Professional Documents
Culture Documents
CHAPTER-IV
WORKS EXPENDITURE
SECTION-B
(AUDIT PARAGRAPHS)
IRRIGATION, POWER,
ROADS AND BRIDGES AND
PUBLIC HEALTH AND ENGINEERING DEPARTMENT
4.2
Stone
chips
(Stone metal)
Soling stone /
Boulder
MOST (IRC)
Specification
Not specified
CPWD
Specification
20%
Norms fixed by
other States
Not known
Remarks
Below 40 mm Nil
From 40 mm to
below 100 mm
7.5%
Jharkhand MOST
specification
Meghalaya 5 to
10%
West Bengal
14.28%
Nagaland 15%
4.2.2 While other state governments have adopted the norms towards
reduction of volume during measurement in the line of norms specified by the
85
CPWD and MOST, the Government of Sikkim although a member of the IRC,
has not adopted the same as yet. Therefore, no works department in the State
is reducing the volume towards void in stacking while measuring and
releasing the payment on procurement of earth/stone, etc.
4.2.3 Scrutiny of measurement books and contingent vouchers pertaining to
procurement of stone for use in different departmental works (except in
respect of Power department where stones were purchased and payments made
for clearance of slips/earth in respect of works executed by contractors)
revealed that during measurement, no void was deducted from the volume of
stones supplied/purchased and slips/earth cleared, resulting in total excess
payment to different suppliers/contractors to the tune of Rs.56.72 lakh during
the period October 1997 to March 2002 for execution of works. The details of
such excess payments were as under:
Table 4.11
Sl.
No
department
IRRIGATION
ROADS AND
BRIDGES
PUBLIC HEALTH
ENGINEERING
DEPARTMENT
POWER
Period
12/2000 to
10/ 2001
10/1997 to
9/2001
8/1998 to
3/2002
11/2000
Quantity
purchased/supplied
(cu.m.)
Stone 45594.79
115.79
Percentage
required to be
deducted towards
void
15
Stone 66533.54
142.26
15
21.34
Stone - 7625.24
23.00
15
3.45
Stone - 35683.40
Earth - 256870.38
25.29
53.83
15
20
3.79
10.77
56.72
Total
Amount
paid
(Rs.in lakh)
Excess
payment
(Rs.in lakh)
17.37
86
POWER DEPARTMENT
4.3
87
4.4
88
4.5
4.6
PHE
R&B
Total
Quantity of stone
purchased
(in cubic metres)
7625.24
66533.54
74158.78
Amount
actually
paid
23.00
142.26
165.26
Cost of stone
calculated at SOR1998
(Rupees in lakh)
7.07
61.68
68.75
Excess
payment
15.93
80.58
96.51
4.6.3 Further as per the analysis of rate, the cost of stone is made up of only
two elements, namely, labour cost and royalty. Therefore, cost of stone,
exclusive of carriage, cannot vary from place to place in the State as wage
rates and rate of royalty are uniform throughout the State.
4.6.4 The departments stated (March and September 2002) that the rates
were inclusive of carriage and therefore these were higher than the SOR. The
reply of the departments is not acceptable as:
i.
Sales Tax at 8 per cent was paid by the departments on the total
amount of the individual bills, which proves the fact that there was
no carriage component.
90
ii.
4.7
91
Table 4.13
Year
1997-98
*Lab Sup
1808
908
Men-in-position
(Nos.)
Requirement as
533
71
per MOST
norms (Nos.)
Excess (Nos.)
1275
837
Total road
1775.35
length (Km.)
Total avoidable
311.41
expenditure
(Lab+Sup)
(Rs.in lakh)
*Lab: Labour; Sup: Supervisor
1998-99
Lab
Sup
1830
958
1999-00
Lab
Sup
1886
1152
2000-01
Lab
Sup
1949
1287
528
533
557
70
71
74
1302
888
1760.35
1353
1081
1776.35
1392
1213
1857.45
322.98
360.29
384.76
92
4.8
93
URBAN DEVELOPMENT
AND HOUSING DEPARTMENT
4.9
4.9.1 The State Government approved (July 1997) a proposal to acquire land
at Dumra Busty, South Sikkim for setting up a rural marketing centre to
improve the economic condition of the rural cultivators and also a satellite
township to ease the growing pressure on Namchi town. Accordingly, land
measuring 34.5480 hectares was earmarked for the purpose for acquisition by
the Urban Development and Housing department (UDHD).
