Professional Documents
Culture Documents
uk
www.enkacollege .com
Part A
Course Book
Measurement
The EDM
Geometry
The Casio Fx7400G Plus
Leveling
Level Book
External works
Errors
Site Check List
Problem sheet
Setting Out Techniques
Coordinates
MEASUREMENT 1
102.567m
TO THE LEFT OF THE DECIMAL TO THE RIGHT OF THE DECIMAL POINT
POINT IS THE NUMBER OF
IS THE NUMBER OF MILLIMETRES
METRES
Unfortunately not all site dimensions are written as above here are a few examples:
98.2
345mm
22.15
4652mm
98.200m
0.345m
22.150m
4.652m
MEASUREMENT 2
3, 5, 8 or 10 metre pocket tapes: These are the essential tools for an engineer and
should be carried at all times (preferably on your belt). Due to their relatively
short length and rigidity there is no appreciative error in the readings taken. For
build reliability and usefulness a 5 or 8 metre tape is recommended.
30 or 50 metre tapes: These tapes should always be available on site, but care
should be taken on their use. There are 3 basic errors that can effect the accuracy
of the reading :
1/ Tension & Sag: You will need to pull the tape to straighten it, but it is
difficult to judge the correct amount of pull (approx. 6kg) in order to
achieve an accurate reading. To make matters worse if the tape is not
continuously supported along its length then the sag will compound the
error. To try to achieve an accurate measurement (Within 10mm) either:
A/ Use a spring balance (not normally available on site)
B/ Take two readings one with the tape pulled straight with no extra
tension and one with the tape fully tensioned then take the mean
reading.
C/ If the tape is unsupported DO NOT pull it so that the sag disappears
this will only give you a false reading it is better to try to support
the tape every few metres to eradicate the sag and if this is not possible
you may have to resort to electronic distance measurement.
2/ Slope: All measurements given on site drawings are HORIZONTAL
distances, and therefore it is imperative that the tape is level when you take
your readings. This may mean that you will have to use spirit levels thus:
SPIRIT
LEVEL
SPIRIT LE
VEL
TAPE
HORIZONTAL DISTANCE
MEASUREMENT 3
TEMP. C
30
TAPE IS 3 mm LONG
25
20
TAPE IS CORRECT
15
10
Fabric tapes: normally 30 metres in length, these tapes are used for approximate
setting out where accuracy between 10 20mm is acceptable e.g. groundwork
excavation. The benefit of this type of tape is its durability in extreme site
conditions.
Levelling staff: used mainly in
conjunction with an automatic
level can also be utilised for
offset work where a pocket tape
is unpractical.
Electronic Measurement
Discussed later on the course
1.450 m
1.430 m
1.414 m
1.395 m
MEASUREMENT 4
READING
Most errors in reading will arise due to incorrect holding of the 0 mark which on 30
& 50m tapes is the outside of the end ring.
When the end ring is hooked over a nail, an inaccuracy of between 5 9 mm will
result unless a correction is made.
0 MARK
8 mm
NAIL
END RING
In the above example the tape has been hooked over a nail resulting in an error of
8mm if you wanted to measure a distance from the centre of nail of 24.560m the
corrected reading would be 24.568m
The difficulty created by holding exactly on the 0 mark is often overcome by
holding the tape on the centre of your nail at 100mm and adding this amount to your
required measurement in the example above you would read 24.660.
REMEMBER WHEN SETTING OUT THE CORRECTION IS ADDED
However if you were checking the distance between two points the tape was hooked
on one at 6 mm correction the tape was reading 30.006m the true distance between
these points is 30.000m
WHEN CHECKING BETWEEN POINTS SUBTRACT THE CORRECTION
FROM THE TAPE READING TO GET THE TRUE DISTANCE
WARNING
THE CORRECTION FOR END OF TAPE READINGS IS ONE OF THE
COMMONEST FORMS OF ERROR IT IS POSSIBLE THAT YOU HAVE
MADE THE WRONG CORRECTION OR THAT YOUR CHAINPERSON HAS
NOT HELD THE TAPE WHERE YOU EXPECTED.
A WAY OF ELIMINATING THIS ERROR IS TO FINALLY TAKE A READING
WITH THE 0 MARK ON THE NAIL AND OBSERVING THAT THE
MEASUREMENT MARKED IS CLOSE TO WHAT WAS REQUIRED
THE EDM 1
DESCRIPTION
The EDM has two basic functions:
1/ To turn vertical and horizontal angles ( identically to a theodolite )
2/ To measure distances ( Electromagnetic Distance Measurement or EDM )
In the late 1980`s engineers were using a theodolite with an EDM bolted to the top.
Nowadays both these instruments are integrated into an instrument called a TOTAL
STATION unfortunately the construction industry refer to these TOTAL
STATIONS as EDM`s !
On this course we will use the industrys convention and call them EDM`s
CARRYING HANDLE
VIEWFINDER
TELESCOPE
FOCUS RING
BATTERY
EYEPIECE
HORIZONTAL
BUBBLE
HORIZONTAL CLAMP
AND SLOW MOTION SCREW
DISPLAY
SCREEN
KEYBOARD
FOOTSCREW
FOOTSCREW
TRIBRACH
OPTICAL
PLUMB
EYEPIECE
ELECTRONIC DATA
TRANSFER PORT
FOOTSCREW
CIRCULAR BUBBLE
THE EDM 2
SETTING UP
The first step is to set up the tripod over the station point.
Looking down on the tripod centralise the
tripod over the station by viewing through
the hollow attachment screw.
ATTACHMENT SCREW
Make sure that the tripod head is set to a
convenient height to make the viewing of
the EDM comfortable.
THE EDM 3
Now slacken the attachment screw and centre the plumb circle over the station by
sliding the EDM over the tripod head.
At this point the circular bubble should still be within the brown ring and the plumb
circle should be centred over your station.
THE EDM 4
THE EDM 5
Focusing
To focus the telescope turn the focus ring
on the telescope.
Whilst focussing you will see an infinity
symbol with an arrow pointing anticlockwise this helps to remind you to
turn the focus ring in this direction when
sighting distant objects.
