Engineering Procedure

SAEP-14

20 September 2006

Project Proposal
Document Responsibility: Project Support and Controls Dept.

Saudi Aramco DeskTop Standards


Table of Contents

1
2
3
4
5
6
7
8

Introduction......... 2
Applicable Reference Documents... 3
Proposal Contents and ER Estimate...... 5
Project Improvement Effort. 21
Reporting and Review Requirements....... 27
Approvals and Waivers....... 30
Contract Bid Package.. 33
Exhibits...... 34

Exhibit I Project Proposal Checklist..


Exhibit II ER Estimate Package Checklist.......
Exhibit III Contract Development Checklist..
Exhibit IV Benchmarking Data Sheet
Exhibit V Bid Quantification Summary.............

Previous Issue: 15 August 2006 Next Planned Update: 15 August 2011


Revised paragraphs are indicated in the right margin
Primary contact: Branton, Minh A on phone 873-9526
CopyrightSaudi Aramco 2005. All rights reserved.

36
38
40
42
46

Page 1 of 48

Document Responsibility: Project Support and Controls Dept.


Issue Date: 20 September 2006
Next Planned Update: 15 August 2011

SAEP-14
Project Proposal

Introduction
This procedure outlines the requirements for preparing the Project Proposal and
Expenditure Request (ER) Estimate package. The procedure is not intended to give
instructions on the engineering effort, but to cover requirements that are important
during the Project Proposal process. In summary it covers:

Engineering specifications, standards and selected design requirements

Quality, cost reduction and schedule improvement techniques, i.e., benchmarking,


value engineering and value practices

Project Proposal reporting, review, approval & waiver requirements

ER Estimate preparation requirements

Project Proposal, ER Estimate Package & Contract Development Checklists

Contract Bid Packages

The intent of the checklists is to insure compliance with key requirements. They are not
intended to cover all detailed requirements of this procedure.
1.1

Definition
The Project Proposal is a document, which establishes the preliminary (front
end) engineering scope definition, cost estimate basis and schedule for a
proposed facility from the requirements included in the Design Basis Scoping
Paper (DBSP) and the approved Project Execution Plan (SAEP-12). This
includes the proposed facility design, general layout and the appropriate
functional and performance specifications including the recently published
applicable standards & codes. Project Proposal shall be of sufficient detail to
prepare a 10% accuracy ER estimate, provide sufficient technical information
for Saudi Aramco review and (where applicable) provide sufficient information
to obtain detailed engineering, procurement and construction contract bids in
accordance with the approved Contracting Plan.

1.2

Purpose
The Project Proposal documents the agreement on, and commitment to, the
project scope, the project cost and design basis by the Saudi Aramco Project
Management Team (SAPMT), Facilities Planning Department, Project Support
& Controls Department, Proponent and other technical support groups. This is
accomplished through careful evaluation of the project objectives during Project
Proposal preparation to ensure the optimum results. The Project Proposal
establishes the basis for Expenditure Request (ER) funding and is the baseline
from which all subsequently considered scope changes are measured.

Page 2 of 48

Document Responsibility: Project Support and Controls Dept.


Issue Date: 20 September 2006
Next Planned Update: 15 August 2011

1.3

SAEP-14
Project Proposal

Preparation Timing
Project Proposals must be completed and approved in time to support the
Expenditure Request Approval (ERA) date.
A complete ER Estimate Package must be submitted to Project Support &
Controls Department / Project Controls & Estimating Division (PS&CD/PCED)
at least 4 weeks prior to the 56D Estimate submittal due date to FPD Budget
Director, as per the Capital Program ER Processing Schedule for Board
EXCOM and local approval. Refer to Section 3.4.2 through 3.4.6 for ER
Estimate Preparation requirements. Approved Project Proposal from SAPMT
Department Manager, Facilities Planning and Proponent organization signatory
is a mandatory requirement prior to issuance of the ER Estimate (Saudi Aramco
Form 56D) to Budget Director.

1.4

Application
With the exception of Master Appropriation projects, Saudi Aramco requires a
Project Proposal and ER Estimate for all Capital, Non-Capital and Expense
Projects, valued more than $2 million, under the control of Engineering and
Operations Services (E&OS). The Project Proponent and SAPMT shall agree
and document the level of detail needed prior to start of the Project Proposal.
Projects that combine the preparation of DBSP and Project Proposal into one
effort shall ensure that the requirements identified in this document which are
relevant to the Project are met.

Applicable Reference Documents


The latest edition of the applicable reference documents shall be applied:
Saudi Aramco Engineering Procedures
SAEP-12

Project Execution Plan

SAEP-13

Project Environmental Impact Assessments

SAEP-25

Estimate Preparation Guidelines

SAEP-31

Corporate Equipment and Spare Parts Data


Requirements

SAEP-140

Project Training Impact Assessment

SAEP-302

Instructions for Obtaining a Waiver of a


Mandatory Saudi Aramco Engineering
Requirement

SAEP-303

Engineering Reviews of Project and Detail Design


Engineering Documentation
Page 3 of 48

Document Responsibility: Project Support and Controls Dept.


Issue Date: 20 September 2006
Next Planned Update: 15 August 2011

SAEP-14
Project Proposal

Saudi Aramco Engineering Report


SAER-5437

Guidelines for Conducting HAZOP Studies

Saudi Aramco Engineering Standards (SAESs)


Saudi Aramco Materials System Specifications (SAMSSs)
Saudi Aramco Cost & Scheduling Manual
Saudi Aramco Construction Safety Manual
Saudi Aramco Safety Management System
Saudi Aramco Form and Data Sheet
8362-ENG

Certification of Review of Saudi Aramco Materials


Source Documents

General Instructions
GI-0005.002

Loss Prevention Policy Implementation

GI-0020.500

Expenditure Control Expenditure Request


Forms

GI-0020.520

Project Change Request

GI-0202.309

Allocation of Costs New Facilities Start-up

GI-0202.451

Engineering Work Order Authorization for


Preliminary Engineering Preparation

GI-0400.001

Quality Management Roles & Responsibilities

Design Basis Scoping Paper (DBSP) and applicable Study Documents


Corporate Loss Prevention Manual
Project Management Loss Prevention Program
Supply Chain Management Manual
DC Surplus Materials - Plant M011 of SAP system
MVG076-01, DC Surplus Deferred Materials System
Unrestricted Use Materials of SAP system (for SAMS Excess Materials)
Saudi Arabian Manufactured Materials Listing from SAP

Page 4 of 48

Document Responsibility: Project Support and Controls Dept.


Issue Date: 20 September 2006
Next Planned Update: 15 August 2011

SAEP-14
Project Proposal

Saudi Arabian Government Safety and Security Directives (SSDs)


Construction Industry Institute (CII) Publications
3

Proposal Contents and ER Estimate


The following sections outline the items normally included in Project Proposals.
3.1

Table of Contents

3.2

Technical Requirements
3.2.1

Project Summary
This section provides a history of the existing conditions, a brief
discussion of the proposed facilities and their justification, outlines the
project objectives/scope and schedule, and briefly describes how these
objectives will be achieved.

3.2.2

Project Description
This section provides scope and design information that establishes the
performance specifications for the facilities, process, waivers or
limitations. It shall address details concerning the design basis, proposed
facilities including equipment design, capacities, location/layouts and
other project related information. The list below provides common
elements found in a typical scope.
1)

Facility/plant location and layout

2)

Facility/process description, design basis and performance


specification

3)

Process Flow Diagrams (PFDs) including heat and material


balances

4)

Major mechanical, electrical, and utility requirements (type and


quantity)

5)

Electrical one-line diagrams electrical area classification drawings

6)

Piping and Instrumentation Diagrams (P&IDs)

7)

Temporary and permanent on-plot and off-plot facilities

8)

Site survey, topography and soil data (Geotechnical Investigation)

9)

Demolition and modifications to existing facilities/plants

10) Operating variables (as required by OSPAS)

Page 5 of 48

Document Responsibility: Project Support and Controls Dept.


Issue Date: 20 September 2006
Next Planned Update: 15 August 2011

SAEP-14
Project Proposal

11) Corrosion control


12) Impact on and interface with other related projects
13) Environmental Impact Assessment (see SAEP-13)
14) Security, fire protection & safety provisions (if required, Hazard
Identification Plan of Major Hazards, fire hazard zone drawings,
and fire system layout drawings)
15) Communications, including government approvals if required
16) Control systems (including SCADA) provided with Control System
Block Diagram or System Architecture, instrument index,
instrument cable routing and I/O count breakdown
17) Project Execution Plan/Schedule
18) Training requirements
19) Land use permits for new facility sites or addition of facilities
within existing plants. Include Proponent approved permits for laydown areas, staging areas and office sites
20) Strategy for project compliance with Project Quality Plan
requirements
21) Process & utilities system definition and turnover sequence
22) Piping, electrical and control system tie-in /hot tap plan
23) Studies & calculations developed during Project Proposal (i.e.
ETAP study, PHA study, process simulation, etc.)
24) Site Investigation Report
25) Project Risks Assessment Report
3.2.3

Scope Change from DBSP


A)

Definition of Scope Change


A scope change is defined as any deviation from the Approved
DBSP. Following are examples of typical scope changes:
1.

Equipment capacity and sizing changes

2.

Addition or deletion of equipment from the original list


provided to PS&CD in conjunction with the DBSP for
preparation of the budget estimate

3.

Plot plan changes

Page 6 of 48

Document Responsibility: Project Support and Controls Dept.


Issue Date: 20 September 2006
Next Planned Update: 15 August 2011

B)

SAEP-14
Project Proposal

4.

Process control plan or system changes (changes in I/O


counts, type of control system, etc.)

5.

Other design changes as a result of the following:

Environmental Impact Assessment

Preliminary Hazard Analysis (PHA) or Hazard and


Operability (HAZOP) studies

Project risk assessment

Underground obstructions such as rock or utilities


interferences, etc.

