Professional Documents
Culture Documents
SUMMARY
1. GENERALITIES ABOUT PROJECT DEVELOPMENT CONTRACTS
!
!
!
!
!
!
!
!
!
!
2. CONTENT OF A CONTRACT
3. THE CALL FOR TENDER PROCEDURE- AWARDING A CONTRACT
4. CONCLUSION
SUMMARY
1. GENERALITIES ABOUT PROJECT DEVELOPMENT CONTRACTS
2. CONTENT OF A CONTRACT
!
!
!
!
SUMMARY
1. GENERALITIES ABOUT PROJECT DEVELOPMENT CONTRACTS
!
!
!
!
!
!
!
!
! PURCHASE ORDER
"Between a Supplier and and a Company, either called Buyer,
Purchaser, Owner or Operator
"The target is the Supply
"Supplier is a specific industrial entity which could buy part of the
supply from others and assemble/fabricate the overall product in
accordance with its own specifications
PURCHASE ORDER
SUMMARY
1. GENERALITIES ABOUT PROJECT DEVELOPMENT CONTRACTS
! Definition of a Contract - Contract or Purchase Order
10
11
12
Supply
Workshop
Engineering
FINAL WORK
Test-Check
Fabrication
Transport
Construction
13
Engineering
Survey and soil study
Equipment and materials
Fabrication (workshops and/or yards)
Construction at site(s)
Commissioning and tests
Maintenance
Insurance
Management or assistance to management
Sometimes Drilling
14
15
SUMMARY
1. GENERALITIES ABOUT PROJECT DEVELOPMENT CONTRACTS
!
!
!
!
!
!
!
!
16
17
18
! Confidentiality
19
MARKET SURVEY
20
SUMMARY
1. GENERALITIES ABOUT PROJECT DEVELOPMENT CONTRACTS
! Definition of a Contract - Contract or Purchase Order
! A contract: between who, for what and when
! Pre-selection of potential suppliers or contractors - Market survey
21
A difficult ex
ercise
Marc Ducros - Apr 2006 -
22
23
24
! Finally the Detailed Cost Estimate, the only way to obtain the agreement from
the Company management. This detailed CE has to be in line with the Basic
Engineering.
25
26
PROJECT
BASIC
PLTF1
FPSO
Onshore Plant
Links
SPS
Offshore
Jacket
Deck
Hull
Unit 1
Wharf
Transportation
Installation
Topsides
Pipeline
S/S Cable
X-Tree
Manifolds
Engineering
Procurement
L.L.I.
details of SWU
- Process Design
- Safety
- Pressure Vessels
- Civil Works
- Structure
- Piping / Install
- Valves / mater.
- Mechanical
- Electrical
- Instrumentation
- Control System
- Architectural
- Telecom
- Package
- Protection Insul.
- Links / Pipelines
- Naval architect.
- Procurement
- L.L.I. 1 (TC's)
- L.L.I. 2 (TG's)
- L.L.I. 3 (Pumps)
- etc...
Onshore
Construction
Prefabrication
Decommissioning
Erection
- Equipment
- Civil Works
- Structure
- Piping
- Electrical
- Instrumentation
- Architectural
- Painting
- Insulation
- Mech.Complet.
Offshore
Construction
Commissioning
Prefabrication
Decommissioning
Off-Shore Works
Preparation
Realisation
- On-Shore
- Off-Shore
- Equipment
- Civil Works
- Structure
- Piping
- Electrical
- Instrumentation
- Architectural
- Painting
- Insulation
- Mech.Complet.
27
28
+ 40
+ 30
+ 20
+ 10
0
- 10
MANAGEMENT
APPROVAL
Comparing
Various scenario
Design Competition
PRELIMINARY CONCEPTUAL
STUDIES
STUDY
- 20
- 30
PRE PROJECT
STUDY
BASIC
ENGINEERING ENGINEERING
Estimate based on
analysis and market
- 40
QUALITY
REVIEW
MEETING
DETAILED
Detailed
Estimate
QUALITY
REVIEW
MEETING
CONCEPT
VALIDATION
Marc Ducros - Apr 2006 -
29
! Once the Cost Estimate is ready and the Project agreed by the
Operator and the Partners, the Initial Budget is finalised.
