Professional Documents
Culture Documents
1. INTRODUCTION
The Punjab irrigation system comprises fourteen barrages/headworks and twenty four canal
systems. The system got disturbed when in 1960 as a result of Indus Water Treaty; the
supplies of three eastern rivers were stopped by India. As a result of reduction in the eastern
river discharges, the hydraulic and sediment characteristics of all the rivers in the Province
and their off-taking canals suffered. The construction of link canals to meet the requirement
of command areas of eastern rivers in Province and new storages of Tarbela, Mangla Dams
under Indus Water Treaty have also changed the morphology of all rivers, As a result of the
recent drought conditions, the water levels downstream of barrages have been lowered with
substantial change in surface flow conditions. Particularly, irregular releases for hydropower
generation at Tarbela and Mangla have also affected the hydraulic flow conditions at Jinnah,
Taunsa, Khanki, Trimmu, Punjnad, Balloki, Suleimanki and Islam Headworks/Barrages.
These barrages are 46 to 110 years old and change in hydraulic conditions has caused so
many problems particularly retrogression and accretion at the barrages which have resulted
in the reduction of discharge capacity.
The Irrigation and Power (I&P) Department during 1997-1998 engaged consultants to review
the health of these structures. The preliminary investigations conducted by the Consultants
indicated a need for major rehabilitation of most of the Barrages/Headworks. Following the
results of study, the I&P Department decided to carry out feasibility studies for
rehabilitation/remodelling works at six barrages; Jinnah, Taunsa, Suleimanki, Islam, Khanki
and Balloki endangered by multitude of problems that threaten their overall stability under
the Punjab Barrages Rehabilitation Project Phase-I.
Out of the six barrages/headworks three were assigned to the Joint Venture comprising
National Development Consultants (NDC) and National Engineering Services Pakistan
(NESPAK) in association with ATKINS Global (Water) of UK for the required feasibility
studies. The assigned barrages are Taunsa on the Indus River, Suleimanki on the Sutlej
River and Khanki weir on the Chenab River. The consultants agreement was signed in
November 2003 and the mobilization took place on 15 December 2003. The consultants
submitted the Inception Report on 30.01.2004 in line with the requirements of Section 2.13.1
of the TOR.
According
to
the
TOR
consultants
will
carry
out
the
feasibility
studies
for
The rehabilitation works and new barrage will be designed following the state of the art
knowledge and existing design norms. The rehabilitation works will be proposed following
the design requirements of the existing structures. The consultants feel that there is a need
of formulating Design Criteria for the Punjab Barrages Rehabilitation Project Phase-I to
ensure the homogeneity and uniformity of the work and obtaining Clients agreement. This
document contains details of criteria for the design of various components of barrages and
will be used by the consultants.
The Design Criteria covers the following subjects:
Hydraulic Design
Structural Design
Geotechnical Aspects
2. HYDRAULIC DESIGN
2.1
BASIC CRITERIA
The Barrage and the Head Regulators of feeder channels and appurtenant structures will be
designed on the basis of standard design criteria established for other barrages and allied
structures, already constructed on the Indus River and its tributaries. The design criteria,
including formulae, coefficients and constants will be used in all hydraulic designs as
applicable.
Punjab Barrages Rehabilitation Project Phase-I comprises the rehabilitation of Taunsa and
Sulemanki Barrages and feasibility design of a new barrage on Chenab River replacing the
existing Khanki weir. Basically the design criteria given in the following sections is for the
design of new barrage on the Chenab River and in general will follow the design principles
practiced for the design of existing Barrages founded on the alluvium on Indus and other
rivers. The rehabilitation works for Taunsa and Sulemanki Barrages will also follow the same
engineering principles as explained in the design criteria until and unless some special
conditions encountered during the execution of rehabilitation works.
2.2
2.2.1
The design flood for any given return period is usually estimated by the frequency analysis
method. Appropriate type of frequency distribution will be selected from among the following:
It is pertinent to point out that Log Pearson Type III distribution has been adopted by United
States Federal Agencies whereas Gumbel distribution has generally been found to be
suitable for most of the streams in Pakistan including river Indus and its tributaries.
2.2.2
A return period of 100 years is generally adopted in the design of important and costly
barrage structures where possible consequences of failure are very serious. Accordingly, the
estimation of design flood will be carried out for various return periods of 100 years, 200 and
500 years subject to Clients concurrence. However, the actual recorded peak flood
discharge will be reviewed for design if it exceeds the discharge calculated for the concerned
return period.
2.3
HYDRAULIC UNITS
The dimensions and units of properties used in solving hydraulic problems are expressed in
three fundamental quantities of Mass (M), Length (L), and time (T). All analyses and designs
will be carried out in the Foot-Pound-Second system of units and conversion to S.I Units will
be made only of important results as necessary.
2.4
WIDTH OF BARRAGE
Three considerations govern the width of a barrage. They are the design flood, the Lacey
design width and the looseness factor. It is generally thought that by limiting the waterway,
the shoal formation upstream can be eliminated. However, it increases the intensity of
discharge and consequently the section of the structure becomes heavier with excessive
gate heights and cost increases, though the length of the structure is reduced.
The design flood is discussed in section 2.2 and the other two considerations are discussed
in the following sections.
2.4.1
The Laceys Design or Stable width for single channel is expressed as:
W = 2.67 Q
(Ref. 2.1)
The ratio of actual width to the regime width is the looseness factor, the third parameter
affecting the barrage width. The values used have varied from 1.9 to 0.9 (Ref. 2.1), the
larger factor being applied in the earlier design. Generally it varies from 1.1 to 1.5. From the
performance of these structures, a feeling arises in certain quarters that with high Looseness
Factor, there is a tendency for shoal formation upstream of the structures, which causes
damages and maintenance problems. The Consultants will use the most appropriate
looseness factor to provide reasonable flexibility keeping the ill effects to the minimum.
2.5
AFFLUX
The rise in maximum flood level of the river upstream of the barrage as a result of its
construction is defined as Afflux. Afflux, though confined in the beginning to a short length of
the river above the barrage, extends gradually very far up till the final slope of the river
upstream of the barrage is established.
In the design of barrages/weirs founded on alluvial sands, the afflux is limited to between 3
and 4 feet - more commonly 3 feet (Ref. 2.2). The amount of afflux will determine the top
levels of guide banks and their lengths, and the top levels and sections of flood protection
bunds. It will govern the dynamic action, as greater the afflux or fall of levels from upstream
to downstream the greater will be the action. It will also control the depth and location of the
standing wave. By providing a high afflux the width of the barrage can be narrowed but the
cost of training works will go up and the risk of failure by out flanking will increase. Selection
and adoption of a realistic medium value is imperative.
2.6
Tail water rating curve for the barrages will be established through analysis of gauge
discharge data. The proposed tail water levels for new designs will be established by
subtracting the designed retrogression values from the existing average tail water levels.
2.7
CREST LEVELS
Fixation of crest level is clearly related with the permissible looseness factor and the
discharge intensity in terms of discharge per foot of the overflow section of the barrage. After
considering all the relevant factors and the experience on similar structures the crest levels
will be fixed in order to pass the design flood at the normal pond level with all the gates fully
open.
2.8
The discharge through a Barrage under free flow conditions shall be obtained from the
following formula (Ref. 2.2):
Q = C. L . H3/2 ..(1)
Where,
Q = discharge in cusecs
C = Coefficient of Discharge
L = Clear waterway of the Barrage (ft)
H = Total Head causing the flow in ft
The value of C is generally taken as 3.09 (Ref.2.3), but may approach a maximum value of
3.8 for modular weir operation (Gibson). However to design a new barrage it will be
determined by physical model studies.
2.9
The flow over the weir is modular when it is independent of variations in downstream water
level. For this to occur, the downstream energy head over crest (E 2) must not rise beyond
eighty (80) percent of the upstream energy head over crest (E1). The ratio (E2/E1) is the
modular ratio and the modular limit is the value (E2/E1 = 0.80) of the modular ratio at
which flow ceases to be free.
2.9.1
Fanes Curve
For submerged (non modular) flow the discharge coefficient in equation (1) above should
be multiplied by a reduction factor. The reduction factor depends on the modular ratio (E 2/E1)
and the values of reduction factor ( C r ) given in the table below are from Fanes curve (Ref:
2.3) which is applicable to weirs having upstream ramp and sloping downstream with slope
2H:1V or flatter:
E2/E1
0.80
0.85
0.90
0.92
0.94
0.95
0.96
0.97
0.98
Value of C r
0.99
0.99
0.98
0.96
0.90
0.84
0.77
0.71
0.61
Q = 3.09. C r .b .E11.5
2.9.2
Gibson Curve
Q C '.b.E 1.5
(Ref. 2.4)
Where:
Q
(ft)
For submerged discharges the free flow discharge coefficient ( C 3.80 ) is multiplied by a
reduction factor ( C ' C ). The coefficient factor depends on the modular ratio (h/E), where
h is downstream depth of flow above crest. The values of reduction factor C ' C given in
the table below are from Gibson curve applicable to the broad crested weirs:
h E
C' C
C'
0.70
0.80
0.90
0.95
0.86
0.78
0.62
0.44
3.27
2.96
2.36
1.67
C d = discharge coefficient
b = width of gate (ft)
a = gate opening (ft)
Hm = upstream energy head above crest
= h 1 + v12/2g
(ft)
2V2
D
Ds D2 1
(1 2 )
gD2
D1
1/ 2
(Ref: 2.5)
Where:
1/ 2
where:
C d = discharge coefficient
(ft)
The top level of stilling basin will be fixed initially by Crumps Method (Ref: 2.3). The
reproduced Figure 2.1 gives the Crumps visualized hydraulic jump formation on the glacis
and curves for determining the various exponents related to the Crumps method.
