0020
0.0020
0.0020
Manning's Coefficient
0.015
0.015
0.015
0.015
0.015
0.015
0.015
0.015
0.015
0.015
0.015
0.015
0.015
Aac
m2
8.035
8.035
8.035
8.035
8.035
8.035
8.035
8.035
8.035
8.035
8.035
8.035
8.035
Wetted Perimeter
Wac
10.713
10.713
10.713
10.713
10.713
10.713
10.713
10.713
10.713
10.713
10.713
10.713
10.713
Hydraulic Radius
Rac
0.750
0.750
0.750
0.750
0.750
0.750
0.750
0.750
0.750
0.750
0.750
0.750
0.750
Velocity of flow
Vac
m/sec
1.517
0.331
0.331
0.331
0.331
0.331
0.331
0.331
0.331
0.331
0.331
0.331
0.331
Lossfr
0.011
0.002
0.002
0.002
0.002
0.002
0.002
0.002
0.002
0.002
0.002
0.002
0.002
0.011
0.002
0.002
0.002
0.002
0.002
0.002
0.002
0.002
0.002
0.002
0.002
0.002
Friction loss
=Lac*((Qtunnel*n)/(Aac*Rac^(2/3)))^2
Headloss
TH6
1379.845
7 Settling basin
No of bay
m3/sec
Length
Lsb
6.094
2.589
5.722
6.094
6.094
6.094
6.094
6.070
3.554
2.443
2.100
1.822
1.878
128.000
128.000
128.000
128.000
128.000
128.000
128.000
128.000
128.000
128.000
128.000
128.000
128.000
25.000
25.000
25.000
25.000
25.000
25.000
25.000
25.000
25.000
25.000
25.000
25.000
25.000
0.015
0.015
0.015
0.015
0.015
0.015
0.015
0.015
0.015
0.015
0.015
0.015
0.015
Ltr
Manning's coefficient
Asb
m2
31.000
31.000
31.000
31.000
31.000
31.000
31.000
31.000
31.000
31.000
31.000
31.000
31.000
Wetted perimeter
Psb
22.500
22.500
22.500
22.500
22.500
22.500
22.500
22.500
22.500
22.500
22.500
22.500
22.500
Hydraulic Radius
Rsb
1.378
1.378
1.378
1.378
1.378
1.378
1.378
1.378
1.378
1.378
1.378
1.378
1.378
Velocity of flow
Vsb
m/sec
0.197
0.084
0.185
0.197
0.197
0.197
0.197
0.196
0.115
0.079
0.068
0.059
0.061
0.300
0.300
0.300
0.300
0.300
0.300
0.300
0.300
0.300
0.300
0.300
0.300
0.300
0.003
Inlet transition
Ktr
Transition coefficients
[GDHIP pg 58]
a.
Lossit
0.035
0.006
0.031
0.035
0.035
0.035
0.035
0.034
0.012
0.006
0.004
0.003
Average width
Wtr
8.000
8.000
8.000
8.000
8.000
8.000
8.000
8.000
8.000
8.000
8.000
8.000
8.000
Average depth
htr
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
Average area
Atr
m2
80.000
80.000
80.000
80.000
80.000
80.000
80.000
80.000
80.000
80.000
80.000
80.000
80.000
Hydraulic radius
Rtr
2.222
2.222
2.222
2.222
2.222
2.222
2.222
2.222
2.222
2.222
2.222
2.222
2.222
Transition loss
=Ktr*(Vac^2-Vsb^2)/(2*9.81)
b.
=Lac*((Qtunnel*n)/(Aac*Rac^(2/3)))^2
Losstr
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
0.0000
c.
Friction loss
=Lsb*((Q*n)/(Asb*Rsb^(2/3)))^2
Lossfr
0.00073
0.00013
0.00064
0.00073
0.00073
0.00073
0.00073
0.00072
0.00025
0.00012
0.00009
0.00006
0.00007
0.150
0.150
0.150
0.150
0.150
0.150
0.150
0.150
0.150
0.150
0.150
0.150
0.150
0.006
0.001
0.005
0.006
0.006
0.006
0.006
0.006
0.002
0.001
0.001
0.001
0.001
0.041
0.007
0.036
0.041
0.041
0.041
0.041
0.041
0.014
0.007
0.005
0.004
0.004
Outlet transition
Kc
Contraction coefficients
[GDHIP pg 58, for cylindrical quadrant contraction]
d.
Contraction loss
Headloss
=Kc*v^2/(2*9.81)
Losscon
TH7
Page 4 of 7
I:\ED\Jobs\OPEN\751220 Nyadi Implementation\03Reports\Final Review 30 MW as per Damodar Hydrology_23 Nov\VOLUME III - Technical Annex\Appendix D - Design Calculations\8.Energy calculation - Q=11.08 _40%.xlsx
Hydro Consult
Headloss Calculation
Description
Formula
Symbol
Unit
Design Value
Baishakh
40.00%
Jestha
40.00%
Ashar
40.00%
Shravan
40.00%
Bhadra
40.00%
Asoj
40.00%
Kartik
40.00%
Mangsir
40.00%
Poush
40.00%
Magh
40.00%
Falgun
40.00%
Chaitra
40.00%
1379.815
8 Tunnel Intake
Intake (Bellmouth)
a.
Diameter
4.000
4.000
4.000
4.000
4.000
4.000
4.000
4.000
4.000
4.000
4.000
4.000
4.000
C/s area
m2
12.566
12.566
12.566
12.566
12.566
12.566
12.566
12.566
12.566
12.566
12.566
12.566
12.566
Velocity of flow
m/sec
C
Lossin
Intake loss
Headloss
TH8
0.882
0.375
0.828
0.882
0.882
0.882
0.882
0.878
0.514
0.353
0.304
0.264
0.272
0.100
0.100
0.100
0.100
0.100
0.100
0.100
0.100
0.100
0.100
0.100
0.100
0.100
0.004
0.001
0.003
0.004
0.004
0.004
0.004
0.004
0.001
0.001
0.000
0.000
0.000
0.004
0.001
0.003
0.004
0.004
0.004
0.004
0.004
0.001
0.001
0.000
0.000
0.000
1379.811
9 Tunnel
Length
Lt
3937.000
3937.000
3937.000
3937.000
3937.000
3937.000
3937.000
3937.000
3937.000
3937.000
3937.000
3937.000
3937.000
Diameter
Dt
3.200
3.200
3.200
3.200
3.200
3.200
3.200
3.200
3.200
3.200
3.200
3.200
3.200
Total height
Ht
3.200
3.200
3.200
3.200
3.200
3.200
3.200
3.200
3.200
3.200
3.200
3.200
3.200
Lcon
1200.000
1200.000
1200.000
1200.000
1200.000
1200.000
1200.000
1200.000
1200.000
1200.000
1200.000
1200.000
1200.000
Slope
St
1 in 500
0.002
0.002
0.002
0.002
0.002
0.002
0.002
0.002
0.002
0.002
0.002
0.002
0.002
nl
0.015
0.015
0.015
0.015
0.015
0.015
0.015
0.015
0.015
0.015
0.015
0.015
0.015
nu
0.022
0.022
0.022
0.022
0.022
0.022
0.022
0.022
0.022
0.022
0.022
0.022
0.022
Sectional Area
At
m2
9.141
9.141
9.141
9.141
9.141
9.141
9.141
9.141
9.141
9.141
9.141
9.141
9.141
Wetted Perimeter
Pt
11.427
11.427
11.427
11.427
11.427
11.427
11.427
11.427
11.427
11.427
11.427
11.427
11.427
Hydraulic Radius
Rt
0.800
0.800
0.800
0.800
0.800
0.800
0.800
0.800
0.800
0.800
0.800
0.800
0.800
Velocity of flow
Vt
m2/sec
1.212
0.515
1.138
1.212
1.212
1.212
1.212
1.207
0.707
0.486
0.418
0.362
0.374
a.
=Lcon*((Qt*nl)/(At*Rt^(2/3)))^2
Lossfr
0.534
0.096
0.471
0.534
0.534
0.534
0.534
0.530
0.182
0.086
0.063
0.048
0.051
b.
=(Lt-Lcon)*((Qt*nu)/(At*Rt^(2/3)))^2
Lossfr
2.621
0.473
2.311
2.621
2.621
2.621
2.621
2.600
0.891
0.421
0.311
0.234
0.249
10.000
Bend 1
[GDHIP pg 62 & 63]
c.
radius
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
3.100
3.100
3.100
3.100
3.100
3.100
3.100
3.100
3.100
3.100
3.100
3.100
3.100
r/d
3.226
3.226
3.226
3.226
3.226
3.226
3.226
3.226
3.226
3.226
3.226
3.226
3.226
First coefficient
k1
0.0910
0.0910
0.0910
0.0910
0.0910
0.0910
0.0910
0.0910
0.0910
0.0910
0.0910
0.0910
0.0910
angle
22.000
22.000
22.000
22.000
22.000
22.000
22.000
22.000
22.000
22.000
22.000
22.000
22.000
Second coefficient
k2
0.388
0.388
0.388
0.388
0.388
0.388
0.388
0.388
0.388
0.388
0.388
0.388
0.388
Bend coefficient
Kb
0.035
0.035
0.035
0.035
0.035
0.035
0.035
0.035
0.035
0.035
0.035
0.035
0.035
0.003
0.000
0.002
0.003
0.003
0.003
0.003
0.003
0.001
0.000
0.000
0.000
0.000
10.000
Bend loss
=Kb*Vt^2/(2*9.81)
Lossbend
Bend 2
[GDHIP pg 62 & 63]
d.
radius
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
10.000
3.000
3.100
3.100
3.100
3.100
3.100
3.100
3.100
3.100
3.100
3.100
3.100
3.100
r/d
3.333
3.226
3.226
3.226
3.226
3.226
3.226
3.226
3.226
3.226
3.226
3.226
3.226
First coefficient
k1
0.0867
0.0910
0.0910
0.0910
0.0910
0.0910
0.0910
0.0910
0.0910
0.0910
0.0910
0.0910
0.0910
angle
38.000
38.000
38.000
38.000
38.000
38.000
38.000
38.000
38.000
38.000
38.000
38.000
38.000
Second coefficient
k2
0.604
0.604
0.604
0.604
0.604
0.604
0.604
0.604
0.604
0.604
0.604
0.604
0.604
Bend coefficient
Kb
0.052
0.055
0.055
0.055
0.055
0.055
0.055
0.055
0.055
0.055
0.055
0.055
0.055
0.004
0.001
0.004
0.004
0.004
0.004
0.004
0.004
0.001
0.001
0.000
0.000
0.000
0.571
2.788
3.162
3.162
3.162
3.162
3.137
1.075
0.508
0.375
0.283
0.300
Bend loss
=Kb*Vt^2/(2*9.81)
Headloss
Lossbend
TH9
3.161
1376.650
10 Penstock
Length
Lp
675.380
675.380
675.380
675.380
675.380
675.380
675.380
675.380
675.380
675.380
675.380
675.380
675.380
Diameter
Dp
1.750
1.750
1.750
1.750
1.750
1.750
1.750
1.750
1.750
1.750
1.750
1.750
1.750
Sectional area
Ap
m2
2.405
2.405
2.405
2.405
2.405
2.405
2.405
2.405
2.405
2.405
2.405
2.405
2.405
Wetted Perimeter
Pp
5.498
5.498
5.498
5.498
5.498
5.498
5.498
5.498
5.498
5.498
5.498
5.498
5.498
Hydraulic Radius
Rp
0.438
0.438
0.438
0.438
0.438
0.438
0.438
0.438
0.438
0.438
0.438
0.438
0.438
Velocity of flow
Vp
m/sec
4.607
1.957
4.326
4.607
4.607
4.607
4.607
4.588
2.687
1.847
1.587
1.377
1.420
0.100
0.100
0.100
0.100
0.100
0.100
0.100
0.100
0.100
0.100
0.100
0.100
0.100
0.108
0.020
0.095
0.108
0.108
0.108
0.108
0.107
0.037
0.017
0.013
0.010
0.010
Entrance coefficient
a.