Building Risk Assessment or any other Loss Prevention


requirements

Savings realized from Value Engineering and other Value


Practices

Site investigations

Notification of Scope Change


SAPMT shall promptly notify FPD, in writing, of any scope
change with the cost and schedule impact and justification as soon
as changes are identified. This allows timely assessment by FPD
of the impact of these changes to the project. Change will be
incorporated in the project scope based on FPD's assessment. All
approved scope changes shall be communicated to PS&CD.

C)

Implementation of Scope Change


If accepted for implementation, FPD shall issue a formal letter or
DBSP amendment to SAPMT within two (2) weeks of the initial
submittal and distribute a copy to PS&CD.

D)

Recording of Scope Change


All scope changes shall be recorded in a special section in the
Project Proposal package and ER Estimate Package. This section
shall contain a list of all scope changes with justification, cost
impact, schedule impact, initiator organization, date
initiated/approved and any supported cost estimate documents.
SAPMT shall maintain the list of the scope changes and
continuously update it from the start of Project Proposal until the
ER Estimate is complete.
Page 7 of 48

Document Responsibility: Project Support and Controls Dept.


Issue Date: 20 September 2006
Next Planned Update: 15 August 2011

3.2.4

SAEP-14
Project Proposal

Communication Requirements
Saudi Aramco construction projects normally require both temporary
(during construction) and permanent communication systems. As
procurement approval for radio frequencies and materials involves long
lead times, communication systems require early identification and
coordination between Information Technology organization and
SAPMT. To facilitate these requirements, the Project Proposal shall
contain the following:

3.2.5

a)

Summary of temporary and permanent communication system


requirements. Identification of additional communication facilities
and/or modification to existing facilities necessary to meet the
project requirements.

b)

Identification of communications requirements to be handled by


Information Technology organization and those, which shall be
provided and funded by the project.

c)

Schedule of communication material requirements with an


estimated site required delivery date.

d)

Identification and implementation plans of all communication


disaster recovery and business continuity aspects of the projects.

Safety and Security Directive (SSD)


The SSD (reference SAES-O series) shall be adhered to by all projects,
with exception of home-ownership & utility projects, in accordance with
the directives given to Saudi Aramco by the Saudi Arab Government's
Supreme Commission for Industrial Security. The SAPMT shall contact
Consulting Services Department, Dhahran and the Safety and Industrial
Security organization to obtain current safety and security requirements
before proceeding with Project Proposal engineering. A separate section
in the Project Proposal shall be devoted strictly to safety and security
requirements.

3.2.6

Preliminary Hazard Analysis (PHA)


The objective in performing PHA studies is to improve process safety
and/or minimize operability problems. The SAPMT in conjunction with
the Loss Prevention Department (LPD), and Environmental Protection
Department (EPD) shall decide which projects and specific facilities
require PHA studies. Duplicate facilities shall not require a new PHA
study. Only new or upgrade facilities that use, produce, process,
transport, or store flammable, explosive, toxic or reactive substances in
large quantities are candidates for PHA studies.
Page 8 of 48

Document Responsibility: Project Support and Controls Dept.


Issue Date: 20 September 2006
Next Planned Update: 15 August 2011

SAEP-14
Project Proposal

The PHA studies shall normally be conducted during the Project


Proposal stage. The Hazard and Operability (HAZOP) studies, if
required, shall be performed during the detail design when the facility
design is firm and no major design changes are forecasted.
For buildings, a building risk assessment shall be performed when
required by SAES-B-014.
Any cost impact as a result of the PHA studies or building risk
assessment must be identified and included in the ER Estimate package.
3.2.7

Environmental Impact Assessment (EIA)


EIA is required at the early stage in project planning. SAEP-13, "Project
Environmental Impact Assessments", establishes the procedures
necessary to prepare the environmental impact assessments which shall
be submitted to Environmental Protection Department Manager by the
30% Project Proposal stage for review and approval. EPD will forward
the final EIA document to the Ministry of Petroleum and Mineral
Resources for their approval. Approval by the Ministry is required for
all capital projects prior to expenditure request. Any cost impact as a
result of the Environmental Impact Assessment must be identified and
included in the ER Estimate Package.
An environmental impact assessment:

describes and quantifies project actions

identifies those discharges and emissions regulated by environmental


standards

predicts the environmental changes resulting from the project, and

demonstrates compliance with applicable Saudi Aramco and/or Saudi


Arab Government environmental standards and policies.

The discovery of new information or significant project changes that


impact a previously completed and EPD approved EIA may result in
cancellation of the existing assessment and re-submittal of an amended
EIA to EPD for approval.
The full environmental report with appropriate calculations is to be
included with the Project Proposals issued to Environmental Protection
Department, Technical Information Center (TIC) Dhahran, and
Corporate Information Center (ASC) Houston. All other volumes will
contain a summary only.

Page 9 of 48

Document Responsibility: Project Support and Controls Dept.


Issue Date: 20 September 2006
Next Planned Update: 15 August 2011

3.2.8

SAEP-14
Project Proposal

Obtaining a Waiver from Saudi Aramco Engineering Standards and


Materials System Specifications.
Identify standards, procedures, equipment and materials that will require
a waiver prior to incorporation into the facilities.
3.2.8.1

Projects shall meet the requirements of Mandatory Saudi


Aramco Engineering Requirements (MSAERs), which are in
effect on the Project Proposal approval date. Changes to
MSAERs approved after the Project Proposal approval date
shall be mandatory only when:

the changes affect safety, health, environment or security


highlighted by the concerned organization. In this case, the
impact of the changes on the project should be reviewed by
Project Management with the Proponent, Loss Prevention,
Industrial Security Operations, Facilities Planning
Department, Project Support and Controls Department,
Process and Control System Department, Information
Technology, and others to determine applicability and
extent of implementation.

the changes result in cost savings to the project. In this


case, SAPMT, Proponent and Engineering Services shall
review and decide on implementation.

A Project Change Request (PCR) shall be initiated to document


and obtain approval to implement changes after the project has
been funded (Refer to GI-0020.520, Project Change
Request).
3.2.8.2

Include waivers (reference SAEP-302 - "Instructions for


Obtaining a Waiver of a Mandatory Saudi Aramco Engineering
Requirement") that shall reduce project cost without impacting
design, safety or operational integrity of the facility.
Describe the variation in sufficient detail to permit technical
evaluation by the appropriate reviewing agency.
Include copies of waiver applications and approvals.
Any approved waiver that has an impact on the Project must be
identified in the Project Proposal and ER Estimate package.

Page 10 of 48

Document Responsibility: Project Support and Controls Dept.


Issue Date: 20 September 2006
Next Planned Update: 15 August 2011

3.2.8.3

3.2.9

SAEP-14
Project Proposal

Deviations from SSD requirements shall be submitted in a


letter format as per SAES-O-100 (General Requirements for
Safety & Security) that describes the variation in sufficient
detail to permit technical evaluation by the appropriate
reviewing agency.

Drawing Index and Drawings


This section provides a list and copies of the drawings that define the
scope of the project. It shall include key drawings such as PFDs, P&IDs,
plant and equipment layouts, electrical one-line diagrams and other
necessary drawings that are required to establish the design basis and
assist in producing an ER quality estimate.

3.2.10 Project Quality Plan


SAPMT shall prepare a Project Quality Plan in accordance with
GI-0400.001 (Quality Management Roles and Responsibilities). The
SAPMT shall also ensure that the specific requirements for inspection
are included in Schedule Q Attachment VI for all applicable contracts.
3.3

Materials Related Requirements


3.3.1

General
The Project Proposal provides a table of major materials and equipment
identified for the project. During preliminary engineering, the
Engineering Contractor, with guidance from the SAPMT, shall review
the Company DC (9COM) Surplus and Excess (9CAT) using SAP
MMBE transaction to identify all acceptable or substitute materials
which are available in Saudi Aramco inventories for possible use on the
project, with the objective of:
a)

Incorporating materials, which require the least new cash outlay to


Saudi Aramco

b)

Making maximum economic use of the materials available from


surplus and excess cataloged material inventories

c)

Making maximum economic use of locally manufactured materials

d)

Providing full justification for any proposed purchases of


contingent quantities or non-installed spares

During Project Proposal preparation, the SAPMT shall request review,


and may request assistance from the Materials Supply (MS) on all
portions of the plan that involve materials related aspects of the work.
Page 11 of 48

Document Responsibility: Project Support and Controls Dept.


Issue Date: 20 September 2006
Next Planned Update: 15 August 2011

SAEP-14
Project Proposal

SAPMT will continue to be responsible to ensure that the purchase order


is in acceptable technical compliance with relevant MSAERs during the
time the Contractor is handling the order. Purchase Orders for
inspectable materials shall be reviewed by Inspection Department prior
to placement, to ensure compliance with the Regulated Vendor List,
Technical and Quality requirements.
If procurement of major equipment and materials is on the critical path
of the project schedule, SAPMT may elect to consider "novation" of
these items to reduce their impact on the project schedule. "Novation"
typically involves:
1.

placement of purchase order by the Management Contractor or


Project Proposal Contractor with commitment only for engineering,
and

2.

after ERA, transfer the purchase order to the successful LSTK


Contractor on contract award.