For design calculations of critical flow depth (C = (q2/g)1/3) above weir crest the value of
discharge intensity (q) will be increased by twenty (20) percent for possible flow
concentration.
For fixing the top level of stilling basin the downstream energy head will be increased by ten
(10) percent to allow for a possible drop in the design flood level due to river bed
retrogression after construction of the weir or the standard practice in I & P Department will
be used after discussion with Client.
2.11.2 Length of Stilling Basin
As a preliminary design, the length of stilling basin without accessories (i.e. no chute blocks,
baffle blocks or end sill) will be determined by the Conjugate Depths formulae:
V1 q
d1
2 g z H a d1
(Ref: 2.7)
Where:
V1 = velocity of flow at the toe of glacis (ft/s)
q = discharge intensity (cusecs/ft)
d1 = flow depth at the toe of glacis (ft)
Z = fall between upstream flow level and stilling basin top level (ft)
Ha = approach velocity head
= V2/2g (ft)
V = approach velocity (ft/s)
g = acceleration of gravity (ft/s2)
For design calculations the value of discharge intensity (q) will be increased by twenty (20)
percent for possible flow concentration.
d2 1
1 8 F12
2
d1
(Ref: 2.6)
where:
d1 = flow depth at the toe of glacis (ft)
d2 = tail water depth above stilling basin (ft)
F1 =Froude number
V1 /(gd 1 )
Lb Kd 1 F11.5
(Ref: 2.8)
Where:
Lb = length of stilling basin (ft)
d1 = flow depth at the toe of glacis (ft)
F1 = Froude number
=
V1 /(gd 1 )
K
1.4
1.7
2.0
blocks
2.11.3 Efficiency of Hydraulic Jump
The ratio of the energy head after the jump (E2) to the energy head before the jump (E1)is
defined as the efficiency of the jump, and can be determined by the equation (Ref: 2.7):
E 2 8F12 1 2 4 F12 1
E1
8F12 2 F12
Where:
F1= Froude number of flow before the jump
E1
E2
.100
hj (1 8F12 ) 2 3
E1
F12 2
2.12 CHOICE OF STILLING BASIN
The practical design of energy dissipaters is based on hydraulic principles. However,
because of the use of accessories like chute blocks, baffle blocks and end sill to stabilize the
jump and shorten the length of horizontal apron, the design of proposed energy dissipaters
will be essentially confirmed by physical model studies.
2.13 GLACIS PROFILE
The glacis profile can be determined by the following equation for a free trajectory (Ref: 2.8):
Y x tan
gx 2
2(1.25V ) 2 Cos 2
where:
x and y = horizontal and vertical coordinates measured from the beginning of the
curve (ft)
= angle between the horizontal and the floor at the beginning of the trajectory
(degree)
V = velocity at vena contracta (ft/s)
g = acceleration of gravity (ft/s2)
The value of is zero and above revised equation is:
gx 2
2(1.25V ) 2
The glacis profile given by the above equation can also be checked by the Montague
equation (Ref: 2.9), given below:
x = v (4y/g)1/2 + y
10
where:
x = horizontal distance along the ordinate (ft)
y = vertical distance below the horizontal (ft)
v = initial velocity of water leaving the crest (ft/sec)
g = acceleration of gravity (ft/s2)
For regulating structures to determine floor profile take two (2) feet gated opening as the
critical to prevent flow separation from the floor. At lesser gate openings, there would be only
sheet flow over the glacis at nearly zero gated opening and then developing to a sudden jet
shoot-out approximately at two (2) feet gated opening. However, the conventional uniform
sloping glacis will also be given proper consideration. Final selection will be confirmed with
model studies.
2.14 CUT-OFFS
Pile cut-offs at both ends are necessary to prevent failure of structure by slipping of soil into
the scour holes, which can occur, both upstream and downstream. At the upstream end, the
force of seepage water will oppose slipping due to earth pressure. At the downstream end,
this force will assist and accelerate slipping due to earth pressure. Consequently failure at
the upstream will generally occur at low heads while failures at the downstream end will
occur at high heads.
The depth of the upstream pile line will be governed by the scour depth alone, while on the
downstream end, both the scour depth and exit gradient have to be considered. The
pressure under the downstream floor increases as the depth of downstream pile increases,
while the upstream pile line has little effect in reducing these pressures as the spacing of
these two is generally much more than the range of influence of each other.
The intermediate sheet pile lines are not required from consideration of scour or exit gradient
but they act as important secondary lines of defense and save total collapse of work in case
of damage to impervious floor or the end piles. They are also helpful in the matter of
distribution of pressure due to uplift forces.
The design of cut-offs will be based on Khoslas and Lanes theories to make the barrage
safe against piping and uplift, and are described as under:
11
Khoslas Theory
Khoslas formula most commonly used for this purpose for the piled structure is given
below (Ref. 2.10):
Ge
H 1
d
where,
Ge = Critical exit gradient
H = Total Head
d = Depth of downstream end pile (the exit gradient is almost by the upstream piles)
2
= 1 1 1
2
= b/d, and
Lanes Theory
The weighted creep distance or percolation path is given as follows:
For flow passing under the structure:
Lu Vv
h
3
12
Ls 0.75 Vh hh
where:
Cr
Lu orLs
C
H
where:
13
Table 2.1
14
Correction for floor thickness: the pressures are corrected by assuming linear
pressure distribution. The correction to be applied for the point E 1 shall be negative
while at point C1 is positive, as shown in Figure 2.3.
ii.
D=
Floor slope correction: is taken as positive for the down slopes and negative for up
slopes relative to the direction of flow. Correction curve for the floor slopes is
reproduced in Figure 2.4. ( Ref: 2.11).
15
16
1
3
Where
R
silt factor
For calculation of the length of block aprons the scour factor of 1.25 for the upstream apron
and 1.5-1.75 for the downstream apron will be used. To calculate horizontal length of block
aprons, factors of 1.0 and 1.5 shall be used for upstream and the downstream aprons
respectively. Application or otherwise of discharge concentration shall be decided on the
basis of conditions prevailing at different sites.
17
Apron slope will fall to a slope between 2H:1V and 3H:1V depending upon the
characteristics of the river bed material.
Thickness of stone apron when fallen should not be less than 3 feet.
The scour factor for aprons varies from 1.25 to 1.75 for the upstream and from 1.75 to 2.25
for the downstream aprons. Application or otherwise of discharge concentration shall be
decided on the basis of specific conditions prevailing at different sites.
2.22 FISH LADDER
Fish ladder has been provided to enable the migratory fish to move across the barrage from
downstream to upstream and vice versa. It has been located near the divide wall in view of
the availability of water throughout the year in the river downstream of the under sluices.
18
In order that the velocity of water emanating from the entrance should be kept constant
(approximately 6 ft./see), whatever the water levels upstream and downstream may be, it is
arranged that as downstream water level rises and progressively drowns the lower pools
additional water can be supplied from a separate supply channel through a system of ducts
and chimneys controlled by sluice valves. The velocity can be maintained at a
predetermined level.
The hydraulic design of the fish ladder is aimed at producing flows of velocity and pattern
attractive for the fish for providing passage upstream which may be attempted by the fish
without difficulty. Upstream water level is pond level and allowance is made for minor
variations in levels, which may occur. Downstream water level depends on the regime in the
river, which is existence at the time. Maximum and minimum values likely to occur during the
period when the fish are migrating will be selected to correspond to the limits of flows
expected in the river at that time.
The fish ladder will be made up of the following parts (commencing at the downstream end):
i.
ii. Pool and weir section, part below maximum downstream water level and part above it.
Control pool with constant water level, between orifice and their section
iii. Exit section of pool and orifice
iv. Supply channel for added water; this runs parallel to and adjacent to the fish ladder.
2.22.1 Fish Entrance Section
The fish entrance will be a vertical slot about 4 feet wide. Velocity of water through entrance
slot will be around 6 feet per second for all probable downstream water levels. This velocity,
together with the accompanying fall in water level (about one foot) should serve to attract
fish from the river to the fish ladder. Inside the entrance section, water will be supplied from
the supply channel through four control gates and diffusers. This water supplements the flow
for fish ladder and provides the required velocity through the fish entrance.
2.22.2 Pool and Weir Section
A fall of one foot per pool will be selected. Both weirs and orifices will be provided to suit fish
of various habits. Velocities over weirs and through the orifices should be around four and
six feet per second respectively.
19
By a suitable arrangement of ducts and chimneys, water is fed from the supply channel
through diffusers of those pools, which have become drowned by the downstream water
level i.e. when the downstream water level is above the normal water level in the pool. In this
way the velocity at the entrance may be kept more or less constant and the velocity in the
drowned section of the fish ladder is itself sufficient to attract the fish upstream without delay.