Entrance loss
=Ke*(Vp^2)/(2*9.81)
Lossent
Page 5 of 7
I:\ED\Jobs\OPEN\751220 Nyadi Implementation\03Reports\Final Review 30 MW as per Damodar Hydrology_23 Nov\VOLUME III - Technical Annex\Appendix D - Design Calculations\8.Energy calculation - Q=11.08 _40%.xlsx
Hydro Consult
Headloss Calculation
Description
Formula
Symbol
No of bend
nos
Kb
Bend loss
Unit
=Kb*(Vp^2)/(2*9.81)
Lossbend
=(f*Lp*Vp^2)/(2*9.81*Dp)
Lossfr
Design Value
Baishakh
40.00%
Jestha
40.00%
Ashar
40.00%
Shravan
40.00%
Bhadra
40.00%
Asoj
40.00%
Kartik
40.00%
Mangsir
40.00%
Poush
40.00%
Magh
40.00%
Falgun
40.00%
Chaitra
40.00%
7
0.415
0.415
0.415
0.415
0.415
0.415
0.415
0.415
0.415
0.415
0.415
0.415
0.415
0.449
0.081
0.396
0.449
0.449
0.449
0.449
0.445
0.153
0.072
0.053
0.040
0.043
0.01230
0.0123
0.0123
0.0123
0.0123
0.0123
0.0123
0.0123
0.0123
0.0123
0.0123
0.0123
0.0123
5.134
0.927
4.527
5.134
5.134
5.134
5.134
5.094
1.746
0.825
0.610
0.459
0.488
5.691
1.027
5.018
5.691
5.691
5.691
5.691
5.646
1.936
0.915
0.676
0.509
0.541
Wall friction
Friction factor
c.
Friction loss
Headloss
TH10
1370.959
Lbr
42.500
42.500
42.500
42.500
42.500
42.500
42.500
42.500
42.500
42.500
42.500
42.500
42.500
Diameter 1
Dp1
1.750
1.750
1.750
1.750
1.750
1.750
1.750
1.750
1.750
1.750
1.750
1.750
1.750
Diameter 2
Dp2
1.550
1.550
1.550
1.550
1.550
1.550
1.550
1.550
1.550
1.550
1.550
1.550
1.550
Vbr
3.657
1.957
4.326
4.607
4.607
4.607
4.607
4.588
2.687
1.847
1.587
1.377
1.420
Vbr
3.630
Contraction coefficient
=0.42*(1-(Dp2/Dp1)^2)
Kbr
=Kbr*Vbr^2/(2*9.81)
Lossbr
0.091
0.091
0.091
0.091
0.091
0.091
0.091
0.091
0.091
0.091
0.091
0.091
0.091
0.098
0.018
0.086
0.098
0.098
0.098
0.098
0.097
0.033
0.016
0.012
0.009
0.009
c.
60.000
60.000
60.000
60.000
60.000
60.000
60.000
60.000
60.000
60.000
60.000
60.000
60.000
r/d
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
2.000
Kbb
0.109
0.109
0.109
0.109
0.109
0.109
0.109
0.109
0.109
0.109
0.109
0.109
0.109
0.075
0.021
0.104
0.118
0.118
0.118
0.118
0.117
0.040
0.019
0.014
0.011
0.011
=Kbb*Vbr^2/(2*9.81)
Lossbb
friction factor
0.0123
0.0123
0.0123
0.0123
0.0123
0.0123
0.0123
0.0123
0.0123
0.0123
0.0123
0.0123
0.0123
Lbr
12.500
12.500
12.500
12.500
12.500
12.500
12.500
12.500
12.500
12.500
12.500
12.500
12.500
0.068
0.019
0.095
0.107
0.107
0.107
0.107
0.106
0.036
0.017
0.013
0.010
0.010
=f*Lbr*Vbr^2/(2*9.81*Dp2)
Lossfr
0.0123
0.0123
0.0123
0.0123
0.0123
0.0123
0.0123
0.0123
0.0123
0.0123
0.0123
0.0123
0.0123
Lbr
30.000
30.000
30.000
30.000
30.000
30.000
30.000
30.000
30.000
30.000
30.000
30.000
30.000
0.248
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
f.
Valve loss
=f*Vbr*Lbr^2/(2*9.81*Dp3)
Lossfr
Kv
Lossv
0.300
0.300
0.300
0.300
0.300
0.300
0.300
0.300
0.300
0.300
0.300
0.300
0.300
0.204
0.059
0.286
0.324
0.324
0.324
0.324
0.322
0.110
0.052
0.039
0.029
0.031
0.117
0.571
0.648
0.648
0.648
0.648
0.643
0.220
0.104
0.077
0.058
0.062
Headloss
TH11
0.692
1370.267
Headloss in headworks
Hh
1.685
0.155
0.756
0.857
0.857
0.857
0.857
0.850
0.291
0.138
0.102
0.077
0.081
Headloss in tunnel
Ht
3.165
0.571
2.791
3.165
3.165
3.165
3.165
3.141
1.077
0.509
0.376
0.283
0.301
Hp
6.383
1.144
5.589
6.339
6.339
6.339
6.339
6.289
2.156
1.019
0.753
0.567
0.602
11.233
1.871
9.136
10.361
10.361
10.361
10.361
10.280
3.525
1.665
1.230
0.926
0.985
Total Headloss
m
m
KW
347.500
336.267
3.23%
32127.840
347.500
345.629
0.54%
14031.026
Page 6 of 7
347.500
338.364
2.63%
30356.693
347.500
337.139
2.98%
32211.146
347.500
337.139
2.98%
32211.146
347.500
337.139
2.98%
32211.146
347.500
337.139
2.98%
32211.146
347.500
337.220
2.96%
32091.702
347.500
343.975
1.01%
19167.723
347.500
345.835
0.48%
13245.991
347.500
346.270
0.35%
11400.255
347.500
346.574
0.27%
9900.726
347.500
346.515
0.28%
10205.280
I:\ED\Jobs\OPEN\751220 Nyadi Implementation\03Reports\Final Review 30 MW as per Damodar Hydrology_23 Nov\VOLUME III - Technical Annex\Appendix D - Design Calculations\8.Energy calculation - Q=11.08 _40%.xlsx
347.50 m
Overall efficiency
85.47%
4%
4%
0.31 m3/s
Length of tunnel
3937.0 m
Turbine
Gen.
Transformer
Overall
Shotcreted tunnel
2737.0 m
90.50%
97.00%
99.50%
87.35%
1200.0 m
89.00%
97.00%
99.00%
85.47%
Generation
Dry season
Wet season
capacity
energy
energy
(kW)
(kWh)
(kWh)
Length of penstock
675.4 m
Manning's coefficient
Friction coeficient
Tunnel Diameter
3.20
Area
1.60
Perimeter
Adopt
9.14 m2
11.43 m
Probability excedence, %
40.00%
Design flow, m /s
11.08
Penstock Diameter, m
1.75
Flow
Month
(Nepali)
Nyadi
Available
available in
Available
Operating
Siuri
Flow
days
Design flow
Headloss
Headloss
Headloss
Total
HW
HRT
Penstok
Headloss
Net head
Tailrace
(m3/s)
Baishakh
Jestha
Ashar
Shravan
Bhadra
Ashoj
Kartik
Mangsir
Poush
Magh
Falgun
Chaitra
(m3/sec)
4.38
9.31
24.94
40.12
35.34
21.44
9.94
5.45
3.75
3.38
3.08
3.34
(m3/s)
(m3/s)
(m3/s)
0.68
0.64
4.71
31
4.71
0.155
0.571
1.144
1.871
345.63
13642.61
9,744,099
1.62
1.40
10.40
31
10.40
0.756
2.791
5.589
9.136
338.36
29516.00
21,081,508
3.87
1.40
26.04
32
11.08
0.857
3.165
6.339
10.361
337.14
30000.00
22,118,400
7.46
1.40
41.21
31
11.08
0.857
3.165
6.339
10.361
337.14
30000.00
21,427,200
7.83
1.40
36.43
31
11.08
0.857
3.165
6.339
10.361
337.14
30000.00
21,427,200
4.62
1.40
22.54
31
11.08
0.857
3.165
6.339
10.361
337.14
30000.00
21,427,200
2.28
1.40
11.04
30
11.04
0.850
3.141
6.289
10.280
337.22
30000.00
20,736,000
1.36
1.32
6.46
29
6.46
0.291
1.077
2.156
3.525
343.98
18637.11
1.04
1.00
4.44
30
4.44
0.138
0.509
1.019
1.665
345.83
12879.31
8,902,178
0.79
0.75
3.82
29
3.82
0.102
0.376
0.753
1.230
346.27
11084.67
7,406,330
0.58
0.54
3.31
30
3.31
0.077
0.283
0.567
0.926
346.57
9626.65
6,653,939
0.43
0.39
3.42
30
3.42
0.081
0.301
0.602
0.985
346.52
9922.77
6,858,620
12,452,572
30,000.00
29,821,067
29.82
150,414,178
150.41
180.24
5.04
Page 7 of 7
GEOTECHNICAL DESIGN
OF
UNDERGROUND STRUCTURES
Hydro Consult
APPENDIX E
OPTIMIZATION STUDY
October, 2010
Hydro Consult
Tables of Contents
1. plant capacity optimization ..................................................................................................... 2
1.1
Introduction ..................................................................................................................... 2
1.2
Objectives ........................................................................................................................ 2
1.3
1.4
Hydrology ........................................................................................................................ 3
1.5
1.6
1.7
Energy Production............................................................................................................. 6
1.8
1.9
1.10
1.11
Hydro Consult
1.2 Objectives
The main objective of optimization is to determine the optimum plant capacity at which the discharge
will produce maximum benefit. The benefit is revenue from sales of the generated energy of the power
plant. It is a comprehensive analysis of cost benefits analysis and fixing the optimum capacity of project.
Hydro Consult
1.4 Hydrology
Hydrology is the prime factor on which energy and revenue are based. The main purpose of the
optimization is to determine the optimum discharge from techno-economic point of view. The
optimization has been carried out based on mean daily flow available in the river. Long-term average
monthly flow of Nyadi intake is calculated by correlating with flow data (DHM) of Seti River, gauge
reading data of Nyadi HP and available flow data in Siuri tailrace (as per feasibility report of Siuri SHP),
which are presented in Table 1.1.
Table 1.1 Intake site average monthly flows in m3/s
Nyadi at intake
(m3/sec)
Siuri Tailrace
(m3/sec)
Combined discharge
(m3/sec)
Baishakh
4.38
0.64
5.02
Jestha
9.31
1.40
10.71
Ashar
24.95
1.40
26.35
Shravan
40.12
1.40
41.52
Bhadra
35.34
1.40
36.74
Asoj
21.44
1.40
22.84
Kartik
9.94
1.40
11.34
Mangsir
5.45
1.32
6.77
Poush
3.75
1.00
4.75
Magh
3.38
0.75
4.13
Falgun
3.08
0.54
3.62
Chaitra
3.34
0.39
3.73
Month
There will be downstream riparian release of 10% of the minimum mean monthly flow for fish and
aquatic life which is equivalent to 0.31 m3/sec.
