Professional Documents
Culture Documents
Issue: 04
Date: 1st June 2011
Revision History
Issue
01
Date
19.07.05
02
23.06.06
03
20.04.07
04
01.06.11
Document Distribution
Copy
01
Recipient
Document Control Master.
Page 2 of 34
NAT/REP/MPI/ENG/EP3736860
Issue: 04
Date: 1st June 2011
Contents
1.
Introduction................................................................................................................................. 4
2.
Scope ........................................................................................................................................... 4
3.
4.
5.
6.
7.
8.
9.
10.
11.
Training...................................................................................................................................... 23
12.
Page 3 of 34
NAT/REP/MPI/ENG/EP3736860
Issue: 04
Date: 1st June 2011
1.
Introduction
This document provides the generic Network Rail technical requirements for the design
and installation of electric points heating equipment and forms an integral part of the
design requirements for site specific detailed design. The Standard Detail Drawings of
points heating installations are included in Appendix D.
2.
Scope
This document applies to all new and replaced electric points heating equipment
installed by Network Rail. The scope includes electrical supply, distribution, control and
track mounted equipment.
This document mandates the requirements of NAT/TW/InfraInv/ENG/EP6248683
Design and Installation of New, Renewed or Refurbished Distribution Network
Operators (DNOs) Intakes and Consumer Facilities in respect of the DNO electrical
supplies.
The Standard Detail Drawings for points heating installations are included in Appendix D
and form part of these design requirements.
Page 4 of 34
NAT/REP/MPI/ENG/EP3736860
Issue: 04
Date: 1st June 2011
3.
DNO
EMC
Electromagnetic Compatibility
MP&I, E&P
RCD
RMU
SCADA
WMCU
PME
PHCC
MCB
MCCB
DC
Direct Current
AC
Alternating Current
TCB
UTX
URX
ELR
O&M
Page 5 of 34
NAT/REP/MPI/ENG/EP3736860
Issue: 04
Date: 1st June 2011
4.
2)
3)
4)
5)
6)
7)
8)
BS 5395-3 : Stairs, ladders and walkways. Code of practice for the design of
industrial type stairs, permanent ladders and walkways.
9)
Any requests for departures from the requirements of this document or relevant
standards shall be submitted in writing to the Employers Representative,
6
Page 6 of 34
NAT/REP/MPI/ENG/EP3736860
Issue: 04
Date: 1st June 2011
together with justification for the request, including any efficiency benefits that
may be achieved.
In the event of any apparent conflict between the requirements of this
document and other relevant standards or Network Rail documents, the matter
shall be referred to the Employers Representative for clarification.
5.
Performance requirements
5.1.
Service Life
The service life shall be at least 20 years, except for strip heaters which shall
have a service life of at least 15 years.
Where existing equipment is considered to have a remaining service life of ten
years or more, the Employers Representative may chose to retain such
equipment as part of the new installation. Where existing equipment is to be
retained the Employers Representative will inform the Contractor and the
sponsor.
5.2.
Product Acceptance
Only product accepted equipment shall be used. If novel equipment is
proposed, prior agreement from the Employers Representative must be sought
and an application made by the Contractor for trial acceptance before the
equipment is installed.
6.
6.1.
Equipment Layout
All points heating equipment is to be located adjacent to the running lines or on
the track apart from the DNO supply cubicle and associated cabling which is
generally to be located remotely dependant upon access constraints.
The location of cabinets for the incoming electrical supplies from Distribution
Network Operator shall be in accordance with the document
NAT/TW/InfraInv/ENG/EP6248683 Design and Installation of New, Renewed
or Refurbished Distribution Network Operators (DNOs) Intakes and Consumer
Facilities.
Where DNO cubicles are located in areas of high vandalism, the Contractor
shall where required by the Employers representative make provision for the
installation of a fenced compound and access gate complete with dual lock
Page 7 of 34
NAT/REP/MPI/ENG/EP3736860
Issue: 04
Date: 1st June 2011
6.2.
Electrical Design
The electrical design shall be compliant with BS7671 Requirements for
Electrical Installations (IEE 17th Edition Wiring Regulations) with an overriding
requirement that accessible touch voltages as a function of time are within the
8
Page 8 of 34
NAT/REP/MPI/ENG/EP3736860
Issue: 04
Date: 1st June 2011
6.3.
