Professional Documents
Culture Documents
1&2, pp 92{103
of
SI
In this paper, a framework for operation of hydropower reservoirs in Iran is discussed. A time
decomposition approach, which breaks down the operation optimization problem to long, mid
and short-term planning stages, is developed. Stochastic dynamic programming models are
developed for long-term and mid-term optimization and a deterministic dynamic programming
model is developed for short-term optimization of two hydropower-reservoirs (a parallel system).
An economic analysis of the benets and cost of the operation are incorporated in all three stages
of planning by developing economic cost functions. The developed algorithm is applied to the
Karoon and Dez river-reservoir systems in the southwest of Iran. The results of this study have
shown the signicant value of the developed models and their relational framework in providing
more exibility and adaptability in using methods and tools for decision-making in real world
situations.
INTRODUCTION
Ar
ch
ive
www.SID.ir
93
SI
Ar
ch
ive
of
www.SID.ir
94
2
X
j =1
t;1
m = t ; 12
12
where:
(1)
(2)
Ar
Rjt
Sjt
ch
ive
(3)
where:
SPm
SI
PGjt
PGTjt
of
(4)
(5)
(6)
www.SID.ir
95
1 +
Power
C (R1t R2t PG1t PG2t )= LossWater
jt + Lossjt
m
w
0
Losswater
jt = Pjt (Rjt ; Dm ) (1 + H )
where:
otherwise
Losspower
jt
j =1
j =1
(7)
(10)
Ar
ch
ive
of
(9)
Losswater
jt
2
X
SI
Rjt
2
X
jt
Pjtw = Cost
R
jt
(8)
w
Losswater
jt = Pjt (Dm ; Rjt )
jt
when ! R
D
1
m
w
00
Losswater
jt = Pjt (Dm ; Rjt ) (1 + H )
otherwise
(11)
(12)
www.SID.ir
96
PLhourly
jkt =
8
>
hourly
>
<PGTjkt
kP
;1
ive
ch
Ar
Table 1.
hourly
if PLjt ; PLhourly
>PGTjkt
m=1 jmt
kP
;1
>
>
:PLjt ;
PLhourly
jmt
m=1
otherwise
(k = 2 : : : 5)
(14)
of
load is highly sensitive to short-term decisions. Therefore, dierent methods for aggregation of the longterm strategies to short-term policies (tactics) should
be selected carefully. Separating peak and rm power
generation is not considered in most of the long-term
operation models developed by dierent researchers.
In this study, in order to have a better estimate
of losses due to power shortages, the values of power
generated at dierent hours are estimated and the
dierence between the maximum economic benets
that could be gained and the benets that are actually
provided, based on power generation, is estimated.
Although no loss is actually incurred, the power costfunction is a reection of an opportunity gain that is
lost. It should be noted that the decits in supplying
loads are provided by thermal units, which have a
signicantly higher cost. Table 1 shows the classication of the value of power generation in dierent
hourly classes in each month. As can be seen in this
table, the cost of no energy production during low-load
hours is much less than no production during high-load
hours. Classication of the value of power generation
in Table 1 is based on the load of the system and is
dened as follows:
Very high load hours (k = 1),
High load hours (k = 2),
Medium load hours (k = 3),
Low load hours (k = 4),
(
hourly if PLhourly >PGT hourly
hourly
j1t
j1t
jkt
PLj1t = PGThourly
PLjt
otherwise
(13)
SI
Figure 2.
where:
PLjt
Value
Load Classication Duration (Hours) (Monetary
Unit/Kwh)
Very high load hours
High load hours
Medium load hours
Low load hours
Very low load hours
80
140
60
260
180
83
74.6
70
56
55
www.SID.ir
97
5
P
k=1
hourly
PL
jkt
hourly
; P Ghourly
Pkt
jkt
if
hourly
PG
jkt
< PL
otherwise
hourly
jkt
(15)
where:
hourly
Pkt
Ar
ch
ive
of
Losspower
jt =
SI
following equation:
www.SID.ir
98
j =1
h
P Lshort
dh
short
; P Gshort
Pdh
dhj
if
otherwise
where:
PLshort
dh
PGshort
dhj
(16)
j =1 d=1 h=1
Ar
ch
ive
SI
P2
of
short
short short
Lossshort
dh (PGdhj PLdh Pdh ): (17)
RESULTS
The monthly operation of the Karoon and Dez reservoir
systems over a 19 year period (1978-96) is simulated
using the optimal policies obtained from the longterm planning model. For this purpose, a general
streamow forecasting model (Auto-Regressive Integrated Moving Average (ARIMA) model, with nonseasonal parameters (p d q) and seasonal parameters
(P D Q) and a seasonality of twelve, for forecasting monthly inow to the reservoirs), was developed,
considering the required transformation of data and
comprehensive statistical analysis. Seasonal and nonseasonal parameters were calculated and inow forecast
time series were generated by going back in time and
forecasting three months at a time from the beginning
of the operation. The ARIMA (1 0 1)(1 0 1)12 and
ARIMA (1 0 1)(1 1 1)12 models were selected as the
best forecasting models for the streamows entering the
Karoon and Dez reservoirs, respectively.
