Professional Documents
Culture Documents
Engineering Structures
journal homepage: www.elsevier.com/locate/engstruct
Application of air cooled pipes for reduction of early age cracking risk
in a massive RC wall
Miguel Azenha , Rodrigo Lameiras, Christoph de Sousa, Joaquim Barros
ISISE Institute for Sustainability and Innovation in Structural Engineering, University of Minho, School of Engineering, Civil Engineering Dept., Azurm Campus, 4800-058
Guimares, Portugal
a r t i c l e
i n f o
Article history:
Received 27 May 2013
Revised 2 December 2013
Accepted 13 January 2014
Available online 15 February 2014
Keywords:
Cement hydration
Service life conditions
Thermal shrinkage
Cracking
Numerical simulation
a b s t r a c t
The construction of massive concrete structures is often conditioned by the necessity of phasing casting
operations in order to avoid excessive heat accumulation due to cement hydration. To accelerate construction and allow larger casting stages (usually increasing lift height), it is usual to adopt internal cooling strategies based on embedding water pipes into concrete, through which water is circulated to
minimize temperature development. The present paper reports the use of horizontally placed ventilated
prestressing ducts embedded in a massive concrete wall for the same purpose, in line with a preliminary
Swedish proposal made in the 1990s. The application herein reported is a holistic approach to the problem under study, encompassing extensive laboratory characterization of the materials (including a technique developed for continuous monitoring of concrete E-modulus since casting), in situ monitoring of
temperatures and strains, and 3D thermo-mechanical simulation using the nite element method. Based
on the monitored/simulated results, it is concluded that the air-cooling system is feasible and can effectively reduce early cracking risk of concrete, provided adequate planning measures are taken.
2014 Elsevier Ltd. All rights reserved.
1. Introduction
The combined effect of the exothermic nature of cement hydration reactions and the relatively low thermal diffusivity of concrete
leads concrete structures to endure temperature increases at early
ages, and eventually return to thermal equilibrium with the surrounding environment. These early temperature variations induce
volumetric changes in concrete that are partially restrained by
adjoining previously cast members, or even due to non-uniform
temperature distributions within a concrete member itself. Such
restraint to deformation may induce stresses that can be relevant
enough to induce early age thermal cracking in concrete, which
is usually unacceptable in view of aesthetics, durability and even
structural performance. Contractors usually attempt to avoid this
thermal cracking by adopting concrete compositions and construction schedules that maintain temperature gradients in concrete below prescribed limits, both along time and space [1]. It has
however been recognized that such approach leads to erroneous
conclusions, as several important issues are disregarded [1], such
Corresponding author. Tel.: +351 938404554; fax: +351 253 510 217.
E-mail addresses: miguel.azenha@civil.uminho.pt (M. Azenha), rmlameiras@
civil.uminho.pt (R. Lameiras), christoph@civil.uminho.pt (C. de Sousa), barros@
civil.uminho.pt (J. Barros).
http://dx.doi.org/10.1016/j.engstruct.2014.01.018
0141-0296/ 2014 Elsevier Ltd. All rights reserved.
149
2. Thermo-mechanical model
The thermo-mechanical simulation approach presented here
has strong similarities with that described in a previous work
[30]. Nonetheless, some particularities are distinct, namely: (i) solar radiation is explicitly considered according to a model based on
the incidence angle of the sun beams; (ii) the effect of internal
cooling ducts is taken into account (iii) the evolution of mechanical
properties is simulated according to the equivalent age concept
(instead of the degree of hydration concept). The following subsections pertain to a general description of the modelling strategy
with specic emphasis on topics (i)(iii) mentioned above.
2.1. Thermal model
The calculation of temperature elds in concrete is based on the
heat balance equation, whose solution is made through the nite
element method [44]:
kr rT Q_ qcT_
qT hcr T b T e
where hcr is a mixed convectionradiation boundary transfer coefcient, Tb is the boundary surface temperature and Te is the environmental temperature.