6.4.
Page 9 of 34
NAT/REP/MPI/ENG/EP3736860
Issue: 04
Date: 1st June 2011
The equipment design shall be compatible with the track circuits installed.
Written approval shall be obtained from the Employers Representative to
confirm the required type of electric points heating and that interdisciplinary
coordination checks have been satisfactorily carried out such that the proposed
design is compliant with regard to track circuit compatibility as specified in
section 7.1 of standard NR/SP/ELP/40045 prior to implementation works
commencing on site.
6.5.
10
Page 10 of 34
NAT/REP/MPI/ENG/EP3736860
Issue: 04
Date: 1st June 2011
6.6.
DNO Supplies
When replacing existing gas fired points heating systems with electrically
operated systems the proposed design shall address the requirement to obtain
a new DNO connection point and the location of the required electrical
distribution equipment.
A comprehensive supply assessment is to be carried out on all sites where the
equipment is to be renewed or modified to confirm the suitability of the existing
DNO supply. Where it is identified that an increase in supply capacity is
required or provision of a new supply is necessary, the Contractor shall at the
early design stage undertake negotiations with the relevant DNO to establish a
robust order of cost for the proposed changes.
Where new or upgraded supplies are to be provided, the DNO supply must be
installed or modified in accordance with NAT/TW/InfraInv/ENG/EP6248683
Design and Installation of New, Renewed or Refurbished Distribution Network
Operators (DNOs) Intakes and Consumer Facilities
Changes with regard to DNO supplies shall be carried out in accordance with
the Network Rail Procedure for Arranging New Utility Supplies and
Disconnections.
Where tenants electricity supplies are derived from the DNO cubicle, including
supplies to Train Operating Companies, a meter shall be provided to record the
tenants electricity consumption.
7.
Equipment Design
7.1.
11
Page 11 of 34
NAT/REP/MPI/ENG/EP3736860
Issue: 04
Date: 1st June 2011
7.2.
12
Page 12 of 34
NAT/REP/MPI/ENG/EP3736860
Issue: 04
Date: 1st June 2011
7.3.
13
Page 13 of 34
NAT/REP/MPI/ENG/EP3736860
Issue: 04
Date: 1st June 2011
7.4.
7.5.
7.6.
GENERIC/000/6.7/ET/023
GENERIC/000/6.7/ET/026
GENERIC/000/6.7/ET/027
GENERIC/000/6.7/ET/028
Heaters
Rail, in-bearer and supplementary detector heaters shall be either of the
constant wattage strip type rated at 200 watts per metre, or of the self
regulating strip type with equivalent heat output capability. Where Clamp Lock
systems are used, they shall be heated with additional cartridge type heater
elements individually rated at 200W.
Allowance shall be made for the fact that Mk Clamp Lock and in-bearer
detectors are padlocked to prevent unauthorised access to the Clamp Lock and
in-bearer detector heaters which can only be fitted by competent Signalling
personnel.
Strip heaters shall have a minimum sheath thickness of 0.8mm. In DC third
and fourth rail electrified areas strip heaters shall be of the insulated type. Rail
clips used for fixing heaters shall be product approved.
Heater leads are to be kept as short as possible and shall not exceed 20m.
Typical details for the installation of strip heating elements are shown on
drawing
GENERIC/000/6.7/ET/025.