The purchase order transferred to the LSTK Contractor will cover the
complete scope involving engineering and manufacture. Use of novated
purchase orders should be approved by Services Review Committee
(SRC) either as part of the contracting plan or as an individual item.
3.3.2

Material Source List


The materials source list identifies major equipment and material items.
Where possible, an estimated dollar value and quantity required shall be
indicated. Also indicate responsibility for inspection, expediting, traffic
and transportation. The Project Proposal effort shall develop Quotation
Requests (QRs) for major engineered equipment and critical items, and
issue these QRs to vendors on a "For Development Only" basis to
determine prices and delivery schedules. For purpose of preparing the
ER Estimate, the major equipment list shall include account number, the
item number, a brief description, the data sheet, a requisition number if
available, the estimated value and other pertinent information. The
following areas shall be segregated:
a)

Surplus Materials - 9COM Materials in Plant M011

b)

Excess Cataloged Materials - Unrestricted use 9CAT Materials in


SAP transaction MMBE

c)

Locally manufactured materials and vendor warehoused materials


(LDOR)

d)

Cataloged Materials Reservation (9CAT)


Page 12 of 48

Document Responsibility: Project Support and Controls Dept.


Issue Date: 20 September 2006
Next Planned Update: 15 August 2011

3.3.3

SAEP-14
Project Proposal

e)

Non-cataloged Materials (9COM)

f)

Contractor procurement Lump Sum Turnkey (LSTK) or Lump


Sum Procure/Build (LSPB)

g)

Sole source materials and equipment

Use-up Target Values


The Surplus Inventory and the Excess Cataloged Materials Listings shall
be reviewed to prepare the listing and estimated values of possible
surplus and excess usage. During the Project Proposal development this
list shall be further refined to set the target values for use-up of those
items that shall be reported during the life of the project. LSTK or LSPB
contracts shall use the same format and shall estimate total commodity
(9CAT) and engineered (9COM) material costs (regardless of originator)
as the basis for determining use-up values. The target values are goals
requiring extra effort to achieve rather than just a restatement of the
original major items listed in section 3.3.2.

3.3.4

Locally Manufactured Material


During Project Proposal development, the SAPMT shall obtain a current
list of approved locally manufactured products and sources from MS.
This list shall be provided to LSTK & LSPB Contractors to encourage
use of locally manufactured materials.

3.3.5

Critical Plant Equipment Unit Spares


A list of proposed installed spares for critical plant unit equipment and a
list of non-installed capital spares proposed for entry into Saudi Aramco
stores custody shall be provided along with the estimated cost for each
item and justification for purchase. Comparison shall be made between
spares specified in the Design Basis Scoping Paper and spares specified
in the Project Proposal.

3.3.6

Start-up Spare Parts


Construct-only project materials furnished by Saudi Aramco need not
address this subject because spares shall be furnished per SAEP-31
(Corporate Spare Parts Data Requirement). For Procure/Build contracts,
the SAPMTs shall specify start-up spare responsibility including how
they shall be provided, the financial impact of purchase and final
disposition of residual spares.
The LSTK Contractor is responsible for providing start-up spares.
Residual and/or unutilized start-up spares remain Contractor's property;
Page 13 of 48

Document Responsibility: Project Support and Controls Dept.


Issue Date: 20 September 2006
Next Planned Update: 15 August 2011

SAEP-14
Project Proposal

such spares may not be purchased from the Contractor by Project


Management. Proponent at their discretion has the option to purchase
these residual spares against their Operating Budget for future use.
Operations shall communicate with MS (Materials Control Department)
to ensure the spares are reviewed against overall inventory needs, and do
not adversely affect existing supplies. Defined start-up spares may be
turned over to Saudi Aramco in accordance with the contract
requirements provided that the quantities and types are in accordance
with the Saudi Aramco stocking policy. For LSTK and LSPB contracts,
start-up spares responsibility for "free issue" equipment provided by
Saudi Aramco shall be stated clearly in the contract.
SAPMT and the respective Contractors are responsible for the spare
parts as outlined under SAEP-31. In all cases, the SAPMT/Contractors
shall provide complete and accurate spare parts data packages necessary
to support Saudi Aramco procurement of operating spare parts.
3.4

Scheduling & Estimating Requirement


3.4.1

Scheduling Requirements
This section contains a Level III project summary schedule that shall be
developed during the Proposal phase based on information from the
Project Milestone Schedule, WER Schedule and other data as they
become available during the DBSP and Project Proposal.
Project Summary Schedule should be developed as soon as Preliminary
Engineering starts and will be used as a "working" tool in the absence of
a detailed schedule by Contractor. The Project Summary Schedule shall
be used as a guide for ER estimate preparation, early identification of
long lead material procurement items, Contracting Strategy and technical
evaluation of Contractors and start-up planning. As-Built schedules
from similar projects can be made available from PC&ED Scheduling
Group to be used as a guide for the initial preparation of the Level III
schedule.
Project Summary Schedule addresses all the project life cycle activities
in a summary format. It must be logic driven, based on the Critical Path
Method (CPM). The Schedule should contain sufficient detail to show
potential material or equipment novation, long lead items, contract
procurement activities, detailed engineering by discipline leading to
major deliverables, mobilization, early works, shutdown, tie-ins, testing,
loop checks, pre-commissioning, start-up, interface with Proponent and
other projects.

Page 14 of 48

Document Responsibility: Project Support and Controls Dept.


Issue Date: 20 September 2006
Next Planned Update: 15 August 2011

SAEP-14
Project Proposal

Project Summary Schedule shall also include ER estimate preparation


and approval activities including Estimate Kick-off, milestone dates for
Scope Compliance and any ER Estimate reviews or any other design
reviews, MTOs for the relevant disciplines, equipment pricing,
NOVATION of equipment and/or Prior Approval Expenditure Request
(PAER), Technical Review Meetings, and the final approval of the
Project Proposal and 56D preparation and submittal to the Facility
Planning Department (FPD).
The schedule shall form the basis for the original (Rev.0) Project
Completion Schedule (PCS). The Project Summary Schedule further
expands the level of detail while still supporting critical and key
milestone dates defined and prescribed in the contract (Schedule "B").
Project Summary Schedule is expanded to include critical milestone
dates as well as any other key milestones that are provided by
Contractors. If novation material and equipment is included in the
execution plan, the date of purchase order and required delivery date
should be incorporated in the schedule. The schedule shall include
review time requirements specified in SAEP-303 (Engineering Reviews
of Project and Detail Design Engineering Documentation). Contact
Scheduling Engineering Group of PS&CD/PCED for more detailed
information on Project Summary Schedule.
3.4.2

ER Estimate Requirements
Project Proposals must be completed and approved in time to support the
Expenditure Request Approval (ERA) date. A complete ER Estimate
Package must be submitted to PS&CD, at least four (4) weeks prior to
submittal of 56D Estimate to FPD Budget Director as per Capital
Program ER Processing Schedules for Board, EXCOM and local
approvals.
SAPMT shall be responsible for preparation of the ER Estimate package:

in accordance with SAEP-25 (Estimate Preparation Guidelines)

in conformance with the Work Breakdown Structure and Standard


Code of Accounts (SCA) established by SAPMT and PS&CD

to achieve a quality estimate with an accuracy of (10%) of project


final cost

using the Estimating Tool Aspentech Kbase, particularly for oil and
gas process facilities, as a preferred estimating software. Selection of
any other estimating tool should be discussed with PS&CD.

Page 15 of 48

Document Responsibility: Project Support and Controls Dept.


Issue Date: 20 September 2006
Next Planned Update: 15 August 2011

SAEP-14
Project Proposal

Effective January 2008, Aspentech KBase shall be used as a mandatory


estimating tool in the preparation of the ER Estimate for oil and gas
projects greater that $100 million. Waiving this requirement must be
approved by the PS&CD Manager.
The final ER Estimate shall be jointly reviewed and approved by
PS&CD and SAPMT.
3.4.3

ER Estimate Review Meetings


Initial, Interim and Final ER Estimate review meetings will be held by
members of SAPMT, Engineering Contractor, and PS&CD during the
course of Project Proposal phase. SAPMT will be responsible for
organizing the meetings, providing the required documents to PS&CD
prior to review meetings and inviting all concerned parties to participate
in the ER Estimate Review meetings.
A)

Initial Kick-off Meeting


The initial kick-off meeting will be conducted before the 30%
completion of Project Proposal. An ER Estimate Plan, as described
in Section 3.4.4, shall be prepared and completed prior to the Kickoff Meeting. PS&CD will take an active role in defining Saudi
Aramco ER estimate preparation requirements and providing basic
information to the SAPMT and Contractor.

B)

Interim ER Estimate Review Meetings


The purpose of the interim meeting is to review the progress of the
ER estimate preparation activities. The number of interim
meetings should be established during the initial ER Review
meeting.
Minimum one (1) week prior to the review meeting, SAPMT shall
provide a complete set (hardcopy and electronic file) of the ER
Estimate with support documents to PS&CD for review.
The interim review meeting deliverables shall include, but not be
limited to:

ER Estimate as developed to date, with MTOs by Area and


WBS

ER Estimate Basis

ER Estimate Detailed Schedule

Page 16 of 48

Document Responsibility: Project Support and Controls Dept.


Issue Date: 20 September 2006
Next Planned Update: 15 August 2011

C)

SAEP-14
Project Proposal

Multiple Discipline Drawings including PFDs, P&IDs, Plot


Plans, One Line Diagrams, etc.

A list of all scope changes from the DBSP identified to date.


The list will include itemized scope changes with justification
and cost/schedule impact for each deviation item (per Section
3.2.3)

Major equipment quotations

Recent quotations for Engineering and Construction rates

All discipline Material Take-offs (MTOs) by Area and WBS

Market Outlook study, as required

Project Risk Assessment, as required

Final ER Estimate Review Meeting


1. A complete ER Estimate Package must be completed in
accordance with the established ER Estimate Plan and
submitted to PS&CD/PCED at least four (4) weeks prior to the
56D Estimate submittal due date to FPD Budget Director.
Refer to Section 3.4.5 for ER estimate deliverables.
2. After receipt of the ER Estimate package, PS&CD will conduct
a meeting with SAPMT and Engineering Contractor to review
and finalize the estimate as deemed necessary.
3. Minimum of two (2) weeks prior to 56D Estimate submittal due
date to FPD Budget Director, SAPMT shall provide PS&CD
the Project Proposal sheet approved by SAPMT, FPD and
Proponent and a copy of the Technical Meeting minutes with a
complete list of all finalized items with detailed cost estimate of
impacted items. These documents are required for finalizing
the 56D Estimate for submittal to FPD Budget Director.
When the ER Estimate is over or under by more than 10% of the
Budget Estimate, PS&CD and SAPMT shall jointly prepare a
scope reconciliation and comparison between the approved Budget
and the established ER Estimate. The review shall include a list of
all scope changes from DBSP which will be part of the ER
Estimate package.