THE EDM 6
270
90
THE TELESCOPE
(UPPER PLATE)
180
THE HORIZONTAL
PROTRACTOR
(LOWER PLATE)
THE EDM 7
Press the PWR button although all EDM`s power up immediately - many
remain inactive until some movement is made to the instrument with the Nikon
(to which the following instructions refer) you have to rotate the telescope
vertically.
Before moving the telescope, on the screen you will see values for TEMPERATURE,
PRESSURE AND PRISM
Because
the temp.
ambient
temperature
pressure and
verywill
slightly
affects the
EDM all
this
should read
: 15
C press.and
750mmHg
be sufficient
to cover
climatic changes during the year. PRISM will be dealt with later on the course.
After tilting the telescope you enter the default screen:
HA: 282 33 43
VA: 110 12 02
SD:
m
DSP1/3
BAT
TOGGLE TO
DSP2/3 BY PRESSING THE [DSP] BUTTON
HA: 282 33 43
VD#
HD#
DSP2/3
m
m
BAT
If you ever get lost in other display screens pressing ESC repeatedly will always bring
you back to this screen. On the Nikon 310 DSP2/3 SHOULD ALWAYS BE SET
HA: = The current Horizontal Angle the telescope is pointing
VA: = The current Vertical Angle the telescope is pointing (DSP1/3)
VD: = The current Vertical distance (when measured)
SD: = The slope distance (when measured) (DSP1/3)
HD: = The horizontal distance (when measured)
DSP1/3 = This is screen 1 of 3 - press the [DSP] button to toggle to 2/3
BAT = Battery voltage level 3 bars MAX 1 bar MIN
The HA value does not mean anything since the EDM is currently BLIND i.e.
you have not given it orientation.
The VA value however is operative because the EDM knows its been levelled
all vertical movement relates to a level datum.
THE EDM 8
We now need to open the EDM`s eyes! PRESS ANG (button No 4)
HA: 282 33 43
1 : 0-Set
3 : Hold
2 : Input 4 : Rept.
ANG
BAT
This is the ANG (Angle) screen confirmed bottom left and determines the way
you are going to set a BACKSIGHT angle before you open the EDM`s eyes.
The HA(Horizontal Angle) at the top of the screen is as the default screen.
You have 3 options on how to set the angle option 4 : Rept is not used.
1st OPTION 0 Set
This option is used where you have a known point directly NORTH or 0 to the
station you are set up over.
Look through the telescope and sight this known point (BACKSIGHT) make sure
the horizontal clamp is on then:
Press button 1 (MSR) and the EDM opens its eyes and knows it is pointing to
0 00 00 (NORTH)
If
you
undo
theout
horizontal
instrument
now
able
to set
any angleclamp
in theand
360rotate
circlethe
to an
accuracyyou
of 1will
. see that you are
This option is also used where you just want to turn 90 between two points.
2nd OPTION - INPUT
This option is used where you have a known point that is at a known angle relative
to your station you are set up over.
Look through the telescope and sight this known point (BACKSIGHT) make sure
the horizontal clamp is on - then press button 2 (DSP): The HA at the top of the
screen disappears and a cursor at the top right of the screen is waiting for you to enter
the known angle. Type in the degrees first then press the button (REC) . Then type in
the minutes with two digits e.g. 02 and then type in the seconds - again with two
digits.
Press ENT and the EDM opens its eyes and knows it is pointing to your known
point with your known angle that you have given it.
3rd OPTION - HOLD
This option is a variant of the 2nd option Instead of inputting your known angle you
rotate the EDM until your known angle is displayed at the top of the ANG screen.
Undo the horizontal clamp and rotate the instrument until the angle you want is
displayed on the top of the screen clamp and use the slow motion screw to get the
minutes and seconds. Press button 3 (TRK) The instrument has now HELD the
angle you turned to and is waiting for confirmation to open its eyes DO NOT
DO SO until you have sighted your known point (BACKSIGHT) THEN press
ENT.
THE EDM 9
ELECTRONIC DISTANCE MEASUREMENT
The course students may wish to know the principles of electronic
measurement in greater detail but because of the time that this would
take, we just give the basic principals which are sufficient for setting
out.
BASIC PRINCIPLES
The EDM sends out an infrared beam that emanates from the centre of
the instrument i.e. directly over your station. This beam is directed to
the centre of your crosshairs whilst you view THE PRISM with the
telescope. THE PRISM reflects the beam back to the EDM and the
resulting phase shift is calculated by the EDM to work out the
distance between your station and where the THE PRISM was
held.
THE PRISM
The prism is a compact number of mirrors that focuses the
EDM beam above the point of the prism i.e. where the
prism is being held. In this photo, this is the point of the
prism.
THE MINI PRISM
Used for accurate setting out within 100m of the EDM
WARNING DUE TO THE DIFFERENT WAYS
THAT PRISMS ARE MANUFACTURED EACH PRISM HAS A
PRISM CONSTANT THAT IS USUALLY EITHER 0mm OR
30mm. YOUR EDM MUST BE SET TO READ THE TYPE OF
PRISM YOU ARE USING IF YOU ARE NOT SURE WHAT THE
PRISM CONSTANT IS, TAPE OUT 5m AND CHECK THE
ELECTRONIC DISTANCE . IF YOU DO NOT GET THE
CORRECT DISTANCE YOU WILL HAVE TO ADJUST THE
PRISM CONSTANT ON THE EDM SEE MANUAL OR
CONTACT ENKA
THE TARGET
This is a larger version of the Mini Prism that can be attached to
a tribrach and tripod and can be set up over a station in the
same way as an EDM. The Target gives accurate results within
1000m (1KM) of the EDM
When a Target is attached to an adjustable rod it is known as a
POGO. The POGO operates in the same way as a mini prism
although it is less accurate. However, the POGO can be used up to
1000m from the EDM
THE EDM 10
When using an EDM your chainperson will be often be at a distance away from you
and unable to hear your instructions.
Two-way radio is an option that any engineer
would consider. Although it may seem the
perfect solution, it may not always operate
properly due to site interference e.g.
compressors, generators, tower cranes etc.
It is therefore necessary to adopt a sign
language with your chainperson and some
engineers design their own system - however
the majority use the following system:
THE EDM 11
METRES
(each pull of the arm
Signifies a metre)
2 metres
3 hundreds
THE EDM 12
ALL COORDINATES that are used on site can be stored in the EDM as a [POINT
NUMBER]. There are 2000 [POINT MUMBERS] that can be used on the NIKON
DTM 310.