2.22.3 Control Pool
Water level in this pool is maintained at a constant level by adding more or less water direct
from the pond. In this way, flow in the non-submerged part of the weir section is kept steady.
2.22.4 Exit Section
The orifices are arranged to be staggered in successive baffles to effect good energy
dissipation. Velocity through the orifices will vary with the pond level from about 3 to 5
feet per second.
2.22.5 Supply Channel
The supply channel carries water from the pond to be fed through the chimneys into the weir
pools when required and water to be fed into the entrance section.
Water level in the supply channel is controlled by a gate at the upstream end of the channel
and is maintained at a level 3 feet above downstream water level at all times the fish ladder
is in operation, i.e. 2 feet above water level in the entrance section.
The chimneys are designed to pass the required amount of water through the diffusers
under this head.
The level of the top of each chimney is fixed so that water commences to flow through
chimneys when the water level in the entrance section rises to a level 1 foot below the
normal water level of the pool fed by that chimney and reaches a constant value when the
water level in the entrance section rises a further 2 feet.
2.22.6 Fish Ladder Operation
Gates to the four openings from the supply channel to the entrance section are adjusted at
minimum downstream water level to give the desired entrance velocity.
20
The water level in the supply channel is maintained 3 feet above the downstream water level
by reference to float gauges in still wells connected to the river downstream and to the
supply channel respectively.
Water level in the control pool is maintained at constant level by adjustment of a gate
opening leading direct to the pond by reference to a float gauge in still well connected to the
control pool.
Any silt deposited should collect at the downstream end of the supply channel. A gated
opening has been provided in the downstream end wall to enable this silt to be washed out
from time to time.
2.22.7 Abstract
Flow through the fish ladder will be calculated using the following formulae:
Flow over weir
C.L.H3/2
Cd .A (2gh)1/2
Cd
It must be mentioned that in problems of this kind the actual flow patterns are most
complicated and depend in part on the interaction of one section on its neighbors.
It is important, therefore, that approximate results obtained by calculations should be verified
by the suitable model tests.
2.23 RIVER TRAINING STRUCTURES
2.23.1 Guide Banks
A river generally flows in a wide khadir (i.e. the historical movement limits or distance
between the two high banks of the river) and it is necessary to narrow down and restrict its
course to flow centrally through the barrage, weir or bridge placed across it. Guide banks are
placed in pairs symmetrical in plan. It is essential that the design should be such that no
21
swirls are produced and alignment is smooth. There should be no spurs projecting from the
guide bank as the spurs produce swirls.
a)
The distance necessary to secure a straight and normal flow approach to the
structure so as to minimize the obliquity of current.
To safely protect the approach banks on both sides of the structure from river
embaying behind the training works.
To ensure that the swirls and turbulence, likely to be created by the spreading out of
flow downstream of the guide banks, do not endanger the structure.
The length necessary to prevent the edge of bend or meandering of the river at
upstream and behind the guide bank.
The typical plan of the guide bank (Bells Bund) showing its length is reproduced (Ref: 2.12)
in Figure 2.6.
b)
The proper radius of upstream bank head depends on the velocity of the river. Spring gives
the following table to design the radii, related with the probable maximum scour and river
gradient (Ref: 2.10):
Sand
Probable
Classification
Maximum
Scour (ft)
< 20
> 20
< 30
> 30
< 40
> 40
< 50
> 50
< 60
> 60
Very Coarse
Coarse
Medium
Fine
Very Fine
The upstream bank head curve should be carried 120 to 140 degrees round the back to
protect the landside of the bank.
22
d)
The typical sections of the guide banks are given in Figure 2.7. The basic design criteria for
the embankment are:
Crest width
30 ft
2H:1V
3H:1V
A six (6) inch (150 mm) thick compacted gravel and sand surfacing will be placed on
(9 m)
the crest of guide bank for protection against flood water spray, rain runoff and traffic
wear and tear.
The embankment will be protected with stone pitching, underlain with graded spawl
and filter layers, and flexible stone apron on the riverside slope, upstream head and
downstream end.
The final geometry of the guide banks will be determined by physical model studies
to suit the site requirements.
23
a)
Alignment of Spurs
Spurs may be aligned perpendicular or inclined to the bank line, pointing upstream or
downstream. The fixing of angle of spur with respect to current axis will require physical
model study.
b) Spacing of Multiple Spurs
The spacing between spurs generally depends on the length projected by each spur in the
series. The general recommendations on spacing are (Ref: 2.13):
The spurs are spaced further apart, with respect to their lengths in a wide river than
in a narrow river, having nearly equal discharge. The normal spacing in straight reach
will be five (5) times the length of spur.
The location of spurs affects their spacing. A larger spacing may be adopted for
convex banks and a smaller spacing for concave banks. In general, the
recommended spacing is:
When the river bank has a curvature, the spurs in series may have varying lengths
and, therefore, varying spacing. The angle of deflection of spurs may also change
continuously according to the curvature of the bank line.
c) Length of Spurs
No general rules can be formulated for fixing the length of spurs. It depends entirely on the
conditions and requirement for the each specific site. The length should not be shorter than
that required to keep the scour hole formed at the nose away from the bank. Short length
may also cause bank erosion upstream and downstream of the spur due to eddies formed at
the nose. A long spur may dam up the river and would not withstand the flood attack from
discharge concentration at the nose and a high head across the spur. Normally spurs longer
than one fifth (1/5) the river width are not provided.
The length of spurs as well as their orientation, shape etc., can best be finalized from
physical model studies.
2.23.4 Diversion Bunds and Cunnettes
24
When meandering of the river to extreme the land between the bends may gradually reduce
to a narrow neck. Unless the banks of the neck and meandering river loop are protected,
continuous caving takes place. The narrowing of the neck reaches a limit and a natural cutoff
may form across the neck. Based on this natural phenomenon an artificial pilot cut (or
cunnette) may be formed to short circuit the river loop and stop the banks erosion. The entry
of the flow in the meandering river channel is checked by placing upstream and downstream
diversion bunds. The typical layout of diversion bunds and cunnette is shown in Figure 2.8.
The diversion bunds will be sufficiently anchored into the river banks to avoid outflanking.
The cross-section of the diversion bunds will be similar to the cross-section of earthen
marginal bund, shown in Figure 2.9. The bunds height will be designed enough to check the
backwater effect in the blocked river channel. The backwater effect will be higher at bund 1
(upstream) than at bund 2 (downstream). The bund 2 (downstream) will have less design
height than the bund 1 (upstream).
2.24 LOCAL SCOUR PROTECTION
The local scour results directly from the impact of the structure on the flow. The development
of the scour process depends on the flow velocity, turbulence intensity and bed materials, so
it is difficult to prescribe a direct local scour prediction method. It is recommended to
calculate the local scour by several available methods and utilize engineering judgment in
selecting the results or establishing the maximum value by the most applicable methods.
2.25 STONE APRON
The function of stone apron is to launch and cover the scoured sub aqueous slope below
pitching level and prevent the possibility of damaging effect of scour coming close to the
structure with possible undermining.
The calculated quantity of apron stone will be laid horizontally along the bank toe, with its top
level at the river bed level for dry conditions or at par with the low water level (LWL) of the
river to form the working platform. When scour occurs, the hand packed stone apron will
launch itself to act as revetment on the scoured sub aqueous slope.
After launching action of stone apron the stone pitching gradually slips down the bank slope
because of its diminished stable toe previously offered by the stone apron. Typical details of
stone apron are shown in Figure 2.10.
a)
25
For designing of apron, it is necessary that the volume of stone should be sufficient to cover
the local scour slope length in its fully developed state and also fill partially the scour hole at
toe of the sub aqueous slope.
i.
Launching Slope
The launching slope of apron could be assumed as the angle of internal friction () of
the river bed subsurface saturated soil forming continuity with the side slope of the
structure.
ii.
iii.
b)
The Isbash Method (empirical), given below will be used to determine the apron stone size.
The related hydraulic design chart for Velocity Vs Stone Diameter is reproduced in Figure
2.11 (2 sheets).
i.
ii.
26
W100 (max.)
W100 (min.)
W50 (max.)
W15 (max.)
W15 (min.)
=
=
=
=
=
4.0W50
2.0W50
1.5W50
1.0W50
0.4W50
(min.)
(min.)
(min.)
(min.)
(min.)
above the
27
R
K tan
H 8 / T H / 2 g 1 / 2
where:
R = wave run-up (or ride) (ft.)
H = wave height (ft.)
K = surface roughness coefficient for the embankment slope
(ft.)
(s)
(degree)
(ft./s)
Wind Set-Up
An appreciable rise in water level may be caused on one slope of reservoir or pond by wind
action, particularly in shallow water. The wind set-up can be estimated by Zuider Zee
formula:
S
U 2F
Cos
1400 D
where:
S = set-up above still pond level (ft.)
U = wind velocity (mile/hour)
F = fetch (mile)
D = average water depth (ft.)
