Professional Documents
Culture Documents
Question 1: Develop a minimum cost production schedule using the transportation optimization
model without and with the Guadalajara facility based on five-year forecasts.
If we consider 4 current production facilities & 6 distribution centers based on the 5 year demand
forecast, production costs, and transportation costs we can calculate minimum cost that is
incurred
Demand over 5 years = 8000 Cartons
Supply Capacity =10000 Cartons
Toronto K.C.
L.A.
Seattle
Chicago Atlanta Supply
Toronto
0.75
2.5
4.5
4.75
1.5
3
2500
K.C.
2.5
1
2.5
2.75
1.5
2.25
1500
L.A.
4.5
2.5
0.5
2.25
3.75
3
3500
Seattle
4.75
2.75
2.25
0.75
2.5
3.5
2500
Demand
1000
750
2500
1500
1500
750
Toronto
K.C.
0.75X1000
1X750
L.A.
Seattle
Chicago
Atlanta
1.5X1500
0.5X2500
3X750
0.75X1500
Toronto
K.C.
14.75X1000
19X750
L.A.
Seattle
13.5X2500
Chicago
Atlanta
15.5X1500
16X750
17.75X1500
Plant Utilization
Toronto
K.C.
L.A.
Seattle
Plant
Supply
Production Utilization
2500
2500
100%
1500
750
50%
3500
3250
93%
2500
1500
60%
If we consider new production facility & distribution center based on the 5 year demand forecast,
production costs, and transportation costs we can calculate minimum cost that is incurred
Demand over 5 years = 10000 Cartons
Supply Capacity =14000 Cartons
Toronto K.C.
L.A.
Seattle
Chicago Atlanta Guadalajara Supply
Toronto
0.75
2.5
4.5
4.75
1.5
3
5.25
2500
K.C.
2.5
1
2.5
2.75
1.5
2.25
3.25
1500
L.A.
4.5
2.5
0.5
2.25
3.75
3
1.75
3500
Seattle
4.75
2.75
2.25
0.75
2.5
3.5
3.75
2500
Guadalajara
5.25
3.25
1.75
2.5
3.75
3.5
0.5
4000
Demand
1000
750
2500
1500
1500
750
2000
L.A.
Seattle
0
0
0
0
0 0.5X2500
0
0
0 0.75X1500
0
0
0
14.75X1000
0
0
0
0 17X750
0
0 19X750
0
0 20.5X750
0
0
0
0 13.5X2500
0
0
0
0
0
0
17.75X1500
0
0
0
0
0
0 19.5X750
0 10.5X2000
0
0
0
0
0
0
0
0
1000
1000
2000
0
Plant
Production Utilization
1750
70%
1500
100%
2500
71%
2250
90%
2000
50%
Question 2: Report the utilization levels by plant without and with the Guadalajara facility at years
five and 10.
If we consider 4 current production facilities & 6 distribution centers based on the 10 year demand
forecast, production costs, and transportation costs we can calculate minimum cost that is
incurred
Demand over 5 years = 10000 Cartons
Supply Capacity =10000 Cartons
Toronto K.C.
L.A.
Seattle
Chicago Atlanta Supply
Toronto
0.75
2.5
4.5
4.75
1.5
3
2500
K.C.
2.5
1
2.5
2.75
1.5
2.25
1500
L.A.
4.5
2.5
0.5
2.25
3.75
3
3500
Seattle
4.75
2.75
2.25
0.75
2.5
3.5
2500
Demand
1000
1000
3000
2000
2000
1000
Toronto
Toronto
K.C.
L.A.
Seattle
0.75X1000
Chicago
Atlanta
Supply
1.5X1500
K.C.
1X1000
L.A.
1.5X500
0.5X3000
Seattle
3X500
0.75X2000
3.5X500
K.C.
L.A.
Seattle
14.75X1000
K.C.
Supply
20.5X500
13.5X3000
Seattle
Atlanta
15.5X1500
19X1000
L.A.
