Professional Documents
Culture Documents
Approved
Date
Sept 18, 2013
Revision
Created Install Procedure
No.
1
Printed: 9/18/2013
General Notes: Use anti-seize compound on all threads. Use Teflon tape and thread
sealant compound pipe dope on all air fittings. Caulk must be 100% silicone or
aquarium grade. Silicone will not bond to wet surfaces, so keep them clean and dry.
Keep sharp objects and surfaces away from rubber parts.
2 of 27
Printed: 9/18/2013
NOTE: Inflation of an Air Bladder, even under low pressure, without clamps
securely tightened, can cause permanent damage or rupture of the Air Bladders.
The Air Bladder should never be inflated unless properly installed.
3 of 27
Printed: 9/18/2013
CLAMP CASTINGS
The Clamp Castings are positioned over the Main Anchor Bolts and retain the Air
Bladder and Hinge Flap in place. The Clamp Castings transmit a force to the bottom
edge of the Gate Panel through the Hinge Flap. This force, and the force imparted to
the Gate Panel by the inflated portion of the Air Bladder, provides the moment required
to support the cantilevered Gate Panel. The Clamp Castings also provide the sealing
mechanism for the Air Bladder.
HINGE FLAP RETAINERS
The Hinge Flap Retainers clamp the Hinge Flap to the upstream edge of the Gate
Panel. With the gate fully raised or fully lowered, the forces tending to pull the Hinge
Flap out from under the Hinge Flap Retainers are low. At intermediate gate positions,
high forces occur, which requires the Hinge Flap Retainers be kept tightly clamped.
RESTRAINING STRAPS
The Restraining Straps are the reinforced rubber strips that attach to the spillway and to
the bottom side of the Gate Panel. The Restraining Strap limits the upstream travel and
height of the Gate Panel during inflation and insures that the Gate Panel does not flip
over upstream when the gate system is fully raised and the water elevation is less than
full pond depth.
RESTRAINING STRAP CLAMPS
The Restraining Strap Clamps fasten the Restraining Strap to the spillway and to the
Gate Panel. The Restraining Strap Anchor Bolts used to fasten the clamp to the
spillway and the hex head bolts used to fasten the clamp to the Gate Panel are typically
of the same diameter and should be kept tight at all times.
NAPPE BREAKERS
The Nappe Breakers divide the water flowing over the top edge of the raised gate
system. This provides an air path to the otherwise closed off space under the raised
Gate Panel created by the water wall. Without the Nappe Breakers, a vacuum could
occur behind the water wall and high gate loads or vibration may occur.
ABUTMENT PLATES
The Abutment Plates may consist of concrete, stainless steel or UHMW polyurethane.
The Abutment Plate component is located at each section end of the gate system. It
provides a smooth vertical surface for the Abutment Seal that is attached at each end of
the Gate system to create a watertight seal.
ABUTMENT SEALS
The Abutment Seals are the reinforced rubber strip that seals the end Gate Panels to
the Abutment Plates.
4 of 27
Printed: 9/18/2013
ORIENTATION
GATE
RIGHT
Flow
LEFT
5 of 27
Printed: 9/18/2013
6 of 27
Printed: 9/18/2013
7 of 27
Printed: 9/18/2013
8 of 27
Printed: 9/18/2013
9 of 27
Printed: 9/18/2013
pic 4.1
5. Install Hinge Flaps onto Gates Panel using Hinge Retainers and stainless steel
fastening hardware. On larger gates it may be necessary to cut the hinge and
install it in multiple sections. (use generous amounts of copper or nickel-based
anti-seize lubricant on all stainless steel threads)
6. On the Gate Panel apply silicon around all the threaded holes and one big bead
along the joint or the round stock and flat as well as up and over where the ribs
come into the round stock (see pic 4.2).