D)

Scope Compliance Review Meetings


Compliance Review meetings will be conducted, as deemed
Page 17 of 48

Document Responsibility: Project Support and Controls Dept.


Issue Date: 20 September 2006
Next Planned Update: 15 August 2011

SAEP-14
Project Proposal

necessary, by SAPMT in coordination with FPD and PS&CD to


ensure that the scope of Project Proposal is in compliance with the
approved DBSP.
SAPMT shall prepare and provide all attendees with a complete list
of accepted scope changes and relevant supported documents for
the Scope Compliance Review meetings. PS&CD shall be
responsible for validation of cost and schedule impacts for all
scope changes.
3.4.4

ER Estimate Plan
SAPMT shall be responsible for developing an ER Estimate Plan which
will be reviewed and discussed during the initial kick-off meeting. At
the minimum, the ER Estimate Plan should contain:

Project scope of work

Site development plan and investigation

A detailed schedule with major and interim milestones for


completing the ER Estimate deliverables

A quality control plan for estimate preparation

Specific plan and methodology for performing market outlook and


project risk assessment for selected projects greater than $300
million (refer to Section 3.4.6)

Methodologies for developing estimate basis, material take-offs


(MTOs), pricing of material and equipment, unit rate for engineering
and construction based on current market conditions and project risk
assessment

Plan and methodology for developing internal and external


benchmarking

Identification of estimating software to be used for preparation of ER


Estimate

Work Breakdown Structures (WBS) and Standard Code of Accounts


(SCA) to be used for the project

A list of ER Estimate deliverables required for interim review and


final review

An organization chart of the estimating team

Roles and responsibilities of all involved parties in developing the


ER Estimate and identifying point of contact from each organization
Page 18 of 48

Document Responsibility: Project Support and Controls Dept.


Issue Date: 20 September 2006
Next Planned Update: 15 August 2011

3.4.5

SAEP-14
Project Proposal

ER Estimate Deliverables
The ER estimate will be based on 100% Project Proposal which includes
equipment lists, equipment sizing, plot plans, P&ID, single line
diagrams, cable schedules, instrument index summaries, I/O counts, bulk
material take-offs, and other related project documents and drawings.
The following major contents of deliverables should be included in the
ER estimate package:

Approved Project Proposal

Drawings, specifications, reports and other relevant documents


necessary to define the project requirements

Approved Execution and Contracting Plan

Project Summary Schedule

An ER Estimate package which includes a hard-bound copy and an


electronic copy on a CD with all required backup documents as
specified in SAEP-25

A complete list of all scope changes from the DBSP that will be
implemented in the Project Proposal. The list will include itemized
scope changes with justification and cost/schedule impact for each
deviation item

Copies of Technical Review Meeting Minutes

Copies of ER Review Meeting Minutes with status of outstanding


and implementation items

Copies of PHA or HAZOP Meeting Minutes with summary of


changes, if applicable

For detailed listing of deliverables, refer to the Exhibit II, ER Estimate


Package Checklist.
3.4.6

Market Outlook Study & Project Risk Assessment


PS&CD/PCED will coordinate with SAPMT to identify projects worth
$300 MM or greater that will be required to do a Market Outlook Study
and Project Risk Assessment. Market trends and project risks are
assessed to avert potential impacts on project development and
execution. Results of these studies shall be included in the basis of
estimate and contingency rates shall be recommended accordingly.
These shall include, but not be limited to, the following:

Worldwide demand for Engineering and Construction services


Page 19 of 48

Document Responsibility: Project Support and Controls Dept.


Issue Date: 20 September 2006
Next Planned Update: 15 August 2011

SAEP-14
Project Proposal

Market conditions that affect major equipment procurement pricing


and delivery

Trends related to supply and demand of major equipment and bulk


material in the Middle East that could affect schedule and costs on
the project

Availability of Engineering Contractors to undertake LSTK contracts


in Saudi Arabia

Assessing the financial markets and institutional support for current


and future Middle Eastern projects

Project risks study on constructability, tie-in execution,


environmental, security and other factors related to a specific project

Forecast of Engineering Contractors Overhead and Profit Margins

Any other factor that can impact the future cost of the project

Following are some of the resources that can be used in developing a


Market Outlook study:

3.5

Trade Organizations

Trade Magazines

Financial Institutions studies and surveys

Government studies and surveys

Industry studies and surveys

Manufacturers and Suppliers data

Appendix
The Appendix shall include letters, minutes, land use permits and other pertinent
documents written during Project Proposal development.

3.6

Numbering Project
All Project Proposals shall be numbered by the issuing office as follows:
Saudi Aramco

APP Series (Numbers assigned by the Technical


Information Center, Dhahran)

ASC

TPP Series (Numbers assigned by the Corporate


Information Center, Houston)

APP or TPP numbers shall be on the Project Proposal cover sheet.


Page 20 of 48

Document Responsibility: Project Support and Controls Dept.


Issue Date: 20 September 2006
Next Planned Update: 15 August 2011

3.7

SAEP-14
Project Proposal

Training Impact Assessment


SAEP-140 (Project Training Impact Assessment) requires that a Training Impact
Assessment be prepared as part of the Project Proposal for all projects for which
training programs for operations and/or maintenance personnel will be required.
These training programs will not be provided by the project and costs for
training are not be paid for by capital funds. (Refer to GI-0202.309, Paragraph
4.5)
The Proponent is responsible for identifying any training requirements for a
project by preparing a Training Requirement Statement prior to the start of the
Project Proposal.
If training is to be required, a Training Impact Assessment is to be prepared in
accordance with SAEP-140. SAPMT is responsible for incorporating the
findings of the Training Impact Assessment in the final Project Proposal.
SAPMT may also be required to implement the findings of the Training Impact
Assessment as included in the approved Project Proposal. These may include:

3.7.1

Incorporating contract provisions that require the Contractor to develop


multiple quotations for specified equipment so that the cost of training
can be taken into consideration when selecting the life-time, low-cost
supplier. These provisions will allow Saudi Aramco to direct the
Contractor to place its order with one of the proposed technically
acceptable suppliers and will provide for additional payment to the
Contractor if the selected supplier did not offer the lowest base price to
the Contractor.

3.7.2

Incorporating requirements for the Contractor to include provision in its


purchase orders for specified equipment that establish fixed prices for
training services or material to be procured at a later date by Saudi
Aramco. This will reduce the possibility of a supplier overcharging
Saudi Aramco when training services or materials are procured on a
single-source basis.

Project Improvement Effort


This section comprises of activities that on implementation would optimize project cost
& schedule, improve quality of the Project Proposal and assure project execution
success.
4.1

Value Engineering
Value Engineering (VE) is an organized analytical process that can be used to
Page 21 of 48

Document Responsibility: Project Support and Controls Dept.


Issue Date: 20 September 2006
Next Planned Update: 15 August 2011

SAEP-14
Project Proposal

optimize the life cycle cost and performance of a facility or system. The VE
process systematically identifies opportunities to increase value by removing
unnecessary costs without sacrificing quality, function, or reliability.
4.1.1

VE Study Selection Criteria


SAPMT shall initiate a formal VE study during the Project Proposal
development stage when:

4.1.2

The estimated BI value exceeds $50 million, or

The estimated BI value is between $10 $50 million and a VE study


was not conducted during the pre-planning or DBSP development
stage, or

The estimated BI value is between $10 $50 million, and the preplanning or DBSP stage VE Report recommends that a Project
Proposal stage VE study is required.

VE Study Planning & Coordination


VE studies should be completed during the early phase of the Project
Proposal, but not later than the 30% completion milestone date. For
scheduling purposes only, VE studies shall be coordinated with the
Capital Program Optimization Division of Project Support & Controls
Department (PS&CD/CPOD). The requirements for conducting VE
studies shall be identified in the Project Proposal Contractors scope of
work.
VE studies shall only be facilitated by either a Certified Value Specialist
(CVS), or local Engineering Contractor personnel who have been
certified by PS&CD/CPOD to conduct VE sessions.
Requests for VE study guidance, and information on Consultants and
local Engineering Contractor personnel certified to facilitate VE sessions
should be directed to PS&CD/CPOD.

4.1.3

VE Proposal Implementation & Reporting Requirements


The effectiveness of a VE study depends on the successful
implementation of accepted proposals and on the prompt resolution of
pending proposals. VE proposals that are accepted by the Proponent
Organization and SAPMT are to be reviewed by FPD, and CSD if
related to standards requirement, before being incorporated into the
Project Proposal Scope of Work.

Page 22 of 48

Document Responsibility: Project Support and Controls Dept.