The simulation of thermal inputs associated to solar radiation in
concrete structures can be made with signicant accuracy through
the adoption of models that are readily used in meteorological sciences [31,47]. Such models can take into account the effects of the
spatial relationship between the earth and sun at a given time of
the day/year and thus predict the solar radiation that reaches a certain point on earth at sea level (i.e. low atmosphere). It is further
possible to compute the angle between the sunbeam and any arbitrarily oriented/inclined surface, and evaluate the intake of energy
throughout the day of such surface.
The calculation of the solar energy that reaches earth at sea level, qm, is based on the solar constant, q0, which represents the total radiation energy received from the sun at a distance
corresponding to 1 Astronomical Unit. Even though q0 varies
slightly throughout the year by 7%, it is usually acceptable to consider q0 = 1367 W m2. The estimation of qm can be done through
the following empirical equation [47,48]:
T l
qm q0 e0:99:4sinh
150
Bearing in mind that the aim of the thermo-mechanical simulations is to assess the risk of cracking, the post-cracking behaviour is
not considered relevant and it is thus not simulated. Thus, linear
elastic behaviour (with creep) is considered for concrete both in
compression and in tension.
qS aS qm cosi
Another particularity of the present application in regard to previous works [30] is the use of prestressing ducts acting as cooling
pipes. A formulation is thus necessary to describe the added internal heat uxes that are caused by the presence of an embedded
cooling pipe, which can be expressed in the following energy balance equation, to be applied throughout the length z along the pipe
[49]:
_ cp
m
dT c
hc P T c T w
dz
t eq
ERa
1 1
Ts T ref
ds
Jt; t 0
1
/
m
n
1 t0 t t0
E0 t 0 E0 t0
3.1. Overview
The Paradela dam, located in the North of Portugal, is a rockll
gravity dam built in the 1950s, with 540 m longitudinal development and maximum height of 112 m from foundation. Due to recent hydraulic problems in one of the dams spillways, it was
necessary to build a new complementary ski-jump spillway on
the right margin of the river [53]. The case study reported in this
paper concerns the cooling measures and assessment of cracking
risk in the construction of the central wall of the spillway entrance.
3.2. Description of the spillway entrance
3.2.1. Geometry and construction phasing
The spillway functions in free surface conditions, and has two
main entrances at the top level of the dam, each with 5.5 m width,
being separated by a hydro-dynamic shaped wall with maximum
width of 2.8 m and 17.4 m height. A three dimensional representation of the entrance region of the dam spillway is shown in Fig. 1a,
whereas its corresponding plan view at approximately mid-height
of the wall is depicted in Fig. 1b. The reinforcement of the middle
wall can be generally characterized by 16//200 mm placed vertically and 12//200 mm placed horizontally near each surface with
a concrete cover of 60 mm.
The construction of the wall was generally performed with
1.2 m tall construction phases, with empirically dened waiting
periods being dened by a target temperature in the core regions
during the cooling period (approximately 27 C, which corresponded to 17 C above average daily temperature during
construction). In order to minimize such waiting periods, an
air-cooling system based on ventilated prestressing ducts placed
horizontally was implemented, allowing lower peak temperatures
and faster return to temperature equilibrium with the surrounding
environment. The main scope of the present paper is the study of a
specic construction phase that corresponds to the zone of embedment of the xation parts of the sluice gates. Such xation parts
were approximately 2.5 m tall, and it was thus desirable to
perform a 2.5 m tall construction phase, labelled as 9th phase in
Fig. 2a. Due to its larger thickness, this construction phase is the
critical one in terms of peak temperatures and cracking risk, being
therefore the object of analysis.