Drawings
GENERIC/000/6.7/ET/026,
GENERIC/000/6.7/ET/027 and GENERIC/000/6.7/ET/028 provide details relating to
14
Page 14 of 34
NAT/REP/MPI/ENG/EP3736860
Issue: 04
Date: 1st June 2011
Clamp Lock
Cartridge
Heater
Bearer
Heater
Strip
Supplementary
Heater Strip
Transformer Size
AV
2 x 4m
2 x 4m
N/A
N/A
N/A
5kVA
BV/CV
2 x 5m
2 x 5m
N/A
N/A
N/A
5kVA
DV
2 x 6m
2 x 6m
N/A
N/A
N/A
5kVA
EV
4 x 4m
4 x 4m
N/A
N/A
N/A
10kVA
FV
4 x 5m
4 x 5m
N/A
N/A
N/A
10kVA
SGV
4 x 6m
4 x 6m
N/A
N/A
N/A
10kVA
GV
4 x 5m + 2 x 4m
4 x 5m + 2 x 4m
N/A
N/A
N/A
1 x 10kVA +1 x 5kVA
HV
6 x 6m
6 x 6m
N/A
N/A
N/A
1x10kVA +1x5kVA
Table 1 Requirements for 113lb Bullhead Rail and Mechanical Frame, HW or equivalent Operating
Mechanism
Clamp Lock
Cartridge
Heater
Bearer
Heater
Strip
Supplementary
Heater Strip
Transformer Size
AV
2 x 4m
2 x 4m
2 x 200W
N/A
N/A
5kVA
BV/CV
2 x 5m
2 x 5m
2 x200W
N/A
N/A
5kVA
DV
2 x 6m
2 x 6m
2x200W
N/A
N/A
10kVA
EV
4 x 4m
4 x 4m
2x200W
N/A
N/A
10kVA
FV
4 x 5m
4 x 5m
2x200W
N/A
N/A
10kVA
SGV
4 x 6m
4 x 6m
2x200W
N/A
N/A
10kVA
GV
4 x 5m +2 x 4m
4 x 5m +2 x 4m
2x200W
N/A
N/A
1x10kVA + 1x5kVA
HV
6 x 6m
6 x 6m
2x200W
N/A
N/A
1x10kVA + 1x5kVA
Table 2 Requirements for 113lb Bullhead Rail and HW or equivalent Operating Mechanism
15
Page 15 of 34
NAT/REP/MPI/ENG/EP3736860
Issue: 04
Date: 1st June 2011
Clamp Lock
Cartridge
Heater
Bearer
Heater
Strip
Supplementary
Heater Strip
Transformer Size
2 x 5m + 2 x 4m
2 x 5m + 2 x 4m
2 x 200W
N/A
N/A
10kVA
2 x 5m + 2 x 4m
2 x 5m + 2 x 4m
2 x 200W
N/A
N/A
10kVA
2 x 6m + 2 x 5m
2 x 6m + 2 x 5m
2 x 200W
N/A
N/A
10kVA
2 x 5m + 4 x 4m
2 x 5m + 4 x 4m
2 x 200W
N/A
N/A
1x10kVA + 1x5kVA
SG
2 x 6m + 2 x 5m +
2 x 4m
2 x 6m + 2 x 5m +
2 x 4m
2 x 200W
N/A
N/A
1x10kVA + 1x5kVA
2 x 6m + 6 x 5m
2 x 6m + 6 x 5m
2 x 200W
N/A
N/A
2x10kVA
4 x 6m + 4 x 5m +
2 x 4m
4 x 6m + 4 x 5m +
2 x 4m
2x200W
N/A
N/A
2x10kVA + 1x5kVA
Clamp Lock
Cartridge
Heater
Bearer
Heater
Strip
Supplementary
Heater Strip
Transformer Size
4x4m
4 x 4m
N/A
380W
104W
10kVA
2 x 5m + 2 x 4m
2 x 5m + 2 x 4m
N/A
380W
104W
10kVA
2 x 6m + 2 x 5m
2 x 6 m + 2 x 5m
N/A
380W
104W
10kVA
2 x 6m + 2 x 5m
2 x 6m + 2 x 5m
N/A
380W
104W
10kVA
SG
2 x 6m + 2 x 5m + 2
x 4m
2 x 6m + 2 x 5m +
2 x 4m
N/A
380W
104W
1 x 10kVA + 1 x 5kVA
16
Page 16 of 34
NAT/REP/MPI/ENG/EP3736860
Issue: 04
Date: 1st June 2011
7.7.
Cabling
All external cabling shall be of the steel wire armoured type with the exception
of the cabling from the trackside connection boxes to the heater strips and
temperature probes which shall be unarmoured. All cabling installed on the
track shall therefore be unarmoured and unscreened.
Unless specifically advised otherwise by the Employers Representative,
cabling shall be installed in concrete troughing where practically possible and
the use of buried cable routes shall be kept to a minimum. Where troughing is
installed the open end shall be sealed and made rodent proof using rigid setting
expanding aerosol foam. In accordance with NR/SP/SIG/19812, where a cable
carrying a voltage above 110 V is required to cross under running lines of track
category 1, 1A or 2, it shall be installed within a full depth Under Track Crossing
in compliance with NR/SP/CIV/044, Design and Construction of Under track
Crossings.