Issue Date: 20 September 2006
Next Planned Update: 15 August 2011

SAEP-14
Project Proposal

The status and resolution of all accepted and pending VE proposals shall
be documented in the Value Engineering Section of the Project Proposal.
A copy of the final VE Report shall be distributed to the PS&CD/CPOD
Division Head.
4.2

Benchmarking
Benchmarking is an improvement process used to discover and incorporate
project cost, schedule, front-end loading, value improvement and operability
into project execution strategy.
The benchmarking process will be centralized so that all benchmarking activities
are managed through PS&CD/PCED. Benchmarking will be conducted at
study, late stages of the DBSP, early stages of the Project Proposal as well as
towards the completion of a project. Projects will be selected by PS&CD for
either external or internal benchmarking.
The objective of Benchmarking analysis at the early stage of Project Proposal is
to identify and compare key project parameters such as project scope, quantity,
cost, schedule, value practices and execution strategy, against the Companys
internal historical statistics of similar projects. The project data also are used for
benchmarking against the industry world class projects with similar scope. The
result of the benchmarking analysis can be used for improving project execution
plan.
4.2.1

Internal Benchmarking Requirements


For all projects except community projects, school and home-ownership,
SAPMT shall provide key project data to PS&CD/PCED for internal
benchmarking purposes. A sample of benchmarking data sheet is shown
in Exhibit IV. This internal benchmarking data will be part of the ER
Estimate package.

4.2.2

External Benchmarking Requirements


PS&CD/PCED will coordinate with SAPMT to identify projects with
value of $100 MM or greater to be benchmarked. Projects less than
$100 MM may be benchmarked if related to core business.
PS&CD/PCED will perform the leading role for the selection of the
Consultant, development of benchmarking criteria, and implementation
of the formal benchmarking study.
The analysis starts as early as the study phase and DBSP, or at any
appropriate stage of the Project Proposal development, but no later than
90% Project Proposal progress, comparing key parameters of the project
Page 23 of 48

Document Responsibility: Project Support and Controls Dept.


Issue Date: 20 September 2006
Next Planned Update: 15 August 2011

SAEP-14
Project Proposal

with an external industry-wide database. The analysis would address


key project outcomes and associated risk based on the Project Proposal
effort to date. As a minimum, the following areas should be addressed
and compared to industry norms, the Gulf Region and Best in Class:

Status of front-end loading (FEL), i.e., project definition, at the time


the benchmark analysis is prepared

Use of value improvement practices

The projected total installed cost (TIC) of the project

An analysis of the contingency requirement based on project scope


and FEL

Engineering as a percentage of TIC

Time required for total project execution (ERA through Onstream)

Time required for the construction phase

Expected time required for start-up

Long lead material deliveries comparison

General or specific requirements included in the Project Proposal


Scope of Work that are non- industry standards

Execution strategies

A Benchmarking section shall be included in the Project Proposal book


to include the summary benchmarking report prepared by an outside
Consultant or by the Engineering Contractor.
4.3

Energy Optimization Study


Capital projects involving the addition of or modifications to industrial
processes with combined fuel and power consumption exceeding $2 million per
year (combined) shall be optimized for the efficient use of thermal and electrical
energy.
For purposes of the energy study, an industrial process is defined as one that
includes fired heaters, boilers, pumps, compressors, steam turbines, or gas
turbines. Non-industrial facilities such as buildings, roads, warehouses, storage
depots, and non-process operations such as IT or instrumentation upgrades are
excluded.
The technical approach and work scope for the energy study should address one
or more of the following issues:

Page 24 of 48

Document Responsibility: Project Support and Controls Dept.


Issue Date: 20 September 2006
Next Planned Update: 15 August 2011

Process Integration, using Pinch Analysis techniques

Equipment Load Management policies

Adjustable Speed Drives

Driver Selection

SAEP-14
Project Proposal

4.3.1

A preliminary Process Integration study of the project facilities shall be


conducted only when the combined fuel consumption of the in-scope
process units exceeds 100 MMBtu/h. It is necessary only to provide the
optimum practical utility consumption targets in comparison to the utility
requirements for the un-optimized process design; detailed design of the
heat exchanger network and combined heat/power system to achieve
these targets is not required.

4.3.2

For energy consuming or conversion equipment (pumps, compressors,


turbines, boilers, and furnaces) in parallel operation, the study shall
identify the optimum number of equipment that should be operated over
the expected range of plant operating rates, considering the trade-off
between energy consumption and meeting production goals. Load
management policies are required only when the energy consumption for
a particular service or application exceeds 1000 HP (if rotating
machinery) or 16 MM Btu/h (if fuel-fired equipment).

4.3.3

The economic feasibility of Adjustable Speed Drives (ASDs), whether


variable frequency type or other, shall be evaluated for individual
motors/drivers of 2000 HP or greater. Capital costs should be balanced
against the combined energy and non-energy benefits.

4.3.4

Rotating machinery with individual power loads of 5000 HP and higher


shall be evaluated for selection of optimum driver type electric motor,
steam turbine, or gas turbine.

4.3.5

Energy efficiency for individual items of equipment (e.g., motors,


boilers, etc.) is covered separately by Saudi Aramco equipment
standards. Evaluation of alternative equipment options is not required as
part of the energy study scope.

The optimum time to conduct such a study is the earliest possible date after
preliminary PFDs, including heat and material balances, are available, and the
plant fuel/power consumption estimates have been determined. Generally, this
would be after 30% completion of the Project Proposal, but no later than 60%
Project Proposal completion.
The full energy optimization study report, including all supporting data and
Page 25 of 48

Document Responsibility: Project Support and Controls Dept.


Issue Date: 20 September 2006
Next Planned Update: 15 August 2011

SAEP-14
Project Proposal

calculations, must be submitted to the Energy Systems Unit of Consulting


Services Department for review.
4.4

Other Value Practices


SAPMT shall implement applicable Saudi Aramco and other industry value
practices during Project Proposal development to optimize project planning and
execution. PS&CD/CPOD is available to assist SAPMT in selecting the
appropriate value practices and facilitating their implementation.
The requirements for conducting specific Value Practices shall be identified in
the Project Proposal Contractors scope of work. Value Practice sessions shall
only be facilitated by either approved Consultants, or local Engineering
Contractor personnel who have been certified by PS&CD/CPOD. For
information on approved Consultants and local Engineering Contractor
personnel certified to facilitate Value Practice sessions, contact PS&CD/CPOD.
The following value practices have shown proven payback for Saudi Aramco
projects.

Constructability
Effective and timely integration of construction knowledge into the
conceptual planning, design, construction and field operations of a project.
Optimum timing during project proposal phase is at 30% Project Proposal.

Project Definition Rating Index (PDRI)


Held at 60% Project Proposal involving SAPMT, Proponent, Contractor, and
other parties as needed to measure project proposal completeness and clarity.
PDRI consists of about 70 elements that identify and very precisely
describes each critical element in a preliminary engineering scope definition
package.

Lessons Learned
Systematic search for applicable existing lessons learned from Saudi
Aramco Project Management Lessons Learned database and other sources.
Implement applicable lessons to avoid repetition of problems and build on
successes experienced by other projects. Also collect and submit new
lessons learned per SAEP-329 Project Close-out Report.

Project Execution Planning Workshop (PEPW)


Half-day workshop to promote ownership, commitment, and alignment of all
project stakeholders including SAPMT, FPD, Proponent, Contracting, Loss
Page 26 of 48

Document Responsibility: Project Support and Controls Dept.


Issue Date: 20 September 2006
Next Planned Update: 15 August 2011

SAEP-14
Project Proposal

Prevention, and other involved parties.

Schedule Optimization
Utilization of Schedule Reduction and Schedule Compression
techniques to optimize the schedule for project completion.

Planning for Startup


Extensive set of tools and techniques used by all Project Stakeholders, PMT,
Proponent, Contractors, etc., to help facilitate a successful facility start-up
and stable long term operation.

Scope Control & Change Management


Scope Control is a preventative process that starts with a detailed project
scope and ensures discipline in changing the scope during execution.
Change Management involves establishing and clearly communicating to all
project stakeholders a system for recognizing, evaluating, and implementing
changes during all phases of the project.

Other
PS&CD will identify and implement other value practices that become
available between revisions of SAEP-14 that offer value improvement to the
project.

Reporting and Review Requirements


5.1

Project Proposal Distribution for Review and Meetings


Draft Project Proposals shall be distributed for review to the appropriate
members of Saudi Aramco Management and attendees of the Technical Review
and Project Proposal Meetings. Distribution of the Project Proposal narrative
shall be in electronic format (in Microsoft Word).
The E-Review electronic review system is the Companys standard method for
review of engineering drawings and documents. SAPMT should submit review
packages through this system unless there is a compelling reason to do
otherwise. The E-Review procedures and guidelines are provided in SAEP-303.
The SAPMT and proponent are responsible for determining the recipients. As a
minimum, the following represents a list of various organizations that shall be
considered for receipt of the Project Proposal. However, only those
organizations with direct involvement shall receive the Project Proposal.

Page 27 of 48

Document Responsibility: Project Support and Controls Dept.


Issue Date: 20 September 2006
Next Planned Update: 15 August 2011

SAEP-14
Project Proposal

Executive Management:
-

Proponent Organizations, i.e.


Ras Tanura Refining
Northern Area Producing
Southern Area Producing
Jeddah/Riyadh Refining
Yanbu Refining
Distribution Operations
Abqaiq Plants & Pipelines
Gas Operations
Medical Services
Employee Relations

Petroleum Engineering and Development


(for production-related projects)

General Management:
-

Industrial Security Operations

Proponent organization

Management:
-

Oil Supply Planning and Scheduling Department


(for all proposals related in any way to oil, gas, NGL and/or refined product
movement and handling)

Computer & Communications Engineering Department


(for all projects involving communications)

Purchasing Department

Power Distribution Department


(for all projects related to power facilities at 2.4 kV and above)

Abqaiq, Dhahran or Ras Tanura Utilities Department


(for the area community projects only)

Facilities Planning Department (mandatory)

Project Support & Controls Department (for information only)

Consulting Services Department

Inspection Department

Loss Prevention Department

Page 28 of 48

Document Responsibility: Project Support and Controls Dept.