! Built in accordance with the WBS structure and the Project
Schedule, this Budget will also be a Life of Project (LOP) Budget.
! Accounting of a Company is normally based on a yearly basis,
while a development Project must be followed along its all Life.
Project Commitments (see below) have to be followed on a pluriannual basis.
30
SUMMARY
1. GENERALITIES ABOUT PROJECT DEVELOPMENT CONTRACTS
!
!
!
!
31
32
COATING
STORAGE
LAY
TIE-INS
HYDRO TESTS
BURYING
LANDING
SURVEY AS BUILT
COMMISSIONING
33
CHOIX 2
STUDIES
STUDIES
TUBING
TUBING
COATING
COATING
STORAGE
STORAGE
LAY
LAY
TIE-INS
TIE-INS
HYDRO TESTS
HYDRO TESTS
SURVEY AS BUILT
BURYING
LANDING
SURVEY AS BUILT
COMMISSIONING
COMMISSIONING
34
CHOIX 2
STUDIES
STUDIES
TUBING
TUBING
COATING
CHOIX 3
STUDIES
TUBING
COATING
COATING
STORAGE
STORAGE
STORAGE
LAY
LAY
LAY
TIE-INS
TIE-INS
TIE-INS
HYDRO TESTS
HYDRO TESTS
HYDRO TESTS
SURVEY AS BUILT
SURVEY AS BUILT
BURYING
COMMISSIONING
LANDING
SURVEY AS BUILT
COMMISSIONING
COMMISSIONING
35
CHOIX 2
STUDIES
STUDIES
CHOIX 4
STUDIES
STUDIES
TUBING
TUBING
CHOIX 3
TUBING
TUBING
COATING
COATING
COATING
COATING
STORAGE
STORAGE
STORAGE
STORAGE
LAY
LAY
LAY
LAY
TIE-INS
TIE-INS
TIE-INS
TIE-INS
HYDRO TESTS
HYDRO TESTS
HYDRO TESTS
HYDRO TESTS
SURVEY AS BUILT
SURVEY AS BUILT
SURVEY AS BUILT
BURYING
COMMISSIONING
COMMISSIONING
LANDING
MAINTENANCE
SURVEY AS BUILT
COMMISSIONING
COMMISSIONING
36
37
SUMMARY
1. GENERALITIES ABOUT PROJECT DEVELOPMENT CONTRACTS
!
!
!
!
!
38
39
40
41
42
43
! THE
PROGRESS
MEASUREMENT
PROCEDURE
WILL
BE
SUFFICIENTLY DEFINED IN THE CONTRACT EXHIBIT AND FINALISED
AT OR JUST AFTER CONTRACT SIGNATURE.
44
I- CONTRACTORS PAYMENT :
PROGRESS - EXPENDITURES INCURRED
M$
BUDGET
INVOICES
(INVOICE APPROVED)
45
! MILESTONE payments will be limited to 10 to 20 "In order to organize payments only every 2 or 3 months
"To be based on well identified events on the Project Schedule
"Representative of the best effort of the Contractor to keep the schedule on
time
! Specific Points
"When Contractor is in advance on one or several milestones, the payment
should not be effective earlier than the date of such milestone as per the
initial Project schedule
46
I- CONTRACTORS PAYMENT
Milestones Payment (example)
Indicative month
after Commencement
date
% of Contract Value
Milestones
10%
7.5%
7.5%
10%
11.5
10%
13
5%
14
5%
16
5%
18
5%
Total
65%
Marc Ducros - Apr 2006 -
47
I- CONTRACTORS PAYMENT
Milestones Payment (Example)
Indicative month
after Commencement
date
% of Contract Value
Milestones
18
7.5%
18
2.5%
19
Generator on foundation
2.5%
20.5
5%
22.5
2.5%
23.5
5%
26
Performance Acceptance
10%
TOTAL
100%
48
SUMMARY
1. GENERALITIES ABOUT PROJECT DEVELOPMENT CONTRACTS
Definition of a Contract - Contract or Purchase Order
A contract: between who, for what and when
Pre-selection of potential suppliers or contractors - Market survey
Cost estimate and budget for a contract
Various types of contract by disciplines- Engineering, fabrication,
construction
! Various types of contract - the remuneration of the contractor
!