3.2.2. Materials
The wall of the spillway entrance was generally cast using concrete of class C30/37 [54] with the composition labelled as S1-D32
in Table 1. In the 9th construction phase, due to increased complexity of reinforcement near the downstream extremity of the
wall (related to the salient concrete blocks), two slightly different
compositions with higher uidity were used in the vicinity of such
region, as shown in Table 1 (S3-D32 and S3-D16). In spite of this,
the areas of most interest to this study (thickest regions of the wall
and monitored sections) correspond to the upstream region. Therefore, and also taking into account the fact that the compositions
have similarities, all the characterizations and modelling in the
scope of this work pertain to mix S1-D32. Steel reinforcement
was S400C [54], with characteristic yield stress of 400 MPa.
151
Fig. 1. Entrance of the dam spillway: (a) three dimensional representation and (b) plan view of the central wall.
Fig. 2. (a) Construction phasing of the central wall (elevation) and (b) overall photo during the construction of the 9th phase.
Table 1
Mix proportions of concrete in the 9th phase of the spillway wall.
Components
Gravel 1432 mm
Gravel 1016 mm
Gravel 48 mm
Sand
CEM I 42.5R
Fly ash
Plasticizer
Water
449
438
306
621
224
96
2.2
170
400
400
316
646
238
102
3.4
180
490
387
763
280
120
4
200
152
Fig. 3. Cooling system at the 9th construction phase: (a) plan view; (b) longitudinal section and (c) cross-section A0 A.
153
Fig. 4. Temperature and strain measurement devices: (a) location of sensors within section A0 A and (b) location of sensors within the tubes T1, T2 and T3. Units: [m].
Fig. 5. Monitored temperatures (two alignments that encompass sensor VW3): (a)
vertical alignment and (b) horizontal alignment.
VW5 (hottest region in concrete) are also represented for comparative purposes. The information provided by such gure allows the
clear identication of the instant at which air ventilation began
(14 h), as the rate of temperature rise is clearly disrupted inside
the duct. Furthermore, the rising temperature tendency along the
ducts length is identiable, as the temperature is consistently
higher in TC3 in regard to TC10, and in TC9 in regard to TC3. Taking
as example the temperatures recorded at the instant of peak temperature (1.88 days), TC9 measured a temperature of 32.2 C,
whereas TC10 indicated a temperature of 29.4 C. This represents
a shift in temperature of approximately 3 C in 3.5 m length of
duct. At three instants of this study, temperatures were measured
also at the entrance of T3 (x = 0) and at x = 1 m through the use of a
handheld temperature probe (PT1000). By joining such data with
the results of TC3, TC9 and TC10, it was possible to plot a temperature prole along the duct for t = 3.84 d, t = 4.56 d and t = 6.58 d
see Fig. 6b. It can be observed that the temperature at the inlet of
the tube matches the environmental temperature, and that the
heating of the air along the tube is strongly dependent on the combination of environmental temperature and internal temperature
of concrete. In fact, in the most unfavourable situation shown by
Fig. 6b, air was heated from 11 C at the air inlet to 26 C at a
point located 25 m away from the air inlet (t = 4.56 d). This increase of air temperature is bound to reduce its cooling capacity.
However, in spite of such diminishment of cooling capacity, the
temperature of the air in the hotter regions of the duct remained
at least 10 C below that of concrete during the periods at which
temperature in concrete was near its peak (see t = 1 d to t = 3 d in
Fig. 6a), showing that the heat removal potential was not negligible
at all.
The observed diminishment of cooling capacity along the length
of the duct highlights the fact that the adopted conguration for
the tubes does not maximize cooling capacity, which would be
conversely maximized if the length of tube inside concrete had
been minimized. Such goal could have been achieved by providing
a vertical arrangement for the tubes and introducing more individual smaller tubes.