= angle of fetch and wind (degree)
For combined effect of wind set-up and wave run-up the total rise in water level is equal to
wind set-up plus two third of wave run-up.
c)
River Set
At curves the deepest point of the river cross-section is near the concave (or outer) bank and
the water surface there is higher than at the convex (or inner) bank. The river set may
cause a super elevation of the water surface at the concave (or outer) bank and this can be
estimated by Schoklitsch formula:
h 2.3
NDC | NESPAK | ATKINS
V2
R2
. log
g
R1
28
where:
h = river set (ft.)
V = average velocity at the upstream straight reach (ft/s)
g = acceleration of gravity
(ft./s)
(ft.)
(ft.)
The Government of Sind Bund Manual (Ref: 2.17) indicates that river set may cause a
rise of the water surface at the concave (or outer) bank as much as 2.0 feet (0.6 m).
d)
Recommended Freeboard
Sufficient freeboard should be provided above the design flood level for safety against
overtopping. For arriving at appropriate freeboard, the design flood level, the wave run-up,
wind set-up and river set be calculated. These values should be added accordingly and one
foot additional freeboard be provided for contingent requirement as factor of safety.
The ultimate foundation and fill settlement will be neglected against one foot contingent
provision. By keeping in view the current local practices on freeboard for the typical flood
protection structures, influenced by different hydraulic conditions and design wind velocity
over land (Uland) assumed as minimum 50 miles/hour (80 km/hour), the recommended
minimum freeboard provisions for various flood protection structures are given in the table
below:
29
Recommended
Minimum Freeboard
(ft.)*
CONTAINING STRUCTURES
-
Flood Bunds
6.0 (1.8 m)
Retired Bunds
Current flow
5.0 (1.5 m)
7.0 (2.0 m)
TRAINING STRUCTURES
-
Spurs/Groynes
5.0 (1.5 m)
Guide banks
7.0 (2.0 m)
Pitched Islands
5.0 (1.5 m)
Diversion Bunds
4.0 (1.2 m)
(*) The recommended minimum freeboard values include one foot additional freeboard for
contingent requirement as factor of safety.
30
a)
Wave Run-up
The wind velocity, duration and direction at the location of hydraulic structure and adjacent
topography affect the generated wave heights. The wave run-up is measured above the still
water level that would theoretically exist if there is no wave action. Waves prediction
methods are based on semi-empirical relationships, as discussed below:
i.
Wind Data
Normally, wind data to establish the design wind velocity over land (Uland) will be
obtained from the nearest located meteorological station with respect to the hydraulic
structure. For cases where wind data is not available from the nearby station then
the value of Uland will be taken as 50
0.5
1
2
4
5 (and over)
1.06
1.13
1.21
1.28
1.31
The Uland are adjusted by the wind velocity ratio to obtain U water.
ii.
iii.
31
gH s
0.0026
U w2
gFe
U2
w
gTs
0.46 gF2e
2
Uw
Uw
0.47
0.28
where:
Hs = significant wave height, the average of the highest 1/3 waves in the spectrum (ft)
Ts = significant wave period, the average interval between successive crests or
troughs of groups of the higher waves (s)
Fe = effective fetch (ft)
Uw= wind velocity over water surface (ft/s)
g = acceleration of gravity ( ft/s2)
The Figure 2.13 reproduced from Ref: 2.17, presents relationship between the wave run-up
ratio (R/Hs) and wave steepness (Hs/Lo) for deep water.
where:
R = wave run-up as vertical height (ft)
Lo= wave length = 5.12 Ts2 (ft)
H s 0.0555(U w Fe ) 0.5
2
Ts 0.50(U w Fe ) 0.25
where:
Hs = significant wave height (ft)
Ts = significant wave period (s)
Uw= wind velocity ( knot)
Fe = effective fetch ( nautical mile)
(1.15 statue mile = 1.0 nautical mile)
Shallow water wave-height (Hs) = 0.65 Hs
where:
H = wave height (ft)
F = fetch (mile)
U = wind velocity (mile/hour)
32
b)
When a wave strikes on the front slope of embankment, it breaks completely or is partially
reflected creating standing waves which are sometimes twice the height of incident waves.
To avoid these standing waves the front slope has to completely break the wave train. The
front slope competency could be checked by satisfying the following equation (Ref: 2.16).
8
tan
Ts
Hs
2g
0.5
where:
= bank slope angle to the horizontal (degree)
Hs = significant wave height (ft.)
Ts = significant wave period (s)
g = acceleration of gravity (ft/s2)
c)
The semi-empirical Hudson and Jackson formula (Ref: 2.18) for determining the required
weight of the stone is:
W50
D50
Wr H 3
K RR S r 1 Cot
6W50
Wr
1/ 3
where:
W50 =median stone weight in gradation by weight (lb)
Wr =unit weight of the stone = 165 (lbs/ft3)
H =design wave height (ft)
Sr = specific gravity of stone = Wr / Ww
Ww =unit weight of water = 62.5 (lbs/ft3)
33
H = 1.25 Hs
where:
Hs = significant wave height (ft)
2.27 STONE PITCHING PROTECTION
The slope protection will consist of hammer dressed stone pitching underlain with transition
layer of well graded rock spawl and filter layer of well graded gravel or crushed stone, up to
the crest level. Typical details of stone pitching protection on embankment slope are shown
in Figure 2.10.
a)
All stones shall be contained within the thickness of stone pitching layer to provide maximum
resistance against erosive forces. The larger stones should not protrude above the general
surface of the stone pitching. As normal requirement the minimum thickness of stone
pitching layer will be kept as 1.5 feet (0.45 m) for containing the larger stone.
Minimum thickness of stone pitching layer =1.5D50 1.5 ft (0.45 m)
b)
It is recommended to provide standard six (6) inches (150 mm) thick rock spawl transition
layer between the stone pitching layer and filter layer. The spawl layer will be well graded
from two (2) to four (4) inches (50 mm to 100 mm). Not more than fifteen (15) percent shall
be larger than four (4) inches (100 mm) and not more than five (5) percent shall be smaller
than two (2) inches (50 mm).
c)
Filter Layer
To prevent infiltration of the material susceptible to draining into the filter, the following
requirement will be met:
D15 percent size of filter material
5 (stability)
25 (segregation)
34
To assure that the filter material is much more permeable than the material being drained
the following requirement will be met:
Permeability:
D15 percent size of filter material
5 (permeability)
35
REFERENCES:
2.1
Sir Thomas Foy and H. Spencer Green, Barrages and Dams on Permeable
Foundations.
2.2
2.3
2.4
Coode and Partners, Design Report Qadirabad Barrage and Works in Connection
Therewith, (1963).
2.5
King H.W. and Brater E.F, Handbook of Hydraulics, Fifth Edition, McGraw-Hill Book
Company.
2.6
Peterka A.J., Hydraulic Design of Stilling Basins and Energy Dissipaters. Engineering
Monograph No. 25, USBR, (1978).
2.7
Chow Ven Te, Open Channel Hydraulics, McGraw Hill Book Company, ( 1973).
2.8
2.9
Shakir B.A., Design of Canal Falls, West Pakistan Engineering Congress, (1963).
2.10
2.11
2.12
2.13
Verma C.V.J. et. al., River Behaviour Management and Training, Volume I, Central
Board of Irrigation and Power, New Delhi, India, (1989).
2.14
2.15
2.16
Zaidi S.M.A., Wind Generated Waves and Their Effects on River Bunds, Proceedings
of Pakistan Engineering Congress. (1978).
2.17
2.18
( May, 1962).
2.19
Taylor K.V., Slope protection on Earth and Rock fill Dams, Commission International
Des Grands Barrages, Madrid, ( 1973).
36
3. STRUCTURAL DESIGN
3.1
GENERAL
These design criteria shall be used in the design of all structures. The supplemental design
criteria applicable to specific structures will be established for any particular requirements/
conditions.
Design for concrete structures will be based on design methods as set out in applicable
Codes of the American Concrete Institute (ACI) or British Standards (BS) where ACI Codes
do not carry pertinent information.
3.2
DESIGN LOADING
All structural members will be designed to withstand dead and live loads expected to be
imposed. These loads will include the self-weight of the structure, imposed load including
earthquake forces, wind loads, internal and external hydrostatic (uplift) and hydrodynamics
(flow) loads, construction loads, impact loads and earth pressures. Where elements would
be precast lifting forces shall be considered.
i.
Dead Loads
materials:
Material Type
(lb/ft3)
150
(kg/m3)
2403
PCC (1:2:4)
144
2307
140
2243
Rubble masonry
140
2243
Brick masonry
120
1922
Dry earth
100
1602
Compacted earth1
115
1842
Saturated earth
135
2163
RCC
ii.
1
Unit Weight
The bridges will be designed or evaluated for the following live loading:
Bridge Classification
A.R. Bridge
Live Load
Class AA loading
Class A loading
NLC loading
Class AA loading
D.R. Bridge
Class A loading
NLC loading
Class A loading
100 lb/ft2 (488 kg/m2)
V.R. Bridge
Foot Bridge
Class AA Loading: This is 70 ton (69 tonne) Army tank. The nose to tail distance between
two successive tanks will not be less than three hundred (300) feet (92 m) and no other live
load shall cover any part of the roadway of the bridge when tank is crossing.