Rated Discharge
(m3/s)
6.74
8.16
11.08
13.26
Probability of
exceedance (%)
50
45
40
35
18.50
30
Gross Head
(m)
333.90
333.90
333.90
333.90
333.90
Head loss
(m)
5.76
5.63
10.36
7.351
Net Head
(m)
328.13
328.27
323.54
326.59
10.66
323.24
Hydro Consult
Hydro Consult
18.50 MW
22.40 MW
30.00 MW
36.30 MW
50.10 MW
1381.50 masl
14 m
Concrete Weir
Two
Frontal with
orifice
2
2.25m*3.50m
57m*2.4m*2.4m
1381.50 masl
14 m
Concrete Weir
Two
Frontal with
orifice
3
2.25m*3.50m
57m*2.6m*2.6m
1381.50 masl
14 m
Concrete Weir
Two
Frontal with
orifice
3
2.25m*3.50m
57m*3m*3m
1381.50 masl
14 m
Concrete Weir
Two
Frontal with
orifice
4
2.25m*3.50m
57m*3.4m*3.4m
1381.50 masl
14 m
Concrete Weir
Two
Frontal with
orifice
4
2.25m*4.50m
57m*4m*4m
84m*8m*8.50m
101m*8m*9m
128m*8m*10.3m
165m*8m*11.3m
230m*8m*12.8m
3981 m
3964 m
3937m
3900 m
3835m
3.2m
3.2m
3.2 m
3.5 m
3.8m
26.26m
5m
27.63 m
5m
29.66m
5m
32.08 m
5m
32.64m
5m
476 m
200m
476 m
200m
476 m
200m
476 m
200m
476m
200m
1550mm
1750mm
1750mm
2150mm
2250mm
19.00 mm
U/G
Horizontal Axis
Pelton Turbine
3 nos.
19.00mm
U/G
Horizontal Axis
Pelton Turbine
3nos.
19.00mm
U/G
Horizontal Axis
Pelton Turbine
3nos.
22.00mm
U/G
Horizontal Axis
Pelton Turbine
4nos.
22.00mm
U/G
Horizontal Axis
Pelton Turbine
4nos.
12m*53 m
225.85m*3.2m*3
.2 m
13.5 KM
52m
14m*53 m
225.85m*3.4m*3
.4m
13.5 KM
52m
14m*53 m
225.85m*3.6m*
3.6m
13.5 KM
52m
15m*64 m
225.85m*
3.8m*3.8m
13.5 KM
52m
225.85m*
4.2m*4.2m
13.5 KM
52m
132kV, 7 KM,
NEA Hub
132kV, 7 KM,
NEA Hub
132kV, 7 KM,
NEA Hub
132kV, 7 KM,
NEA Hub
132kV, 7 KM,
NEA Hub
No. of Orifice
Orifice Size
Intake Tunnel
Settling Basin
Cavern
Headrace Tunnel
Length
Headrace Tunnel
Diameter
Surge Shaft Height
Surge Shaft
Diameter
Surface Penstock
Drop Shaft and
Horizontal parts
Diameter
Average Thickness
Powerhouse
Turbine Type
No of Units
Powerhouse
Cavern Size (B*L)
Tailrace Tunnel
(L*B*H)
Access road
Bridge Over
Marsyangdi River
Transmission Line
15m*64 m
Hydro Consult
18.50 MW
22.40 MW
30MW
36.30 MW
50.10 MW
128.97
145.97
177.30
192.40
223.01
0.27
0.27
0.27
0.27
0.27
1.78
1.78
1.78
1.78
1.78
126.92
143.92
175.25
194.45
234.06
Hydro Consult
Based on design discharge and rated head, the type and size of turbine are calculated. Sizes of
powerhouse caverns are determined accordingly. Then the cost estimate of powerhouse of each option
is estimated accordingly. The cost of electro-mechanical parts including turbine, governor, generator,
transformers, etc. are estimated based on prevailing practice and market prices.
The estimated base costs of project include transportation, installation and custom duties as well as
other applicable taxes. Similarly the cost of transmission line has been estimated based on per kilometre
cost of construction of 132kV transmission line and it also includes interconnection arrangement at
delivery location. Other cost like tapping of tailrace water of Siuri SHP, access road, environmental
mitigation, land acquisition, infrastructures, owner development cost and contingencies have been
proportionately increased for the respective plant capacities
Table 1.5 Comparison of the base project costs for various installed Capacities
Amout in US$ Milion
Summary of project contract costs for various installed capacities
50.10 MW
36.30 MW
30.00 MW
22.40 MW
18.50 MW
Civil works
34.94
26.70
23.87
21.53
21.05
Electromechanical works
19.16
14.15
10.33
8.95
7.75
3.86
3.66
3.26
3.15
2.88
1.35
1.35
1.35
1.35
1.35
2.47
2.47
2.47
2.47
2.47
1.41
1.41
1.41
1.41
1.41
0.91
0.68
0.45
0.45
0.45
1.79
1.23
1.02
1.02
1.02
0.54
0.54
0.54
0.54
0.54
0.37
0.37
0.37
0.37
0.37
66.80
52.56
45.06
41.24
39.30
Engineering fees
5.34
4.20
3.61
3.30
3.14
7.48
5.92
5.22
4.81
4.66
3.08
2.82
2.15
2.15
2.15
82.70
65.50
56.04
51.50
49.25
Total Project cost for year 2011 based on price escalation @ 5 p.a.
86.84
68.77
58.84
54.08
51.71
Hydro Consult
purchaser after finalizing the power purchase agreement (PPA). The relevant specific parameters applied
for the financial analysis in this study are adapted as given in section 15.2.
18.50 MW
22.40 MW
30MW
36.30 MW
50.10 MW
IRR on Equity
11.28%
13.63%
17.13%
15.47%
14.12%
IRR on Project
13.67%
15.04%
16.995
16.08%
15.32%
EIRRVsPercentageExceedance
18.00%
17.13%
17.00%
16.00%
15.47%
EIRR
15.00%
14.12%
14.00%
13.63%
13.00%
12.00%
11.28%
11.00%
10.00%
25
30
35
40
45
50
55
PERCENTAGEEXCEEDANCE(%)
Hydro Consult
APPENDIX F
COST ESTIMATE AND
FINANCIAL ANALYSIS
October, 2010
Hydro Consult
TABLES OF CONTENTS
F. COST ESTIMATE AND FINANCIAL ANALYSIS ................................................................ 2
F.1
Cost estimate....................................................................................................................................................... 2
F.1.1
Preliminary site works ................................................................................................................................ 2
F.1.2
Main civil works............................................................................................................................................ 2
F.1.3
Mechanical and electrical ........................................................................................................................... 2
F.1.4
132 kV transmission line ............................................................................................................................ 3
F.2
Engineering fees .................................................................................................................................................... 3
F.3
VAT and taxes ...................................................................................................................................................... 3
F.4
Contingency sums ................................................................................................................................................ 3
F.5
Benefit Calculation ............................................................................................................................................... 3
List of Tables
Table F 1. Project cost summary ...................................................................................................................................... 4
Table F 2. Owners direct cost .......................................................................................................................................... 5
Table F 3. Land acquisition cost ........................................................................................................................................ 6
Table F 4. Access road and Marsyangdi Bridge cost .................................................................................................... 7
Table F 5. Infrastructure development costs ................................................................................................................. 8
Table F 6. Civil Works Cost .............................................................................................................................................. 9
Table F 7. Hydro mechanical cost .................................................................................................................................. 15
Table F 8. Electromechanical cost .................................................................................................................................. 16
Table F 9. Transmission line and intergrid connection cost ..................................................................................... 17
Table F 10. Environmental monitoring and mitigation cost ...................................................................................... 18
Table F 11. New rate summary ....................................................................................................................................... 19
Table F 12. Rate summary of Miscellaneous Item....................................................................................................... 23
Table F 13. Tunnel Excavation Rate ............................................................................................................................... 24
Table F 14. Energy Calculation Sheet of NHP ............................................................................................................. 25
Table F15. Benefit Calculation sheet of NHP.....................................................................................................................26
Hydro Consult
F.1
The total project cost for year 2011 is presented in Table F1.The detailed cost estimate for different packages
are presented in Tables F 2 to F 10. New rate summary is given in Table F 11. Other assumptions on which
the estimate is based are indicated below.
The cost estimate has been split into five cost packages. The packages are as follows:
Contract C1
Land Acquisition
Access road
Contract C2
Contract C3
Elect mechanical
Contract C4
Contract C5
F.1.1
This contract contains the items necessary to expedite the work in the initial stage which is preliminary civil
works including the permanent access road, preparation of construction areas, housing for this phase, offices,
water supplies, sewage disposal. The program critical path items are Bridge over Marshyangdi and the access
road.
F.1.2
Contract C2 comprises the main civil works including the Headworks, waterway including surge shaft and
vertical shaft, underground powerhouse, tailrace tunnel, access tunnel and switchyard.
The following assumptions have been made:
The average tunnelling rate for the headrace tunnel is minimum 15 m to maximum 25 m per week
The unit rates are developed based on the experience of other similar projects in Nepal.
Water supply
Total daily volumes of water demands are based on experience at Khimti Hydropower Project. Water supply
costs allow for chlorinating at each major site and have a nominal allowance for simple water treatment (e.g.
roughing filter). Water supply costs are order of cost only and would need to be verified after further design.
Sewerage
The cost allows for sewer collection system, septic tank and soaks away trenches. At the Headworks
however, given the steep and rocky ground, septic effluent disposal by conventional trenches is considered
problematic. Therefore an allowance for a package treatment plant to treat septic tank effluent is included.
F.1.3
The cost includes supply and installation of all the mechanical and electrical equipment from the powerhouse
to the outdoor switchyard.
Hydro Consult
Steel penstock
Costs are based on budget cost advice from Nepal Hydro Electric (NHE) in Butwal.
F.1.4
This cost package includes the erection of the switchyard electrical items and the 132 kV line and
commissioning of the line.
The following assumptions have been made:
F.2
There will be no NEA charge for connecting the 132 kV line into the grid at proposed NEAs Hub
at Tunikharka.
Steel Type towers are used in the cost estimate
Engineering fees
The 8% engineering fees are assumed to cover the additional studies described in Section 13.4, Volume 1,
main report, the hydraulic model study , all detailed design and including construction supervision by a local
Consultant.
F.3
The amount of VAT payable has been based on assumed Nepal currency expenditure percentages of total
contract values. This is indicated in Table F.1. VAT is assumed to 13%. Tax deducted at source is assumed
payable on engineering fees at 5%.
F.4
Contingency sums
A general sum of 10% has been included on contract C1, C2 and C4 and 8% has been included in C3 and C5.
A higher sum of 10% has been included on the C2 main civil works contract to cover the higher risk of the
underground works. However, 5% contingencies sums are taken in preliminary site works.
F.5
Benefit Calculation
The basis for the benefit calculation is the adopted hydrological parameters and possible tariff rates of the
energy which could be agreed while reaching PPA.
Annual dry and wet energy production in a normal year are calculated based on the adopted hydrological data.
Allowance is made for downstream release (10 % of the driest mean monthly flow) while estimating the
energy production. Planned and forced outages are considered as 4 % for both wet and dry seasons. The
monthly energy estimate is carried out based on average monthly flow. The estimated monthly energy
production in a normal year after deducting energy for rural electrification and pumping for the base case is
summarized in Table F 14.
While calculating the energy benefit in terms of money, the flat tariff rates (base case) of 6.30 NRs/kWh have
been assumed for both dry and wet energy with 6 % escalations per annum up to 10 years period after
commissioning date of the project. Details of the benefit calculations based on project base cost for year 2011
are presented in Table F15.
