Professional Documents
Culture Documents
Language English
Header Data
Released On 15.12.2005 15:49:38
Release Status Released for Customer
Component
PS-PRG-EVA Progress Analysis
Priority
Recommendations / Additional Info
Category
Consulting
Symptom
This note contains notes on searching for errors in progress value analysis for the following subject areas:
l
Non-appended orders
Other Terms
Progress value analysis, CNE1, CNE2, CNE5, milestone technology
Solution
Adjusted/original actual POCs explained by the "Degree of processing from confirmation" measurement technique
In period 10, the degree of processing confirmed for an activity is 25%. Consequently, an actual percentage of completion of 25% is calculated
for period 10. A further confirmation occurs, retroactively as it were, for period 10. It has a degree of processing of 35%. In general,
percentages of completion in progress analysis are not changed for a past period (that is for a period for which progress analysis has already
been carried out). Consequently, the original actual percentage of completion of 25% for period 10 in our example remains unchanged during
progress analysis - until period 11. However, 35% is displayed as the adjusted actual percentage of completion. The difference is updated
internally in RPSCO/RPSQT as business transaction PEV2. The original value of 25% in this example is shown as business transaction PEV1.
Additionally: If progress analysis is only started up to period 10 instead of period 11, the original value of 25% is overwritten by a value of
35% and displayed as an adjusted value of 35% in the report.
Analysis with Transaction RKACSHOW for WBS element/network activity
Remark: Statistical key figures (Customizing setting!!)
10 non-aggregated percentages of completion
20 aggregated percentages of completion
30 percentages of completion for results analysis
GJAHR WRTTP VERSNSTAGR VRGNG -> Detail screen Period 10
1999P2EV110PEV125%
1999P2EV110PEV210%<--- only delta
PS: In the case of aggregated percentages of completion, the subordinated subhierarchy is taken into account in the standard SAP way.
Percentages of completion for results analysis are only displayed on the billing elements. If none occurs in a subhierarchy, such a percentage
of completion is updated in every object in this hierarchy (this is not displayed in reporting, it is only relevant for results analysis).
Display in reporting (progress analysis):
Non-appended orders
If you carry out the progress analysis and non-appended orders are assigned to your project, you should take the following into account:
A WBS element has, for example, costs of 200 dollars, an order which is assigned to the WBS has costs of 100 dollars. In the reporting, a total
of 200 dollars costs are displayed (non-appended). The progress value can, however, in this instance have a maximum value of 300 dollars. If
you now compare the progress values and the costs with each other, the result can be "confusing" as when totaling the progress values no append
logic is used and there are 200 dollar costs against 300 dollars progress values.
After transferring the data, the progress values need to be calculated for all projects using Transactions CNE1/CNE2. Then the progress values
can be analyzed again via Transaction CNE5.
Validity
Software Component From Rel. To Rel. And Subsequent
SAP_APPL
45A
45B
46A
46B
References
This document refers to:
SAP Notes
176111 CNE5: Missing progress values
516476 Consulting note Progress analysis
153051 CNE5: Missing percentage of completion