NLC loading: This has a maximum twin wheel loading of 20 x 10-inch (50.8 x 25.4 cm). The
nose to tail distance between successive truck trailer units shall not be less than sixty (60)
feet (18 m).
Class A loading: is a train of one truck plus two trailers. The nose to tail distance between
successive truck units shall not be less than 60 feet (18 m).
Live load stresses shall be increased for impact effect as below:
= 25%
50
L 125
Where:
I = Impact factor
L= Length of span (ft)
iii.
Wind Loads
accordance with
Building Code of Pakistan, for a maximum wind velocity of hundred (100) mph (161 kmph)
acting horizontally in any direction.
iv.
Earthquake Load
The earthquake loading will be selected according to the established earthquake zones of
Pakistan.
v.
Flow Pressure
Uplift Pressure
Uplift pressure will be assumed to correspond to full head across. Uplift will be assumed to
act on hundred (100) percent of the base area.
vii.
Earth Pressure
Lateral earth pressures due to backfill under static conditions will be computed by the
Coulombs Method, taking into account the effects of any soil saturation or submergence.
A surcharge of two hundred (200) lb/ft2 (975 kg/m2) will be added for computing earth
pressure.
viii.
Loading Combinations
The loads listed above will be divided into two main groups:
Group-I
Loads:
Earth pressure.
Uplift pressure.
Group-II
Loads:
Wind loads.
Earthquake load.
The following three different loading combinations will be considered for the design of
structures:
Normal Loading Condition: will result from the combination of Group-I loads only.
Exceptional Loading Condition: will arise from the combination of any one load from
Group-II with the Group-I loads.
Extreme Loading Condition: will occur when two loads from Group-II loads are combined
with Group-I loads.
3.3
STABILITY CRITERIA
Stability analysis will be carried out for structures for most severe conditions of horizontal
and vertical forces. Stability criteria are aimed at ensuring the overall safety of structure
against overturning and sliding.
i. Overturning
Allowable limits under different loading conditions will be a follows:
Normal Loading
Resultant of all forces acting on structures will fall within the middle third of the base (i.e.
no tension allowed between concrete and foundation) and the allowable foundation
pressure will not be exceeded.
Exceptional loading
base and allowable design foundation pressure (20% higher than for Normal loading
case) will not be exceeded.
Extreme loading
Resultant of all forces acting on the structure will remain within the middle half of the
base provided that a minimum of 75% of the base area is subject to compression and
the maximum base pressure will not exceed the allowable design foundation pressure
(33% higher than for Normal loading case).
ii.
Sliding
(Normal Forces)
(Forces in sliding plans)
where:
= coefficient of friction at rough interface of foundation base
The minimum factor safety will be as follows:
Loading Condition
Factor of Safety
Normal loading
Exceptional loading
Extreme loading
1.50
1.25
1.1
3.4
FLOATATION
3.5
Normal loading
= 1.25
Exceptional loading
= 1.15
Extreme loading
= 1.05
ALLOWABLE STRESSES
The following allowable stresses will be followed in the design of the members of various
structures:
i.
Description
Allowable Stress (psi)
Modulus of elasticity ratio n =Es/Ec
= 29,000,000/57,000
fc '
- Normal
- Exceptional
- Extreme
Extreme fiber stress in tension in plain concrete footings
and walls
0.45 fc
1.2 of the Normal
1.33 of the Normal
1.6 f c '
1.10 f c '
1.2 of the Normal
1.33 of the Normal
Shear:
- Normal
- Exceptional
- Extreme
1.20
fc '
5.0
fc '
2.0
fc '
4.8
3.4
Bond:
Main bars
Top bars
0.25 fc
0.375 fc
Bearing:
On full area
On one third area or less
0.5fy
1.2 of the Normal
1.33 of the Normal
REINFORCEMENT
- Normal
- Exceptional
- Extreme
where:
with ASTM
A615)
d = bar diameter (in.)
ii.
PCC (1:2:4)
PCC (1:3:6)
iii.
Lean Concrete
The lean concrete (or blinding concrete) will have 28 days compressive strength of:
Cylinder = 2,000 psi (141 kg/cm2)
Cube
iv.
Bricks
The bricks will have a minimum crushing strength of 2,000 psi, (141 kg/cm2) when tested
flat.
3.6
A minimum area of reinforcement is required to control the cracking, which occurs in the
concrete due to temperature, shrinkage and creep. It enables cracking to be uniformly
distributed and therefore minimizes individual crack width.
The following criteria will be used to determine the cross-section area of temperature or
minimum reinforcement required in hydraulic structures. The percentages indicated are
based on the gross cross-sectional area of the concrete to be reinforced. Where the
thickness of the section exceeds fifteen (15) inches (380 mm), a thickness of fifteen (15)
inches (380 mm) should be used in determining the temperature or minimum reinforcement.
For concrete gravity structures like piers, divide walls, abutments etc. minimum temperature
reinforcement may be provided with area equivalent to # 9 @ 12" (or # 6 @ 5") in each face
(Ref: Para 2-8, Engineering Manual 1110-2-2104, Strength Design for Reinforced Concrete
Hydraulic Structures, U.S. Army Corps of Engineers).
Concrete Member/Face
SINGLE LAYER REINFORCEMENT
Slabs not exposed to direct sun joints spacing < 30 ft (9 m).
Slabs exposed to direct sun joints spacing < 30 ft (9 m).
Slabs not exposed to direct sun joints spacing >30 ft (9 m).
Slabs exposed to direct sun joints spacing >30 ft (9 m).
DOUBLE LAYER REINFORCEMENT (EACH FACE)
Face adjacent to earth - joints spacing < 30 ft (9 m).
Face not adjacent to earth nor exposed to direct sun joints spacing
< 30 ft (9 m).
Face not adjacent to earth but exposed to direct sun joints spacing
< 30 ft (9 m).
If member exceeds 30ft (9m) in any direction parallel to
reinforcement, add to the above reinforcement requirement in that
direction because of the increased length.
Minimum
Reinforcement
Percentage
0.25 %
0.30 %
0.35 %
0.40 %
0.10 %
0.15 %
0.20 %
+0.05 %
The temperature reinforcement shall not be less than inch (13 mm) at nine (9) inch (230
mm) centre to centre. All concrete stilling basins, glacis and floors and all concrete aprons of
regulators and similar structures (with slab thickness > 15 inch (380 mm)) shall be reinforced
in the exposed (top) face with inch (19 mm) bars at twelve (12) inch (300 mm) centre to
centre, both ways, placed three (3) inch (75 mm) clear from concrete face, unless otherwise
designed.
Nominal reinforcement of concrete chute blocks, baffle blocks and sills for stilling basins,
aprons and other portion of regulators, falls and similar structures shall consist of inch (19
mm) bars at twelve (12) inch (300 mm) centre to centre, both
3.7
The following minimum concrete cover shall be provided for the nearest reinforcement.
Minimum
Concrete Element
Face in contact with earth
Face exposed to weather and flowing water
Beam, girder, column and wall dry condition
Beam, girder, column and pier exposed to water and weather
Slabs not exposed (dry condition)
3.8
Concrete Cover
(in)
(mm)
3
75
3
75
1.5
40
2
30
1.5
40
CONCRETE JOINTS
There are three (3) types of joints generally used in concrete construction. These are:
Construction Joints
Contraction Joints
Expansion Joints
One joint may be combination of the two or more of these types. The joints for the structures
which are subjected to internal and external hydrostatic (uplift) pressure, shall be provided
with rubber or polyvinyl chloride (PVC) water stop of suitable sizes.
i.
Construction Joints
These shall be provided where necessary for the practical placing of concrete. The
reinforcement steel shall be continued across the construction joint. Unless required to resist
heavy shear caused by lateral loads, keys shall not be placed in construction joints. Where
necessary to ensure water tightness in construction joint, water stop shall be provided.
ii.
Contraction Joint
These shall be used to relieve tensile stresses induced in the concrete by shrinkage. They
differ from construction joints wherein means are used to prevent bond between the joint
faces, and the reinforcement does not cross the joint face. Concrete on one side of the joint
is cast first, and after the form is removed from the joint face, the joint is painted with sealing
compound to prevent bond with the concrete placed against it. Water stop shall be placed in
contraction joints to provide water tightness, where necessary. Contraction joints may also
serve as construction joints.
iii.
Expansion Joints
These are used to eliminate or reduce compressive stresses that would otherwise result
from thermal expansion, creep, or settlement of the concrete. Water stop shall be placed in
expansion joints to provide water tightness, where necessary. Expansion joints may also
serve as construction joints.
3.9
PRE-STRESS CONCRETE
0.06 f cl
Post-tensioned members
0.55 f cl
Tension
Pre-compressed tensile zone
b)
0.40 fc
c)
Cracking Stresses
Modulus of rupture from tests or if not available
d)
7.5
6.3
5.5
Anchorage-bearing stress
Post-tensioned anchorage at service load
3,000 psi
0.70 fpu
10
4. GEOTECHNCIAL DESIGN
4.1
GENERAL
A detailed knowledge of subsurface condition would be required for safe and economical
design of foundations of various components of barrage structures. Punjab Barrages
Rehabilitation Project Phase I includes rehabilitation of Taunsa and Sulemanki Barrages and
feasibility design of a new barrage on Chenab River replacing existing Khanki weir.