Where cables are required to cross under a road, vehicular access track or
hard standing, within Network Rail property, the cables shall be installed in
ducts at a minimum depth of 500mm from the wearing course to the top of the
duct. At each Under Road Crossing two spare ducts shall be provided complete
with a draw ropes. Following installation of cables, ducts shall be sealed with
rigid setting expanding foam. Draw pits or bell mouths shall be provided at each
end of the URX except where terminating directly into the concrete base of a
cubicle. All URX installations shall comply with the requirements of
NR/SP/ELP/27224.
All point heater connection cables between the trackside connection boxes and
heating elements shall be installed in concrete troughing terminating adjacent
to sleepers. Cables shall then cross the ballast to the sleeper where they shall
be clipped to the top of the sleeper towards the longitudinal edge. Where there
multiple cables are routed along a sleeper edge they shall be secured in flat
formation. Drawing GENERIC/000/6.7/ET/024 provides typical details with regard
to the appropriate fixing of cables to sleepers. Orange pipe traditionally used for
the protection of cables crossing tracks shall not be used.
110 Volt point heater connection cables are allowed to cross a maximum of 4
tracks with the heaters installed on the fourth track. Where longer runs are
required, a full depth UTX shall be used where available. Where this is not
possible cables shall be clipped to the sleepers with additional lengths of
concrete troughing installed where appropriate. After crossing to the 10ft
nearest to the point to be heated or the far cess if nearer to the point to be
heated, the cables shall terminate at a second trackside connection box.
Heater element cable tails shall then be routed back to the heater element
concerned.
Where cables are clipped to the sleeper and pass underneath the running rail,
an approved cable protector shall be installed to protect the cable against
damage from the running rail.
17
Page 17 of 34
NAT/REP/MPI/ENG/EP3736860
Issue: 04
Date: 1st June 2011
7.8.
ELR.
7.9.
Cubicle Construction
Cubicles shall be rigidly constructed from type 316L folded stainless steel sheet
to the relevant European and British standards with a minimum thickness 2.5
mm. The cubicle shall be constructed using stainless steel with a mill finish to
ensure sunlight glare is kept to a minimum. Panels or doors larger than
1800mm x 1200mm shall be suitably reinforced.
The cubicles shall be weatherproof to IP 54 and independent certification by a
testing authority shall be provided for each particular design of cubicle.
Sufficient ventilation shall be provided to allow for natural convection and to
prevent the internal temperature from rising above the operating temperature of
the equipment within the cubicle.
The welding of stainless steel shall be carried out by welders qualified to the
relevant European and British standards. Door sealing edges shall be suitably
prepared, butt welded, dressed flush and burnished. Appropriate seals shall be
fitted to the doors. The cubicle shall have sufficient ventilation to prevent
condensation without compromising the specified IP rating. Finished panels
shall be without sharp edges and all screws, bolts, washers and similar
fastenings shall be of a suitable grade of stainless steel or brass to prevent
corrosion for the design life of the equipment. During manufacture, due care
shall be taken to ensure that clean conditions apply to prevent cross
18
Page 18 of 34
NAT/REP/MPI/ENG/EP3736860
Issue: 04
Date: 1st June 2011
Where dual access to a cubicle is required a dual padlock locking bar shall be
fitted to the door opening onto the public highway and this must be fitted initially
with two approved railway padlocks as detailed in Appendix C. The locking bar
shall be 20mm in diameter and drilled to allow the designated padlocks to be
fitted to both ends. All cubicles are to be locked through a single lockable
handle. The locking mechanism is to be of the multipoint type, which
simultaneously locks the top and bottom of the door on operation of a single
handle. Once locked the cubicle doors must not be able to come ajar. When
cubicles have double doors the door with the locking handle is to overlap the
non-locking door so that only one locking mechanism is required to lock both
doors.
Wooden back boards shall be marine grade ply with a minimum thickness of 18
mm.
Where practicable, cables and wiring shall be accommodated in trucking.
Cables and wiring shall not obscure labels or prevent access for maintenance
including testing.
