You are on page 1of 7

2014 [POWER SYSTEM OPERATION AND CONTROL]

B.Sc (Electrical Engineering)


VIIIth Semester

Lagrange Relaxation

mm

Fall 2014

Page 6

2014 [POWER SYSTEM OPERATION AND CONTROL]

The objectives of the power system operational planning involves the best utilization of
available energy resources subjected to various constraints and to transfer electrical energy
from generating stations to the consumers with maximum safety of personal/equipment,
continuity, and quality at minimum cost. The operational planning involves many steps
such as short term load forecasting, unit commitment, economic dispatch, hydrothermal
coordination, control of active/reactive power generation, voltage, and frequency as well as
interchanges among the interconnected systems in power pools etc. In the early days the
power system consisted of isolated stations and their individual loads. But at present the
power systems are highly interconnected in which several generating stations run in
parallel and feed a high voltage network which then supplies a set of consuming centers.
Such system has the advantages of running the number of stations with greater reliability
and economy, but at the same time the complexity in the operational and control procedures
has increased. The power industry therefore requires the services of the group of men who
are specially trained to look after the operation of the system. These men are known as the
system engineers and are responsible for the operation, control and operational planning of
the system.
Unit Commitment involves the hour-to-hour ordering of the units on/off in the system to
match the anticipated load and to allow a safety margin. Having solved the unit
commitment problem and having ensured through security analysis that present system is
in a secure state then the efforts are made to adjust the loading on the individual generators
to achieve minimum production cost on minute-to-minute basis. This loading of generators
subjected to minimum operation cost is in essence the economic dispatch. Load forecasting
gives an accurate picture of the expected demand over the following few hours. In an
anticipation of the variations in demand and for reasons of economic operation of the
system the unit commitment activity is carried out.
Lagrange Relaxation Method
In 1983, A. Merlin, proposed a new implementation in solving UCP by Lagrangian
relaxation method. Numerous developments were envisaged, to make the algorithm
flexible such as simultaneous management of pumping units, probabilistic determination of
the spinning reserve. This decomposition method used is flexible and Lagrange multiplier
provides a new solution to the conventional problem. In 1987, R. Nieva, proposed an
approach to solve very large and complex UCP. The proposed approach gives an estimate
of suboptimality that indicates the closeness of the solution near to the optimum. In contrast
with the technique of Lagrangian Relaxation, this approach makes no attempt of
maximizing the dual function. In 1988, F. Zhuang, presented an LR method for large scale
problem. The algorithm in divided into three phases. First the Lagrangian dual of the unit
commitment is maximized with standard subgradient techniques, second a reserve-feasible
dual solution is find, and finally ED is performed. On 100 units to be scheduled over 168
hours, gives a reliable performance and low execution times. Both spinning and timelimited reserve constraints are treated. In 1989, S. Virmani et al. presented a paper in
which they provide an understanding of the practical aspects of the Lagrangian Relaxation
methodology for solving the thermal UCP. In 1995, R. Baldick formulated UCP in
generalized form and solved using LR method. The algorithm, presented, approximately

mm

Fall 2014

Page 6

2014 [POWER SYSTEM OPERATION AND CONTROL]


solves the dual optimization problem. The algorithm was slower in solving the special
cases of the generalized UCP than algorithms demonstrated by other authors. The approach
has been tested for ten units for a time period of 24 hours. In 1995, W.L. Peterson,
proposed a Lagrange Relaxation to incorporate unit minimum capacity and unit ramp rate
constrains. The proposed method is used in finding a feasible UC schedule considering a
new approach for ramping constraints. The algorithm incorporates other practical features
such as boiler fire-up characteristics and non-linear ramp up sequences.
In 2000, A. G. Bakirtzis, demonstrated the difference between the lambda values of the
economic dispatch and the UCP based on economic interpretation of the Lagrangian
Relaxation solution framework. During the LR solution of the UCP two sets of lambdas are
used. Although both set of lambdas represent marginal cost of electricity. The first one, is
assigned as a Lagrange multiplier (Lambda) to the UC power balance equations and second
one, is the Lagrange multiplier of the power balance equation in the economic dispatch
problem. In 2004, W. P. Ongsakul, proposed an enhanced adaptive Lagrangian relaxation
(ELR). Enhanced LR approach consists of heuristic search and adaptive LR. ALR is
enhanced by introducing new 0-1 decisions. After the ALR the best feasible schedule is
obtained. The heuristic search is used to fine tune the schedule. The total system production
costs are less for the large scale system. The computational time is much less compared
with others approaches. In 2005, D. Murtaza, et al.presented an algorithm for the unit
commitment schedule using the Lagrange relaxation method by taking into account the
transmission losses. For better convergence and faster calculation, a two stage Lagrange
relaxation was provided. First, conventional Lagrange relaxation was applied in order to
determine the unit commitment schedule neglecting transmission loss. The results are then
input to the proposed method, and the unit commitment schedule including transmission
losses was produced.

mm

Fall 2014

Page 6

2014 [POWER SYSTEM OPERATION AND CONTROL]

mm

Fall 2014

Page 6

2014 [POWER SYSTEM OPERATION AND CONTROL]

mm

Fall 2014

Page 6

2014 [POWER SYSTEM OPERATION AND CONTROL]

mm

Fall 2014

Page 6

2014 [POWER SYSTEM OPERATION AND CONTROL]

mm

Fall 2014

Page 6

You might also like