TO ENTER A COORDINATE AS A [POINT NUMBER]
In the Site Office you can enter all known coordinates into the EDM before you go
onto site. At the default screen press FNC
You require Data press 6
You now require Input press 1 (wait)
Confirm Input press ENT
THE EDM 13
OBTAINING THE COORDINATES OF A POINT
USING THE CASIO FX-7400 AND THE EDM OUT ON SITE
USE COOR-CAL
3RD POINT
0 00 00
ND
CLOCKWISE
ANGLE
DISTANCE TO
3RD POINT
POINT
1ST POINT( EDM SET UP)
GEOMETRY 1
ANGLE
SIDE C (HYPOTENUSE)
SIDE B
ANGLE
90
SIDE A
PROPERTIES
ALL INTERNAL ANGLES TOTAL 180
THE AREA = SIDE A x SIDE B
2
FROM PYTHAGORAS THEOREM
GEOMETRY 1A
REARRANGING MATHEMATICAL FORMULAE
PYTHAGORAS THEOREM
C
B
A
C = A + B
OR
C = ( A + B)
A = C- B
OR
A = (C - B)
B = C - A
OR
B = ( C - A)
TRIG FUNCTIONS
HYP
OPP
ADJ
TAN
= OPP
ADJ
ADJ =TAN
OPP
OPP = TAN
x ADJ
= TAN -1 OPP
ADJ
SIN
= OPP
HYP
HYP = SIN
OPP
OPP = SIN
x HYP
= SIN -1 OPP
HYP
COS
= ADJ
HYP
HYP = COS
ADJ
ADJ = COS
x HYP
= COS -1 ADJ
HYP
GEOMETRY 2
THE CIRCLE
0 or 360
270
90
180
PROPERTIES
THERE ARE 360 DEGREES ( ) IN A CIRCLE EACH DEGREE IS
DIVIDED INTO 60 MINUTES ( ) AND EACH MINUTE DIVIDED INTO 60
SECONDS ( )
THE AREA OF A CIRCLE =
x RADIUS
x DIAMETER
GEOMETRY 3
ANGLE B
ANGLE A
ANGLE C
ANGLE D
PROPERTIES
A SQUARE OR RECTANGLE IS FORMED WHEN BOTH THE OPPOSITE
SIDES AND THE DIAGONALS ARE EQUAL
ANGLE A + ANGLE B = 90 ( AND LIKEWISE IN THE OTHER 3
CORNERS)
ANGLE A = ANGLE C AND ANGLE B = ANGLE D
THE TWO RIGHT ANGLED TRIANGLES FORMED BY A DIAGONAL
WILL BE IDENTICAL
GEOMETRY 4
NORTH
12
11
0 or 360
10
270
90
4
7
180
6
Can you work out the what the whole circle bearing will be at 7 o`clock ?
GEOMETRY 5
Because a clock is divided into 12 hours, each hour must represent 360 degrees of the
whole circle i.e. 30 - therefore 7 oclock would be at a WCB of 21012
Now that you know what Whole Circle Bearing means we will continue by
shortening this term to just bearing
NORTH
12
11
0 or 360
10
270
90
4
7
180
6
From the above diagram you can see that the bearings of 90 and 270 form a straight
line. You will notice that the difference in these two bearings is 180
A LINE HAS TWO BEARINGS THAT DIFFER BY 180
Because a line has two bearings it is inportant to arrow the required bearing.
Can you work out the two missing bearings below ?
NORTH
?
45
?
GEOMETRY 6
IT IS WORTH REMEMBERING:
12 O`CLOCK = 0 = 360 = NORTH
BEARINGS INCREASE CLOCKWISE AND DECREASE ANTI-CLOCKWISE
In the previous problem we start from NORTH = 360 and travel ANTI-CLOCKWISE
by 45 . Therfore our first bearing is 360-45 = 315
The second bearing we are looking for is on the SAME LINE as the first i.e
180 different. There are two ways we can work out this bearing:
1/ WORKING CLOCKWISE We add 180 to 315 to get 495 but whole circle
bearings only go up to 360 and reset to 0. Therefore we must subtract 360 from 495 to
get the bearing we are looking for = 135 .
2/ WORKING ANTI-CLOCKWISE We subtract 180 from 315 to get the bearing
we are looking for = 135 .
You
that the
method
is farthe
more
simple and should always be considered
whencan
bothsee
adding
andsecond
subtracting
through
0 bearing.
Upto now we have used NORTH (N) to calculate bearings, but we can use ANY known
bearing as our starting point.
We also made NORTH pointing to the top of the page but in practise this is not
always the case, and you may wish to turn the page/drawing around to orientate
NORTH as you would normally view it.
Can you work out the three missing bearings for A,B & C below ?
Note
the line AC is straight (ie 180 )
the line D has a bearing of 250
40
C
B
85
A
GEOMETRY 7
With reference to COORDINATE SHEETS 1 & 2 we can work out how distance/
bearing information can be related to coordinated points.
North
B
120m
110m
100m
A
90m
EAST
400m
410m
420m
20 m
EAST
10m
GEOMETRY 8
X = 580.980 E , 789.958 N
Y = 489.805E , 699.985 N
A = 1038.780 E , 4569.894 N
B = 976.985 E , 4607.643 N
C = 1002.780 E , 4698.098 N
THE EDM IS SET UP OVER POINT A FIND THE BEARING & DISTANCE TO
POINTS B & C
USING PYTHAGORAS
example C = (9+7)
1ST PRESS SHIFT THEN X
2ND PRESS ( BUTTON
3RD PRESS 9 THEN X
4TH PRESS +
5TH PRESS 7 THEN X
6TH PRESS ) BUTTON
7TH PRESS `EXE` TO GET THE ANSWER OF 11.402
SOP 900.000 E
400.000 N
MH35
800.000 E
390.000 N
BACKSIGHT
MH34
SOP 840.000 E
345.000 N
MH36
SOP 920.100 E
303.000 N
EDM
890.000 E
295.000 N
BACKSIGHT STATION
SOP 918.780 E
598.340 N
MH43
1050.720 E
560.470 N
BACKSIGHT
MH42
SOP 1000.240 E
476.750 N
MH44
SOP 922.100 E
458.000 N
EDM
990.565 E
465.267 N
KNOWN COORDINATED
POINT 2
CLOCKWISE ANGLE
DISTANCE
THE ONLY TIME THIS DOES NOT OCCUR IS WHEN THE POINT 1, POINT 2
AND THE UNKNOWN POINT 3 ARE ALL ON THE SAME LINE.