Each cubicle shall contain the facility to store a set of drawings. This shall take
the form of a black plastic drawing tube, which is to be fitted to the inside of the
cubicle door complete with a retaining clip to allow easy removal of the tube.
Typical cubicle foundation and other relevant civil construction details are
shown
on
drawings
in
appendix
D:
GENERIC/000/6.7/ET/034,
GENERIC/000/6.7/ET/035 and GENERIC/000/6.7/ET/036.
7.10.
19
Page 19 of 34
NAT/REP/MPI/ENG/EP3736860
Issue: 04
Date: 1st June 2011
7.11.
8.
cubicles;
power distribution equipment;
fencing and gates;
concrete troughs;
ground material;
concrete bases;
gas bottles and storage tanks;
gas manifolds and regulating apparatus;
gas pipe work;
rail mounted gas burners;
electric equipment;
scrap materials.
Page 20 of 34
NAT/REP/MPI/ENG/EP3736860
Issue: 04
Date: 1st June 2011
21
Page 21 of 34
NAT/REP/MPI/ENG/EP3736860
Issue: 04
Date: 1st June 2011
9.
Site Layouts;
DNO Cubicle Layout;
Sub-distribution Cubicle Layout;
Points Heating Control Cubicle Layout;
Schematics of all Cubicles;
Transformer Details;
Foundation Details;
Track Equipment Layout;
Termination Diagrams.
22
Page 22 of 34
NAT/REP/MPI/ENG/EP3736860
Issue: 04
Date: 1st June 2011
10.
Asset Recording
All Network Rails asset recording and maintenance systems including Ellipse are
to be updated by the project covering all asset changes.
11.
Training
Training shall be provided where equipment which is new or novel to an area is
provided.
This shall include 2 half day sessions for each maintenance area in which the
equipment is installed.
The training shall include as a minimum how to set up the equipment, how to
maintain the equipment, testing requirements and fault finding.
12.
Page 23 of 34
NAT/REP/MPI/ENG/EP3736860
Issue: 04
Date: 1st June 2011
Expected
Results
Labelling Internal
Labelling External
Visual
Visual
External Probes/Aerials
Visual
10
Visual
11
Visual
12
Visual
13
Visual
14
Earth Bonding
Visual
15
Cable Identification
Visual
16
Terminal Identification
Visual
17
Visual
18
Single/Three Phase
Refer to 1
19
Refer to 1
Phase Supply
Test Engineer
Test Date
Location of Test
................................................
................................................
................................................
................................................
................................................
................................................
................................................
24
Result
Comments / Remedial
Pass
/ Action
Fail
Serial
Customer
No.
Approval
Page 24 of 34
NAT/REP/MPI/ENG/EP3736860
Issue: 04
Date: 1st June 2011
Note:
25
Page 25 of 34
NAT/REP/MPI/ENG/EP3736860
Issue: 04
Date: 1st June 2011
PART 2 -
Live Tests
No. DESCRIPTION
EXPECTED
RESULT
RESULTS
Pass / Fail
COMMENTS
ACTION
Lamps
Monitoring
Voltage Check
Voltage
110 v A.C
Voltmeter
Correct
Bulkhead Light
Switch on
Correct
operation
Panel Heater
Switch On
Correct
operation
Override Button
Operate
Correct
operation
Timed light
Control circuits
Energise
Connected
connected to correct
individual
correctly
MCB
MCBs
Sensor
Moisten
Icelert
probe
Phase Supply
Test Engineer
Test Date
Test Instrument
Location of Test
................................................
................................................
................................................
................................................
................................................
................................................
................................................
................................................
................................................
Serial
Customer
No.
Approval
Calibration Certificate
Note: Test Schedules will only be signed following remedial corrective actions and
successful retest
26
Page 26 of 34
NAT/REP/MPI/ENG/EP3736860
Issue: 04
Date: 1st June 2011
................................................
Test Actual Voltage
................................................
Test Engineer
................................................
Cubicle Serial No.
................................................
Test Date
................................................
Customer
Approval
................................................
Test Instrument ................................................
Calibration Certificate
................................................
................................................
................................................
Location of Test ................................................
Note: Test Schedules will only be signed following remedial corrective actions and
successful retest.