Chicago
16X500
17.75X2000
20.5X500
2500
1500
3500
2500
Plant
Production Utilization
2500
100%
1500
100%
3500
100%
2500
100%
Considering maintenance cost there plant would not be running on 100% utilization levels. Thus
without the new facility we would be losing out on sales
If we consider new production facility & distribution center based on the 10 year demand forecast,
production costs, and transportation costs we can calculate minimum cost that is incurred
Demand over 10 years = 13000 Cartons
Supply Capacity =14000 Cartons
Toronto K.C.
L.A.
Seattle
Chicago Atlanta Guadalajara Supply
Toronto
0.75
2.5
4.5
4.75
1.5
3
5.25
2500
K.C.
2.5
1
2.5
2.75
1.5
2.25
3.25
1500
L.A.
4.5
2.5
0.5
2.25
3.75
3
1.75
3500
Seattle
4.75
2.75
2.25
0.75
2.5
3.5
3.75
2500
Guadalajara
5.25
3.25
1.75
2.5
3.75
3.5
0.5
4000
Demand
1000
1000
3000
2000
2000
1000
3000
K.C.
L.A.
Seattle
0.75X1000
K.C.
Chicago
Atlanta
Guadalajara
1.5X1500
1X1000
L.A.
1.5X500
0.5X3000
Seattle
3X500
0.75X2000
3.5X500
Guadalajara
3.5
0.5X3000
K.C.
L.A.
Seattle
14.75X100
0
K.C.
L.A.
Seattle
Guadalajar
a
Plant Utilization
Chicago
Atlanta
Guadalajar
a
15.5X150
0
19X100
0
20.5X500
13.5X300
0
16X500
17.75X200
0
20.5X50
0
10.5X3000
Supply
Production Utilization
Toronto
2500
2500
100%
K.C.
1500
1500
100%
L.A.
3500
3500
100%
Seattle
2500
2500
100%
Guadalajara
4000
3000
75%
Question 3: Use the difference in annualized system costs to perform a net present value analysis
using the planning parameters outlined in the case.
Cost
5 yr with
Guadalajara
5 yr w/o
Guadalajara
10 yr with
Guadalajara
10 yr w/o
Guadalajara
Annual
Cost
124625
45488125
153125
55890625
155500
56757500
193000
70445000
Cost
Difference
10402500
13687500
Year
4
5
6
7
8
9
10
Demand Forecast
9400
10000
10600
11200
11800
12400
13000
Annual cost
difference
-0.77
3.33
-0.77
-4.87
-8.97
-13.07
-17.17
Net
Avg
Margin
Additional Additional
cost/
over
unit sold
Profit/
unit
COGS
over 9000 day
$13.55
15%
400
$5,421
$13.78
15%
1000
$13,780
$14.01
15%
1600
$22,413
$14.24
15%
2200
$31,319
$14.46
15%
2800
$40,499
$14.69
15%
3400
$49,953
$14.92
15%
4000
$59,680
Annual
additional
profit(in $
Million)
$2.37
$6.04
$9.82
$13.72
$17.74
$21.88
$26.14
It is assumed that construction would start by 2nd year and it would end by 4th year. SO based on
this we are calculating NPV.
NPV = 25.551%
Question 5: Determine the internal rate of return for the project.
It is assumed that construction would start by 2nd year and it would end by 4th year. SO based on
this we are calculating IRR.
IRR =11.29%
Calculations
Considering initial investment of new plant $30 million, Discount factor =10%
Operational Year
10
Capital
Expenditure
-30
Annual Sales
Revenue
2.37
6.04
9.82
13.72 17.74
21.88 26.14
-30
2.37
6.04
9.82
13.72 17.74
21.88 26.14
Hurdle Rate
0.91
0.83
0.75
0.68
0.62
0.56
0.51
PV
-30
1.96
4.53
6.71
8.52
10.01
11.23 12.19
25.155
11.3%
Question 6: Provide the rationale for when the new plant should be constructed.
0.47
Looking at utilization capacity of all the plants with and without new facility we can find
out that if we do not go for a new plant then we would be losing out on a lot of demand.
Around 3000 cartons demand would be lost over 10 year period.
IRR > Hurdle Rate
Also as IRR is greater than Discount Rate (Hurdle Rate) 10% hence it would be profitable