180
REPRESENTS THE
SITE
TO
FIND
THE
HA = 87 45 33
DIST 45.584m
DIST 53.895m
HA= 162 56 34
POINT 1
EDM
245.000 E
85.000 N
WORK OUT THE COORDINATES OF THE 3 SECONDARY CONTROL
POINTS
FROM THE DISTANCES AND ANGLES ( HA ) GIVEN BY THE
EDM
DIST 67.780m
HA = 325 20 40
3rd POINT
DISTANCE
(GIVEN ON DRAWING)
POINT 2
POINT 1
270 CLOCKWISE
TO WORK OUT ALL DRAWING COORDINATES YOU WILL BE USING
CLOCKWISE ANGLES OF 0 - 90 - 180 - 270 - AND DIMENSIONS FROM
THE SITE DRAWINGS
POINT 2
876.780E
456.900N
POINT 1
857.977E
423.654N
Y
23.230m
LEVELLING 1
WHATS A LEVEL ?
Level is a commonly used word and one with different meanings - which can include:
1/
2/
3/
4/
5/
However:
For a surface to be FLAT & HORIZONTAL all HEIGHTS of that surface - from
whatever level datum you have chosen -must be equal.
A SPIRIT LEVEL checks that a surface is FLAT & HORIZONTAL whilst AN
AUTOMATIC LEVEL checks HEIGHTS.
In summary:
IS IT LEVEL means CHECK THAT THE SURFACE IS FLAT AND
HORIZONTAL BY USING A SPIRIT LEVEL OR AUTOMATIC LEVEL.
GIVE ME A LEVEL means PROVIDE ME WITH A HEIGHT USING A
TAPE MEASURE AND/OR AUTOMATIC LEVEL.
FOCUS SCREW
HORIZONTAL SLOW
MOTION SCREW
EYEPIECE
FOOTSCREWS
LEVELLING 2
LEVELLING 3
NEWLYN
TAUNTON
SET UP 1
BRISTOL
SET UP 2
HIGHWORTH
SET UP 3
?
60m
80m
95m
0.000m
staff reading 70m - staff reading 10m
SET UP 2
staff reading 40m - staff reading 20m
SET UP 3
staff reading 50m - staff reading 35m
A Bench mark will have been established in Highworth by the O.S. on a permanent
position e.g. kerb, side of an existing building etc. and a level value assigned to it e.g.
96.120m THIS IS THE HEIGHT ABOVE MEAN SEA LEVEL AT NEWLYN.
The land surveyor would then have set up his dumpy and establish a TEMPORARY
BENCH MARK (TBM) on site.
Staff reading 2m
Staff reading 1m
SITE
TEMPORARY BENCH
MARK (T.B.M )
VALUE 95.120m
LEVELLING 4
A TEMPORARY BENCH MARK (TBM) can be any point on site which is not
likely to move vertically e.g. pencil cross on concrete slab, nail in road, control
station.
THE TBM NOW CONTROLS ALL SITE LEVELS AND OTHER TBM`S
(SECONDARY TBM`S) MAY BE ESTABLISHED ON SITE BASED ON THE
ORIGINAL TBM.
JUST LIKE PRIMARY CONTROL STATIONS AND SECONDARY CONTROL
STATIONS IN EDM WORK ORIGINAL TBM`S AND SECONDARY TBM`S
SHARE THE SAME ACCURACY DEPRECIATION.
1.000m
TBM 1 VALUE 95.120
(supplied by others)
NEW T.B.M
ESTABLISHED BY YOU
VALUE 95.600
97.900m
INSTRUMENT HEIGHT = COLLIMATION LEVEL
300mm
VALUE 97.600m
Staff reading
1.500m
2m
95.600 m
TBM VALUE
96.100 m
LEVELLING 5
SETTING A LEVEL
EVERY LEVEL THAT YOU CALCULATE ON SITE IS MADE FROM :
THE INSTRUMENT HEIGHT = TBM VALUE + STAFF READING =
COLLIMATION HEIGHT (from now on )
= COLLIMATION
The site drawings will specify that all elements of buildings and external works are
constructed to a required height (level) ABOVE SEA LEVEL.
EXAMPLE 1
SET THIS PIN/PEG TO THE PROPOSED STRUCTURAL SLAB LEVEL (SSL)
STAFF
COLLIMATION=87.500 m
STAFF READING
= 1.800 m
1.800m
SSL = 85.500m
TOP OF PIN
IS AT 85.700m
LEVELLING 6
STAFF
COLLIMATION=87.500 m
STAFF READING
= 2.020 m
2.020m
SSL = 85.500m
TOP OF PIN
IS AT 85.480m
. The top of the Pin is now at a level of 85.480m
COLLIMATION STAFF READING
87.500m
2.020m
Therefore we must pull up the pin 0.020m (20mm)
to achieve slab level and re-check.
COLLIMATION=87.500 m
STAFF READING
= 1.600m
1.600m
0.400m
TOP OF PIN
IS AT 85.900m
SSL = 85.500m
The top of the pin is currently at a level 85.900m
COLLIMATION STAFF READING
87.500m
1.600m
Therefore the top of the pin is 0.400m (400mm) above the slab level we now
measure down 400mm with a tape measure and wrap some insulating tape around the
pin THE TOP OF THE TAPE =SSL =85.500m.
LEVELLING 7
STAFF READING
1.700m
COLLIMATION
TBM 34
VALUE 95.000m
96.700m
SLIDE STAFF
UNTIL YOU
READ 200mm
You would COLLIMATE the dumpy by placing the staff on the nearest TBM in
this example TBM 34, which has a value of 95.000m You would ADD the staff
reading to the TBM value to get a COLLIMATION OF 96.700m.
FFL ON THE SITE DRAWINGS IS GIVEN AS 95.500m THEREFORE
FFL + 1m = 96.500m.