3.3.3. Strain monitoring
Strain measurement was carried out with vibrating wire strain
gauges of metallic casing with 14 cm reference length (TES/5.5/T
Gage Technique). Past laboratory tests and in situ applications
[44,57,58] have shown that this kind of sensor is robust and adequate for strain measurement in concrete at early ages. The strain
gauges were placed at the locations identied in Fig. 4a (VW1
VW6), dully positioned in order to measure strains in the longitudinal direction of the wall. VW7 has distinct intents and shall be
154
Fig. 6. Monitored temperatures in duct T3: (a) Global results for TC3, TC9 and TC10 and (b) temperature prole along the duct at three selected instants. Units: [m].
155
Fig. 10. Heat generation rate of a cement paste with CEM I 42.5R and w/c = 0.5.
Fig. 9. In situ determination of TDC: (a) overview of installed no-stress specimen and (b) evolution of strain and temperature evolutions in VW7.
156
Fig. 11. (a) Evolution of compressive and tensile strength of concrete. (b) Basic creep of concrete: specic creep for loading at the ages of 1.1, 3.3 and 7.3 days.
testing setup and procedure applied for the concrete of this spillway application can be found in [56,66,67], as it corresponds to
an improved version of the originally devised test (a steel mould
is used). The collected results with EMM-ARM and cyclic compression tests on cylinders are shown in Fig. 12, where the feasibility of
EMM-ARM is conrmed in view of the resemblance of results. Also,
the richness of information that can be obtained through EMMARM represents an added value for the numerical simulation.
Fig. 12. E-modulus of concrete assessed by compressive cyclic testing and EMMARM.
4. Numerical modelling
4.1. Geometry, mesh, materials, initial/boundary conditions and time
integration
157
Fig. 13. (a) Scheme of the simulation model and phasing; (b) section A0 A of the model and (c) nite element mesh.
of the model was equal to half the actual perimeter of the tubes. As
solar radiation does not represent a symmetrical energy input to
the structure, the symmetry simplication adopted is not truly valid. However, as solar radiation has most of its effect near the surface, it was decided to keep the symmetry simplication by
considering the southeast half of the wall, which is most subject
to solar radiation effects.
4.1.2. Materials (thermal and mechanical properties)
The thermal conductivity and specic heat of concrete were
estimated with basis on the pondered average of the corresponding
thermal properties of the constituent materials of the mix [44,68].
The adopted values for k and qc for concrete were, respectively
2.40 W/m K and 2.4 106 J/m3 K. Even though it is known that
these thermal properties suffer variations during early ages [69
75], the adopted modelling approach considers them constant in
view of the conclusions of the parametric analyses reported by
Azenha [44], where a relatively small impact of considering evolving k and qc was found on computed temperatures in hardening
concrete.
In regard to the data for heat of hydration, the parameters mentioned in Section 3.3.4 were used. The adequacy of these parameters was evaluated through the semi-adiabatic calorimeter
described in the same section, whose behaviour was simulated
through a FE simulation model that explicitly considered the extruded polystyrene (XPS) and wood walls of the calorimeter. The
material modelling parameters for concrete coincide with those
158
herein described, whereas additional information and mesh representation are shown in Fig. 14a. The results of the simulation of the
calorimeter were quite coherent with those collected experimentally, as seen in Fig. 14b, leading to the conrmation that the strategy described in Section 3.3.4 to determine the heat generation
and activation energy was adequate for dening the heat of hydration modelling parameters adopted in the simulations.
The thermal dilation coefcient (TDC) of concrete was assessed
with basis on the no-stress specimen described in Section 3.3.3.