!
!
!
!
! Instruction to tenderers
! The Contractual Plan option
49
INSTRUCTION TO TENDERERS
A transparent process
! Is tendering a costly process ?
! How long shall we grant to tender ?
! Shall we pay for bids ?
! shall we authorize alternative tenders ?
50
INSTRUCTION TO TENDERERS
! It has to include:
"definitions: tender, tenderer, work..
"acknowledgement by tenderer
"conditions of tender: cost of tender, partial or full answer, company
acceptation and right to reject, modify
"knowledge of the site by tenderer
"confidentiality
"JV scenario (tenderer side)
"Visit of tenderer by company
"Validity of the tender
"Clarification procedure
"Notification by Company
51
INSTRUCTION TO TENDERERS
But more important are the following points
! Closure date
! Bid Bond process
! Pricing/remuneration of the contract
! Time schedule
! Required guarantees
! The way to take exceptions to the Companys requirement
52
SUMMARY
1. GENERALITIES ABOUT PROJECT DEVELOPMENT CONTRACTS
Definition of a Contract - Contract or Purchase Order
A contract: between who, for what and when
Pre-selection of potential suppliers or contractors - Market survey
Cost estimate and budget for a contract
Various types of contract by disciplines- Engineering, fabrication,
construction
! Various types of contract - the remuneration of the contractor
! Instruction to tenderers
!
!
!
!
!
53
54
55
56
CONTRACTUAL
STRATEGY
PLANNING
BUDGET
57
58
OPTIONS
SEPARATE CONTRACT CASE
EPSC CONTRACT CASE
EPSCC CONTRACT CASE
TURN KEY CONTRACT CASE
MAIN OPTIONS COMPARISON SUMMARY
59
PROCUREMENT,
SUPPLY
AND
60
CONTRACTUAL
STRATEGY
FOUR MAIN TYPES
OF DEVELOPMENT
CONTRACTS
Separate contract case
EPSC contract case
EPSCC contract case
Turn Key contract
EPSC
EPSCC
TURN KEY
PREPROJECT
PREPROJECT
PREPROJECT
PREPROJECT
BASIC DESIGN
BASIC DESIGN
BASIC DESIGN
PROCUREMENT
LONG LEAD
ITEMS
SUPPLY
SUPPLY
BASIC
DESIGN
DETAIL
ENGINEERING
DETAIL
ENGINEERING
PROCUREMENT
DETAIL
ENGINEERING
PROCUREMENT
DETAIL
ENGINEERING
PROCUREMENT
SUPPLY
OTHER EQUIPMENT
SUPPLY
SUPPLY
ASSIGNED L.L.