Issue Date: 20 September 2006
Next Planned Update: 15 August 2011

5.2

Environmental Protection Department

Process & Control Systems Department

Roads & Heavy Equipment Department

Industrial Security Department

Fire Protection Department

SAEP-14
Project Proposal

Technical Review Meeting


The Technical Review Meeting shall be held no sooner than ten (10) working
days after distribution of the Project Proposal for review. Location, date, and
time of the meeting shall be announced in the cover letter distributed with the
Project Proposal. The Technical Review Meeting shall discuss all technical
aspects of the Project Proposal, resolve technical questions, address
environmental issues and review the Project Summary Schedule. Interim
technical review meetings shall be conducted as required by SAPMT depending
upon the type and complexity of the project. Items not resolved at the final
technical review meeting shall be addressed in the Project Proposal Meeting.
Substantive changes resulting from the technical review meeting shall be
incorporated as appropriate into the Project Proposal documents.
SAPMT shall prepare minutes of the Technical Review Meetings and distribute
the minutes, electronically whenever possible, to all persons who either received
the Project Proposal or attended the Technical Review Meeting. The minutes
shall include the estimated cost and schedule effects of major changes from the
DBSP/Project Proposal as originally prepared. Refer to 3.2.3 for definition of
major scope change.
The subject of critical plant equipment unit spares (capital spares) per section
3.3.5 shall be addressed, and proposed purchases shall be reviewed.

5.3

Project Proposal Meeting


The purpose of the Project Proposal Meeting is to resolve any outstanding items
remaining after the Technical Review Meeting and to finalize the project scope.
The Project Proposal Meeting shall be scheduled no sooner than five (5)
working days after distribution of the minutes of the Technical Review Meeting.
The delegated representatives of the Project Proposal approval authorities
(section 6.1.1) shall attend this meeting in order to make decisions on matters
not resolved in the Technical Review Meeting.
SAPMT shall be responsible for preparing and distributing the minutes of the
Project Proposal Meeting to those persons who either received a copy of the

Page 29 of 48

Document Responsibility: Project Support and Controls Dept.


Issue Date: 20 September 2006
Next Planned Update: 15 August 2011

SAEP-14
Project Proposal

Project Proposal or attended the Project Proposal Meetings.


For selected small projects, the Technical Review and Project Proposal
Meetings can be combined into one meeting if concurred by Proponent and
FPD. In this case, the reviewing organizations should send personnel authorized
to make decisions to attend the meeting.
5.4

Distribution & Storage of Approved Project Proposals


Following the approval of the Project Proposal, a final approved copy shall be
distributed as follows:
5.4.1 ASC
An electronic copy of every Project Proposal shall be sent to Corporate
Information Center (CIC), Houston.
5.4.2

Saudi Aramco
SAPMT shall send copies of the approved Project Proposal to:
-

Facilities Planning Department (FPD) - one hard copy, to be used as


a "working" document for five years or for the duration of the
project, whichever is longer.

Technical Information Center (TIC), Room E-3100, EOB, Dhahran one electronic copy for archival purpose.

Project Support & Controls Department (PS&CD) - one electronic


copy, for input in the Electronic Image Document Management
System.

The electronic file submissions shall be on CD-ROM and contain an


index at the beginning of each file medium to facilitate retrieval of stored
data. The electronic text, spreadsheet, and graphical data shall be in
Microsoft format, and drawings shall be in accordance with Saudi
Aramco standards and formats. Scanned documents shall be in Acrobat
format in accordance with the corporate standard maintained by EDSD.
6

Approvals and Waivers


6.1

Approval Process
6.1.1

Approvals
SAPMT shall be responsible for obtaining Saudi Aramco approval for
the Project Proposal from the appropriate individuals listed. Executive
Page 30 of 48

Document Responsibility: Project Support and Controls Dept.


Issue Date: 20 September 2006
Next Planned Update: 15 August 2011

SAEP-14
Project Proposal

Management may delegate the approval authority to General


Management level. Obtaining these signatures constitutes full Project
Proposal approval. The recommended order for routing and approval
will be as follows, however, SAPMT may seek parallel approval from
more than one organization at the same time where appropriate.
-

6.1.2

Manager, Facilities Planning Department


Manager, Loss Prevention Department
Manager, Power Distribution Department
(for all projects having power facilities of 2.4 kV and above)
Manager, Consulting Services Department
Manager, Environmental Protection Department
Manager, Oil Supply Planning and Scheduling Department
(for all proposals related in any way to oil, gas, NGL and/or refined
product movement and handling)
Manager, Process and Control System Department
(for Instrumentation & Control Systems)
General Manager, Industrial Security
Vice President, Petroleum Engineering and Development
(for production-related projects)
Vice President, Engineering Services
Vice President/Executive Director, Proponent Organization
Vice President, Project Management

Unresolved Items
If unresolved items exist that would preclude obtaining approvals as
described in section 6.1.1, SAPMT shall refer any unresolved item(s)
through appropriate channels of authority until resolution is obtained.
The Project Proposal minutes shall show the estimated cost and schedule
effects of any changes from the DBSP/Project Proposal as originally
prepared.

6.1.3

Obtaining Changes to an Approved Project Proposal


For a project with an approved Project Proposal which has not yet
received Expenditure Request (ER) approval, scope changes shall be as
follows:

SAPMT will document and estimate all scope changes approved by


FPD and submit the revised ER estimate to PS&CD as an addendum
to the approved Project Proposal
Page 31 of 48

Document Responsibility: Project Support and Controls Dept.


Issue Date: 20 September 2006
Next Planned Update: 15 August 2011

6.2

SAEP-14
Project Proposal

The proposed change in the meeting minutes or an addendum shall


include justification and the cost/schedule impact

The required minimal approval authority for the proposed change is


Project Manager level

SAPMT shall distribute the approved changes to PS&CD and all


those that received the original Project Proposal

Project Proposal Waiver


6.2.1

Request
For selected projects, Project Management may request to waive the
requirement for a Project Proposal / Front End Engineering Design
(FEED) and proceed directly with detailed design using preliminary
engineering funds. This request will permit SAPMT to use TC-68 funds
to carry out detailed design, perform selected project proposal
requirements and to prepare an ER quality estimate for funding approval.
Project Proposal waiver does not exempt ER Estimate and any other
Value Practices requirements.

6.2.2

Approval
The following steps are required to obtain a waiver of project proposal
and proceed with detailed design:

SAPMT Department Manager shall prepare a formal letter requesting


to carry out detailed design during Project Proposal. The letter shall
be addressed to Vice President, Project Management and Vice
President Proponent. The letter should state the present situation,
scope of work, justification for the waiver and identify what project
proposal requirements, if any that will be performed during detailed
design, i.e., value engineering, CII concepts, etc.

SAPMT shall obtain Vice Presidents, Project Management and


Proponent approval for this request.

On receiving approval, SAPMT shall prepare an Engineering Work


Order Authorization for Project Proposal Preparation (Form 6891ENG) to request approval of TC-68 funds to carry out detailed
engineering and contract preparation based on GI-202.451,
(Engineering Work Order Authorization for Preliminary Engineering
Preparation).

Approval is accomplished on obtaining the signature on Form 6891ENG.


Page 32 of 48

Document Responsibility: Project Support and Controls Dept.


Issue Date: 20 September 2006
Next Planned Update: 15 August 2011

SAEP-14
Project Proposal

Contract Bid Package


The Contract Bid Package will be developed in close coordination with the Contracting
Department. Refer to Exhibit III, Contract Development Checklist, for key activities in
developing Contract Bid Package.
A complete Contract Bid Package shall be prepared in accordance with Contracting
Manual and typically contain the following:

Invitation for Bid documents

Technical Proposal documents

Commercial Proposal documents

As part of Commercial Proposal requirements, Bidders shall be required to submit a


Bid Quantification Summary as shown on Exhibit V for bid analysis purposes.
Copies of the final Bid Quantification Summary from the awarded Contractor will
be provided to PS&CD

Fully developed and approved Contract documents which include Schedules A


through H, and Q

Issue for Bid package (normally prepared by Engineering Contractor) which includes,
but is not limited to, drawings, specifications, applicable reports, and other relevant
documents necessary to define the project requirements and clearly describes the
contract scope of work. SAPMT should take into consideration the current project
execution plan and responsibilities of all contractual parties when revising the Project
Proposal package to Issue for Bid Package.
The following Sections in the Project Proposal should be reviewed carefully to
determine if they are applicable for inclusion in the bid package. If they are to be
included, SAPMT shall modify as required to ensure that Contractors scope of work is
clearly defined in the Issue for Bid Package:

Project Schedule

Training requirements

Land Permits

Operating Variables (as required by OSPAS)

Strategy for projects compliance with quality requirements

Project Risk Assessment

Temporary construction and communications

Page 33 of 48

Document Responsibility: Project Support and Controls Dept.


Issue Date: 20 September 2006
Next Planned Update: 15 August 2011

SAEP-14
Project Proposal

Exhibits
The intent of the checklists is to facilitate the review and ensure all key requirements
are considered, but not to cover all detailed requirements as stated in this procedure.
8.1

Project Proposal Checklist

8.2

ER Estimate Package Checklist

8.3

Contract Development Checklist

8.4

Sample of Benchmarking

8.5

Bid Quantification Summary

28 June 2000
29 January 2003
15 August 2006
20 September 2006

Revision Summary
Major revision.
Editorial revisions.
Major revision.
Editorial revision to paragraph 3.7.

Page 34 of 48

Document Responsibility: Project Support and Controls Dept.


Issue Date: 20 September 2006
Next Planned Update: 15 August 2011

SAEP-14
Project Proposal

EXHIBITS

TABLE OF CONTENTS

EXHIBIT I

PROJECT PROPOSAL CHECKLIST

EXHIBIT II

ER ESTIMATE PACKAGE CHECKLIST

EXHIBIT III

CONTRACT DEVELOPMENT CHECKLIST

EXHIBIT IV

BENCHMARKING DATA SHEET

EXHIBIT V

BID QUANTIFICATION SUMMARY SHEET

Page 35 of 48

Document Responsibility: Project Support and Controls Dept.