10 of 27
Printed: 9/18/2013
Silicon
pic 4.2
b. Bend the end of the spiral insert so it will not slip over the end of the hose
barb during installation. Measure the length of the spiral insert and make
sure it will span the length between the hose barbs, minus the plastic insert.
c. Insert the clear plastic insert in the hose between the stainless spiral and
the brass barbed fitting on the bladder and clamp the hose to the brass
fitting with provided Mikalor clamp.
9. Position the wedge of Air Bladder on spillway just downstream of Main Anchor
Bolts. The wedge should touch the upstream wall of the wedge embed. Make
sure the Air Bladder fitting fits correctly into Air Block-Out.
11 of 27
Printed: 9/18/2013
10. Roll the Air Bladder in half from left to right, or lift the wedge of the bladder to
expose Air Bladder connection.
a Loop the hose back around to the stainless fitting and secure with provided
Mikalor clamp
b Fill the Air Block-Out with expandable foam isolation, in geographical
locations where freezing is present.
11. Roll Air Bladder into final position. Make sure the air supply line does not kink.
12. Repeat steps 4 thru 11 for remaining Air Bladder(s).
13. Apply generous amounts of copper or nickel-based anti-seize lubricant on all
stainless steel threads.
14. Place assembled Gate Panel/Hinge Flaps onto Air Bladders. Reference drawing
11-820-110 for section view. Align the upstream edge of Hinge Flap with the Air
Bladder wedges. The upstream profile of the two 30 degree Air Bladder wedges
and the single Hinge Flap 30 degree wedge should follow a circular 90 degree
arc.
15. Locate Main Anchor Clamp Castings. Position Main Anchor Clamp Castings over
the Air Bladder and Hinge Flap wedges so the hinge wedge is tight against the
arch of the clamp. Make sure to use generous amounts of copper or nickel-based
anti-seize lubricant on all stainless steel threads and on bearing surfaces of
stainless steel nuts. Tighten nuts enough to get the next clamp placed
16. Install Abutment Seals. Refer to Section 8.0
17. Do not torque anchor bolts or inflate the system until the Abutment Seals are
installed.
18. Tighten stainless steel hex nuts starting at the Abutment Seals working toward the
middle of each bladder. After all nuts are snug (135-270 N-m), torque to 1400 Nm, working from the ends of the bladders to the middle. Make sure the main
anchors are tightened evenly to keep the clamp even. Make sure to use generous
amounts of copper or nickel-based anti-seize lubricant on all stainless steel
threads and on bearing surfaces of stainless steel nuts.
19. Repeat steps 14 through 18 for remaining Gate Panel(s). Double check the
abutment-to-abutment direction measurement after placing each gate, to ensure
that Gate Panels and Air Bladders are set correctly.
20. Beginning at the Abutment seal and working toward the center of the Air Bladder,
re-torque each of the Main Anchor Bolts to 1400 N-m
12 of 27
Printed: 9/18/2013
21. Starting at one end re-torque all Main Anchor Bolts to 1400 N-m.
22. Wait 24 hours and again torque all anchor bolts 1400 N-m. (Note: 1400 N-m is
an estimated only, temperature affects on the rubber may require a higher torque
value to seat rubber into casting)
23. Inflate gate system to proper height of 3 M and then lower the gate and re-torque
the bolts.
CAUTION: Be careful when inflating the system at this time. Since the
Restraining Straps are not installed yet, the gates can tip over upstream if raised
to far. See Section 9.0 to install the Restraining Straps.
24. Install Nappe Breakers on downstream top edge of each Gate Panel.
13 of 27
Bladder Side
Upstream
Printed: 9/18/2013
B1
Downstream
Abutment Side
4. Install seal using generous amount of 100% silicone caulk between the seal and
the Gate Panel. Place a bead of silicone caulk along the edge of the Gate Panel
where the Abutment Seal will be bolted to the gate. Place a bead of silicone caulk
on the bladder before placing the Abutment Seal down.