Hydro Consult
Installed capacity
SUMMARY OF DIFFERENT
%
CONTRACT COSTS
Civil works
Contingency sum
NRs
337,075,604
33,707,560
10
US$
NRs Total
370,783,164
Electromechanical works
Contingency sum
109,701,337
10,970,134
10
35,272,100
2,821,768
134,441,099
13,444,110
10
16,225,634
1,622,563
10
81%
1,449,929,510
42.59%
10,325,112
8%
61,950,673
18.42%
120,671,471
1,646,725
44%
106,216,494
5.81%
38,093,868
842,833
100%
101,306,375
2.41%
147,885,209
494,460
100%
184,969,677
4.40%
17,848,197
1,172,351
56%
59,233,723
2.52%
100%
33,940,200
0.81%
100%
76,860,923
1.83%
40,337,701
0%
0.96%
28,000,000
0%
0.67%
100%
270,382,806
6.43%
780,401
62,432
449,509
44,951
1,065,773
106,577
Sub - Total
Socio-environmental mitigation costs
Contingency sum
Sub - Total
Item
Allocations
1,497,023
149,702
Sub - Total
Marsyangdi Bridge and Access Road
Contingency sum
Sub - Total
VAT complying
NRs equivalent
18,923,377
Sub - Total
VAT
complying
9,560,289
764,823
US$ Total
17,203,070
1,720,307
Sub - Total
32,324,000
1,616,200
33,940,200
41,730,729
2,086,536
419,602
20,980
43,817,266
440,582
38,416,858
1,920,843
28,000,000
841,377,075 33,845,440
45,063,801
75
30.0 MW
3,605,104
48,668,905
730,034
49,398,939
0.015
2,344,790,381
4,064,303
54,077
372,300
4,490,680
53,889,618
2,149,590
56,040,000
2,802,000
5%
58,842,000
TOTAL PROJECT COST (Nearest $1000) for 2011
Notes:
Unit rates are based at the site local to construction.
Unit Cost US$
1,961
Unit rates include cost of labour plant and materials
Contingency sum cover forseen and unforseen risks. It does not cover cost overrun.
Risks - ground conditions, strikes, material shortage, political instability, delay in license, manpower shortage
per KW
Hydro Consult
Description of Items
Feasibility Study
Detail design including tender doc
preparation
Office Setup
Office building rent
Salary for personnel
Project Director
Resident Project Manager
Planning,Account/Admin, Contract Manager
Engineers/geologist/mitigation officer
Peons
Guard
Secretary
Drivers
Vehicle
Office furniture
Owner's Overhead
Site Security
Officers
Assistants
Housing and facilities
Nos.
Quantity
Rate
(US$)
Amount
(US$)
L.S.
106,670.00
106,670.00
L.S.
400,000.00
400,000.00
months
48
270.00
12,960.00
months
months
Months
months
months
months
months
months
Nos.
1
1
3
8
5
4
2
6
6
48
48
48
48
48
48
48
48
1
L.S.
L.S.
3,500.00
1,800.00
1,500.00
1,000.00
250.00
250.00
250.00
245.00
50,000.00
50,000.00
168,000.00
86,400.00
216,000.00
384,000.00
60,000.00
48,000.00
24,000.00
70,560.00
300,000.00
30,000.00
50,000.00
40
40
L.S.
200
125.00
45,000.00
48,000.00
100,000.00
45,000.00
Units
months
months
6
20
Total Cost
2,149,590.00
Hydro Consult
Description
Unit
Quantity
Amount
(NRs)
Land purchased
Upto 27 July,2010
Access road
Ropani
130
7,373,356.00
Hydropower components
Ropani
308
19,651,728.00
Total
27,025,084.00
Ropani
16
814,052.80
671,601.00
116,913.00
1,689,207.00
Ropani
Ropani
Ropani
Ropani
20
2,900,000.00
Ropani
10
1,450,000.00
Transmission line
Ropani
25
3,750,000.00
Total
Total Amount
Remarks
11,391,773.80
38,416,857.80
Hydro Consult
Unit
Quantity
Rate(US$)
Rate (Nrs)
Amount
(US$)
1 US$
75 NRs.
Amount (Nrs)
Remarks
Reference from contract
to be signed
Marsyangdi
Bridge
Civil works
Bailey Bridge with
Complete fitting
2,517,784.00
992,000.00
137,027.20
20% contribution by Siuri
SHP
Sub Total
Access road
Total Length
Km
13.500
28,933.473
12,215,121.73
312,481.51
131,923,315
449,508.71
134,441,098.67
Sub Total
Total
Hydro Consult
Hydro Consult
S.N.
1
1.1
2
2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
2.9
2.10
2.11
3
3.1
3.2
3.3
3.4
3.5
Item Descriptions
GENERAL ITEMS
Insurances
Mobilization
Demobilization
Specified
requirements
Testing of materials;
aggregates, cement,
concrete, shotcrete
cores, density tests
construction power cost
(Desiel Generator) with
11 KV line
Sub-total
General, Headworks
Site Clearence
Sub-total
Diversion tunnel and
fish ladder
Surface rock excavation
with blasting
Tunnel excavation
(Underground)
Inlet pipe Dia 0.5m (8
mm thickness)
Reinforced Cement
Concrete (C25)
Reinforcement
Shotcrete (5cm steel fibre
reinforced)
Rockbolt (2m long, 25mm
dia grouted)
Formwork
Trimming and
preparation
Water control in tunnel,
25 lps
Grouting
Sub-total
Coffer Dam
Filling with rock in 45 cm
thick layer in compaction
PVC sheet 1 mm thick
Hard stone lining ( 0.4m
thick)
Removal of coffer dam
Water control in coffer
dam(25-50 lps)
Unit
Quantity
Rate ,
USD
Amount
USD
sum
sum
sum
sum
30,000
sum
919,127.83
949,127.83
m2
Amount
NRs
1,500,000
1,000,000
4000.00
90.02
608,171.84
3,108,171.84
360088.00
360088.00
m3
m3
600.00
22.67
300.00
13600.00
180000.00
1400.00
56.67
750.00
79333.33
1050000.00
2.00
2393.00
170500.00
2878.42
136723.73
5.70
0.45
121.33
1360.00
4900.00
18000.00
691.60
608.53
27930.00
8054.10
57.00
566.67
7500.00
32299.66
427495.50
320.00
38.00
34.00
450.00
1000.00
10880.00
0.00
144000.00
38000.00
90.00
0.00
10800.00
11.25
150.00
5865.94
146307.48
0.00
77637.40
2100640.73
ton
m3
ton
m3
No
m2
m2
Day
kg
m3
m2
m2
No
Day
120.00
15.00
6901.10
10.00
0.85
1680.00
640.00
0.33
12.50
1106.02
553.16
8000.00
1858118.77
0.00
80.00
2.00
34.25
7706.25
100000.00
2740.00
616500.00
200000.00
10.00
10.00
100.00
11393.16
0.00
2674618.77
Sub-total
Nyadi Hydropower Limited
Rate,
NRs
NRs 75.00
Remarks
Hydro Consult
S.N.
4
4.1
4.2
4.3
4.4
4.5
4.6
4.7
4.8
4.9
4.10
4.11
4.12
4.13
4.14
4.15
4.16
4.17
4.18
4.19
6
6.1
6.2
6.3
6.4
7
7.1
7.2
7.3
7.4
7.5
7.6
7.7
7.8
7.9
7.10
7.11
7.12
8
8.1
Item Descriptions
Weir and Bottom
Sluice
Surface rock excavation
with blasting
Boulder mixed soil
excavation on river bed
Earthwork in backfilling
Blinding concrete (C15)
Reinforced Cement
Concrete (C35)
Reinforced Cement
Concrete (C25)
Reinforcement
Geotextile
Hard stone lining (0.4m
thick)
Water control in weir
Laying 300 mm thick filter
layer
Boulder lining
Formwork
Expansion Joints
Seleant
Hydro cell
Water bars
Curtain grouting
GI Pipes (50mm dia)
Sub-total
Gravel Trap
Tunnel excavation
(Underground)
Reinforced Cement
Concrete (C35)
Reinforcement
Formwork
Sub-total
Intake Tunnel
Tunnel excavation
(Underground)
Reinforced Cement
Concrete (C25)
Reinforcement
Formwork
Shotcrete (5 cm steel
fibre reinforced)
Rockbolt (1.5m long,
25mm dia grouted)
Water control in tunnel
(25 lps)
Expansion Joints
Seleant
Hydro cell
Water bars
Grouting
Sub-total
Settling Basin
Tunnel excavation
Unit
Quantity
Rate ,
USD
Rate,
NRs
Amount
USD
Amount
NRs
m3
6362.13
22.67
300.00
144208.28
1908639.00
6362.13
5211.22
1353.00
3.18
65.00
39.94
85.00
2625.00
20211.69
0.00
87945.00
254132.30
442953.70
3551625.00
2887.84
143.00
5775.00
412961.12
16677276.00
4331.77
850.11
1485.00
121.33
1246.67
1.49
4900.00
16500.00
308.66
525588.09
1059802.65
2213.16
21225673.00
14026799.78
458360.10
330.40
34.25
20.00
7706.25
1500.00
0.00
m2
m2
m
m
m
m
kg
m
1865.50
1025.00
5344.60
14.00
14.00
14.00
14.00
57.30
135.00
19.95
11.67
21.25
23.80
16.15
16.15
0.85
4.00
1496.39
2625.00
670.00
30.00
315.00
213.75
213.75
11.25
200.00
37220.19
11958.33
0.00
297.50
333.20
226.10
226.10
48.71
540.00
2305280.12
2791514.05
2690625.00
3580882.00
420.00
4410.00
2992.50
2992.50
644.63
27000.00
67646939.56
m3
630.00
56.67
750.00
35700.00
472500.00
m3
98.25
143.00
5775.00
14049.75
567393.75
ton
m2
7.71
135.00
1246.67
16500.00
670.00
9615.07
59364.82
127258.31
90450.00
1257602.06
m3
m3
m3
m3
m3
ton
m2
m3
Day
m3
75.00
m3
677.25
56.67
750.00
38377.50
507937.50
m3
185.85
121.33
4900.00
22549.80
910665.00
ton
m2
m3
14.59
323.93
323.95
1360.00
566.67
18000.00
1000.00
7500.00
19841.35
0.00
183569.40
262606.05
323925.00
2429595.00
No
105.00
28.33
375.00
2975.00
39375.00
Day
25.00
10.00
250.00
0.00
m
m
m
m
kg
5.00
5.00
5.00
5.00
2490.43
21.25
23.80
16.15
16.15
0.85
30.00
315.00
213.75
213.75
11.25
106.25
119.00
80.75
80.75
2116.87
270066.66
150.00
1575.00
1068.75
1068.75
28017.38
4505983.43
m3
29263.34
56.67
750.00
1658255.93
21947505.00
10
Remarks
Hydro Consult
S.N.
8.2
8.3
8.4
8.5
8.6
8.7
8.8
8.9
8.11
8.12
8.13
8.14
8.15
8.16
81.8
9
9.1
9.2
10
10.1
10.2
10.3
10.4
10.5
10.6
10.7
10.8
10.9
10.10
10.11
10.12
10.13
10.14
10.15
Item Descriptions
(Underground)
Reinforced Cement
Concrete (C25)
Reinforcement
Formwork
Shotcrete (10cm steel
fibre reinforced)
Shotcrete (5cm steel fibre
reinforced)
Rockbolt (1.5m long,
25mm dia grouted)
Rockbolt (2 m long,
25mm dia grouted)
Rockbolt (3.5 m long,
25mm dia grouted)
Water control in tunnel,
50 lps
Expansion Joints
Seleant
Hydro cell
Water bars
1:4 Stone masonry
S4 System including
automatic gates
Sub-total
River Protection
Earthwork in excavation
Gabion works
Sub-total
Headrace tunnel
Rock Excavation
Blinding Concrete (C15)
Structural Concrete
(C25)
Rebar
Formworks
Subase Preparation
50 mm of unreinforced
shotcrete
50 mm steel fibre
reinforced shotcrete
100 mm steel fibre
reinforced shotcrete
150 mm steel fibre
reinforced shotcrete
200 mm steel fibre
reinforced shotcrete
2 m long 25 mm dia.
