INSPECTION AND TEST PLAN for: Grounding Installation


Work area: (Insert work area)
R Review
H Hold Point

Activity
Description

Specification/
Code Reference

W - Witness
Responsi
bility

Verifying
Document
s

Inspection Requirements
Meade
Customer
Owner
Rep
Rep

Document Review of Applicable Procedures,


Specifications, Drawings, Contract
Documents
Verify the electrical systems that require
grounded neutrals are installed/tested in
accordance with specifications and drawings
Verify Grounding electrode system materials
are in accordance with specifications and
drawings
Verify Grounding electrode system
installation in accordance with specifications
and drawings
Verify Grounding electrode system is tested
in accordance with specifications and
drawings
Verify buried/above ground grounding
system conductors between equipment and
grounding electrode system are installed,
routed in accordance with specifications and
drawings
Verify Buried Grounding cable taps and
splices are exothermically welded or
connected with an approved mechanical
connector, and coated in accordance with
specifications and drawings
Verify Grounding conductors between
equipment and grounding electrode system
are resistance tested in accordance with
specifications and drawings
Verify Grounding conductors are protected
by conduit sleeves where required
Verify Grounding connections tight, and are
per specifications
Verify Rebar Grounded per specifications
Verify Ground conductors installed in duct
Version:
1.0

Revision
Date:

Description of Change:

Original Issue
This document is controlled electronically on the Meade Intranet. Printed or electronically transmitted copies are uncontrolled.

Comments

Grounding Installation Inspection and Test Plan


(ITP)

Page 2 of 2

Division/Department: Engineering
Discipline:

13
14
15
16

banks per specifications


Verify DCS grounding is in accordance with
specifications and drawings
Verify electrical equipment grounding is
visible in accordance with OSHA
Production to inform QC of near completion
of work scope prior to demobilization for
final acceptance/walkdown
Compile and Review of completed QC
package and submit

Name

Position

Signature

**** Site Project Manager/Forman


Designee:
**** Quality Manager/Designee:
Customer Quality Approval or Job
Rep:

Version:
1.0

Revision
Date:

Description of Change:

Original Issue
This document is controlled electronically on the Meade Intranet. Printed or electronically transmitted copies are uncontrolled.

Date

You might also like