However, in order to obtain the thermal deformation and calculate
the TDC, it was necessary to subtract the autogenous shrinkage
deformation from the total deformation. As data on autogenous
shrinkage was not available, an estimate of the autogenous shrinkage evolution based on Eurocode 2 [54] was used. Another issue to
take into account is the fact that the TDC of concrete is not constant
during the rst hours of age. In fact, several authors have dealt
with this subject, and it generally agreed that the initial TDC tends
to be larger than that of hardened concrete, and tends to decrease
sharply within the rst 12 to 24 h of age, reaching then the plateau
level corresponding to hardened concrete [69,73,76]. The nostress specimen cast in the scope of this research cannot be used
to estimate TDC at concrete early ages, due to the absence of data
in the rst 8 h reported in Fig. 9b. Nonetheless, as the peak temperature occurred later than 24 h age, and full data is available for
temperatures and strains occurred in such period, calculations
could be made under the assumption that TDC was already at its
plateau value. The TDC was estimated between instants t = 2.0 d
(peak temperature) and t = 8.0 d (local minimum) as shown in
Fig. 9b, and the autogenous shrinkage strain variation in such period was estimated to be of 8.45 le (considering fcm = 42.3 MPa in
Eurocode 2 [54]). The estimated constant TDC to be used in the
numerical simulation was 11.07 le/C. Nonetheless, since it is
known that TDC varies during the rst 24 h of age, an alternative
formulation for the evaluation of the TDC was considered, based
on experimental evidence reported by Laplante and Boulay [77].
Therefore, this alternative formulation considers that during the
rst 16 h the TDC varies according to TDC(t) = 0.16t2 4.88t
+ 48.93 (t in hours), and remains constant after such age.
The E-modulus evolution of concrete for the simulation model
was directly extracted from EMM-ARM data reported in Fig. 12,
whereas creep modelling was made through the adjustment of
DPL parameters to the creep data experiments. The best-t creep
parameters and their adjustment to the experimental data are
shown in Fig. 11b. Prestressing ducts were modelled with
Fig. 14. (a) FE model for the semi-adiabatic calorimeter (geometry and general data/units in millimetres). (b) Calculated and recorded temperature in the geometrical centre
of the calorimeter.
159
Fig. 15. (a) Measured and simulated temperatures for VW1, VW2, VW4 and VW5. (b) Temperature distribution within the thicker section of the wall for the instants that the
maximum temperatures are attained. (c) Calculated temperatures in the points where the highest temperatures are attained in the thicker section of the wall.
160
perature to thermal equilibrium with the environment was accelerated, with advantages for construction phasing.
The fact that the calculated temperatures matched well the
monitored ones is a solid starting point for the analysis of results
of the mechanical simulation, as any detected deviations are
bound to be solely attributed to issues in the mechanical simulation itself. The calculated and measured strains for the same set
of sensors that has just been discussed for temperature development are shown in Fig. 16. The experimentally measured strains
in this gure are represented by their value according to the
zeroing procedure mentioned in Section 3.3.3 (Fig. 7), but also
with a lower and upper bound related to possible uncertainties
in the instant for zeroing of the sensors output of 2 h. It can
be seen that all the computed strains with consideration of constant TDC underestimate the peak strain at 1.96 day, but the
post-peak kinetics seems to have been well captured. As the constant TDC assumption may lead to underestimations of early
strain development [57], a further calculation was made using
a plausible TDC evolution during the rst 24 h, as discussed in
4.1.2. The corresponding simulation results are shown in
Fig. 16, where a better overall t is seen between experimental
and calculation data (particularly for core regions). Even though
the variable TDC was not based on experimental evidence obtained in the scope of this research, it is feasible to assume that
a signicant part of the strain deviations regarding experimental
results can be explained by the variable TDC at early ages. It has
to be kept into consideration that another possible source of
deviation of results may be related to the instant at which measured strains were zeroed, which can be debatable. Nonetheless,
the adequate prediction of strains that was attained is a good
indication of the feasibility of the computed stresses which are
to be analyzed.
Fig. 16. Measured and simulated strains for VW1, VW2, VW4 and VW5.
Fig. 17. Principal tensile stresses at the point corresponding to the maximum
tensile stress in the wall (x = 8.5 m, y = 0.36 m, z = 11.7 m) for three simulation
models considered.
161
5. Conclusions
Acknowledgements
162
References
[1] Bernander S. Practical measures to avoiding early age thermal cracking in
concrete structures. In: Springenschmid R, editor. Prevention of thermal
cracking in concrete at early ages: state-of-the-art report prepared by RILEM
Technical Committee 119. RILEM report 15. E&FN Spon; 1998. p. 255314.