Figures 4 and 5 show the comparison between
www.SID.ir
99
Karoon and Dez reservoirs and the study area in the southwest part of Iran.
ive
Figure 3.
of
SI
Ar
ch
www.SID.ir
100
Table 2.
1010.05
1050.91
817.47
1096.98
1242.51
1127.56
772.51
207.32
77.36
100.03
276.76
640.92
8420.38
SI
1010.05
1032.71
814.3
1085.63
1116.3
1075.28
772.51
207.32
77.36
100.03
276.76
640.92
8209.17
of
April
May
June
July
August
September
October
November
December
January
February
March
Total
DDSP Demand
ive
Month
ch
Assumptions for mid-term planning including results of the long-term model in September 1995.
Ar
Table 3.
Reservoir
Karoon
Dez
1523.2
962
1912.2 1073.5
130.75
40.1
135
45.3
140.25
49.7
137
52.5
154
76.1
14340
14467.1
14628.7
15507.4
180
www.SID.ir
101
Results of the mid-term model in September 1995.
Reservoir
1616.69
1712.56
1815.34
1912.2
10002
10111
10105
10774
Dez
984
1009.8
1039.4
1073.5
4338.5
4356
4524
4732
ch
ive
of
SI
Karoon
Ar
Figure 6.
power demands, while it has also satised the longterm model constraints. The results also show that
the weekly model has failed to meet the demands and
constraints of the long-term model, when the errors in
the inow forecasts have been signicant.
In the short-term model, the weekly load pattern
shown in Figure 6 is used. Figure 7 shows the results
of the short-term model for the rst week of September
1995. Considering the high load for this week, the
system was not able to provide the total power load,
due to limited water that could be released, based
on optimal policies of the mid-term model. The
hourly variation of the power value (price) is shown
in Figure 8. The highest power load occurs in early
evening and is higher than power plant capacity. The
hourly variation of the power generated by the system
www.SID.ir
102
COMPUTATIONAL REQUIREMENTS
Table 5.
Power Load
Very high load hours
High load hours
Medium load hours
Low load hours
Very low load hours
SI
In this paper, the decision-making framework for operation of hydropower reservoirs in Iran is considered
as a basis for formulating a set of reservoir operation
optimization models. A temporal decomposition approach is employed, including long, mid and shortterm planning models. The main objective of these
models was to create more exibility in the decisionmaking process. The Demand Driven Stochastic Dynamic Programming Model (DDSP) is developed for
operation of two hydropower-reservoirs in a parallel
system for long and mid-term planning. In the long and
mid-term models, the inow/forecast uncertainties are
incorporated in developing optimal operation policies.
In short-term scheduling, the inow uncertainties do
not have a major eect on power generation estimation. Therefore, a deterministic dynamic programming
model is formulated for hourly operation of the two
reservoirs.
The benets and costs of reservoir operation are
incorporated at all planning levels through economic
cost functions. For this purpose, the annual reservoir
costs are estimated and used for determining cost
associated with the water supply. The hourly variation
of power value (price) is also considered in determining
the cost of reservoir operation associated with the
decits in supplying energy demands.
The approach was applied to the Karoon and
Dez river-reservoir systems in southwest Iran. Results
of this study show that the developed framework
provides a exible tool for the system operation. The
optimal DDSP policies produce a 10 percent larger
power generation compared with historical records.
Also, more than 97 percent of the water demands are
supplied.
The mid-term model (weekly) incorporates the
uncertainties associated with weekly inow and develops the weekly operation policies that can be used for
real-time operation. The short-term model (hourly)
determines the optimal schedule of hourly reservoir
releases that maximize the power generation benets.
Overall, the developed models provide acceptable
levels of reliability for water and power supply in
ch
ive
of
Ar
Figure 7.
Figure 8.
www.SID.ir
103
REFERENCES
6.
7.
8.
9.
Ar
ch
ive
of
5.
ACKNOWLEDGMENTS
4.
SI
www.SID.ir