Professional Documents
Culture Documents
http://www.cigre.org
14-114
Session 2002
CIGR
R GULATI
ALSTOM Systems Ltd
India
1.
INTRODUCTION
2.
Generation (TWh)
400
350
300
250
200
150
100
50
0
1986
1988
1990
1992
1994
1996
1998
2000
Year
120
Capacity (GW)
100
80
60
40
20
0
1986
1988
1990
1992
1994
1996
1998
2000
Year
Rihand-D elhi,1500M W
V indyachal, 500M W
Barsoor-Low er Sileru,100M W
Chandrapur, 1000M W
Chandrapur-Padghe, 1500M W
V ishakhaptnam ,500M W
Sasaram , 500M W
Talcher-K olar,2000M W
D elhi
N O RTH
N O RTH -EA ST
Rihand
EA ST
W EST
K olkata
Chandrapur
M um bai
SO U TH
Back-to-Back
Point-to-Point
Cities
Chennai
Bangalore
OVERALL BENEFITS OF
INTERCONNECTION
Environmental
Fuller use is made of seasonal high rainfall run-off,
transferring extra hydro capacity to the other regions
Hydro resources are conserved and more efficiently
managed by utilising thermal energy in times of
drought
Reduced coal burning due to the import of energy
from hydro resources when available
Construction of fewer generating stations by sharing
reserves for outages and peaks
On the down side there is the cost (both economic and
environmental) of the losses of the convertor stations but
these are small in comparison to the AC transmission
losses and so do not alter the normal balance of
transmission costs versus location of generation.
5.
400
0.8
300
200
0.6
100
0.4
0.2
-100 0
10
-200
10
M va r
Tim e (Sec)
Tim e (Sec)
400
MW
300
0.8
200
0.6
100
0.4
0
-100 0
0.2
0
10
M var 10
-200
Tim e (Sec)
Tim e (Sec)
Results
Figure 4, 5, 6 and 7 show results of a three phase fault
applied to one circuit of an AC transmission line in region
A. Figure 4 shows that when the regions are not
interconnected the system is recovering stability following
the fault, with voltage and power flow oscillation
decreasing in amplitude. In contrast, figure 5 shows that,
when the regions are interconnected with an AC tie, the
system becomes unstable with continuously increasing
oscillation of both terminal voltage and line power flow in
Region A. The AC line power is measured in one of the
circuits that is connected to the eventual convertor bus.
Busbar Voltage (pu)
MW
400
0.8
300
0.6
200
100
0.4
0
-100 0
0.2
0
MW
5
Time (Sec)
10
10
M var
-200
Tim e (Sec)
200
1
100
0.8
0
-100 0
0.6
M var
10
-200
0.4
-300
0.2
-400
0
5
Tim e (Sec)
10
MW
-500
Tim e (Sec)
Inverter AC P/Q
1.1
1
0.9
Bus 2
0.8
Bus 1
0.7
0.6
0.5
0
10
13000
11000
9000
7000
5000
3000
1000
-1000
M var
MW
0
Tim e (Sec)
1.1
Bus 2
250
Bus 1
MW
150
0.9
0.8
50
0.7
0.6
-50 0
10
0.5
0
10
M var
-150
Tim e (Sec)
10
Tim e (Sec)
6.2
5
Tim e (Sec)
6.3
IN V ERTER
6.6
RECTIFIER
RECTIFIER
2
1
0
0
Tim e (Sec)
Tim e (Sec)
IN VERTER
IN VERTER
0.5
Frequency Control
IN VERTER
1
3
RECTIFIER
7.
RECTIFIER
0.5
1
0
0
0
Tim e (Sec)
Tim e (Sec)
6.4
AC Voltage Control
CONCLUSION
2.
3.