Grouted rock bolts at
1.5m*1.5m c/c
Spot bolting , 2m long
25mm dia grouted rock
bolts
2m long 25mm dia
grouted rock bolts at
1.3m*1.3m c/c spacing
2m long 25mm dia
Unit
m3
ton
m2
m3
Rate ,
USD
Rate,
NRs
3137.28
246.28
5480.52
121.33
1360.00
4900.00
18000.00
1000.00
380656.64
334936.01
15372672.00
4432976.64
5480520.00
934.13
453.33
6000.00
423473.17
5604792.00
280.16
566.67
7500.00
1875.00
28.33
375.00
53125.00
703125.00
1092.00
34.00
450.00
37128.00
491400.00
4140.00
51.00
675.00
211140.00
2794500.00
130.00
27.00
27.00
27.00
27.00
1986.86
20.00
21.25
23.80
16.15
16.15
55.00
30.00
315.00
213.75
213.75
3300.00
2600.00
573.75
642.60
436.05
436.05
109277.30
0.00
810.00
8505.00
5771.25
5771.25
6556638.00
Quantity
m3
No
No
No
Day
m
m
m
m
m3
sum
Amount
USD
Amount
NRs
2101192.50
Andhikhol
a
454092.00
3666772.51
65506178.64
m3
m3
1315.60
965.00
3.18
11.67
39.94
2625.00
4179.50
11258.33
15437.83
52551.03
2533125.00
2585676.03
m3
m3
m3
62557.22
1120.62
3417.12
56.67
78.00
121.33
750.00
3150.00
4900.00
3544909.13
87408.36
414610.56
46917915.00
3529953.00
16743888.00
ton
m2
m2
m3
268.24
11412.00
14941.60
424.15
1360.00
453.33
18000.00
1000.00
90.00
6000.00
364811.73
0.00
0.00
192279.52
4828390.56
11412000.00
1344744.00
2544876.00
m3
119.88
566.67
7500.00
67929.17
899062.50
m3
496.99
453.33
6000.00
225299.87
2981910.00
m3
233.90
396.67
5250.00
92781.33
1227988.13
m3
141.34
396.67
5250.00
56066.45
742056.00
no
3568.00
34.00
450.00
121312.00
1605600.00
no
5178.00
34.00
450.00
176052.00
2330100.00
no
4110.00
34.00
450.00
139740.00
1849500.00
no
1295.00
34.00
450.00
44030.00
582750.00
11
Remarks
Hydro Consult
S.N.
10.16
10.17
10.18
10.19
10.20
11
11.1
11.2
11.3
11.4
11.5
11.6
11.7
11.8
11.9
11.10
11.11
11.12
12
12.1
12.2
12.3
12.4
12.5
12.6
12.7
12.8
12.9
12.10
12.11
12.12
12.13
12.14
12.15
12.16
13
Item Descriptions
Unit
Quantity
Rate ,
USD
Rate,
NRs
Amount
USD
Amount
NRs
360.00
4.30
m2
m3
120.00
60.00
1.49
19.95
12
1548.00
308.66
244.38
178.84
1197.11
571164.78
37039.20
14662.50
13011880.14
Remarks
Hydro Consult
S.N.
13.1
13.2
13.3
13.4
13.5
13.5
13.6
13.7
13.8
13
13.1
13.2
13.3
13.4
13.5
13.6
15
15.1
15.2
15.3
15.4
15.5
15.6
15.7
15.8
15.9
15.10
15.11
15.12
15.13
15.14
16
16.1
16.2
16.3
16.4
16.5
16.6
16.7
16.8
Item Descriptions
Support piers
Rock Excavation
Boulder mix soil
excavation
Blinding Concrete (C15)
C20 with 40% plum
concrete
C25 Concrete
Rebar
Formworks
Back Filling
Subase Preparation
Sub-total
Vertical Shaft
Rock Excavation
Structural Concrete
(C25)
Rebar
70 mm of steel reinforced
shotcrete
2 m long 25 mm dia.
Grouted rock bolts at
1.5m*1.5m c/c
Double grouting
Sub-total
Powerhouse Main
Building
Rock Excavation
200mm thick Shotcrete
25mm dia 4m long rock
bolts @1.2m C/C
Shotcrete ribs
Rebar in Shotcrete ribs
Water control in cavern
50-70 l/s
Cement grout
Concrete (C25)
Reinforcement
Formwork
Steelwork
CGI sheets 20 gauge
CGI sheet ceiling
accessories
Finishes
Sub-total
Powerhouse Control
building
Rock Excavation
120mm thick Shotcrete
25mm dia 4m long rock
bolts @1.2m C/C
Cement grout
C25 Concrete
Rebar
Formwork
Finishes
Unit
Quantity
Rate ,
USD
Rate,
NRs
Amount
USD
Amount
NRs
m3
m3
432.88
8947.39
22.67
0.24
300.00
600.88
9811.95
2150.51
129864.00
5376263.89
m3
m3
70.44
2414.70
78.00
60.67
1050.00
2450.00
5494.55
146491.96
73965.15
5916021.31
m3
ton
m2
m3
m2
685.28
119.46
1885.54
3728.67
875.24
104.00
1360.00
4200.00
18000.00
670.00
11.81
90.00
71268.92
162460.78
399448.02
2878167.87
2150216.24
1263309.12
44032.29
78771.60
17910611.47
0.47
1769.35
m3
m3
1627.72
682.53
90.67
130.00
1200.00
5250.00
147579.49
88728.64
1953258.00
3583272.00
ton
m3
53.58
136.83
1360.00
510.00
18000.00
6750.00
72866.69
69781.01
964412.06
923572.13
no
830.00
30.50
383.47
25313.34
318278.03
kg
52659.68
0.85
11.25
44760.73
449029.90
592421.45
8335213.66
m3
m3
no.
10415.74
336.00
1260.00
56.67
396.67
62.33
750.00
5250.00
825.00
590225.27
133280.00
78540.00
7811805.00
1764000.00
1039500.00
m3
ton
day
264.00
14.98
180.00
396.67
1360.00
20.00
5250.00
18000.00
104720.00
20378.03
3600.00
1386000.00
269709.26
0.00
kg
m3
ton
m2
ton
9056.12
298.93
19.52
1048.53
23.52
0.85
121.33
1360.00
2392.98
7697.71
36270.02
26541.25
0.00
33769.77
101881.40
1464750.96
351281.24
1048525.12
1604064.00
m2
m2
575.00
575.00
11.21
10.68
11.25
4900.00
18000.00
1000.00
170500.0
0
119.03
129.95
6446.01
6143.38
68439.38
74721.25
LS
1.00
7500.00
7500.00
1055111.44
0.00
16984677.60
m3
m3
no.
1119.38
29.81
264.00
56.67
396.67
62.33
750.00
5250.00
825.00
63431.25
11825.63
16456.00
839531.25
156515.63
217800.00
kg
m3
ton
m2
LS
1707.01
105.89
8.31
690.94
1.00
0.85
121.33
1360.00
11.25
4900.00
18000.00
1000.00
1450.96
12848.47
11305.24
0.00
5000.00
19203.83
518880.60
149628.22
690940.00
0.00
5000.00
13
Remarks
Hydro Consult
S.N.
Item Descriptions
Unit
16.9
16.10
16.11
m2
LS
LS
17
17.1
17.2
17.3
17.4
17.5
17.6
17.7
17.8
17.9
18
18.1
18.2
18.3
18.5
18.6
18.7
19
19.1
19.2
19.3
19.4
19.5
19.6
19.7
19.8
19.9
19.10
19.11
Quantity
31.33
1.00
1.00
Rate ,
USD
4.03
3000.00
3000.00
Rate,
NRs
3318.14
Amount
NRs
103957.37
0.00
0.00
128443.79
2696456.90
15000.00
0.00
500.00
0.00
LS
1.00
Day
50.00
10.00
m3
m3
no.
3640.00
226.20
968.00
56.67
396.67
41.93
750.00
5250.00
527.27
206266.67
89726.00
40592.84
2730000.00
1187550.00
510395.24
Kg
m3
ton
7267.26
125.30
9.84
0.85
121.33
1360.00
11.25
4900.00
18000.00
6177.17
15203.07
13377.03
81756.68
613970.00
177048.90
no
383.00
28.33
375.00
10851.67
397694.44
143625.00
5444345.82
m3
m2
no.
4792.35
356.64
2799.00
56.67
453.33
34.00
750.00
6000.00
450.00
271566.50
161676.80
95166.00
3594262.50
2139840.00
1259550.00
m3
ton
day
7.00
1.03
60.00
78.00
1360.00
10.00
3150.00
18000.00
546.00
1400.80
600.00
22050.00
18540.00
0.00
530956.10
7034242.50
m3
150.30
0.17
437.00
26.27
65681.10
m3
m3
414.00
150.00
19.95
32.67
1496.39
1050.00
8260.07
4900.00
619505.13
157500.00
m3
m2
m3
m3
m3
m3
7901.50
900.00
601.50
14.44
7.00
127.47
0.47
11.67
55.00
65.00
86.67
104.00
11.81
2625.00
3300.00
2625.00
3500.00
4200.00
3749.47
10500.00
33082.50
938.44
606.67
13257.09
93309.76
2362500.00
1984950.00
37898.44
24500.00
535382.66
m2
ton
387.08
21.15
1246.67
670.00
16500.00
0.00
26362.58
101683.09
17203069.92
259345.28
348916.55
6489488.92
337009789.71
Total
Amount
USD
126.24
3000.00
3000.00
14
Remarks
Hydro Consult
15
Hydro Consult
16
Hydro Consult
17
Hydro Consult
18
Hydro Consult
S No
A
1
2
3
4
5
6
7
8
9
B
1
2
3
C
1
3
4
6
7
Item description
Unit
0.07
163.88
0.09
218.50
0.24
600.88
Earthwork Excavation
Excavation on soft clay &silty soils including disposal
(up to 10 m lead & 1.5 m lift).
Excavation of Hard soil, Gravel/Boulder Mixed Soil
including disposal (up to 10 m lead & 1.5 m lift).
Excavation of Soft Rock without blasting, disposal (up
to 10 m lead & 1.5 m lift)
Excavation of hard rocks with blasting (Manual Drill),
disposal (up to 10 m lead & 1.5 m lift)
Excavation of hard rocks without blasting, disposal (up
to 10 m lead & 1.5 m lift) with chisel
Ditch cutting in hard soils, disposal (up to 10 m lead
and 1.5 m lift).
Excavation for foundation in all types of soil including
disposal up to 20 m and relevant lift (Depth upto
1.5m)
Excavation for foundation work including disposal up
to 20 m and relevant lift,soft moorum rocks.
Excavation for foundation work including disposal up
to 20 m and relevant lift, Medium hard rocks (without
blasting).
m3
m3
m3
m3
3.56
796.95
m3
1.05
2,622.00
m3
0.13
327.75
0.17
437.00
0.24
600.88
1.05
2,622.00
0.47
11.81
0.33
1,106.02
0.14
1,150.00
143.00
5,775.00
104.00
4,200.00
65.00
2,625.00
99.99
11,271.15
86.49
9,988.44
64.64
7,327.92
57.37
6,637.80
m3
m3
m3
Filling work
Filling with suitable (excavated) material in 15 cm thick
layer compaction using machinery, (haulage distance
10 m )With sprinkling water
Filling with rocks in 45 cm thick layer compaction,
sprinkling water and haulage distance 10 m.