5. Locate Abutment Seal Retainers, washers, and nuts. Install according to drawing
11-820-120-1. Do not forget to apply generous amounts of copper or nickel-based
anti-seize lubricant on all stainless steel threads and on bearing surfaces of
stainless steel nuts.
6. Refer to Section 14 for the required torque values.
7. Place Clamp Casting over wedges and Main Anchor Bolts and torque Main Anchor
Bolts to 1400 N-m.
8.
Beginning at the ends of the Gate Panels and working toward the middle of the
bladder, re-torque each of the Main Anchor Bolts to 1400 N-m.
9. Test seal by checking for any visual gaps between the seal and the Abutment
Plate with the gates in the fully closed position. Adjust seal as required so that no
visual gap is present.
10. Wait 24 hours, and again torque all anchor bolts 1400 N-m.
14 of 27
Printed: 9/18/2013
GATE
LONG SIDE OF CLAMP
UPSTREAM SIDE
NYLON ROD
CONCRETE
UPSTREAM SIDE
4. Tighten the Restraining Strap anchor nuts to avoid slippage of the strap
temporarily.
5. Torque all restraining strap anchors to 350 N-m.
15 of 27
Printed: 9/18/2013
16 of 27
Printed: 9/18/2013
2.
Using a marker, mark the holes on the wall or floor accordingly. Move the
cabinet away from the marked holes.
3.
Using the concrete drill, bore holes which match the manufacturers
recommended depth and diameter for the stainless steel wedge type anchors.
Install the wedge type anchors.
4.
Place the cabinet in the appropriate position. Tighten anchors until the cabinet
is firmly anchored.
5.
6.
Repeat the process for the air compressor equipment, blowers, and Program
Logic Controller (PLC).
11.0 ELECTRICAL
1. Contractor to supply and install control wiring between the ACC and PLC per
applicable building codes.
2. All electrical conduit shall be as specified in the drawing.
3. Contractor to supply and install power supply conduit and wiring between the
circuit breaker and compressor & blower motors per project drawings.
4. Contractor to supply and install sensor cabling between external termination
boxes and the PLC cabinet per project drawings.
5. Contractor to procure circuit breaker panel per project drawings and install in
accordance with appropriate building codes.
17 of 27
Printed: 9/18/2013
3. A wet test of the air lines may be performed with a leak detection solution at 50
psi in place of the 24 hour timed test.
4. Any joints or fittings exhibiting leakage during this time shall be repaired or
replaced.
5. The air piping between the air control cabinet and high pressure equipment
shall be tested by pressurizing to 150 psi for 24-hours. Pressure readings and
ambient air temperature shall be recorded at six different times during the test.
Any joints or fittings exhibiting leakage during this time shall be repaired or
replaced.
6. After installation of the gate system, before removing the cofferdam the spillway
gates shall be fully raised and lowered three (3) times using a portable air
supply. The gate shall operate smoothly with no binding.
7. Do not inflate air bladder past the operating pressure found in the hydraulic
calculations.
18 of 27
Printed: 9/18/2013
1400 N-m
270 N-m
350 N-m
270 N-m
270 N-m
100 N-m
50 N-m
b. Required Tools
Controls & Compressor (tools)
Adjustable wrenches
Pipe wrenches
Screw driver
Fine point permanent marker
8 Stainless steel M12 diameter x 150mm length wedge anchors
Concrete drill for M12 diameter wedge anchor
Lifting/moving apparatus
Gate System Installation (tools)
Wrench and socket for Main Anchor Bolts. Air impact wrench in
combination with manual torque wrench is satisfactory. A hydraulic
torque wrench is more convenient if available.
Sockets and ratchet wrenches for seal retainer and hinge flap nuts.
Utility knives for cutting rubber
3lb hammer and (7/8=22mm) rubber punches for Abutment/J-Bulb seals
Anti-seize compound sufficient for all studs, washers, and nuts.
32 tubes of 100% silicone or aquarium grade caulk and 2 caulk guns.
Rags for cleaning up silicone messes.