Geotechnical investigations will be carried out at the new location of Khanki Barrage to
explore the subsurface strata and determine the engineering characteristics of foundation
material. Where as Geophysical explorations will be made at Taunsa and Sulemanki
Barrages to ascertain the subsurface conditions below the existing structures, which will help
in suggesting the rehabilitation measures.
4.2
GROUND EXPLORATION
Explorations in the river bed shall be confined to periods of low river flows, i.e., from
November to March. The three barrages are located in the Punjab flood plains and available
data indicates that the river bed alluvium comprises fine to medium sands with varying
degree of silt. Occasional clay layers have also been reported at places. Keeping this in view
wash boring/straight rotary drilling techniques will be selected for explorations. Bentonite will
be used as the drilling fluid to support the hole as an alternate to casing. However, bentonite
will not be used when permeability tests are undertaken. Test pits through manual
labour/back hoe will also be excavated to expose the top stratum for physical examination,
in-situ testing and sampling.
The main objectives in making the ground explorations would be:
i.
Standard penetration tests will be carried out in the boreholes, generally at a depth interval
of 1m. The number of blows for penetrating the last 30cm of sampler will be recorded. Cone
penetration tests (CPTs) will also be performed at various selected locations. The results
from these tests will be used for direct as well as indirect determination of strength and
deformation characteristics using empirical correlations.
The undisturbed samples will also be taken at appropriate depths in various subsurface
strata if found necessary. Piston/Shelby samples will be used at shallow depths in softer
conditions. For alluvial sands Pitcher sampler will be used while for cohesive soils Denison
sampler will be used. The samples recovered shall be carefully cleaned, waxed, labelled and
stored at site with a minimum of delay after sampling, before being transported to the
laboratory. Special care would be exercised during transportation so as to avoid any
disturbance due to vibration and shock.
Permeability tests in boreholes will be performed at selected locations either with the flush
bottom or lifted casing cases if considered necessary. Any difference between the results of
the two tests is an indication of a difference between the vertical and horizontal
permeabilities due to thin stratification. However, if the two tests are entirely within one
stratum, similar permeabilities will be obtained even if on a larger scale, horizontal
permeability is higher than vertical permeability. The permeability data will be analysed and a
ratio of horizontal to vertical permeability will be established.
In-situ density will be determined through tests carried out in the test pits by sand
Replacement Method and CPT carried out in boreholes.
The initial description of soils will be done on site. An experienced geotechnical
engineer/engineering geologist will be at site in the early stages to see that the site staff is
on the right lines. For quality control and sporadic check intermittent visits by senior
personnel will be made.
4.3
GEOPHYSICAL EXPLORATIONS
The Electrical Resistivity (horizontal profiling), gravity and shallow Refraction surveys will be
carried out to delineate the voids and probable channels below concrete mass and also to
demarcate the shape and size of the voids and channels.
4.4
LABORATORY TESTING
Depending on the ground conditions some or all of the following tests will be carried out on
selected soil/water samples transported to the laboratory:
i.
The results obtained through ground explorations and laboratory testing will be studied in
conjunction with each other and judicious engineering judgment to evolve design
parameters. Where ever possible more than one method would be adopted in evaluating the
design parameters.
The results of the geotechnical investigations will be used for the design of specific
structures, but the general layout of the Barrage will mainly be influenced by the
topographical features, river approach conditions and environmental considerations.
4.6
There must be an adequate factor of safety against local and general shear failure in
soil.
The settlements and particularly the differential settlements must be kept within the
tolerable limits imposed by functional and structural design requirements.
4.7
In this approach ultimate bearing capacity of soils shall be evaluated using the following
Meyerhofs (Ref.4.1) bearing capacity equation. A factor of safety (FOS) of 3 shall be used to
calculate the allowable foundation pressures from the calculated values.
qult cN C S C d C qN q S q d q 0.5BN S d
Where,
qult = ultimate bearing capacity
NC , N q , N
of internal friction
S C , S q , S
= shape factors
Nqetantan2452
Ncq1Cot
Nq1tan4.
S102.Kpc
S10.Kpq
B
L
B
L
d102.Kpc
D
B
d1.0Kpq
D
B
Kptan245
2
For granular soils of high permeability drained soil strength parameters will be used.
Cone Penetration Test (CPT) results from the field shall be used to determine a notional
value of angle of shearing resistance. (Ref.4.2) Fig. 4.1 shows Meyerhofs correlation
between static cone penetration resistance and angle of shearing resistance of sand. This
value shall be judiciously used to determine the ultimate bearing capacity using the
Meyerhofs approach.
4.9
The prevalent subsurface conditions at the three barrage sites indicate that, the allowable
pressure which may be applied to the barrage foundation will be governed by consideration
of settlement, rather than of the shear strength of the soil. Therefore accurate prediction of
the settlement of the structures founded on sands is very important. The settlement based
design will be carried out using the following approaches:
i.
qa
N
Kd
F1
B <F4
NBF
q3Kdq
F2 B
BF4
qa
N
F2
for rafts
Kd =
1 0.33
Df
B
1.33
Df = depth of footing
Factors in ft
F1 = 2.5
F2 = 4
F3 = 1
F4 = 4
CPT Cr Value
The cone penetrometer has proved to be a reliable tool for predicting settlements on shallow
as well as deep foundations. Safe prediction of strength and relative density has also been
made through this test.
Cone penetration tests shall be carried out at the selected locations as per ASTM D3441, BS
5930. The test is performed by pushing the standard cone (with a 600 point and base
diameter of 36 mm with cross-sectional area of 10 cm2) into the ground at a rate of 10 to 20
mm/sec. Data collected is the static cone resistance (Cr or qc), which shall be used for
estimation of relative density and angle of internal friction using correlations developed by
Schmertmann (1978) and Robertson and Campanella (1983), (Ref.4.1) Fig. 4.2 and Fig. 4.3.
Schmertmanns relationship given below shall be used for determining the settlement.
(Ref.4.2)
2B
C12pIEZz
0
, where
C1105.'p0p
C2102.log10t.
t = period in years for which settlement is to be calculated
E = deformation modulus depending on the L/B ratio (Fig.4.4)
Cr = static cone point resistance in ton/ft2 or kg/cm2
Soil parameters shall be evolved from laboratory tests on undisturbed samples but more
likely from SPT or CPT data obtained in the field.
The results of the above-mentioned field tests shall be judiciously used for predicting the
ultimate bearing capacity of either shallow or deep foundations with much greater accuracy
than using the results of routine laboratory tests only.
Curves selecting minimum of the above criterion will be developed for half of an inch, one
inch and two inches total settlements, giving allowable foundation pressures Vs foundation
sizes.
4.10 DEEP FOUNDATIONS
Wells/caissons shall be used as deep foundations so as to provide greater upward,
downward and lateral bearing capacity as compared to piles because of their larger
diameter. The following equations shall be applicable to the design of caissons in sands:
Q Q S Qb
Q S L f AS
Qb q b Ab
Where
Q, QS and Qb are the ultimate loads for axial, skin and end bearing.
fs = friction between caisson and adjacent sand
As = circumferential area of the shaft
qb = unit ultimate end bearing
Ab = area of the base of the caisson
QS shall be calculated by using the fs given by Reese(Ref.4.3) in the following form:
fSVtan
where
fS N
fS fC
N
= average standard penetration blow count within the caisson
embedment length corrected to an effective overburden pressure and
q b N q V
Where following table shall be used for determination of Nq by Peck.(Ref.4.4)
Standard penetration
Friction angle
Nq
Blow Count N
10
32
30
40
50
30
33
36
39
41
18
26
37
55
72
The ultimate base resistance shall also be estimated from correlations given by Meyerhof.
qb= 120 N
qb = qc
The ultimate lateral load resistance of intermediate fixed-headed caissons, for (1<L<2)
where L is the caisson length and
h 0.2
EI
Loose sand
Medium sand
Dense sand
kN/m3
Dry or moist
940
6590
17560
Submerged
1250
4390
10660
2M
Pult P1
Pult2
e.054
DKP
Pult = ultimate lateral load applied at a distance e above ground level
M = ultimate moment capacity of the caisson section
L = caisson length
D = caisson diameter
= unit weight of the soil
KPta2n45
2
= the angle of internal friction of soil
A factor of safety of 3.0 shall be used for design.
4.11 SOIL LIQUEFACTION
The liquefaction potential of the foundation alluvium will be evaluated under the Peak
Ground Acceleration (PGA) for each barrage site if applicable. The PGA will be established
on the basis of the seismic zoning map of Pakistan developed on the basis of geophysical
centre Quettas instrumental macro-earthquake data. Seismic zoning map of Punjab is
appended as Fig. 4.5. A PGA for Suleimanki, Khanki and Taunsa barrage shall be
determined from the seismic zoning map.
The evaluation shall be based on relative density of the in-situ soils using Seed and Idriss
(1971) approach.(Ref.4.1)
High
liquefaction
probability
Dr < 33%
< 48
< 60
< 70
Low liquefaction
probability
Dr > 54%
> 73
> 85
> 92
For the zones which would be identified as potentially liquefiable, further studies shall be
required. In the zones where the above studies indicate high strains and where the
embankments are not safe, appropriate remedial measures like densification of liquefiable
soils or deep foundations below the liquefiable zone shall be recommended.