SO YOU CAN NOW CALCULATE THE DIFFERENCE BETWEEN YOUR
REQUIRED LEVEL AND YOUR COLLIMATION LEVEL =0.200m(200mm).
THIS IS THE READING YOU NEED TO TAKE ON AN UPRIGHT STAFF AS
THE REQUIRED LEVEL IS BELOW COLLIMATION (IF THE REQUIRED
LEVEL WAS ABOVE COLLIMATION THE STAFF WOULD BE INVERTED).
PUT THE STAFF ON THE COLUMN AND SLIDE IT UP OR DOWN UNTIL
YOU READ 200mm MARK THE BOTTOM OF THE STAFF - THIS MARK IS
YOUR REQUIRED LEVEL OF 96.500m. EXTEND THE MARK FULL WIDTH
OF THE COLUMN USING A SPIRIT LEVEL AND CLEARLY WRITE ABOVE
THE LINE WHAT IT REPRESENTS i.e. FFL + 1m (96.500m).
AN ALTERNATIVE METHOD WOULD BE TO MARK THE COLLIMATION
LEVEL DIRECTLY ONTO THE COLUMN BY MOVING A PENCIL UP OR
DOWN UNTIL IT CORRESPONDS WITH THE HORIZONTAL CROSSHAIRS
ON THE DUMPY. THE REQUIRED LEVEL IS THEN MEASURED FROM THIS
MARK WITH A TAPE MEASURE.
LEVEL BOOK 1
Date.
From.
BACK
SIGHT
INTERMEDIATE
FORE
SIGHT
COLLIMATION
OR H.P.C.
REDUCED LEVEL
To
DISTANCE
REMARKS
The level book is where the S.O. engineer records all measurements taken on site.
Contrary to its name it also used to hold setting out information that has been
transferred from the site drawings.
The most important aspect in using the level book is filling in the top line not only
does this make sense of all the figures entered below but also acts as a diary of all
operations that have occurred on site.
The FROM-TO lines can give additional location information but are not essential.
To use the book for levelling your first entry will be the top left cell under the
heading BACKSIGHT
This is the first time that you will look through the level and observe a reading on
the staff. The second entry will still be on the first line under the heading
REDUCED LEVEL this is not an observed reading, but a known level on which
the staff is being held, the value may come from the site drawings or from
previously calculated data from your book. The third entry on the first line is under
the heading COLLIMATION OR H.P.C. ( Height of Plane of Collimation) and is
the addition of your first two entries.
LEVEL BOOK 2
Date.
From.
BACK
SIGHT
INTERMEDIATE
FORE
SIGHT
COLLIMATION
OR H.P.C.
REDUCED LEVEL
To
DISTANCE
REMARKS
You are now ready to move the staff to a new location wherever a level is to be
determined.
The staff is held at the new location and the instrument is turned to take the reading on
the staff. This reading is now entered on the second line under the heading INTERMEDIATE. You will then enter under the REMARKS column (on the same line) the
staff location at your reading e.g. concrete slab level at Grid line B/4.
The above procedure is repeated for all new locations and the corresponding readings
entered on a separate line of the book together with an entry in the REMARKS
column.
REMEMBER EACH NEW READING = NEW LINE OF BOOK
When you have finished taking all your readings there are 3 options open to you:
1/ Pack up the instrument and calculate the levels you have taken.
2/ RECOMMENDED ; Put the staff back on the original position that you first
started with and take a new reading this should be entered on the next line
under FORESIGHT. (This basically checks that the instrument has remained
level throughout your readings i.e. the FORESIGHT READING SHOULD BE
THE SAME AS YOUR BACKSIGHT READING 1 to 2mm.) You can then
pack up the instrument and calculate the levels you have taken.
3/ If you need to move the instrument to a new location and cannot use your
original level datum location (your initial BACKSIGHT) you can create a
CHANGE POINT. Put the staff on any desired location that is solid and
identifiable and enter the reading under the column FORESIGHT not forgetting
to enter the location of the reading under the REMARKS column highlighting that
this point is a change point (C.P.) You are now in a position to move your
instrument to a new location and use the change point as a new backsight.
LEVEL BOOK 3
Date.
From.
BACK
SIGHT
INTERMEDIATE
FORE
SIGHT
COLLIMATION
OR H.P.C.
REDUCED LEVEL
To
DISTANCE
REMARKS
EXTERNAL WORKS 1
MOST EXTERNAL WORKS ARE DESIGNED TO A FALL - SLOPE GRADIENT BECAUSE THE MAIN CONSIDERATION IS THE TRANSFER
OF WATER.
GOOD DESIGN
BAD DESIGN
WATER MOVES PROPORTIONALLY TO THE ANGLE OF THE SLOPE
QUICKER
SLOWER
1- TWO LEVELS
PLUS A DISTANCE
(HD or SD)
90.000m
SD
80.000m
HD
EXTERNAL WORKS 2
2- ONE LEVEL
PLUS A (HD or SD)
PLUS A GRADIENT
90.000m
SD
1 in 40
VD
HD
HD
HD
WHAT IS A GRADIENT ?
1 in 40 - THE VD IS 1m WHEN THE HD IS 40m or THE VD IS 0.5m WHEN THE
HD IS 20m etc.
% - THE VD DIVIDED BY HD x 100
.
HOW TO CALCULATE A GRADIENT
1- TWO LEVELS
PLUS A DISTANCE
(HD or SD)
90.000m
VD =10.000m
80.000m
CALCULATED
HD =60.000m
FROM THE ABOVE DIAGRAM
DIVIDE TOP AND BOTTOM OF EQUATION BY VD
TO GET THE 1 IN X
VD = 10 = 10 / 10 = 1 = 1 IN 6
HD 60
60 / 10 6
EXTERNAL WORKS 3
2- ONE LEVEL
PLUS A (HD or SD)
PLUS A GRADIENT
92.000m
1 in 80
HD
HD
HD = 50.000m
TO FIND LEVEL Z
YOU ARE REDUCING LEVEL AT A
RATE OF 1m EVERY 80m
THEREFORE THE REDUCTION IN LEVEL ON THE ABOVE EXAMPLE
IS:
1 DIVIDED BY 80 = 0.0125m
THIS IS THE
x 50 METRES = 0.625 m
VD =0.625m
CALCULATED
CALCULATED
91.375m
HD = 50.000m
EXTERNAL WORKS 4
TO GET THE 1 IN X
TO CONVERT 1 IN 80 TO %
? m
VD
94.000m
HD
16m
4m
EXTERNAL WORKS 5
DRAINAGE
DIG WIDTH
PIPE DIAMETER
PIPE THICKNESS
INVERT LEVEL
PIPE
BEDDING
SECTION
PLAN
EXTERNAL WORKS 6
SETTING OUT DRAIN RUNS
Manhole
areofnormally
and can
be scaled
from
theset
drawing
and
set out to positions
a tolerance
approx non
300critical
mm. Some
manholes
have
to be
out more
accurately where their location is close to other structural elements of the works.
