You can enter, update, and view parent-child quality results within the forms application or from
the Quality Workbench user interface. You can enter quality results directly.
In this topic, you will enter quality results for parent-child collection plans.
Additional Information
Procedure
Step Action
1. Begin by navigating to the Enter Quality Results page.
Step Action
2. Click the Manufacturing and Distribution Manager link.
Step Action
3. Click the vertical scrollbar.
Step Action
4. Click the Enter Quality Results link.
Step Action
5. Use the Organizations page to select the appropriate organization.
Step Action
6. Click the M1 list item.
Step Action
7. Click the OK button.
or Press [Alt+O].
Step Action
8. Use the Enter Quality Results page to enter the name of the parent collection plan
for which you want to enter quality results.
Step Action
9. Click in the Collection Plan field.
Step Action
10. Enter the desired information into the Collection Plan field. Enter "IC
COLLECTION PLAN".
Step Action
11. Click the Find Plan button.
or Press [Alt+i].
Step Action
12. Use the Results region to enter quality results.
You must enter data in the collection elements that you defined as mandatory
during the collection plan set up
Step Action
13. Click in the Item field.
Step Action
14. Enter the desired information into the Item field. Enter "IC2323".
Step Action
15. Click in the Quantity field.
Step Action
16. Enter the desired information into the Quantity field. Enter "10".
Step Action
17. Click in the Sub field.
Step Action
18. Enter the desired information into the Sub field. Enter "FGI".
Step Action
19. Click the Save button.
Step Action
20. Click the Child Plan list.
Step Action
21. Click the IC DISPOSITION PLAN list item.
Step Action
22. Click the Enter button.
Step Action
23. Note that the in the Results region, the quality results you entered for the parent
plan displays in the child plan.
Step Action
24. Click in the Disposition Quantity field.
Step Action
25. Enter the desired information into the Disposition Quantity field. Enter "5".
Step Action
26. Click in the Disposition field.
Step Action
27. Enter the desired information into the Disposition field. Enter "REPAIR".
Step Action
28. Click in the Disposition Status field.
Step Action
29. Enter the desired information into the Disposition Status field. Enter
"PENDING".
Step Action
30. Click the Save button.
Step Action
31. Click the OK button.
Step Action
32. Click the OK button.
or Press [Alt+O].
Step Action
33. Click the Close button.
Step Action
34. You have completed the Entering Quality Results in Parent-Child Plans procedure.
End of Procedure.