[2] Springenschmid R. In: Thermal cracking in concrete at early ages: RILEM
proceedings. RILEM report 25. Routledge: Taylor & Francis; 1995.
[3] Du C. Dam construction concrete temperature control using y ash. Concr Int
1996;18:346.
[4] Utsi S, Jonasson J-E. Estimation of the risk for early thermal cracking for SCC
containing y ash. Mater Struct 2012;45:15369.
[5] Kurita M, Goto S, Minegishi K, Negami Y, Kuwahara T. Precooling concrete
using frozen sand. Concr Int 1990;12:605.
[6] Takeuchi H, Tsuji Y, Nanni A. Concrete precooling method by means of dry ice.
Concr Int 1993;15:526.
[7] St John J. Construction of the Hoover Dam Bypass. Concr Int 2011;33:305.
[8] Hedlund H, Groth P. Air cooling of concrete by means of embedded cooling
pipes. Part I: laboratory tests of heat transfer coefcients. Mater Struct
1998;31:32934.
[9] Groth P, Hedlund H. Air cooling of concrete by means of embedded cooling
pipes. Part II: application in design. Mater Struct 1998;31:38792.
[10] Roush K, OLeary. Cooling concrete with embedded pipes. Concr Int
2005;27:302.
[11] Maggenti R. From passive to active thermal control. Concr Int 2007;29:2430.
[12] Ishikawa S, Matsukawa K, Nakanishi S, Kawai H. Air pipe cooling system. Concr
Int 2007;29:459.
[13] Nobuhiro M, Kazuo U. Nonlinear thermal stress analysis of a massive concrete
structure. Comput Struct 1987;26:28796.
[14] Emborg M. Thermal stresses in concrete structures at early age. Doctoral
thesis. Lule University of Technology; 1989.
[15] Ishikawa M. Thermal stress analysis of a concrete dam. Comput Struct
1991;40:34752.
[16] de Borst R, van den Boogaard AH. Finite-element modeling of deformation and
cracking in early-age concrete. J Eng Mech 1994;120:251934.
[17] Torrenti JM, De Larrard F, Guerrier F, Acker F, Grenier F. Numerical simulation
of temperatures and stresses in concrete at early ages: the French experience.
In: Springenschmid R, editor. Thermal cracking in concrete at early ages.
RILEM proceedings 25, Paris; 1994. p. 2818.
[18] Fairbairn EMR, Ferreira IA, Cordeiro GC, Silvoso MM, Filho RDT, Ribeiro FLB.
Numerical simulation of dam construction using low-CO2-emission concrete.
Mater Struct/Mater Constr 2010;43:106174.
[19] De Schutter G, Vuylsteke M. Minimisation of early age thermal cracking in a Jshaped non-reinforced massive concrete quay wall. Eng Struct 2004;26:8018.
[20] Dolmatov AP, Neidlin SZ. Temperature control of the massive concrete of the
Krasnoyarsk hydroelectric station dam. Hydrotech Constr 1968;2:95660.
[21] Blinov IF, Shaikin YP, Galperin IR. Field studies of the temperature regime and
stress state of the concrete in arch dams subjected to various methods of
cooling. Hydrotech Constr 1980;14:1923.
[22] Torrenti J-M, Buffo-Lacarrire L, Barr F. CEOS.FR experiments for crack control
of concrete at early age. In: RILEM-JCI international workshop on crack control
of mass concrete and related issues concerning early-age of concrete
structures (ConCrack 3), Paris; 2012. p. 310.
[23] Cussigh F. Experience in limiting early age concrete temperature for DEF
prevention. In: RILEM-JCI international workshop on crack control of mass
concrete and related issues concerning early-age of concrete structures
(ConCrack 3), Paris; 2012. p. 7988.