Filling soils in pipe line trenches in 20 cm thick layers
including hand and water sprinkling. Filling by stones in
the foundation and levelling incl. Haulage dist. Up to
30 m
m3
m3
m3
Concrete Work
Machine Mixed Concreting Works(of super
structures, deck slabs, beams including supply of
materials and haulage dist up to 30 m) Concrete grade
C35
Machine Mixed Concreting Works(of super
structures,deck slabs, beams including supply of
materials and haulage dist up to 30 m) Concrete grade
C25
Machine Mixed Concrete grade C15 (Supply of
materials & haulage dist up to 30 m) in Foundation,
Footing etc
Manual Mixed Concreting Works(of super structures,
deck slabs, beams including supply of materials and
haulage dist up to 30 m) Concrete grade C35
Manual
Mixed
Concreting
Works(of
super
structures,deck slabs, beams including supply of
materials and haulage dist up to 30 m) Concrete grade
C25
Manual Mixed Concrete grade C15 (Supply of
materials & haulage dist up to 30 m) in Foundation,
Footing etc
Plum Concrete grade C15 (1:3:6) (Supply of materials
& haulage dist up to 30 m) (30% Plum)
m3
m3
m3
m3
m3
m3
m3
19
Hydro Consult
S No
8
Item description
Machine Mixed Concrete grade C20 (Supply of
materials & haulage dist up to 30 m) in Foundation,
Footing etc
Machine Mixed Concrete grade c20 with 40% Plum
Steel Work
Formwork
F
1
1
2
86.67
3,500.00
m3
60.67
2,450.00
MT
1,246.67
16,500.00
m2
m2
m2
m2
m2
611.84
366.37
447.91
549.40
-
m2
m2
m2
m2
m2
452.20
539.85
670.00
-
744.47
m3
m3
m3
32.99
55.00
23.87
3,211.11
3,300.00
2,651.54
m3
m3
m3
m3
31.81
28.13
22.69
3,394.30
3,168.00
2,834.73
6.48
1,226.33
50.13
7,885.20
m3
Brick Work
4
5
6
Stone Masonry
Unit
m3
m3
48.06
7,596.37
m3
46.08
7,320.99
m3
m3
m3
49.12
47.04
45.07
7,943.44
7,654.61
7,379.23
1.29
119.54
1.15
117.75
m2
m2
20
Hydro Consult
S No
Item description
4
5
6
7
mortar
Plastering 12.5 mm thick thick 1:6 cement sand
mortar
Plastering 20 mm thick thick 1:3 cement sand mortar
Plastering 20 mm thick thick 1:4 cement sand mortar
Plastering 20 mm thick thick 1:6 cement sand mortar
3 mm thick Cement Punning
Wood works
1
2
3
4
5
6
3
4
Painting Works
Fencing works
Gabion Work
M
1
0.89
114.21
1.97
1.73
1.32
0.96
144.76
141.58
136.11
66.70
67.91
59,093.11
4.03
3,318.14
2.67
2,578.57
2.45
2,499.74
2.33
1,037.78
0.33
163.73
m2
11.21
119.03
m2
10.68
129.95
kg
kg
1.71
1.55
31.03
20.77
m2
m2
0.12
10.01
0.35
136.56
m2
0.93
68.08
4.14
25.30
18.57
19.41
21.62
11.25
32.67
69.69
71.13
77.59
244.38
1,050.00
19.95
1,496.39
11.67
2,625.00
m2
m2
m2
m2
m2
m3
m2
m2
m2
m2
m2
Roofing Works
CGI Sheet roofing works with supply of materials
complete
Making ridge of CGI plain sheets and fitting with supply
of materials complete
Fixing and supply of steel tubular truss
Fixing and supply of steel tubular pipe for purlins
Unit
m3
m3
m3
m3
m3
m2
21
Hydro Consult
S No
Item description
N
1
Geotextile
Supply and Laying of geotextile materials
Site preparation
Unit
m2
each
m2
m2
m3
m3
m2
22
1.49
308.66
90.02
13.50
9.23
630.15
9.00
105.78
Hydro Consult
1
USD
Item
no.
Description
Unit
75
US$
Increment
12%
Remarks
NRs.
Rate
in
US$
Current
Rate in
US$
Current
Rate in
NRs.
25.00
21.25
30.00
0
1
Expansion Joints
Seleant
24.53
28.00
23.80
315.00
Hydrocell
16.10
19.00
16.15
213.75
Water bars
16.60
19.00
16.15
213.75
3.00
1.80
90.00
KG
Curtain Grouting
kg
Railings
1.00
0.85
11.25
m3
121.50
137.00
34.25
7,706.25
m2
334.00
375.00
225.00
11,250.00
rm
12.50
14.00
8.40
420.00
4.30
5.00
4.00
70.00
14.00
16.00
10
11
rm
m3
12
Sub-Grade Preparation
m2
13
Backfilling by compaction
1,200.00
90.00
85.00
23
Hydro Consult
24
Hydro Consult
333.90 m
Overall efficiency
85.47%
4%
4%
0.31 m3/s
Length of tunnel
3937.0 m
Turbine
Generator
Transformer
Overall
Shotcreted tunnel
2737.0 m
90.50%
97.00%
99.50%
87.35%
1200.0 m
89.00%
97.00%
99.00%
85.47%
Length of penstock
675.4 m
Manning's coefficient
Friction coeficient
Tunnel Diameter
3.20
Area
1.60
Perimeter
9.14 m2
11.43 m
40.00%
Probability excedence, %
Design flow, m3/s
11.08
Penstock Diameter, m
1.75
Flow
Month
(Nepali)
Nyadi
Available
available in
Available
Operating
Siuri
Flow
days
Design flow
Headloss
Headloss
Headloss
Total
HW
HRT
Penstok
Headloss
Net head
Generation
capacity
Tailrace
(m3/s)
Baishakh
Jestha
Ashar
Shravan
Bhadra
Ashoj
Kartik
Mangsir
Poush
Magh
Falgun
Chaitra
Adopt
(m3/sec)
4.38
9.31
24.94
40.12
35.34
21.44
9.94
5.45
3.75
3.38
3.08
3.34
(m3/s)
(m3/s)
(m3/s)
(kW)
Energy for
Rural
Electrification
(kWh)
Energy for
Pumping
(kWh)
Dry season
Wet season
energy (after
energy (After
deduction
deduction
outage, RE and
outage,RE and
Pumping)
(kWh)
Pumping))
(kWh)
0.68
0.64
4.71
31
4.71
0.155
0.571
1.144
1.871
332.03
13105.79
22,500.00
148333.50
9,189,849
1.62
1.40
10.40
31
10.40
0.756
2.791
5.589
9.136
324.76
28329.98
22,500.00
296667.00
19,915,237
3.87
1.40
26.04
32
11.08
0.857
3.165
6.339
10.361
323.54
30000.00
22,500.00
0.00
22,095,900
7.46
1.40
41.21
31
11.08
0.857
3.165
6.339
10.361
323.54
30000.00
22,500.00
0.00
21,404,700
7.83
1.40
36.43
31
11.08
0.857
3.165
6.339
10.361
323.54
30000.00
22,500.00
0.00
21,404,700
4.62
1.40
22.54
31
11.08
0.857
3.165
6.339
10.361
323.54
30000.00
22,500.00
0.00
21,404,700
2.28
1.40
11.04
30
11.04
0.850
3.141
6.289
10.280
323.62
29944.90
22,500.00
296667.00
20,378,747
1.36
1.32
6.46
29
6.46
0.291
1.077
2.156
3.525
330.38
17900.24
22,500.00
296667.00
1.04
1.00
4.44
30
4.44
0.138
0.509
1.019
1.665
332.23
12372.83
22,500.00
296667.00
8,232,931
0.79
0.75
3.82
29
3.82
0.102
0.376
0.753
1.230
332.67
10649.31
22,500.00
148333.50
6,944,608
0.58
0.54
3.31
30
3.31
0.077
0.283
0.567
0.926
332.97
9248.89
22,500.00
148333.50
6,221,996
0.43
0.39
3.42
30
3.42
0.081
0.301
0.602
0.985
332.92
9533.32
22,500.00
148333.50
6,418,600
11,641,058
30,000.00
27,818,136
27.82
147.43
175.25
147,434,892
5.30
25
(USD in '000)
Typical Disbursement percentage
Capacity
MW
NRs.