27
Page 27 of 34
NAT/REP/MPI/ENG/EP3736860
Issue: 04
Date: 1st June 2011
Type
External
Engraved
Designation Point No
External
Engraved
Designation
Circuit
Engraved
Fuse Ratings
Circuit
Engraved
Internal
Engraved
Internal
Engraved
GPS Reference
External
Engraved
Internal
Engraved
Internal
Engraved
External
Engraved
Internal
Engraved
Supply Feeds To
Circuit
Engraved
Heater Connection (i.e. H1, H2, H3, H4 , CHL 1, CHL2 , BH1, BH2 )
Internal
Engraved
Internal
Engraved
External
Engraved
External
Printed
28
3
3
3
3
3
3
3
Page 28 of 34
Point End
Trackside
Connection
Box
Transformer
Distribution
Board
Circuit
Designation
Other
Distribution
Board
Circuit
Designation
Points
Switch Gear
Fitted
Control
Cubicle
Label
Supply &
Sub
Distribution
NAT/REP/MPI/ENG/EP3736860
Issue: 04
External
Engraved
29
Point End
Trackside
Connection
Box
Engraved
Transformer
External
Distribution
Board
Circuit
Designation
Other
Distribution
Board
Circuit
Designation
Points
Type
Switch Gear
Fitted
Control
Cubicle
Label
Supply &
Sub
Distribution
3
3
Page 29 of 34
NAT/REP/MP&I/ENG/EP3736860
Issue: 04
Date: 1st June 2011
Great Northern
Application
LT 205
Control cubicles
Transformers
JW 442
JW 442
North Eastern
Application
Locking arrangement
Electrical Power
Supply single sided cubicle
Electrical Power Supply double sided
cubicle
Electrical Power
Supply single sided cubicle
Electrical Power Supply double sided
cubicle
Control cubicles
Transformers
Locking arrangement
JW 442
JW 442
JW 442
Page 30 of 34
NAT/REP/MP&I/ENG/EP3736860
Issue: 04
Date: 1st June 2011
Application
Locking arrangement
Electrical Power
20mm dia dual locking bar
Supply single sided cubicle
RC 27
Electrical Power Supply double sided 20mm dia locking bar.
cubicle
Locking handle Network Rail
side
Control cubicles
Locked handle
RC 27
Locked cover plate
JC 27
Transformers
East Anglia
Application
LT 205
Control cubicles
Transformers
LT 205
RKB 222
Locking arrangement
Electrical Power
Supply single sided cubicle
Electrical Power Supply double sided
cubicle
Locking arrangement
CCC 2
Control cubicles
Transformers
CCC 2
RKB 222
Locking arrangement
Electrical Power
Supply single sided cubicle
Electrical Power Supply double sided
cubicle
Electrical Power
Supply single sided cubicle
Electrical Power Supply double sided
cubicle
Control cubicles
Transformers
RC 27
BPH
BPH
31
Page of 34
NAT/REP/MP&I/ENG/EP3736860
Issue: 04
Date: 1st June 2011
Scotland
Application
Electrical Power
Supply single sided cubicle
Electrical Power Supply double sided
cubicle
Control cubicles
Transformers
Locking arrangement
20mm dia dual locking bar
PS 1
PS 1
PS 1
32
Page of 34
NAT/REP/MP&I/ENG/EP3736860
Issue: 04
Date: 1st June 2011
Title
GENERIC/000/6.7/ET/018
GENERIC/000/6.7/ET/023
GENERIC/000/6.7/ET/024
GENERIC/000/6.7/ET/025
GENERIC/000/6.7/ET/026
GENERIC/000/6.7/ET/027
GENERIC/000/6.7/ET/028
GENERIC/000/6.7/ET/031
GENERIC/000/6.7/ET/034
GENERIC/000/6.7/ET/035
GENERIC/000/6.7/ET/036
GENERIC/000/6.7/ET/037
GENERIC/000/6.7/ET/039
GENERIC/000/6-7/ET/041
NR-EP/4002
NR-EP/4003
NR-EP/4004
NR-EP/4005
NR-EP/4006
NR-EP/4007
NR-EP/4008
NR-EP/4102
NR-EP/4103
NR-EP/4104
NR-EP/4105
NR-EP/4106
33
Page of 34
NAT/REP/MP&I/ENG/EP3736860
Issue: 04
Date: 1st June 2011
34
Page of 34