Example kerbs, between two buildings close together, all internal manholes.
Position both manholes each end of a drain run taking consideration of the above a
pin / peg driven into the ground to mark each manhole. A string line attached to both
these pins/pegs is then spray-painted to indicate the centre of the dig - you will have
to tell the digger driver the dig width so that he can attach the correct excavating
bucket to his machine.
CONTROLLING DRAIN LEVELS
MIN REQUIREMENT IS A PROFILE AT EACH MANHOLE
PLAN
offset
Profiles
SECTION
TRAVELLER
PIPE BEDDING
88 m
DIG LEVEL
EXTERNAL WORKS 7
PROBLEM
SET OUT 5 PROFILE BOARDS AT 22m SPACINGS THE PIPE THICKNESS IS
20mm THE PIPE BEDDING IS TO BE 150mm DEEP
MH SW63 I.L 67.900 m
SECTION
TRAVELLER
FOR DIG
PIPE BEDDING
DIG LEVEL
88 m
70.200
22m
22m
70.200
70.250
22m
22m
68.330m
DIG LEVEL
67.730m
DIG LEVEL
EXTERNAL WORKS 8
EXTERNAL WORKS 9
SETTING OUT KERBS
TOP OF KERB (TOK) IS HOW YOU CONTROL THE HEIGHT OF THE
KERB
FACE OF KERB
NORMALLY 125 mm
FOF THE ENKA COURSE THE SITE DRAWINGS
AS:
TOP OF KERB (TOK)
125mm
FINISHED ROAD LEVEL (FRL)
ARE SPECIFIED
KERB RADIUS
RADIUS POINT
T.P
T.P
TANGENT POINTS (i.e. T.P) ARE WHERE THE STRAIGHT LINE STARTS TO
TURN INTO A CURVE YOU MUST HAVE THE COORDINATES OF POINTS.
PINS MUST BE SET OUT AT THESE POINTS. TANGENT POINTS ARE AT 90
FROM THE STRAIGHT LINES TO THE RADIUS POINT.
EXTERNAL WORKS 10
KERB RADIUS CONTINUED
RADIUS =80m
POGO
ERRORS 1
ALL SETTING OUT ENGINEERS WILL MAKE MISTAKES WE ARE
HUMAN SOME ENGINEERS THINK THEY ARE FROM A DIFFERENT
PLANET AND NEVER MAKE A MISTAKE BELIEVE THEM IF THEY
ARE GREEN AND HAVE POINTED EARS !
BECAUSE WE ARE GOING TO MAKE MISTAKES WE CAN ENSURE THAT IF
WE SET OUT WRONGLY IT CAN BE PUT RIGHT BUT WHEN?
EVERYTHING YOU SET OUT ON SITE WILL BE CONSTRUCTED VERY
QUICKLY - BUT YOU MAY HAVE THE OPPORTUNITY TO DOUBLE.
CHECK YOUR SETTING OUT BEFORE THIS PROCESS BEGINS.
THIS IS THE TIME TO DOUBLE CHECK YOUR SETTING OUT.
FROM ALL ASPECTS: EDM INITIAL SET UP - HAVE I USED THE CORRECT STATION
AND BACKSIGHT POINT?
DID I SIGHT THE BACKSIGHT ACCURATELY ?
HAVE I READ THE SETTING OUT BEARING CORRECTLY ?
HAVE I READ THE SETTING OUT DISTANCE CORRECTLY ?
DUMPY AM I USING THE CORRECT TBM ?
HAVE I READ THE STAFF READINGS CORRECTLY ?
HAS THE DUMPY BEEN DISTURBED WHILST IV`E BEEN TAKING
STAFF READINGS ?
CASIO CALCULATOR DID I PUNCH IN THE CORRECT VALUES INTO
THE CALCULATOR.
ERRORS 2
COMMON SENSE
AM I USING THE LATEST REVISION OF THE SITE DRAWING?
HAVE I DOUBLE CHECKED THE SITE DRAWINGS AND
TRANSFERRED THE INFORMATION CORRECTLY TO MY LEVEL
BOOK?
DID I SET OUT BACK OF KERB & TOP OF KERB ?
HAVE I COMMUNICATED WITH THE TRADESMAN PROPERLY
AND GIVEN THEM THE LINE OR LEVEL THEY REQUIRED ?
HAVE I GIVEN THE CORRECT TRAVELLER ?
DIMENSIONAL CHECKS
IF YOU ARE SETTING OUT A SQUARE OR RECTANGLE
MEASURE BETWEEN THE POINTS YOU HAVE SET OUT
TO CONFIRM THE SQUARENESS.
CHECK DIAGONALS.
VISUAL CHECKS
LOOK ALONG THE PINS YOU HAVE JUST SET OUT FOR A KERB
LINE DO THE TOP OF TAPES THAT YOU HAVE ESTABLISHED
AS BEING TOP OF KERB LINE IN THE SAME APPLIES FOR
PROFILES.
LOOK AT WHAT YOU HAVE JUST SET OUT DOES IT RELATE
TO OTHER SITE FEATURES - CHECK MEASUREMENTS FROM
EXISTING COLUMNS, EDGE OF SLAB ETC. ?
LOOK AT WHAT YOU HAVE JUST SET OUT DOES IT RELATE
TO SITE BOUNDARIES
- USE A SCALE RULE ON THE SITE
DRAWINGS AND COMPARE TO ACTUAL
MEASURED
DISTANCES .
ERRORS 3
TOLERANCES
EVERY ELEMENT OF THE CONSTRUCTION PROCESS REQUIRES
A DIFFERING AMOUNT OF ACCURACY ON THE INITIAL
SETTING OUT.
