Professional Documents
Culture Documents
7786
Abstract
Many underground structures are constructed for use as car parks and shops in basements of buildings and as mass rapid
transit stations, depressed roadways and civil defense shelters in cities located in coastal areas where the ground is level and the
elevations are low, with an attendant high groundwater table. This paper discusses the various methods of resisting hydrostatic
uplift. These include the use of tension piles and the installation of a water pressure relief system under the base slab of the
basement. A case history in Singapore employing a pressure relief system below a three-level basement is presented. 2001
Elsevier Science Ltd. All rights reserved.
Keywords: Deep excavation; Groundwater pressure; Uplift; Stiff; Soft soils
1. Introduction
A large amount of underground space is being constructed each year in Singapore and other cities. Basements in buildings mainly serve as car parks and shops.
In Singapore, government regulations require the developers of shopping malls, offices, apartment complexes and hotels to provide on-site vehicle parking.
The very high costs of land here have forced developers
to house the car parks within the buildings, mostly in
basements. Underground space is also used as mass
rapid transit stations, depressed roadways and civil
defense shelters.
Many cities are located in coastal areas where the
ground is level and the elevations are low, with an
attendant high groundwater table. The underground
structures in these cities thus have to be designed to
resist high hydrostatic uplift loads. Many jurisdictions
require that the design groundwater table for uplift be
taken at the ground level.
This paper discusses the various methods of resisting
U
0886-7798r01r$ - see front matter 2001 Elsevier Science Ltd. All rights reserved.
PII: S 0 8 8 6 - 7 7 9 8 0 1 . 0 0 0 3 7 - 2
78
Where:
w s
z s
B s
79
80
152-mm Diameter
concrete pipe
2.8 m2 Aggregate
drain
12 m2 Aggregate
drain
370 m2 Aggregate
drain
Aggregate
size
mm.
Permeability
of aggregates
mrday.
Gradient
0.01
1925
619
Clean pea
gravel
36 500
0.01
9100
0.01
300
0.01
81
Table 2
Discharge capacities of drain pipes of various sizes
Pipe
radius R
m.
Hydraulic
radius r
m.
Hydraulic
gradient i
Discharge
Qp
m3rs.
Discharge
Qp
m3rh.
0.05
0.075
0.10
0.15
0.025
0.0375
0.05
0.075
0.01
0.01
0.01
0.01
0.0048
0.0141
0.030
0.089
17.28
50.76
108.0
320.5
Ratio
Qp r Qb
640
1880
4000
11 870
82
83
In Singapore the maximum water draw down is generally limited to 3 m except for works in the vicinity of
mass rapid transit system while the limit is only 1 m
where soft clayey soils are present. Recharging of the
surrounding ground with recharge wells is often used to
reduce the ground and structure settlements caused by
dewatering. While recharging has often been utilized
for temporary excavation projects, its use in connection
with a permanent under-drain system is uncommon
and thus its effectiveness uncertain.
84
Table 3
Index properties of clay matrix of bouldery clay at Raffles City
Complex
Index properties
Range of
values
Liquid limit %
Plasticity index %
Percent fines %
Percent clay %
3754
2136
64100
3854
Sump 1
Sump 2
Sump 3
Sump 4
Sump 5
Sump 6
Sump 7
Sump 8
Sump 9
Total flow
Flow rate on
23 March 1995
lrmin.
Flow rate on
15 August 1996
lrmin.
Flow rate on
19 February 1997
lrmin.
Sunny day
Rainy day
Sunny day
0.165
0.097
0.143
0.106
0.085
nil
0.031
nil
0.025
0.652
0.515
0.113
0.355
0.269
0.097
0.061
0.098
0.016
0.075
1.599
0.151
0.068
0.145
0.089
0.046
Trickle
0.054
0.012
Trickle
0.565
noted in Table 4, on 2 of the 3 days when flow measurements were made, the weather was dry, and on the
third day, it was raining. The total flow ranged from 0.6
to 1.6 lrmin, which is very small.
85
10. Conclusions
Methods of resisting hydrostatic uplift loads at the
base of basements and other substructures include the
use of tension piles, shear keys and under-drains.
Tension piles that can be used to resist uplift loads
include steel H piles, micropiles and bored piles. Published literature strongly suggests that steel piles installed in undisturbed, native soil undergo very little
corrosion. Piles installed under a substructure would
invariably be in natural soil since the overlying fill will
mostly likely have been excavated. Micropiles similarly
are suitable for resisting uplift loads. Bored piles are
uneconomical structurally as tension piles because the
concrete in the bored piles cannot carry tension loads.
Installing shear keys into the soil beyond the perimeter of the basement is not practicable in situations
where diaphragm walls, secant pile walls, or contiguous
bored pile walls serve as permanent walls.
Where ground conditions are suitable, under-drains
are very effective for relieving the hydrostatic pressure
acting at the base of substructures, particularly if the
substructures are located in stiff and impermeable soils.
For very stiff or hard soils, the lowering of the
groundwater level induce little or no adverse effects on
surrounding ground or adjacent structures
For sites surrounded by soft soils or deep pervious
layers permanent dewatering is not feasible because of
the potential for large ground settlements and for the
influence zone of the groundwater lowering to spread
far from the substructure site.
Fig. 7. Photographs of sumps in under-drain system at Raffles City complex after Anand, 1997..
86
References
Anand, S., 1997. Design of basement slabs against hydraulic uplift.
MSc Dissertation. Nanyang Technological University, Singapore.
British Standard Institution, 1986. British Standard Code of Practice
For Foundations, BS 8004:1986. London.
Cedegren, H.R., 1967. Seepage, Drainage and Flow Nets. John Wiley,
New York.
Romanoff, M., 1962. Performance of steel pilings in soil. NBS Monograph 58, National Bureau of Standards. US Dept. of Commerce.
Romanoff, M., 1969. Performance of Steel Pilings in Soil. Proc. 25th
Conference. National Assoc. of Corrosion Engineers, USA.
Shirlaw, J.N., Poh, K.B., Hwang, R.N., 1990. Properties and origins of