Professional Documents
Culture Documents
Application1:CalculatinganMRPRecord
Item H10-A is a produced item (not purchased) with an order quantity of 80 units.
Complete the rest of its MRP record using the fixed order quantity (FOQ) rule.
Item:H10ALotSize:FOQ=80units
Description:ChairseatassemblyLeadTime:4weeks
Week
31
32
Grossrequirements
60
Scheduledreceipts
80
Projectedonhandinventory
Plannedreceipts
Plannedorderreleases
.
20
20
100
33
34
35
36
37
35
40
40
40
40
0
80
80
38
39
45
5
80
40
60
40
40
80
MaterialRequirementsPlanning
Application3:MRPRecordusingthelotforlot(L4L)Rule
Revise the H10-A record using the lot-for-lot (L4L) Rule.
Item:H10ALotSize:L4L
Description:ChairseatassemblyLeadTime:4weeks
Week
31
32
Grossrequirements
60
Scheduledreceipts
80
Projectedonhandinventory
Plannedreceipts
Plannedorderreleases
20
20
100
33
34
35
36
37
35
40
40
40
40
0
40
60
38
39
45
5
40
40
60
0
60
MaterialRequirementsPlanning
Application4:MaterialRequirementsPlanforSingleProductCase.
A firm makes a product (Item A) from three components (Items B, C, and D). The latest
MPS for product A calls for completion of a 250-unit order in week 8, and its lead time is
2 weeks. The master schedule and bill of material for Product A are given below.
Week
5
MPS Quantity
MPS Start
a.
8
250
250
Develop a material requirements plan for items B, C, and D, given the following
inventory data. Blank MRP records are also provided.
ITEM
Data Category
Lot-sizing rule
Lead time
Scheduled receipts
B
L4L
2 weeks
None
C
FOQ=1000
1 week
1000(week 1)
D
L4L
3 weeks
None
Beginning inventory
200
Application Supplement
Item: End Item A
MPS Quantity
MPS Start
250
Item: B
Lot size:
L4L
1
Gross Requirements
Scheduled Receipts
Projected On-hand Inven.
Net Requirements
Planned Order Receipts
Planned Order Releases
Lead Time: 2
3
500
0
0
500
500
500
Item: C
Gross Requirements
Scheduled Receipts
Proj. On-hand Inv. 200
Net Requirements
Planned Order Receipts
Planned Order Releases
8
250
Week
5
6
250
0
0
250
250
250
Lot size:
FOQ = 1000
1
1000
1000
1200
0
0
200
200
Lead Time: 1
4
500
0
200
300
1000
Week
5
700
6
250
0
700
0
450
450
1000
Item: D
Lot size:
L4L
1
Gross Requirements
Scheduled Receipts
Proj. On-hand Inven.
Net Requirements
Planned Order Receipts
Planned Order Releases
Lead Time: 3
3
500
Week
5
6
500
0
0
500
500
Your Question: What determines the order time in B and C of the forks that are not on
week 6? How come, for example, in B you are ordering 500 in week 3 for the right fork
when it only needs 250? and in C when 1000 is ordered in week one for the right fork
when it only needs 500?
Answer: You must follow the decisions down the BOM for each fork. They are color
coded, as above. Basically, you end up multiplying requirements for the level above, by
the number required at the next level. As a result, your requirements keep growing with
each level down the BOM that you go.
BLUE = decisions about materials required for the leftmost fork of the bill of materials
PURPLE = decisions about materials required for middle fork
GREEN = decisions about materials required for right fork
Moving down the left fork, we need 2 C's to assemble each B, so our gross requirement
of C's will be 250 * 2 = 500 C's during Week 4. During Week 4, we will have 200 C's
projected to be onhand inventory, so we will only have a Net Requirement of 300 C's.
Since we are ordering fixed order quantities of 1000, we will plan to receive an order of
1000 C's during Week 4, and due to the one week Lead Time, we'll place the order for
1000 C's during Week 3.
MIDDLE FORK
Finally, the middle, and easiest/shortest, fork (PURPLE NUMBERS). For each A, we
need one C. Thus, for 250 A's during Week 6, we'll need to have 250 C's available. So,
our gross requirement will be 250 C's in Week 6. We will have 700 C's in on-hand
inventory left over from our order that we receive in week 4, so this will cover the need
for 250 C's in Week 6, leaving us with 450 C's in inventory for Weeks 7 and 8.