Issue Date: 20 September 2006
Next Planned Update: 15 August 2011

SAEP-14
Project Proposal

EXHIBIT I PROJECT PROPOSAL CHECKLIST


Item

Ref.
Section

3.2.2

Description

Included

Project Proposal documents as described in Section 3.2.2.


Obtain necessary land use permit
Obtain proponent approved permits for construction site area
Complete piping tie-in and hot tap plan
Complete electrical and control system tie-in plan
Prepare site investigation report

3.2.4

Temporary and Permanent Project Communication Requirements

3.2.5

Comply with Safety and Security Directive (SSD)

3.2.6

Perform of PHA or HAZOP Study

3.2.6

Perform of Building Risk Assessment

3.2.7

Perform of Environmental Impact Assessment

3.2.8

Apply Waivers from SA Engineering Standards and Material


System Specification

3.2.9

Include a list of drawings and drawings define project scope

3.2.10

Prepare Project Quality Plan as per GI-0400.001 including


Schedule Q Att. VI

10

3.3.1

Identify project major material and equipment to be reviewed by


Inspection Dept.

11

3.3.2

Develop a Material Source List of major material and equipment

12

3.3.3

Develop a Surplus Inventory and Excess material Listing

13

3.3.4

Obtain a list of approved locally manufactured products and source

Page 36 of 48

Document Responsibility: Project Support and Controls Dept.


Issue Date: 20 September 2006
Next Planned Update: 15 August 2011

Item

Ref.
Section

14

3.3.5

Develop a list of critical plant equipment spares

15

3.3.6

Identify required start-up spares with Proponent with concurrence


of MS

16

3.4.1

Prepare Level III Project Summary Schedule

17

3.4.2

Prepare ER Estimate Package ( See Exhibit II - ER Estimate


Package Checklist)

18

3.7

Review Project Training Impact Assessment (SAEP-140) and


identify required implementation

19

4.1

Perform Value Engineering Study

20

4.2.1

Provide project data for Internal Benchmarking

21

4.2.2

External Benchmarking Analysis

22

4.3

Perform Energy Optimization Study

23

4.4

Perform Value Practices

Description

SAEP-14
Project Proposal

Included

1. Constructability Study
2. Project Definition Rating Index (PDRI)
3. Lesson Learned
4. Project Execution Planning Workshop
5. Schedule Optimization
6. Planning for Startup
7. Scope Control and Change Management

Page 37 of 48

Document Responsibility: Project Support and Controls Dept.


Issue Date: 20 September 2006
Next Planned Update: 15 August 2011

SAEP-14
Project Proposal

EXHIBIT II ER ESTIMATE PACKAGE CHECKLIST


Following are minimum documents required to accompany the ER Estimate Request
to PS&CD:
Item

Description

100% Project Proposal package ( Project Proposal must be approved prior to


issuance of 56D)

Approved technical review meeting minutes

Project Scope summary including new as well as demolition of existing


facilities.

Internal/External Benchmarking data

Piping and Instrument Diagrams (P&IDs)

Plot plan showing major facilities/buildings

Proposed Piping lay-out and routing

Electrical scope with one-line diagrams, MTO quantities for Transformers,


Switchgear, etc,

Field Instrument specifications and Data Sheets

10

Control system (DCS) scope with I/O counts, Block Flow Diagrams and Vendor
Quotations

11

Communications System scope including, MTO and quotations

12

Fire Protection, Safety and Security requirements

13

Building/Equipment data sheets

14

Material specifications including Materials Diagram.

15

DC Surplus, etc,

16

Identify Start-Up and Capital Spares

Included

Page 38 of 48

Document Responsibility: Project Support and Controls Dept.


Issue Date: 20 September 2006
Next Planned Update: 15 August 2011

Item

Description

17

Catalyst, Chemicals & Licensor Fee costs.

18

HAZOP Review report if applicable.

19

Site survey and soil data report

20

List of Deviations from DBSP with cost/schedule impact

21

Copy of Approved Waivers

22

SAPMT/PMC, Insp., CMT & other related costs

23

Exploratory Trenching

24

Environmental Assessment (Contamination)

25

Approved Project Schedule

26

Approved Project Execution Plan

27

Contracting and Material Procurements Plans. Identify customs duties.

28

Detail Engineering Equivalent A size Drawings count and man hours

29

Detail Design Location i.e., (IK or OOK)

30

Draft ER brief and BISI from FPD

31

Facility Location and Camp Requirements

32

Identify Commissioning and As-Built Requirements

33

Quality Material take-off (MTO)

34

Process Equipment list, sizes, capacities & specifications.

35

Recent (valid for 3 months) quotations for major equipment & material

SAEP-14
Project Proposal

Included

Page 39 of 48

Document Responsibility: Project Support and Controls Dept.


Issue Date: 20 September 2006
Next Planned Update: 15 August 2011

SAEP-14
Project Proposal

EXHIBIT III CONTRACT DEVELOPMENT CHECKLIST


Following are the list of key activities for developing the contract package.
Item

Description

Included

Contracting Strategy

Develop and Approve Contracting Strategy Required as part of the Abbreviate


PEP for all projects (SAEP-12). Strategy is to be updated if there are changed
during the progress of the project.

Enter and maintain data on all contract action covered by the Contracting
Strategy in to the PMIS Contracting Action Development and Administration
(CADA) module.
Pro Forma Contract & Specific Instructions to Bidders (SIB)

Complete preliminary Evaluation Plan so appropriate technical and commercial


questions are included in the SIB.

Secure approvals for all singe source procurement and included appropriate
language in Schedule H.

Complete Schedule Q language in accordance with approved Quality Plan (GI


400.001) and review proposed language with Inspection as needed.

Include language relating to approved training requirements, if any (SAEP140).

Review any language related to contractor-supplied LAN and PC equipment


with the appropriated IT office(s).

Include requirements for bidder price breakdowns as part of the Commercial


Proposals and quantity lists as part of the Technical Proposals.
Hypothetical Quantities and Bid Conditioners

Prepare hypothetical quantities to be used to evaluate rates proposed by the


bidders (e.g., change order rates).

10

Prepare, in conjunction with other members of the Bid Review Team, data to be
used for allowed bid conditioner (e.g., different PMT cost for various locations).

Page 40 of 48

Document Responsibility: Project Support and Controls Dept.


Issue Date: 20 September 2006
Next Planned Update: 15 August 2011

Item

Description

SAEP-14
Project Proposal

Included

Review of Contract and Contract Supplement as Part of the Bid Review Team

11

Ensure the Contract is structured correctly for SAP SRV releases (for lump
sum, three items lump sum price, change orders, and other expenditures; and
use of VAL with the amount in the quantity column).

12

Ensure that that AEL includes reasonable amounts for all applicable Other
Expenditures (e.g., incidental services, Saudi manufacturer equalization, standby time, reimbursable start-up and commissioning assistance, variations from
target quantities, etc.).

13

Ensure the Contract Supplement includes an appropriate Change Order limit


(percent).

14

After award of the contract, provide copies of the bidders price breakdowns
and quantity lists to PS&CD.

Note: For a project using an LSTK contracting strategy, these actions are required during or just after the Project
Proposal period. For other strategies (e.g., GES + LSPB) some of the activities take place at later stages of
the project.

Page 41 of 48

Document Responsibility: Project Support and Controls Dept.


Issue Date: 20 September 2006
Next Planned Update: 15 August 2011

SAEP-14
Project Proposal

EXHIBIT IV BENCHMARKING DATA SHEET


for
CRUDE PRODUCTION FACILITY (GOSP)

BUDGET ITEM (BI)

ERA

JOB ORDER (JO)

ERC

DESCRIPTION

AREA NAME

INLET FACILITY

PRODUCTION
TRAP

PARAMETER

UOM

QUANTITY OF SCRAPER TRAPS

EACH

QUANTITY & SIZE (INCHES) OF TRAP A

EACH

QUANTITY & SIZE (INCHES) OF TRAP B

EACH

QUANTITY & SIZE (INCHES) OF TRAP C


TOTAL INSTALLED COST (INLET
FACILITY)

EACH

QUANTITY

UNIT
COST

COST
$

DOLLARS

UNIT CAPACITY

MBD

NUMBER OF HIGH PRESSURE TRAPS


NUMBER OF INTERMEDIATE PRESSURE
TRAPS

EACH

NUMBER OF LOW PRESSURE TRAPS

EACH

WATER CUT

% VOL

DOLLARS

UNIT CAPACITY

MMSCFD

HP COMPRESSORS QUANTITY

EACH

HP COMP DRIVER TYPE (MOTOR/CGT)

EACH

IP COMPRESSORS QUANTITY

EACH

IP COMP DRIVER TYPE (MOTOR/CGT)

EACH

LP COMPRESSORS QUANTITY

EACH

LP COMP DRIVER TYPE (MOTOR/CGT)

EACH

HP COMPRESSORS TOTAL HP

HP

EACH

GAS OIL RATIO


CRUDE TYPE (AL/AM/AXL/ASL) or API
TOTAL INSTALLED COST (PRODUCTION
TRAP)

GAS GATHERING

IP COMPRESSORS TOTAL HP

HP

LP COMPRESSORS TOTAL HP
TOTAL INSTALLED COST (GAS
GATHERING)

HP
DOLLARS

Page 42 of 48

Document Responsibility: Project Support and Controls Dept.