4.9.2 During August 1997, UDHD acquired 15.71 hectares of land at a cost
of Rs.31.12 lakh. Thereafter, there was no evidence of any progress till
December 1998, when a meeting was convened by the Chief Secretary to
discuss the project. As a follow up to the meeting, the Commissioner-cumSecretary, UDHD initiated action (December 1998) to find out the size of
adjacent land - government as well as private, which would be required for
acquisition in addition to the land acquired earlier, for establishment of the
proposed township. Despite the survey of 60 acres of land in the area during
January / March 1999 by a Kolkata based firm engaged by the department at a
cost of Rs.1.64 lakh, there was no further acquisition of land and the project
was completely stalled since August 1997.
4.9.3 Thus, the intention of the Government to provide the rural cultivators
with a marketing facility as well as establishment of a satellite township had
not fructified due to poor follow up action by the department. This not only
led to blocking of Government funds of Rs.31.12 lakh for a period of four and
a half years, but also cost the exchequer Rs.17.48 lakh on account of
opportunity cost of borrowing, calculated at the average rate of interest
applicable during the period.
4.9.4 In reply, the Commissioner-cum-Secretary, UDHD while admitting the
delay in taking up follow-up action, stated (May 2002) that the land had been
acquired as a matter of policy directive and strategic planning and as the
Government ultimately stood to gain from the acquisition due to the scarcity
and increase in value of land. The delay in implementation of the project due
to non-acquisition of more land was attributed to frequent transfer of officers.
94
4.9.5 The reply of the department was not tenable as the land was acquired
with the objective of establishing a marketing centre for rural cultivators
which had not materialised so far.
4.10
The benefits derived after spending Rs.77.68 lakh under the EIUS Scheme
during 1998-99 to 2001-02 (upto December 2001) were uncertain and
achievements reported to the Central Government were wrong.
4.10.1 Mention was made in para 3.9.8(a) of the Audit Report 1997-98 about
expenditure of Rs.41.27 lakh incurred by the Urban Development and Housing
department (UDHD) under the programme Environmental Improvement of
Urban Slums (EIUS) during 1993-98 without conducting any survey to
identify slum areas and the basic amenities to be provided to the slum
dwellers. A substantial amount was spent on developed areas of Gangtok,
which was also not in accordance with the programme objectives. In its
submission to the PAC, the department stated (June 2000) that the works had
been executed mostly in slum areas and a detailed survey had also been taken
up which was almost complete. In view of this reply, the PAC made no
recommendations.
4.10.2 Audit of the UDHD during January 2002 disclosed that no such survey
to identify slum areas and the basic amenities to be provided to slum dwellers
was conducted by the department. To a specific request (June 2002) by the
Accountant General for a copy of the Survey Report, the Commissioner-cumSecretary replied (June 2002) that the survey taken up by the department to
identify families living below the poverty line (BPL) was abandoned due to a
similar exercise being undertaken by the Planning and Development
department (PDD). It was not clear to Audit how a BPL survey conducted by
the PDD would serve the purpose of the UDHD for undertaking
environmental improvement of urban slums.
4.10.3 Scrutiny of records further revealed that the department persisted with
undertaking projects in developed areas of the State, which was not the
objective of the EIUS programme. These projects, such as, protective works,
throwing of spoils, construction of footpath and drainage, etc. were also not
covered by the programme. In the absence of any master/perspective plans,
the department took up these works in an ad hoc manner. Against this
backdrop, the extent of benefits derived from the expenditure of Rs.77.68 lakh
incurred during 1998-99 to 2001-02 (upto December 2001) under the EIUS
programme was uncertain. The department reported an achievement of 3000
for the period 1998-2000 against the target prescribed by the Government of
India of covering 3000 slum dwellers during 1998 to 2000 which was likewise
suspect considering that no survey to identify the slum dwellers and the nature
of basic amenities to be provided had been carried out.
95
96