4.12 COEFFICIENT OF HORIZONTAL EARTH PRESSURE
The at-rest earth pressure for static case and active earth pressure for dynamic case will be
used for the design of abutment and wing walls. If the soils retained behind the abutment
and wing walls are compacted backfill adequate increase in pressures due to compaction
efforts will also be taken into account.
4.13 BARRAGE EMBANKMENTS
a)
General
The embankment sections for the new barrage at Khanki shall generally be designed in line
with the guidelines issued by the Federal Flood Commission (FFC) with the following main
objectives:
i.
To provide a safe and economical design to suit the foundation conditions and
geology at the site.
ii. To maximize the use of river alluvium materials available within and around the
project area.
iii. To check the stability of the section under static loading and should be able to
withstand Maximum Design Earthquake.
b)
The stability shall be checked for following loading conditions and the minimum acceptable
factors of safety:
c)
1.3
Steady Seepage
1.5
1.2
Filters
The design of filters shall be based on filter rules developed by Sherard and Dunnigan
(1985) and adopted by USBR (1987) and USSCS (1986).
REFERENCE:
1.
2.
3.
4.
5. MECHANICAL DESIGN
5.1
GENERAL
The barrages under study are aged structures with ages ranging from 47 to 112 years, and
so are their mechanical and regulation systems. The barrages and the main off-taking canal
regulators are installed with vertical lift gates, radial gates or a combination of gates and
drop shutters. The vertical gates are supported either through Fixed Wheel System or Roller
Train System. Gates are designed to move vertically on the track fixed within the groove of
the pier.
The gates and hoisting mechanisms are in general badly deteriorated and will have to be
rehabilitated/and replaced where beyond repairs. The Consultants will identify the defects
and assess the present conditions/capabilities of the regulating gates system in detail and
establish the needs for rehabilitation, remodeling or replacement of the systems or parts
thereof including the most appropriate level of automation compatible with the needs,
structure acceptability and maintainable operatability.
5.2
5.2.1
Radial type gates being used successfully for the various recently constructed barrages
have been considered appropriate for new structures. Number of gates and their dimensions
will be fixed during detailed design stage of the Project. The barrage gates will be in lowered
position in order to retain the pond upstream and will be raised only at time of flood. The
gates of the under sluices will be opened more frequently for removing the silt.
5.2.2
Operation
The gates will be raised and lowered by means of wire rope hoists. The machinery will be
located at the top of the piers downstream of the bridge of the Barrage and Canal Regulator
gates. For pond control, the gates shall be moved from the fully closed position to the fully
open position with the low point of steel of the gate at Elevation to be fixed later. Matching
gate stops shall be provided in the piers to prevent over travel of the gates, in the event of
failure of the electrical controls to stop the gate.
Each gate will have its own electric motor and Raise-Lower contactor gear and in addition to
the push button control sited at the contactor gear, arrangements will be made whereby
contactors can operated by remote-control from one of the abutments, and extent of the gate
opening also be known automatically. As a stand-by precaution, all gates will be fitted with
hand operated gear.
5.2.3
Gate Features
In the case new structures to be installed with radial gates, the gates will be of all welded
construction, except the gate arms, which will be site-bolted to the horizontal girders and
trunnion assemblies. The arms of the end frames will frame into a trunnion hub assembly,
which will transmit the gate loads through trunnion pin into yoke mounted on a concrete
trunnion girder. The site thrust of the gate reaction resulting from inclination of the end
frames will be transmitted directly to the concrete piers. Provisions will be made for setting
and adjusting the trunnion shoes so that the axis of the trunnion hub assemblies when
seated shall be brought to a true and common horizontal line. The side seal will be in contact
with side seal steel plates embedded in the face of the concrete pier. The bottom seal will be
fastened to the lower edge of the gate and will contact a steel sill beam embedded in the
face of the Barrage or Canal Regulator crest. The side seals shall be set to a slight initial
compression to ensure positive contact with the side seal plates. The bottom seal shall be
compressed, as the bottom edge of the gate comes to rest on the sill.
5.2.4
Hoist Features
All the hoists would be identical for Barrage and Regulator gates. They will be wire rope
hoists having two drums each. There will be one motor per hoist. Each motor will be located
over a pier, so that power is transmitted to one drum by a drive shaft. The drive shaft will be
supported throughout its length by bearing pedestals located on a catwalk. Each drum will
wind required number of corrosion resisting wire ropes spirally, thus minimizing the drum
lengths. There will be a drum gear and pinion, with the remainder of speed reduction
accomplished by a triple reduction gear speed reducer and a right angle worm gear unit.
Limit or position sensor switches will be provided as required to implement the desired
operation control for the gates.
5.3
CODES
AGMA
AISC
ASTM
ASME
5.4
DESIGN LOADS
The gate equipment shall be designed for the applicable loads described hereunder:
i.
Dead Load
The dead load includes the weight of the components, machinery elements, equipment,
protective devices and contained fluids. Eccentricity of loading shall be taken into account
when the actual loading conditions are asymmetrical.
ii.
Hydrostatic Load
Hydrostatic loads shall be calculated with a specific weight of 62.5 lb/ft3 (1000 kg/m3) for
fresh water. Components of gate subjected to water pressure will be designed for hydrostatic
loads corresponding to the maximum differential pressure expected during the life of the
Project.
iii.
Buoyancy
The nominal buoyancy shall be calculated using the volume of the gate including any other
equipment mounted thereon.
iv.
Friction Forces
applicable coefficients of
Maximum
Minimum
0.50
0.10
steel, lubricated
0.18
0.08
Rubber on steel
1.00
0.30
0.15
0.05
0.50
0.15
Corrosion-resisting steel
on carbon steel, non-lubricated
Corrosion-resisting steel on carbon
v.
Wind Load
Horizontal wind load of 30 lbs/sq.ft., acting in any direction on the projected area of affected
components, will be considered in the design.
vi.
Seismic Loads
Seismic effect shall be calculated by applying a horizontal force resulting from the specified
earthquake acceleration on all masses in any direction and adding the dynamic water loads
to the static water loads acting on the gates.
vii.
Live Loads
Walkway flooring shall be designed for a uniformly distributed load (UDL) of 100 lbs/ft2 plus
a superimposed concentrated load of the heaviest piece of hoisting equipment or subassembly. Stair treads and their fastenings shall be designed for a concentrated live load of
1000 lbs. The catwalk shall be 3 ft. clear width and shall be designed for a UDL of 50 lbs/ft2
plus a single movable concentrated load of 1000 lbs.
viii.
Thermal Loads
The thermal forces will be considered in the design of the components when temperature
fluctuations relative to an assumed erection temperature would exceed 10o C.
A temperature variation of 5o C to 55o C shall be used for design of the components located
periodically exposed and submerged respectively.
ix.
Miscellaneous Loads
Loads due to changes in conditions of support, lifting and raising forces as well as impact will
also be considered in the design of components thus affected.
5.5
The detailed design of equipment will be based on the following most critical loading
condition applicable to major components.
i.
Erection Conditions
Normal loading
Equipment in any stage of erection subjected to applicable dead and live loads plus forces
resulting from the erection procedures.
Exceptional loading
Normal loading plus wind/earthquake effects.
ii.
Operating Conditions
Normal loading
Gates closed. Effects of the following loads shall be combined:
Water load.
Dead weight.
Gates being raised or lowered, at any point of travel. Effects of the following loads shall be
combined:
Water load.
Dead weight.
Additional friction and/or blocking forces originating in the guiding devices and at the
seals in contact, and having the magnitude required to match the rated hoist
capacity.
Exceptional loading
Exceptional loading conditions shall be obtained by combining each one of the normal
loading conditions with the effect of one exceptional force component. The following
exceptional combinations shall be considered:
Water load.
Earthquake effect.
Exceptional operating forces, including maximum hoist pull, combined with any
normal loading condition.
5.6
i.
Wind effect.
WORKING STRESSES
Factor of Safety Mechanical Components
A factor of safety not less than 5, based on the ultimate strength of material, will be used
under normal loading conditions.
ii.
Allowable Stresses
The allowable stresses for structural steel under normal loading conditions shall be those
given in the AISC Specifications for the Design, Fabrication and Erection of Structural Steel
for Buildings but shall not exceed the following:
Fy = Yield stress
Fu = Ultimate stress
Fa = Allowable stress
Type of Stress
STRUCTURAL MEMBER
Bending
Shear
Tension
Bearing pressure (machined surfaces)
Combined stresses
Buckling
- AISC value
- Hertzian stresses Kg/mm2
MECHANICAL COMPONENTS
For all mechanical components
Load Cases
Normal
Exceptional
0.60 Fy
0.40 Fy
0.45 Fy
0.80 Fy
0.75 Fy
0.80 Fy
0.50 Fy
0.50 Fy
0.85 Fy
0.95 Fy
1.00 Fa
0.55 BHN
1.30 Fa
0.60 BHN
0.33 Fy
or
0.20 Fu
whichever are minimum
0.67 Fy
or
0.40 Fu
5.7
5.7.1
GATE DESIGN
Gate Leaves
Gate leaves shall be designed by considering a vertical unit width of skin plate as a
continuous beam with supporting haunches and modified end cantilevers. The flanges of the
horizontal beams are the supporting haunches and shall be considered to have an effective
width equal to the actual flange width for welded construction. The portions of the skin plate
above the top beam and below the bottom beam are cantilevered sections supported
laterally at frequent intervals by brackets welded to the horizontal beams. Those portions of
the skin plate shall be designed as a series of rectangular plates with edges supported at the
brackets, fixed at the horizontal beam bending. The skin plate is subjected to biaxial stresses
resulting from skin plate bending and from horizontal beam bending. The combined stress
shall be evaluated by means of Westergaards criteria of failure for ductile material subjected
to two-dimensional stress and shall be limited to the value given for combined stress under
allowable stresses.