US$
0%
2%
30.00
US$
60,019
30%
18,006
Debt Portion
70%
42,013
Interest Rate
After Capitalization
58,842
1,177 of Project Cost
of Project Cost
Equity Portion
Construction P Year 1
75
14%
Per Annum
10
Years
74218
37.84%
22265
Year 2
Year 3
Year 4
Year 5
Year 6
Year 7
100.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
2
3
4
5
60.0%
30.0%
20.0%
20.0%
40.0%
40.0%
20.0%
20.0%
0.0%
30.0%
30.0%
20.0%
0.0%
0.0%
30.0%
20.0%
0.0%
0.0%
0.0%
20.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
0.0%
15.0%
15.0%
15.0%
15.0%
25.0%
15.0%
0.0%
15.0%
12.0%
13.0%
15.0%
15.0%
15.0%
15.0%
51953
Actual Project Cost (USD'000)
64279
TRUE
Construction Period Years
Total Project Cost
Investment Outlays
4
0th year
Cost %
1st Year
1.5%
2nd Year
18.5%
964
3rd Year
20.0%
11,892
4th Year
30.0%
5th Year
30.0%
12,856
6th Year
0.0%
SUM Check
7th Year
0.0%
-
0.0%
-
TRUE
19,284
19,284
20.0%
8,403
30.0%
12,604
30.0%
12,604
0.0%
-
0.0%
-
0.0%
-
TRUE
20.00%
4,453
30.00%
6,680
30.00%
6,680
0.00%
-
0.00%
-
0.00%
-
TRUE
Debt
Debt %
Amount (USD '000)
0.0%
-
20.0%
8,403
Equity
20.00%
964
Equity %
Amount (USD '000)
3,489
O&M Cost
2.00%
of Project Cost
1.50%
2625
of Project Cost
20 th year
5%
Other Important Input Factors
Royalty:
BPC's S/H
2%
1 - 15 Years
100.00%
Employee Bonus
1.33 USD/KW installed
2%
Working Capital
30
Dividend Payout
95%
% of PAT
10%
16 - 50 Years
Discount Rate
Income Tax
Days
14.0%
21.5%
Total
Energy Production ( GWh)
Dry
175.25
0.00%
0.00
Total
Wet
27.82
147.43
Dry
Wet
Interest Factor
6.30
6.30
6.30
0.0840
0.0840
0.0840
6%
0%
Depreciation Year
25
Depreciation %/Year
of FCFs
for Project CF
10 for Yrs
onwards
4.00%
(USD in '000)
Construction Periods
Develop
2067/68
2011
Years #
Year of Operation
Total Energy (GWh) Produced
Dry
Wet
Energy for Outages (GWh)
Tariffs (USD/KWh)
Dry
Wet
Total Revenue from Energy Sale
2012
1
2013
2
2014
3
2015
4
2016
5
2017
6
2018
7
2019
8
1
175.25
27.82
147.43
0.084
0.084
0.084
14,721
2
175.25
27.82
147.43
0.089
0.089
0.089
15,604
3
175.25
27.82
147.43
0.094
0.094
0.094
16,488
0.0077
0.0075
0.0073
11,892
12,856
19,284
19,284
964
(964)
(964)
11,892
(11,892)
(11,892)
12,856
(12,856)
(12,856)
106
19,389
(19,389)
(19,389)
1,430
1,073
334
2,838
11,883
2,571
8,034
1,278
1,502
1,126
352
2,981
12,624
2,571
7,619
2,434
1,577
1,183
370
3,130
13,358
2,571
7,145
3,641
964
-
11,892
-
12,856
-
19,284
(19,284)
(19,284)
19,284
-
(0)
19,389
-
9,312
2,838
1,278
10,053
2,981
2,434
10,787
3,130
3,641
964
11,892
12,856
19,284
2020
9
4
175.25
27.82
147.43
0.00
0.099
0.099
0.099
17371
2021
10
5
175.25
27.82
147.43
0.00
0.104
0.104
0.104
18254
2022
11
6
175.25
27.82
147.43
0.00
0.109
0.109
0.109
19137
2023
12
7
175.25
27.82
147.43
0.00
0.114
0.114
0.114
20021
2024
13
8
175.25
27.82
147.43
0.00
0.119
0.119
0.119
20904
2025
14
9
175.25
27.82
147.43
0.00
0.124
0.124
0.124
21787
2026
15
10
175.25
27.82
147.43
0.00
0.129
0.129
0.129
22670
2027
16
11
175.25
27.82
147.43
0.00
0.134
0.134
0.134
23554
2028
17
12
175.25
27.82
147.43
0.00
0.134
0.134
0.134
23554
2029
18
13
175.25
27.82
147.43
0.00
0.134
0.134
0.134
23554
2030
19
14
175.25
27.82
147.43
0.00
0.134
0.134
0.134
23554
2031
20
15
175.25
27.82
147.43
0.00
0.134
0.134
0.134
23554
2032
21
16
175.25
27.82
147.43
0.00
0.134
0.134
0.134
23554
2033
22
17
175.25
27.82
147.43
0.00
0.134
0.134
0.134
23554
2034
23
18
175.25
27.82
147.43
0.00
0.134
0.134
0.134
23554
2035
24
19
175.25
27.82
147.43
0.00
0.134
0.134
0.134
23554
2036
25
20
175.25
27.82
147.43
0.00
0.134
0.134
0.134
23554
2037
26
21
175.25
27.82
147.43
0.00
0.134
0.134
0.134
23554
2038
27
22
175.25
27.82
147.43
0.00
0.134
0.134
0.134
23554
2039
28
23
175.25
27.82
147.43
0.00
0.134
0.134
0.134
23554
2040
29
24
175.25
27.82
147.43
0.00
0.134
0.134
0.134
23554
2041
30
25
175.25
27.82
147.43
0.00
0.134
0.134
0.134
23554
2042
31
26
175.25
27.82
147.43
0.00
0.134
0.134
0.134
23554
2043
32
27
175.25
27.82
147.43
0.00
0.134
0.134
0.134
23554
28
175.25
27.82
147.43
0.000
0.134
0.134
0.134
23554
2044
33
29
175.25
27.82
147.43
0.000
0.134
0.134
0.134
23554
0.0071
0.0069
0.0065
0.0068
0.0064
0.0061
0.0065
0.0061
0.0062
0.0063
0.0064
0.0065
0.0076
0.0077
0.0078
0.0080
0.0119
0.0083
0.0084
0.0086
0.0087
0.0089
0.0079
0.0081
0.0083
0.0085
1,656
1,242
387
1,739
1,304
405
1,826
1,369
423
1,917
1,438
440
2,013
1,510
458
2,113
1,585
476
2,219
1,664
493
2,330
1,748
511
2,447
1,835
511
2,569
1,927
511
2,697
2,023
511
2,832
2,124
511
2,974
2,230
2,755
3,123
2,342
2,755
3,279
2,459
2,755
3,443
2,582
2,755
3,615
2,711
8,466
2,755
3,795
2,847
2,755
3,985
2,989
2,755
4,184
3,138
2,755
4,394
3,295
2,755
4,613
3,460
2,755
4,844
3,633
2,755
5,086
3,815
2,755
5,341
4,005
2,755
5,608
4,206
2,755
3,285
14,085
2,571
6,605
4,909
3,448
14,806
2,571
5,990
6,245
3,618
15,520
2,571
5,288
7,660
11,514
3,285
4,909
12,235
3,448
6,245
12,948
3,618
7,660
3,795
16,225
2,571
4,488
9,166
985
13,654
4,780
8,181
3,980
16,923
2,571
3,576
10,776
1,158
14,352
5,139
9,618
4,174
17,613
2,571
2,536
12,505
1,344
15,042
5,519
11,161
4,377
18,293
2,571
1,351
14,371
3,090
15,722
7,467
11,281
4,589
18,965
2,571
16,394
3,525
16,394
8,113
12,869
4,793
18,761
2,571
16,190
3,481
16,190
8,273
12,709
5,007
18,547
2,571
15,976
3,435
15,976
8,441
12,541
5,231
18,322
2,571
15,751
3,386
15,751
8,618
12,365
5,467
18,086
2,571
15,515
3,336
15,515
8,803
12,179
7,960
15,594
2,571
13,023
2,800
13,023
10,759
10,223
8,220
15,334
2,571
12,763
2,744
12,763
10,964
10,019
8,493
15,061
2,571
12,489
2,685
12,489
11,178
9,804
8,780
14,774
2,571
12,203
2,624
12,203
11,403
9,579
17,547
6,007
2,571
3,435
739
3,435
18,286
2,697
9,397
14,156
2,571
11,585
2,491
11,585
11,888
9,094
9,729
13,824
2,571
11,253
2,419
11,253
12,149
8,834
10,078
13,475
2,571
10,904
2,344
10,904
12,423
8,560
10,444
13,109
2,571
10,538
2,266
10,538
12,710
8,272
10,829
12,725
2,571
10,154
2,183
10,154
13,012
7,971
11,232
12,321
12,321
2,649
12,321
13,881
9,672
11,656
11,897
11,897
2,558
11,897
14,214
9,339
12,101
11,452
11,452
2,462
11,452
14,564
8,990
12,569
10,985
10,985
2,362
10,985
14,930
8,623
10,647
9,672
9,339
8,990
8,623
964
19,389
11,883
12,624
13,358
14,085
14,806
15,520
15,240
15,765
16,269
15,204
15,440
15,280
15,112
14,936
14,750
12,794
12,590
12,375
12,150
5,268
11,665
11,405
11,131
10,844
106
(11,892)
(12,856)
(19,284)
(19,389)
11,883
12,624
13,358
14,085
14,806
15520
15240
15765
16269
15204
15440
15280
15112
14936
14750
12794
12590
12375
12150
5268
11665
11405
11131
10844
10647
9672
9339
8990
8623
19137
3618
20021
4780
20904
5139
21787
5519
22670
7467
23554
8113
23554
8273
23554
8441
23554
8618
23554
8803
23554
10759
23554
10964
23554
11178
23554
11403
23554
18286
23554
11888
23554
12149
23554
12423
23554
12710
23554
13012
23554
13881
23554
14214
23554
14564
23554
14930
5268
54
9672
193
9339
187
8990
180
8623
172
(964)
50019
40161
9858
1.25
16.99%
Year 0
964
-
Year 1
3,489
8,403
8,403
1,176
9,579
Year 2
4,453
8,403
17,982
2,517
20,499
Year 3
6,680
12,604
33,103
4,634
37,737
Year 4
6,680
12,604
50,341
7,048
57,389
Year 5
-
Year 6
-
Year 7
-
11,892
12,856
19,284
19,389
14,721
2,838
15,604
2,981
16,488
3,130
57389
11002
57389
57,389
1
11,002
8,034
2,968
54,421
2
11,002
7,619
3,383
51,038
3
11,002
7,145
3,857
47,181
11,883
26
12,624
49
13,358
73
11,002
0
11,002
0
11,002
0
17371
3285
18254
3448
Years
51283
964
0
964
(964)
3489
4453
6680
(3,489)
(4,453)
(6,680)
6,680
(6,680)
855
855
1,573
2,283
1,573
2,283
4
11,002
6,605
4,397
42,784
5
11,002
5,990
5,012
37,772
6
11,002
5,288
5,714
32,058
7
11,002
4,488
6,514
25,543
8
11,002
3,576
7,426
18,117
10
11,002
2,536
8,466
9,651
11,002
1,351
9,651
-
11
12
13
14085
98
14806
125
15520
153
15240
164
15765
192
16269
223
15204
226
15440
257
15280
254
15112
251
14936
247
14750
244
12794
204
12590
200
12375
196
12150
192
11665
182
11405
177
11131
171
10844
165
10647
159
11002
11002
11,002
0
11,002
0
11,002
0
11,002
0
11,002
0
5,214
11,484
11,228
10,960
10,678
10,488
9,479
9,153
8,810
8,451
5,214
11,484
11,228
10,960
10,678
10,488
9,479
9,153
8,810
8,451
2,985
3,679
4,364
4,074
4,570
5,043
3,976
15,183
15,026
14,861
14,688
14,507
12,590
12,389
12,179
0.00
11,959
2,985
3,679
4,364
4,074
4,570
5,043
3,976
15,183
15,026
14,861
14,688
14,507
12,590
12,389
12,179
11,959
19722
13960
5762
1.41
26
Hydro Consult
APPENDIX G
ACCESS ROAD AND BRIDGE
DESIGN REPORT
October, 2010
Hydro Consult
Table of contents
Page no.
SUMMARY ................................................................................................................................... I
1. INTRODUCTION ................................................................................................................ 1
1.1
1.2
1.3
1.4
1.5
Background ...............................................................................................................................................1
Geomorphology and Geology ..............................................................................................................2
Climatic Condition ..................................................................................................................................2
Vegetation .................................................................................................................................................2
Hydrology and Meteorology .................................................................................................................3
Introduction ..............................................................................................................................................4
Survey Procedure ....................................................................................................................................4
Discarded Road Alignment ...................................................................................................................4
Proposed Alignment Description ........................................................................................................4
Material survey .........................................................................................................................................5
Longitudinal Section and Cross Section .............................................................................................5
3.4
3.5
3.6
3.7
3.8
3.9
3.10
3.11
3.12
3.13
3.14
3.15
Horizontal Curvature............................................................................................................................... 6
Minimum radius of curvature ................................................................................................................. 7
Extra widening ........................................................................................................................................... 8
3.5.1
3.5.2
3.5.3
Super Elevation.........................................................................................................................................8
Vertical alignment ....................................................................................................................................9
Hydro Consult
Page no.
ii
Hydro Consult
List of abbreviations
BH
Borehole
BPC
DHM
DoR
Department of Roads
DoS
Department of Survey
km
Kilometer
Meter
m2
Square meter
MCT
US $
VDC
GON
Government of Nepal
NHP
NHL
iii
Hydro Consult
SUMMARY
Background
The access road to the site of Nyadi Hydropower Project is designed as a district level road located
in Lamjung District. This road links Beshishar - Chame road at Thakanbeshi near Nyadi Bazaar to
Powerhouse site, Surge Shaft and headworks area of Nyadi Hydropower Project. Among two
alternatives studied, the proposed one proves to be better alignment for Access Road in terms of
geometric standard and cost effectiveness.
The length of the proposed access road will be about 9KM from its roadhead at Thakanbeshi
(Besishashar Chame road) at the right bank of Marsyangdi River near Nyadi Bazaar to Naiche
Village. Around 2KM road is also considered for access from Naiche Village to Headworks area for
the construction of the project. A 52.0m long major bridge will be constructed for crossing
Marsyangdi River at Thakanbeshi. In order to provide access to surge shaft location, additional 2.4KM
of road from Thulobeshi village to Surge Adit is considered as well. The access to the powerhouse
site can be provided by the construction of access tunnel with its starting point at Ch. 4+500 near
the proposed switchyard location.