ITEMS
OTHER
EQUIPMENT
BULK MATERIALS
OTHER
EQUIPMENT
OTHER
EQUIPMENT
CONSTRUCTION
BULK MATERIALS
BULK MATERIALS
CONSTRUCTION
CONSTRUCTION
COMMISSIONING
COMMISSIONING
PROCUREMENT
ASSIGNMENT
LONG LEAD
ITEMS
BULK MATERIALS
CONSTRUCTION
COMMISSIONING
OPERATING TESTS
PERFORMANCE
TESTS
COMMISSIONING
OPERATING
OPERATING TESTS
TESTS
PERFORMANCE
PERFORMANCE
Marc Ducros - Apr
2006 TESTS
TESTS
OPERATING TESTS
PERFORMANCE
TESTS
61
CONTRACTUAL STRATEGY
SCHEDULING APPROACH
PROCUREMENT /SUPPLY
SEPARATE
CONTRACTS
BASIC
DESIGN
PRE PROJECT
DETAIL
ENGINEERING
EPSC
BASIC
DESIGN
PRE PROJECT
TEST
EPSCC
PRE PROJECT
BASIC
DESIGN
TEST
TURN KEY
PRE-PROJECT/
BASIC DESIGN /
DETAILED ENGINEERING /
CONSTRUCTION/
COMMISSIONING
TESTS
Y1
Y2
Y3
Y4
62
SUMMARY
1. GENERALITIES ABOUT PROJECT DEVELOPMENT CONTRACTS
2. CONTENT OF A CONTRACT
!
!
!
!
63
2- CONTENT OF A CONTRACT
CONTRACT DEFINITION
! A "Contract" is an agreement between two or more parties by
which they commit themselves to fulfil defined obligations.
64
2- CONTENT OF A CONTRACT
CONTRACT DEFINITION
! The Contract usually includes remedies to be implemented in case:
" One party cannot or does not want to fulfil its contractual
obligations,
" The relationship between the parties is modified due to an
external event.
65
2- CONTENT OF A CONTRACT
CONTRACT DEFINITION
! In this context, it is understood that:
1. Both parties must perform their respective obligations ;
2. Should one party fail to perform, that party is said to be in
breach of contract ;
3. However, if a failure of performance was caused:
" Either by an outside influence not anticipated under the
Contract
" or by the other contracting party
the non-performing
performance.
party
may
be
excused
for
its
non-
66
67
! 1/B
! 1/C
4
LIABILITY
SUBCONTRACTORS
AND
INSURANCE
AGREEMENT
FROM
68
- COMPANY REPRESENTATIVE
! ARTICLE 9
- CONTRACTOR'S ORGANIZATIO
! ARTICLE 11
- SUBCONTRACTORS
! ARTICLE 12
69
- MAINTENANCE SERVICES
! ARTICLE 17
AND
PROVISIONAL ACCEPTANCE
CERTIFICATES
70
LAWS
CUSTOMS
REGULATIONS -
AUTHORIZATIONS
! ARTICLE 23
! ARTICLE 24
CONTRACTOR'S PERSONNEL
! ARTICLE 25
CONSTRUCTION EQUIPMENT
! ARTICLE 26
WORK LOCATIONS
! ARTICLE 27
SITE REQUIREMENTS
! ARTICLE 28
REPORTS
! ARTICLE 29
71
CONTRACT PRICE
! ARTICLE 31
! ARTICLE 32
! ARTICLE 33
BANK GUARANTEES
! ARTICLE 34
LIQUIDATED DAMAGES
! ARTICLE 35
72
73
THE
WORK
BREAKDOWN
STRUCTURE
74
75
" WHEN APPLICABLE, THE LUMP SUM PRICE, USUALLY BROKEN DOWN
ACCORDING TO THE WORK BREAKDOWN STRUCTURE,
" THE TABLE OF THE UNIT RATES WHICH WILL BE USED FOR THE
EVALUTION OF THE COMPENSATION OF THE MODIFICATIONS TO THE
SCOPE,
" THE TABLE OF THE TIME RATES, WHICH WILL BE, USED FOR THE
EVALUTION OF THE COMPENSATION OF THE MODIFICATIONS TO THE
SCOPE AND TO THE CONTRACT CONDITIONS.