Issue Date: 20 September 2006
Next Planned Update: 15 August 2011

WET CRUDE
HANDLING &
WOSEP

CONDENSATE
STABILIZATION

CRUDE
STABILIZATION

WATER INJECTION
FACILITY

COGENERATION
FACILITY

PIPERACK &
PIPING

SUPPORT
INFRASTRUCTURE

SAEP-14
Project Proposal

NUMBER DESALTING STAGES

EACH

UNIT CAPACITY
TOTAL INSTALLED COST (WET CRUDE
HANDLING & WOSEP)

MBD

DOLLARS

UNIT CAPACITY
TOTAL INSTALLED COST (CONDENSATE
STABILIZATION)

MBD

DOLLARS

UNIT CAPACITY

MBD

UNIT CAPACITY

MBD

QUANTITY OF PUMPS

EACH

PUMPS TOTAL HP

HP

PUMP DRIVER TYPE (MOTOR/CGT)


TOTAL INSTALLED COST (WATER
INJECTION FACILITY)

EACH
DOLLARS

ISO RATING

MW

TONNAGE STEEL (PIPERACK)

TONS

TONNAGE PIPE

TONS

WIDTH OF PIPERACK

LM

LENGTH OF PIPERACK

LM

HEIGHT PIPERACK

LM

LEVELS OF PIPERACK

EACH

TOTAL LENGTH OF ALL PIPES

LM

TOTAL INSTALLED COST (PIPERACK)

DOLLARS

TOTAL INSTALLED COST (PIPING)

DOLLARS

SITE PREPARATION

SM

CONCRETE

CM

STRUCTURAL STEEL

TONS

FENCING

LM

CONTROL BUILDINGS (ALL BLDGS)

SM

PIBS (ALL BLDGS)

SM

OTHER TYPES OF BUILDING

SM

SUBSTATION
TOTAL INSTALLED COST (SUPPORT
BLDGS ONLY)
TOTAL INSTALLED COST
(INFRASTRUCTURE)

SM

DOLLARS

DOLLARS

Page 43 of 48

Document Responsibility: Project Support and Controls Dept.


Issue Date: 20 September 2006
Next Planned Update: 15 August 2011

OFFSITES &
UTILITIES

ELECTRICAL

PROCESS
CONTROLS

COMMUNICATIONS

OTHERS

SAEP-14
Project Proposal

BOILER QTY

EACH

BOILER CAPACITY

LBS/HR

BOILER PRESSURE

PSIG

COOLING TOWER CAPACITY

GPM

AIR COMPRESSOR QTY

EACH

AIR COMPRESSOR CAPACITY

SCFM

FLARE SIZE

SCFM

FIREWATER SYS CAPACITY

GPM

NITROGEN GEN SYS CAPACITY

SCFM

WATER TREATMENT FACILITY


TOTAL INSTALLED COST (OFFSITES &
UTILITIES)

GPM

DOLLARS

TRANSMISSION LINE LENGTH

KM

TRANSMISSION LINE VOLTAGE

KV

SWITCHYARD VOLTAGE

KV

MAIN SUBSTATION

EACH

MAIN SUBSTATION

KVA

UNIT SUBSTATION

EACH

UNIT SUBSTATION

KVA

ELECTRICAL CABLE TRAY

LM

ELECTRICAL CABLE

LM

TOTAL INSTALLED COST (ELECTRICAL)

DOLLARS

DIGITAL CONTROL SYSTEM (DCS)

I/O

EMERGENCY SHUTDOWN SYSTEM (ESD)

I/O

VIBRATION MONITORING SYSTEM (VMS)

I/O

WORKSTATIONS QTY

EACH

NEW TRANSMITTERS QTY

EACH

INSTRUMENTATION CABLE TRAY

LM

INSTRUMENTATION CABLE
TOTAL INSTALLED COST (PROCESS
CONTROLS)

LM

DOLLARS

FIBER OPTIC CABLES

LM

COMMUNICATION EQUIPMENT
TOTAL INSTALLED COST
(COMMUNICATIONS)

EACH

DOLLARS

LIST MISCELLANEOUS FACILITIES

EACH

Page 44 of 48

Document Responsibility: Project Support and Controls Dept.


Issue Date: 20 September 2006
Next Planned Update: 15 August 2011

ENGINEERING

CONSTRUCTION

SAEP-14
Project Proposal

ENGINEERING (PROJECT PROPOSAL)

MHRS

ENGINEERING (DETAIL DESIGN)

MHRS

ENGINEERING (PMT SUPPORT)

MHRS

TOTAL COST (ENGINEERING)

DOLLARS

DIRECT CONSTRUCTION

MHRS

INDIRECT CONSTRUCTION

MHRS

CONSTRUCTION (PMT SUPPORT)

MHRS

TOTAL COST (CONSTRUCTION)

DOLLARS

CRUDE PRODUCTION FACILITY (GOSP)

MBD

ACTIVITY

DESCRIPTION

IN MONTH(S)

PROJECT PROPOSAL (PP) DURATION


PROJECT PROPOSAL (PP) TO ERA DURATION
DETAIL DESIGN DURATION
SCHEDULING

ERA-MCC DURATION
CONSTRUCTION DURATION
START-UP & COMMISSIONING DURATION
MATERIAL & EQUIPMENT WITH MORE THAN 6 MONTHS LEAD-TIME
DELIVERY

VALUE
PRACTICES
CONTRACTING
STRATEGY

LIST OF VALUE PRACTICES IMPLEMENTED


TYPE OF CONTRACT TO BE EXECUTED (LSTK, OPENBOOK, LSPB,
LSCR, etc.)

Page 45 of 48

Document Responsibility: Project Support and Controls Dept.


Issue Date: 20 September 2006
Next Planned Update: 15 August 2011

SAEP-14
Project Proposal

EXHIBIT V BID QUANTIFICATION SUMMARY SHEET

PROJECT TITLE
CONTRACT
NUMBER
CONRTACT TYPE

BI

JO

:
:

SUMMARY OF COST
BY WORK BREAKDOWN STRUCTURE (WBS)
AREA OF WORK

BULK
MATERIALS

ENGINEERING

CONSTRUCTION

TOTALS

AREA OF WORK 1

AREA OF WORK 2

AREA OF WORK 3

AREA OF WORK 4

TOTAL PROJECT COST

SUMMARY OF QUANTITY AND COST


BY DISCIPLINE
DISCIPLINE

DEMOLITION
(SCA 007)

CIVIL / STRUCTURE
(SCA 200 & 400)

DESCRIPTION

UNIT

QUANTITY

COST

UNIT COST

TOTAL DEMOLITION WORK COST

LUMPSUM

SITE PREPARATION /
DEVELOPMENT
(PLOT SIZE)

SM

CONCRETE

CM

FENCE

LM

LANDSCAPING & IRRIGATION

SM

STRUCTURAL STEEL

TONS

BUILDINGS (TYPE OF BLDGS)


TOTAL CIVIL/STRUCTURE
MANHOURS & COST

SM

MHRS

Page 46 of 48

Document Responsibility: Project Support and Controls Dept.


Issue Date: 20 September 2006
Next Planned Update: 15 August 2011

MECHANICAL/
PROCESS
EQUIPMENT
(SCA 500)

PIPING
(SCA 600)

ELECTRICAL
(SCA 700)

COMMUNICATIONS
(SCA 780)

Project Proposal

STATIC EQUIPMENT

EACH

HEAT EXCHANGERS

EACH

AIR COOLERS

EACH

PUMPS

EACH

COMPRESSORS

EACH

OTHER PACKAGE EQUIPMENT

EACH

TOTAL MECHANICAL/PROCESS
EQUIPMENT MANHOURS & COST

MHRS

LM

TONS

LM

LM

TONNAGE CARBON STEEL PIPES


TOTAL PIPING MANHOURS &
COST

TONS

MHRS

TRANSMISSION LINE LENGTH

KM

MAIN SUBSTATION

MW

UNIT SUBSTATION

MW

ELECTRICAL CABLE TRAY


UNDERGROUND ELECTRICAL
CABLE
ABOVEGROUND ELECTRICAL
CABLE
TOTAL ELECTRICAL MANHOURS &
COST

LM

LM

LM

MHRS

I/O

EACH

EACH

INSTRUMENTATION CABLE TRAY


UNDERGROUND
INSTRUMENTATION CABLE
ABOVEGROUND
INSTRUMENTATION CABLE
TOTAL INSTRUMENTATION
MANHOURS & COST

LM

LM

LM

MHRS

FIBER OPTIC CABLES

LM

COMMUNICATION EQUIPMENT
TOTAL COMMUNICATIONS
MANHOURS & COST

EACH

MHRS

LENGTH OF PIPERACK
TONNAGE CARBON STEEL
(PIPERACK)
UNDERGROUND CARBON STEEL
PIPING
ABOVEGROUND CARBON STEEL
PIPING

PROCESS CONTROL SYSTEM


(DCS/ESD/VMS)
CONTROL VALVE COUNT
(MOV/GOV/MANUAL)
FIELD INTRUMENTS
(TRANSMITTERS/TGS)
INSTRUMENTATION
(SCA 800)

SAEP-14

Page 47 of 48

Document Responsibility: Project Support and Controls Dept.


Issue Date: 20 September 2006
Next Planned Update: 15 August 2011

INSULATION &
COATINGS
(SCA 900)

CONSTRUCTION

ENGINEERING

INSULATION AND FIREPROOFING


(EQUIPMENT, STRUCTURES,
BUILDINGS, etc.)
TOTAL INSULATION & COATINGS
MHRS & COST
TOTAL DIRECT CONST
MANHOURS & COST
TOTAL INDIRECT CONST
MANHOURS & COST
TOTAL CONSTRUCTION
MANHOURS & COST
TOTAL ENGINEERING MANHOURS
& COST

TOTAL PROJECT COST

Project Proposal

MHRS

MHRS

MHRS

MHRS

MHRS

DOLLARS

ACTIVITY
SCHEDULING

SAEP-14

IN MONTH(S)

DETAIL DESIGN DURATION


CONSTRUCTION DURATION
EQUIPMENT WITH MORE THAN 6 MONTHS LEAD-TIME
DELIVERY

Page 48 of 48