Abrasive cutoff saw and motorized reciprocating saw (e.g. Sawzall) or
chain saw for trimming Hinge Flaps to length.
Air bladder lifting clamps (designed by OHI).
Hand held angle grinder.
Lifting shackles to fit Gate Panel lifting holes, spreader bar for bladders.
2 Pry bars approximately 1M long.
Electric drills.
Pipe joint compound and Teflon tape for air fittings.
Pipe wrenches for air fittings.
Pliers
Shackles to fit crane hook to L shaped clamp casting lifting bracket.
Thread File.
Thread cutting dies to fit all smaller threads for repair if required.
19 of 27
Printed: 9/18/2013
Abutment Plate to Abutment Plate Spacing Not Correct This is a very common
mistake. If the span width is too great the gate system may not seal properly.
If the span width is too short, the gates may not fit. There could also be permit
issues related to insufficient waterway width.
Anchor Bolt Assemblies Not Secured for Concrete Placement - Anchor bolt
assemblies can move from pressure of concrete causing shifting so they are no
longer perpendicular to abutment wall (which creates interference with how the
gate swings up and down), or to drift left or right (which will cause the clamp
castings and bladders to not fit.
Anchor Bolt Spacing Anchors are not spaced properly because hole pattern
not used properly or other reason. This will cause clamp castings to not fit.
Abutment Walls Not Plumb When abutment walls are not cast plumb, the OHI
supplied Abutment Plates (either stainless steel or UHMW plastic) will not be
plumb. This will create a variable width gap between the Abutment Wall and
gate which could lead to gate interference and water leakage.
Abutment Walls Bowed Insufficient form bracing can cause the Abutment
Walls to bow out. If this exceeds 12mm the OHI Abutment Seals will not work
properly. This may lead to the gate system not sealing as it should. Steel form
work is recommended.
Concrete Surface not Level If top of concrete elevation varies by more than
12mm over a span of 1.5M, or more that 50mm over the width of the waterway,
the clamp castings will not seat as designed possibly leading to leak paths
between the Gate Panels (that can not be sealed) or a total gate system crest
height that varies, which reduces overall storage capacity.
20 of 27
Printed: 9/18/2013
21 of 27
Printed: 9/18/2013
a)
b)
c)
(mm)
B.
d.1)
d.2)
e.1)
e.2)
f.1)
f.2)
22 of 27
Printed: 9/18/2013
C.
g.1)
g.2)
h.1)
h.2)
i.1)
i.2)
Measured Offset
2 stand off
at edge of
plate
23 of 27
Printed: 9/18/2013
Actual Angle
Left Abutment
Actual Angle
Right Abutment
j.1)
j.2)
5 ft
b(? ft)
B
A
3 ft
24 of 27
Printed: 9/18/2013
k.1)
Distance between Right Abutment Plate Face to Center of nearest anchor bolt
k.2)
Distance between left Abutment Plate Face to Center of nearest anchor bolt
l)
Distance between center line of anchor bolts and bolt most out of alignment
25 of 27
Printed: 9/18/2013
m.1)
Difference between highest and lowest elevations across the spillway crest (measured near
the main anchor bolts
(mm)
n.2)
26 of 27
Printed: 9/18/2013
Distance between
centerline of first air
block out and center of
second air block out
o.1)
Distance between Left abutment wall and centerline of first air assembly block out
__
o.2)
Distance between CL first left air block out and CL of second air block out
__
p.1)
Distance between Right abutment wall and centerline of first air assembly block out
__
p.2)
Distance between CL first right air block out and CL of second air block out
__
q.1)
Distance between Left abutment was and centerline of first restraining strap block out _____
q.2)
Distance between CL first left restraining strap block out and CL of second restraining strap
block out _______
r.1)
Distance between Right abutment was and centerline of first restraining strap block out ____
r.2)
Distance between CL first right restraining strap block out and CL of second restraining strap
block out _______
27 of 27