The horizontal beams shall be designed to resist the moment produced by the hydrostatic
load on the continuous skin plate. Since the skin plate is attached to the horizontal beams, it
adds to the moment of inertia of the beam. The width of skin plate effective in resisting
bending as a part of the horizontal beam area shall be considered as equal to 30 times the
thickness of the skin plate.
5.7.2
In case of the design of vertical gates with wheels, adequate number of wheels shall be
provided to take up the hydrostatic load and they should be symmetrically positioned about
the vertical central axis of the gate.
The tracks shall be slightly crowned in order that the point of contact remains in the central
portion of the track even though the side beams have rotated slightly due to the bending of
the main beams. Hence the stresses should be analysed for point contact.
The wheel pins shall be designed for bearing, bending and shear. They may be supported at
both ends within the gate frame or cantilevered out from a box.
The pin supports shall be designed for bearing and shearing forces.
5.8
5.8.1
GATE HOISTS
Loads
Efficiencies
90 per cent
95 per cent
95 per cent
Drum bearings
96 per cent
ii.
Operating Speed
The speed at the rope attachment will be approximately one foot per minute when half the
amount of rope, from closed to normal full open position, is wound on the drums.
5.8.2
i.
Gate in lowered position either resting on sill or being lifted off pond at maximum Elevation.
This case is considered a normal loading condition.
ii.
Gate in lowered position either resting on sill or being lifted off pond at maximum Elevation,
earthquake forces acting downstream. This case is considered an exceptional loading
condition.
iii.
Gate in fully raised position, lower edge of gate clearing maximum water in pond. Wind load
acting in either the upstream or downstream direction, whichever is critical. This case is
considered an exceptional loading condition.
iv.
Gate jammed at both sides. Pool at maximum Elevation. Rope tension caused by maximum
motor torque, load divided equally between rope attachments. This is considered an
exceptional loading condition.
v.
A uniformly distributed live load of 100 pounds per square foot plus a superimposed
concentrated load of the heaviest piece of hoist equipment of subassembly will be used to
design the hoist machinery platform. Deformation of the hoist platforms will be limited to the
amount which will limit the maximum gear misalignment to that permitted by AGMA
(American Gear Manufacturers Association) Standards.
5.8.3
Working Stresses
Allowable working stresses for the design of the gate and its component members for the
various loading conditions will be the percentages of the yield stress of the respective
material used as shown in Table 5.1 below.
TABLE 5.1
Allowable Working Stresses
Allowable Working Stress
Tension (on net section)
Bending (tension and compression on extreme
55
73
75
33
45
50
girder webs)
Working stress values for welds and bolts may be obtained by multiplying comparable
values in the AISC Specifications for the Design, Fabrication and Erection of Structural Steel
for Buildings, 1967, by a factor of 83 per cent, to obtain allowable stress to be used for
normal loading conditions. AISC values should be multiplied by 111 percent to obtain
allowable stresses for exceptional loading conditions, and by 125 percent to obtain allowable
stresses for extreme loading conditions. Combined stresses, where existent, shall be
computed on the basis of the Hencky von Mises formula and will be limited to 75 percent of
the yield stress of the material for any loading condition.
ii.
Mechanical parts will be designed for the loads described above using a factor of safety of 5,
based on the ultimate strength of the materials used. The unit stress at momentary overload
due to maximum torque of the motor will not exceed 85 percent of the yield point stress of
the materials used except that rope tension at maximum motor torque will not exceed 70
percent of the bearing strength. All rope fittings and attachment of the rope will develop the
full strength of the rope.
5.9
5.9.1
MACHINERY DESIGN
Shafting
Shafting will be designed in accordance with Sub-Clause 1.1f (2) Mechanical Working
Stresses and Safety Factors. A shock or fatigue factor of 1.25 will be used for shafting,
except for speed reducers.
5.9.2
Anti-friction Bearings
Anti-friction bearings will be of standard design most suitable for the applications and shall
have both inner and outer races. The bearing manufacturers published ratings will be used
in determining the bearing capacity. They will have a B-10 life of 5000 hours, which is the
number of hours (at a given constant speed and load) that 90 percent of a group of tested
bearings will exceed before the first evidence of fatigue develops.
5.9.3
Gears
Drums
The minimum diameter of the drum for winding the first turn of rope will be not less than 30
times the nominal rope diameter. The outside diameter of the drum flanges or spacers will be
not less than the outside diameter of the final spiral wrap with gate fully raised, plus four rope
diameters. With gate resting on the sill, there will be at least two complete wraps per rope on
each drum.
5.10 WALKWAYS AND CAT WALKS
Walkway flooring will be designed for a uniformly distributed live load of 100 pounds per
square foot plus a superimposed concentrated load of the heaviest piece of hoist equipment
or sub-assembly. Stair treads and their fastening will be designed for a concentrated live
load of 1000 pounds. The catwalk will be 36 inches clear width and will be designed for a
uniform live load of 150 pounds per linear foot plus a single movable concentrated load of
1000 pounds. The catwalk structure will be sufficiently rigid to deflect no more than inch
under the above maximum live load conditions.
5.11 HOIST PLATFORMS
The hoist platforms and catwalks shall be designed to suit the proposed equipment layout.
All mechanical components will be supported directly on the structural members of the hoist
platform. The hoist platform and catwalk gratings will be all welded construction and will be
fastened to the steel supports by clips or fasteners. Hoist platforms will be tied down to pier
concrete by means of anchor bolts designed to resist all possible loading casers. Hoist
platforms will be designed to carry the specified live loads, dead loads, machinery loads,
catwalk loads, and normal gate hoisting loads at the specified basic stress, including the
effect of one gate fully opened and the adjacent gate resting on the sill. The platform will also
be designed to resist the loads resulting from stall torque of the hoist motors together with
dead and machinery loads. Deformation of the hoist platforms will be limited to the amount,
which will limit the maximum gear misalignment to that permitted by AGMA Standards.
1.
2.
INTRODUCTION............................................................................................................. 1
HYDRAULIC DESIGN.....................................................................................................1
STRUCTURAL DESIGN.................................................................................................1
3.1 General.............................................................................................................................1
3.2 Design Loading ...............................................................................................................1
3.3 Stability Criteria...............................................................................................................4
3.4 Floatation..........................................................................................................................5
3.5 Allowable Stresses............................................................................................................5
3.6 Minimum Reinforcement (or Temperature Reinforcement)............................................7
3.7 Minimum Concrete Cover for Reinforcement.................................................................8
3.8 Concrete Joints.................................................................................................................8
3.9 Pre-stress Concrete...........................................................................................................9
4.
GEOTECHNCIAL DESIGN.............................................................................................1
4.1 General.............................................................................................................................1
4.2 Ground Exploration..........................................................................................................1
4.3 Geophysical Explorations................................................................................................2
4.4 Laboratory Testing............................................................................................................3
4.5 Data Evaluation and Analyses..........................................................................................3
4.6 Foundation Design Criteria..............................................................................................3
4.7 Estimation of Foundation Stresses...................................................................................4
4.8 Shear Based Design..........................................................................................................4
4.9 Settlement Based Design..................................................................................................5
4.10 Deep Foundations...........................................................................................................7
4.11 Soil Liquefaction............................................................................................................9
4.12 Coefficient of Horizontal Earth Pressure.....................................................................10
4.13 Barrage Embankments.................................................................................................10
5.
MECHANICAL DESIGN..................................................................................................1
5.1 General.............................................................................................................................1
5.2 Type and Description........................................................................................................1
5.2.1 General......................................................................................................................1
5.2.2 Operation...................................................................................................................1
5.2.3 Gate Features.............................................................................................................2
5.2.4 Hoist Features............................................................................................................2
5.3 Codes................................................................................................................................2
5.4 Design Loads....................................................................................................................3
5.5 Load Combinations and Conditions.................................................................................5
5.6 Working Stresses..............................................................................................................6
NDC | NESPAK | ATKINS
(ii)
(iii)
LIST OF FIGURES
Figure 2.1
Figure 2.2
Figure 2.3
Figure 2.4
Figure 2.5
Figure 2.6
Figure 2.7
Figure 2.8
Figure 2.9
Figure 2.10
Figure 2.13
Figure 4.1
Figure 4.2
Figure 4.3
Figure 4.4
Figure 4.5
(iv)