Well Name
Damar-A14
ORIG:
CC:
Slot
5
AFE No
909/13009.1.01.01
Page 1 of 21
TABLE OF CONTENT
BACKGROUND
PROCEDURE OUTLINE
EQUIPMENT REQUIRED
WELL INTERVENTION PROGRAM
ATTACHMENTS
A.
B.
C.
D.
E.
F.
WELL SCHEMATIC
DEVIATION SURVEY
STETHOSCOPE DATA
SLICKLINE PRESSURE CONTROL EQUIPMENT (PCE) D IAGRAM
'H' MANIFOLD AND PUMPING LINE LAYOUT
BHA DIAGRAMS
Page 2 of 21
Background
As of July 30th 2014, Drilling operations are on-going at Damar A with the West Leda Jack-up Rig. The
production hole of DaA-5 is currently being drilled / cased.
DaA-14 was completed on June 16, 2014. While start-up checks were conducted on this well to ready it for
production, it was found that the production casing annulus had sustained pressure. Pressure would build
back up gradually after each bleed down. Surface diagnostics have been conducted on this well, indicating
that there could be a tubing leak in this well. This leak also appears to be small based on the pressure build
up rate in the production casing annulus. The plan for DaA-14 is to conduct further diagnostics to pin point
the location of the leak while DaA-5 is drilled and completed. This work needs to be completed before DaA5 is completed to allow option to workover the well while the drilling rig is at location.
Note: High Rate Water Pack (HRWP) in DaA-14 was compromised during installation. It is suspected that
the screens have failed and there may be gravel in the LS below the upper completion (2,515m RKB
onwards). If any intervention is to be done past this depth, proceed with extra caution and conduct pull tests
regularly prior to passing this depth. Discuss with town prior to proceeding with any intervention past this
depth.
Page 3 of 21
Procedure Outline
All pressures shall be monitored and recorded in every step of this program as part of the diagnostics. Signs
of communication between strings shall be observed at all times.
1.
2.
3.
4.
5.
Equipment
1. Deleum slickline unit
a. Reel skid
b. Power pack X 2
c. Telescopic mast
d. BOP / SCSSV control panel
e. Lubricator skid
f. Tool container
g. Logging container with EMR gauge, MPLT, and Ultrasonic tool
h. Air compressor (contingency)
2. SVP equipment
a. H manifold
b. Treating lines and coflex hoses
c. 2-1/16 5K flange to 2 1502 X-over for PCA
3. Tubing plugs
a. 2.813 X-lock mandrel 3
220093411 MANDREL,X-LOCK,3-1/2",OTIS#810XO28106
b. 2.81 plug body 4
220071517 PLUG,PXN,2.813",OTIS#24-PXX-28100
c.
Vee packings 20
220071182 PACKING,VEE,OTIS#91V1330,2.813"X2.370"
Page 4 of 21
1. Spot Deleum and SVP equipment on the platform and prepare to rig-up on well.
All lines should be hooked-up as necessary and pressure tested to 200/3,500psi.
The H manifold will be hooked-up to:
Tubing string via pumping tee
Production Casing Annulus via 2-1/16 5K flange to 2 1502 X-over
Flow back well via tree top X-over
Cementing unit on the rig via a high pressure coflex line
2. Fill up the Production Casing Annulus (PCA) with 9.9 NaCl brine via the lubricate and bleed method and
measure volume required to fill up PCA.
Attempt to lock 2,000psi in PCA. Discuss results with town.
3. Rig-up slickline PCE on SS.
Pressure test PCE to 200/3,500psi.
Lock the SSV actuator with fusible cap.
Open the SCSSV with Deleums control panel observe for pressure equalizing (SCSSV is of the selfequalizing type).
Zero slickline unit on tubing head spool (Elevation is 25.1m)
4. RIH with 2.80 gauge ring to tag XN Nipple at 2,458m RKB.
Slow down across SCSSV to ensure SCSSV is fully open before passing SCSSV.
Conduct pick-up checks as needed to ensure there are no abnormalities.
POOH.
5. RIH with 2.813 PXN plug body and set at XN-Nipple at 2,458m RKB. POOH.
RIH with plug prong and set in same.
POOH.
6. Lubricate and bleed SS tubing full of 9.9 NaCl brine, pressure up to 2,000psi, attempt to lock pressure in
SS. Observe all pressures for 30 minutes.
7. If SS is in communication with the PCA, attempt to maintain 2,000psi in the SS while bleeding off
pressure from the PCA. (If pressure test on SS is good, skip this step and proceed with step 8).
While maintaining differential pressure between SS and PCA, RIH with ultrasonic log to PXN plug,
and log-up at 30ft/min. If leak rate is high such that it is able to establish flow rate of 0.25bpm,
consult town on potential of running MPLT tool instead of ultrasonic tool.
After logging is done, pressure up SS and allow PCA to equalize, testing SS and PCA as a system
against top packer and PXN plug.
Discuss with town on logging results, and if repeat runs needs to be conducted.
Page 5 of 21
End of procedure
Page 6 of 21
Attachments
Completion Report
Page 7 of 21
Page 8 of 21
Page 9 of 21
Page 10 of 21
Page 11 of 21
Deviation Survey
Page 12 of 21
Page 13 of 21
Page 14 of 21
Stethoscope Data
Page 15 of 21
Page 16 of 21
Page 17 of 21
BHA diagrams
Page 18 of 21
Page 19 of 21
MPLT toolstring
Page 20 of 21
Ultrasonic Toolstring