Hence, the total length of the whole access road for the project will be about 13.45KM starting from
the existing Besisahar-Chame road.
Geometric Design Standards
This access road for Nyadi Hydropower Project falls under District Road Class A type according to
NRS 2045 and DoLIDAR 1998. This road as being the hill road is so designed by considering
minimum radius of curve of 12.5m, carriage way width 3.0m, formation width 4.50m and design speed
is 20kmph. The Right Of Way (ROW) of the access road is taken as 10m on each side of the road
centreline at most of the stetches except around those areas where the ROW can be reduced
depending upon field condition and design requirement. It is assumed that for design, the transport
unit has been taken less than 400 per day in this road and maximum axle wheel load is 14.4 tons.
Alignment Survey
First of all, Reconnaissance survey was done for fixing the alignment. After the completion of
reconnaissance survey, the tentative fixing of alignment was done using Abney level and tape. After
fixing tentative alignment, a traverse was run along the road corridor of specified width by using total
station instrument. In general, the alignment passes through steep slopes, forests and cultivated lands
while the few stretches have to pass through hard cliff.
Design
The design has been done according to Nepal Road Standard (First Revision 2045). Horizontal and
vertical curve has been provided as per necessity. Since the road is considered as hill road, some
hair-pin bends have been introduced as well to maintain the required gradient. The side slope of
filling and cutting of the road was so chosen to ensure the stability of the road in a balanced way.
Proper drainage system has been provided in order to prevent the road formation from further
damage due to monsoon flow. The side drains, both lined and unlined depending upon flow and
catchment area are kept along the route and drain out to the near-by natural water course or into
the meeting of cross-drainage structures. Gravel has been considered as the pavement material to be
used in Sub-base layer with no other layers considered. The use of retaining walls and structures has
been minimized as far as possible from viewpoint of economy and construction simplicity with some
stone masonry and gabion walls provided at unavoidable areas.
S-i
Hydro Consult
S-ii
Hydro Consult
1. INTRODUCTION
1.1 Background
Construction of Nyadi Hydropower Project requires an access road which provides an access to the
powerhouse site at Thulobesi of Bahundada VDC and reaches the headworks site of the same VDC.
At present, there is no motorable road except around 10 km long foot trail access from Nyadi
Bazaar.
The alignment of the road runs mostly along the river valley of the rain fed catchments of Nyadi
khola. The proposed access road starts from Besishar Chame road at Thakanbeshi and reaches up
to headworks site of NHP at Bahundada VDC. The primary objective of this road is to facilitate the
construction of NHP in time by making project accessible to the main road at Nyadi Bazaar. Further,
it will facilitate the people of Bahundada VDC of Lamjung district by making the area accessible using
vehicle from the existing motorable road. The access road project area is located on hilly areas of
Western Development Region of Nepal and it has been designed on the basis of Green (Agricultural)
Road concept with the flexibility in construction technique by the use of both man and machine so as
to reduce cost.
Table 1-1 Salient feature of the access road
S.N.
1.
2
4
5
6
6.1
6.2
6.3
6.4
6.5
6.6
7
8
9
Parameters
Name of the Project
Geographical location
Region
Zone
District
Geographical feature:
Climate
Geology
Hydrology
Meteorology
Classification:
Length of road
Starting point
End point
Total length of road
Design Criteria:
Design speed
Stopping Sight Distance
Gradient
Maximum gradient
Minimum gradient
Cross section
Right of way
Formation width
Carriage way
Shoulder
Side drain
Minimum horizontal curve radius
Pavement
Cross Drainage Structure
Bridge 52.0m span
0.6m dia Pipe Culvert
Retaining Structure
Gabion
Description
Nyadi Hydropower Project
Western Region
Gandaki
Lamjung
Sub-Tropical.
Mountainous.
Rain fed catchment of Nyadi khola
Unevenly distributed precipitation controlled by monsoon
District Rural Road Class 'A'
Upstream of Nyadi Bazaar at Thakanbeshi (Right Bank of
Marsyangdi River)
Proposed Headworks Site.
13.50KM
20 kmph.
20 m.
12.0%
0.5% to facilitate better drainage.
10 m from the road centerline on either side.
4.5 m.
3.0 m.
0.75 m.
Earthen Tick/ Trapezoidal Dry Stone/ Stone Masonry Drain
12.5m
Gravel (15 cm Thick)
1 no. (Proposed)
23 nos. (Proposed)
610m3
Hydro Consult
1.4 Vegetation
The overall natural vegetation cover within the study area has been categorized as forests, shrub and
bushy land and agricultural land. Forests have been disrupted by fuel wood, fodder, timber collection
and extensive cultivation.
The vegetation along the Access Road consists of mixed forest. The different types of vegetation
along the road alignment are listed below.
Hydro Consult
The ground cover consists of Nigalo (Arundinaria sp), Chutro (Berberis aristata), Ainselu (Rubus
elipticus), Banmara (Eupatorium adenophorum), Titepati (Artimisia vulgaris), Ghodtapre (Centella
asiatica), etc.
Hydro Consult
2.
ALIGNMENT SURVEY
2.1 Introduction
The access road under this design study is totally a new construction with only foot trails available in
the project area. This chapter deals with all the necessary survey works related to the design and
construction of the road.
Hydro Consult
Hydro Consult
National Highway
Feeder Roads
District Roads
City Roads
Village Roads (According to revised NRS)
The access road for Nyadi Hydropower project falls under District Road according to NRS (First
Revision-2045). For the purpose of movement of heavy laden vehicles, the carriage way and
formation width (total width of the road) were taken as 3.0 m and 4.5 m respectively. It is assumed
that for design, transport unit has been taken less than 400 per day in this type of road. The
maximum axle load standard is 14.4 tons for the design of pavement.
= Intersection point
T1
= Commencement of tangent
T2
= Point of tangency
BC
= Beginning of Curve
EC
= End of Curve
Ax
R.
= Radius of curvature
= Deflection angle
Hydro Consult
The various parameters of curves were calculated by taking appropriate value of Radius of curvature
and Deflection Angle, which are obtained actually noted from the field work.
Then,
Apex distance = R. sec 1
2
Curve length =
R
180 0
Now,
a)
b)
c)
d)
When centerline of the road deviates from its original position, the horizontal curve is introduced to
facilitate the safe and smooth movement of vehicles.
3.3.2 Minimum radius of curvature
Empirical Formula has been given for obtaining the minimum radius of horizontal curve as below:
R = V2/(127*(e+f)
Where,
R = Radius in m,
V = Design Speed in kmph,
e = superelevation in m per m,
Nyadi Hydropower Limited
Hydro Consult
Widening on curves in m.
No. of lanes
To
Soft verges
Hard verges
>1.5m
<1.5m
12.5
2.0
2.0
12.6
20
1.5
1.5
21
40
1.2
1.2
41
60
0.8
0.8
61
80
0.5
0.5
81
100
0.3
0.3
101
1000
0.0
0.0
Full width of the adopted extra widening of the road has been applied for the whole part of the
corresponding horizontal curve. The transition has been provided at the rate of 0.1m per m along
the straight portions as there is no provision made for transition curve.
e = V2/(127*R)-f
Nyadi Hydropower Limited
Hydro Consult
Where,
e = superelevation in m per m,
V = Design Speed in kmph,
R = Radius in m,
f = frictional coefficient taken as 0.15.
This empirical formula has been modified in tabular form for compatibility in design as presented in
Table 3-2.
Table 3-2 Super Elevation
Radius (m)
From
To
0.0
20.0
20.0
35.0
35.0
55.0
55.0
80.0
80.0
1000.0
SE (%)
7.0
6.0
5.0
4.0
3.0
Hydro Consult
120
100
80
60
50
40
30
20
10
Hydro Consult
The inner and the outer edges of the roadway should be concentric with respect to the
centreline of the road.
A minimum intervening length of 60m has been provided as far as possible between two
successive bends to enable the driver for smooth vehicle manoeuvre.
3.8 Drainage
The drainage system has been designed in order to drain out the surface run off along the pavement
to the nearest natural water course. Following empirical formulae have been applied in the design of
Side drains and Cross drainage structures:
Rational method of Rainfall-Runoff:
Q=0.28*C*I*A
Where, Q= discharge in cumecs.
C= run-off coefficient.
I= Rainfall intensity in mm/hr.
A= Catchment area in sq. km.
Mannings formula: Q= A*(1/n)*R^(2/3)*S^(1/2)
Where, Q= discharge in cumecs.
A= Cross-sectional area of flow in sqm.
n= roughness coefficient.
R= Hydraulic Radius in m.
S= Bed slope.
The nature of hydrology is almost similar in majority of the sections of the road alignment The side
drains, the size and shape of which has been fixed from design using above formulae are kept along
the route. The flow coming from side drains has been designed to discharge properly to the near-by
natural water course or into the meeting cross-drainage structures using drop structures of standard
design at suitable places.
With regard to cross drainage structures, pipe culvert using NP3 0.6m dia hume pipe has been
considered in most of the cases to control the surface drainage due to existing waterways. This
minimum size has been selected in view of easy handling and transportation, maintenance ease during
choking and economy as well.
11
Hydro Consult
12
Hydro Consult
13
Hydro Consult
Cultivation and grazing in the sloping area and illegal cutting of trees to be strictly
prohibited,
Major portion of excavated muck to be utilized in cut and fill operation and the remaining
muck to be used for backfilling of quarry and burrow pits and for land reclamation,
The excavated muck to be levelled and surface runoff by monsoon rain to be properly
drained out ,
The forest clearance to be minimized by cutting trees of formation width only as far as
possible,
SHRUBS
14
Hydro Consult
TREES
The plants that should never be used for bioengineering are listed below
ii.
iii.
15
Hydro Consult
16
Hydro Consult
6. MARSYANGDI BRIDGE
In order to link the project area with the existing road head, the access road has to cross Marsyangdi
river. Hence, a bridge has been proposed to fulfill the accessibility requirement of the project having
its location at about 1.1KM upstream of the Marsyangdi-Nyadi confluence. The proposed bridge not
only provides access to the project area but also connects several villages like Thulobeshi and Naiche
of Bahundanda VDC to the existing motorable road. Hence, this bridge should be given utmost
importance and be made an integral part of access road for overall development of the surrounding
area of the project.
The bridge has been designed as bailey bridge with its length of about 52.0m. The estimated cost of
the bridge as obtained from design comes out to be NRs. 25,517,784.00. The details of technical
aspects regarding the bridge design have been provided in the bridge design report separately.
17
Hydro Consult
18
Hydro Consult
8. REFERENCES
IRC
DHM:
Lamjung District
District Rate
DoLIDar, 1998
DoLIDar, 1998
Work Norms for Agricultural and Rural Roads. Ministry of Local Development,
Transport Division. 1999
DoLIDar, 1999
The Approach for the Development of Rural and Agricultural Roads. Ministry of
Local Development, Transport Division. 1998
DOR
DOR
DOR
Standard design;
Design Section Government of Nepal (GON), Ministry of
Works and Transport, Department of Road (DOR)
ICIMOD
Highway Engineering.
19
Hydro Consult
APPENDIX H
PHOTOGRAPHS
October, 2010
Hydro Consult
H-i
Hydro Consult
H-1
Hydro Consult
H-2
Hydro Consult
H-3
Hydro Consult
Nana
Tunnel level
H-4
Hydro Consult
H-5
Hydro Consult
H-6
Hydro Consult
H-7
Hydro Consult
H-8