76
77
PERFORMANCE GUARANTEES
78
79
The
Production
Platform
80
81
DORIS
McDermott
BW
82
SUMMARY
1. GENERALITIES ABOUT PROJECT DEVELOPMENT CONTRACTS
2. CONTENT OF A CONTRACT
3. THE CALL FOR TENDER PROCEDURE- AWARDING A CONTRACT
! Process for tendering - Analysis of tenders
! Clarification meetings
! Recommendation to award
4. CONCLUSION
83
3 TENDERING PROCEDURE
Five Main Phases
Prequalification of potential Tenderers
4 to 8 months
2 to 4 months
84
3 TENDERING PROCEDURE
Submittal of the Tenders
Tenders are generally requested to be submitted in three parts:
! The contractual part (essentially the qualifications or items of non
compliance with the contractual conditions),
! The technical part (essentially the qualifications to the design
dossier (plant definition and specifications)) including the execution
plan with the means and the proposed work time schedule,
! The commercial part with the proposed price conditions.
85
3 TENDERING PROCEDURE
Opening of the Tenders
Several philosophies exist for Tenders opening:
Technical and
contractual
Commercial
Updated tenders
Analysis, clarifications,
confirmations
Recommendation
Technical and
contractual
Analysis, clarifications,
technical confirmations
Lowest bid
selected
86
3 TENDERING PROCEDURE
Analysis of the Tenders
! Qualifications in the Tenders are usually split into three categories:
"Acceptable: for which the Operator has no objection and even may
consider they are helpful for clarification purpose,
"Not acceptable: for which the relevant Tenderer will be requested to
withdraw if he wants to remain into the competition,
"Negotiable: which are usually technically acceptable, but may
affect the price and the work time schedule.
! In some instances, the contents of the Tenders are measured against pre
established criteriae, all weighted to arrive at an overall assessment and a rating
of the Contractors, e.g. (based upon a more detailed breakdown)
" Planning: rating 3/5
Weighting: 20%
" Technical: rating 2/5
Weighting: 50%
" Organisation: rating 4/5 Weighting: 30%
87
3 TENDERING PROCEDURE
Clarification meetings
The objective of Clarification meetings is for the Operator is to review and clarify with
each Tenderer:
The Contract execution plan submitted by the Tenderer, including the
work time schedule,
The qualifications that the Tenderer has submitted with his tender,
The alternative Tenders submitted by the Tenderer,
his reaction to the acceptable qualifications or suggestions made by other
Tenderers,
His position vis--vis the endorsement of the plant design dossier.
The joint review with each Tenderer of the comments he has made to the design
dossier will enable:
The Operator to appreciate the understanding and motivation of the
Contractor
The Tenderer to improve his understanding of the Clients position,
The Operator to improve the general quality of the dossier by taking into
account the relevant comments.
88
3 TENDERING PROCEDURE
Revised CFT.s (not always)
If necessary, the result of the clarification meetings will be that the Client will update the basic
documents and issue modified call for tender documents to the Tenderers (all of them or
only short list of acceptable ones), with:
! The technical documents amended by the relevant qualifications and comments of the
Tenderers
89
3 TENDERING PROCEDURE
Revised tenders
! The final tenders usually has to include:
The main Contract documents already initialled by the Tenderer showing
his agreement with and commitment to the updated conditions,
# The updated execution plan with a time schedule compatible with the
completion date requested by the Operator,
# The additional information requested from the Tenderer during the
clarification meetings,
# The final fully inclusive price.
#
! The Tenderer will have to submit his final tender in two parts with the commercial
part separated from the other documents.
90
3 TENDERING PROCEDURE
Final selection
Opening of final tenders and selection of the Contractor
! After having checked that each tenderer has accepted (through his initialling) the Contract
conditions, the Operator opens the commercial proposals.
! The selection is made in principle on the lowest price basis, or at least on the most
economical solution, based upon Life cycle cost (OPEX +CAPEX)
! If it is not the case, the Operator is usually requested to document his decision, which he
may do on the basis of the weightings and detailed scored evaluations
! To accept at the last minute an uncontrolled price reduction from one contractor outside
the normal competitive procedure would be :
" - Unfair to the other Tenderers (and counter-productive for next project)
" - Risky, as the Contractor will probably try to recover such reduction during the
performance of the Contract
91
92
93