A SPECIFICATION DOCUMENT
ON EVERY SITE THERE WILL BE ONE OF THESE
THAT WILL TELL YOU THE REQUIREMENTS FOR SETTING OUT
ACCURACY.
ERRORS 4
INSTRUMENT CHECKS
30M
15M
5M
TAKE ACCURATE STAFF READINGS ON POINTS A & C WORK
OUT THE DIFFERENCE BETWEEN THESE READINGS VALUE Y.
ERRORS 5
PROBLEM SHEET 1
A
5.346 m
12.782m
Angle
PROBLEM SHEET 2
EXISTING
BRICK WALLS
THE BRICKLAYER
REQUIRES THIS MARK ON
THE FACE OF THE WALL
5.4 m
START POSITION
OF NEW WALL
PROBLEM SHEET 3
0 MARK
8 mm
NAIL
END RING
YOU WANT TO SET OUT A NEW NAIL AT 5.76m FROM THE NAIL
FEATURED ABOVE - THE TAPE IS HOOKED ON THE NAIL ABOVE
WHAT READING ON THE TAPE DO YOU PUT YOUR NEW NAIL AT ?
100 mm
END RING
NAIL
0 MARK
8 mm
NAIL
END RING
YOU WANT TO SET OUT A NEW NAIL AT 49.9m FROM THE NAIL
FEATURED ABOVE - THE TAPE IS HOOKED ON THE NAIL ABOVE
WHAT READING ON THE TAPE DO YOU PUT YOUR NEW NAIL AT WHEN
THE AMBIENT TEMPERATURE IS 0 ?
PROBLEM SHEET 4
LOCAL COORDINATES
3
12.250m
FACE OF BRICKWORK
NORTH
6
23.500m
1000.000 E
500.000N
PROBLEM SHEET 5
YOU WILL BE CONTROLLING THIS STRUCTURE WITH THE EDM SET
UP OVER A CONTROL STATION 2 ( 1090.480 E, 568.789 N ).
HOW WOULD YOU SET OUT ABC,D FROM STATION 2
37.250
A
A=1105.193E, 560.000N
C=1105.193E, 550.000N
E
7.2m
B
7.2m
A
4.8m
F
6.8m
1034.560 E
567.545 N
3.4m
12.5m
PROBLEM SHEET 6
GLOBAL COORDINATES
98.500m
98.500m
1245.354 E
567.896 N
L
1378.941E
489.535N
PROBLEM SHEET 7
107.645m
106.985m
38.345 m
WHAT IS THE FALL PER METRE ON THE ABOVE SLOPE ?
102.823m
A
B
41
99.150m
41.205m
58.437m
149.632 m
PROBLEM SHEET 8
4.869m
4.600m
4.780m
A
120.560 TOK
C
D
4.450m
E
119.270 TOK
TBM = 120.500
PUTTING THE STAFF ON TOP OF THE FIVE PINS YOU OBTAIN THE
FOLLOWING STAFF READINGS:A = 1.653m
B = 1.528m
C = 1.579m
D = 1.498m
E = 1.640m
FOR A TO E - WHAT IS THE DISTANCE DOWN FROM TOP OF PIN TO
THE CORRESPONDING TOK LEVEL?
PROBLEM SHEET 9
SWMH 124
450 FALL 1 IN 120
106.670m
PROBLEM SHEET 10
SWMH 124 IL. 45 .870
A
THE EDM IS SET UP OVER
STN 4 - 1090.679 E
571.879
300
FALL 1 IN 150
SWMH 126
SWMH 125
E
450 FALL 1 IN 120
C
450 1 IN 100
SW 124
SW125
SW126
SW127
1089.090E 567.980 N
1077.470E 589.785 N
1081.208E 608.600 N
1065.453E 605.650 N
PROBLEM SHEET 11
A CONCRETE SLAB IS TO BE CONSTRUCTED AROUND A BUILDING
(GREY SHADED AREA).
THE ARCHITECT REQUIRES THE SLAB TO FALL AWAY FROM THE
BUILDING, WITH A TOTAL FALL OF 36mm REQUIRED AT THE
OUTSIDE EDGE. THE SLAB LEVEL ADJACENT THE BUILDING IS
78.600m.
PINS HAVE BEEN SET OUT AT POINTS A TO M
2.65m
A
3.760m
B
2.5m
M
F
1.8m
PROBLEM SHEET 12
THE FOLLOWING GRIDS HAVE NOT BEEN DRAWN TO SCALE AND
THEREFORE YOUR ANSWER IS BASED ON YOUR KNOWLEDGE OF
COORDINATES AND BEARINGS ONLY.
A = 1205.000 E
563.500 N
B = 1467.200 E
456.400 N
INDICATE WHERE
NORTH IS ON THE GRID ?
A
C = 47295.000 E
56583.500 N
C (EDM)
D = 47237.200 E
56796.400 N
THE EDM IS SET UP ON C A ND
HAS BEEN BACKSIGHTED TO D
D
THE EDM HAS BEEN TURNED
AND IS NOW DISPLAYING A
HORIZONTAL BEARING OF 270 00'00"
INDICATE WHERE THE EDM POINTING ON THE GRID ?
APPROXIMATELY INDICATE
WHERE NORTH IS ?
STN 6 = 245678.975 E
187964.674 N
STN 7 = 245618.653 E
187842.754 N
STN 6
STN 7
FORMING A RIGHT-ANGLE
3M
5M
4M
90 can be set out using tapes and string lines in the proportion of the 3-4-5
PYTHAGORAS TRIANGLE. Any proportion will work e.g. 18(3x6),
24(4x6),30(5x6) or
1.5(3/2),2(4/2),2.5(5/2) the selected scale used is determined by the size of the area
available.
`
C
A
If A must be between 500mm and 700mm and B can be any length what
suitable lengths of a 3-4-5 triangle would you use to form the right angle ?
8m
20m
To set out the above rectangle given AB we will use a 9-12-15m scale.
X
1m
Cc
E
15m
9m
9m
12m
Measure 12m along BA and mark Y. Measure 9m from B and scribe an arc.
Measure 15m from Y and scribe another arc- the intersection of these arcs
is X. String a line between X and B. Measure 1m from X towards B and
mark C.
Point E on the rectangle is achieved in the same way from A (the triangle
being handed).
There is a quicker method of forming the above rectangle using the
PYTHAGORAS THEOREM D = L + H
C
D
H
B
L
Try to set out the 8m x 20m rectangle ABCE using this method..
E
D
H
B
A
L
D = L + H
D = 20 + 8
D = 400 + 64
D = 464
D = 21.541m (This is not only the distance between AC but also between
BE)
You can now set out point C by measuring 8 m from B and 21.541 m from A
E by measuring either 21.541 from B and 8 m
from A
or by measuring 20 m from C and 8 m from A.
Setting out a rectangle with an E.D.M.
To set out the above rectangle you could set up the EDM on point A sight
B turn 90 and measure 8m to establish E. Then set up on point B sight
A turn 90 and measure 8m to establish C. However a more efficient
method would be to establish C & E from ONE set up of the EDM.
A
L
= Opposite(H)
Adjacent(L)
Tan
=8
20
= 21.801 or 21 48 04
So now the EDM is set up on point A sighting B at 0 00 00 - the
instrument is then turned to read 21 48 04 and at a distance of 21.541m
- point C is established. The EDM is then turned to read 90 00 00 and at
8m - Point E is established.
5m
C
The
EDM
sighting
pointisB set
at 0 up
00 on
00 .point A What angle and at what distance
should point C be set out to ?
Offset Distance
Whenever a building is set out - the initial setting out lines are very quickly destroyed
by the building process and therefore it is necessary to establish offset points so that
control can be re-established at any time.
The engineer must decide on a suitable offset distance that will be clear of excavators
and general access to the building process.
In this example a nail has been put on the offset board to correspond with the grid line
given on the site drawings but additional marks on the board can represent other
required lines that are required during the building process.
Face of cladding
GRID LINE
COORDINATES 1
THE GRID
Coordinates
areeach
a numerical
lines that cross
other at value
90 . given to a grid intersection. A grid is a number of
THIS IS A
HORIZONTAL
GRID LINE
THIS IS A
VERTICAL GRID
LINE
When these vertical and horizontal grid lines are given values then the grid
intersection points will have a vertical value and a horizontal value.
300
The grid intersection
Value of this point is
50 vertical and 200
Horizontal.
200
100
25
50
75
COORDINATES 2
NORTH
300
NORTHINGS
COORDINATE
200
EAST
EASTINGS
100
25
50
75
We can now change the descriptions of the grid that were given on the previous page
to:
A VERTICAL GRID LINE = AN EASTING
A HORIZONTAL GRID LINE = A NORTHING
A GRID INTERSECTION POINT = A SET OF COORDINATES
Therefore:
These COORDINATES for the point shown above are 50 EASTINGS ,200
NORTHINGS.
THIS SET OF COORDINATES CAN BE SIMPLIFIED TO 50 E, 200 N.
** ALWAYS REMEMBER **
A NORTHING IS A LINE RUNNING EAST WEST
AN EASTING IS A LINE RUNNING NORTH- SOUTH
A NORTHING VALUE INCREASES TO THE NORTH
AN EASTING VALUE INCREASES TO THE EAST
COORDINATES 3
500 m
600m
The land Surveyor has measured the approximate overall size of the land and
accordingly has decided the values in metres that the grid should cover (the scale of
the map). The land Surveyor now decides the orientation of the grid:
N?
N?
NORTH can be related to magnetic North, National Grid North and indeed could be
decided by the shape of the land and how it fits on a drawing.
COORDINATES 4
Once North has been decided the Land surveyor lays out a grid in this example the
grid SIZE is 100m. Because NORTH is arbitrary in this example the Land Surveyor
can choose where the ORIGIN of the grid lies i.e. THE COORDINATE 0 E , 0 N.
The ORIGIN (Point A) should always lie in the SW corner of the grid so that all
Eastings and Northings are POSITIVE on site.
B
NORTH
400m N
300 N
C
200 N
D
100 N
0N
A
0E
100 E
200 E
300 E
400 E
500m E
The land Surveyor now establishes CONTROL STATIONS on site at B,C & D.
COORDINATES 5
NORTH
400m N
300 N
Y
200 N
X
100 N
0N
0E
100 E
200 E
300 E
400 E
500m E
The architect has now positioned the proposed building and has issued the coordinates
of two corners of the building X and Y.
COORDINATES 6
STATION FENCED
OFF
STATION REF.
600mm Sq CONCRETE
BLOCK
- WOODEN PEGS
COORDINATES 7
SMALL PROJECTS
Sometimes there are no control stations instead the architect has controlled the new
works from existing buildings and or features you would then set up your own
coordinate system.
SEE COORDINATE SHEET 10
EXISTING BUILDINGS
15m
6m
ROAD
Whatever type of Primary control stations you encounter -the first thing you must do
is check their accuracy and inform your superior if you find an error (double check
your calculations before doing this).
SEE ERRORS
COORDINATES 8
REMEMBER
EDM SET UP ON
BACKSIGHT
ACCURACY
PRIMARY
PRIMARY
BEST
SECONDARY
PRIMARY
GOOD
SECONDARY
SECONDARY
TEMPORARY
SECONDARY
POOR
TEMPORARY
TEMPORARY
WORST
AVERAGE
SECONDARY
STATIONS SET
BY PRIMARY
TEMPORARY
STATIONS SET
BY SECONDARY
COORDINATES 9
POINT B
POINT A
EDM SET UP ON STN 37
STN 37 =235.700 E, 100.000 N
THE EDM IS SIGHTING POINT A AT A BEARING OF 285 34 23 AND AT
A DISTANCE OF 56. 675 m.
THE EDM IS SIGHTING POINT B AT A BEARING OF 345 38 56 AND AT
A DISTANCE OF 27.468 m.
COORDINATES OF A = .E .N
COORDINATES OF B = ..E ...N
GLOBAL
LOCAL
COORDINATES 10
COORDINATED SETTING-OUT
THE KEY TO COORDINATED SETTING-OUT IS BEING ABLE TO
FULLY COORDINATE YOUR EDM AND BEING ABLE TO READ
COORDINATES DIRECTLY FROM THE EDM SCREEN.
COORDINATES 11
N
1.450m
200mm
EDM ( FULLY COORDINATED)
1067.870 m
579.987 m
198.98 m