[24] Benboudjema F, Torrenti JM. Early-age behaviour of concrete nuclear
containments. Nucl Eng Des 2008;238:2495506.
[25] Craeye B, De Schutter G, Van Humbeeck H, Van Cotthem A. Early age behaviour
of concrete supercontainers for radioactive waste disposal. Nucl Eng Des
2009;239:2335.
[26] Briffaut M, Benboudjema F, Torrenti JM, Nahas G. Numerical analysis of the
thermal active restrained shrinkage ring test to study the early age behavior of
massive concrete structures. Eng Struct 2011;33:1390401.
[27] Waller V, dAloa L, Cussigh F, Lecrux S. Using the maturity method in concrete
cracking control at early ages. Cem Concr Compos 2004;26:58999.
[28] Xiang Y, Zhang Z, He S, Dong G. Thermalmechanical analysis of a newly cast
concrete wall of a subway structure. Tunn Undergr Space Technol
2005;20:44251.
[29] Faria R, Azenha M, Figueiras JA. Modelling of concrete at early ages:
application to an externally restrained slab. Cem Concr Compos
2006;28(6):57285.
[30] Azenha M, Faria R. Temperatures and stresses due to cement hydration on the
R/C foundation of a wind tower a case study. Eng Struct 2008;30:2392400.
[31] Boutillon L, Linger L, Kolani B, Meyer E. Effects of sun irradiation on the
temperature and early age stress distribution in external concrete structure.
In: Toutlemonde F, Torrenti J-M, editors. RILEM-JCI international workshop on
crack control of mass concrete and related issues concerning early-age of
concrete structures. ConCrack 3, Paris; 2012. p. 18192.
[32] Zreiki J, Bouchelaghem F, Chaouche M. Early-age behaviour of concrete in
massive structures, experimentation and modelling. Nucl Eng Des
2010;240:264354.
[33] Zhu Y-M, Liu Y-Z, Xiao Z-Q, He J-R, Lin Z-H, Ma Y-F. Analysis of pipe-cooling
system in mass concrete. College of Water Conservancy & Hydropower Eng.,
Hohai Univ., Nanjing, China; 2004.
[34] James RJ, Dollar DA. Thermal engineering for the construction of large concrete
arch dams. In: The 6th ASMEJSME thermal engineering joint conference,
Hapena Beach, Hawaii; 2003.
[35] Xie H, Chen Y. Inuence of the different pipe cooling scheme on temperature
distribution in RCC arch dams. Commun Numer Methods Eng
2005;21:76978.
[36] Myers TG, Fowkes ND, Ballim Y. Modeling the cooling of concrete by piped
water. ASCE J Eng Mech 2009:137583.
[37] Yamamoto T, Ohtomo T. Practices for crack control of concrete in Japan. In:
Toutlemonde F, Torrenti JM, editors. RILEM-JCI international workshop on
crack control of mass concrete and related issues concerning early-age of
concrete structures (ConCrack 3). ParisRILEM Publications; 2012. p. 193200.
[38] Tanabe T-a, Yamakawa H, Watanabe A. Determination of convection
coefcient at cooling pipe surface and analysis of cooling effect. Proc JSCE
1984;34:1719.
[39] Yang J-K, Lee Y, Kim J-K. Heat transfer coefcient in ow convection of pipecooling system in massive concrete. J Adv Concr Technol 2011;9(1):10314.
[40] Yang J, Hu Y, Zuo Z, Jin F, Li Q. Thermal analysis of mass concrete embedded
with double-layer staggered heterogeneous cooling water pipes. Appl Therm
Eng 2012;35:14556.
[41] Kim JK, Kim KH, Yang JK. Thermal analysis of hydration heat in concrete
structures with pipe-cooling system. Comput Struct 2001;79:16371.
[42] Azenha M, Magalhes F, Faria R, Cunha . Measurement of concrete E-modulus
evolution since casting: a novel method based on ambient vibration. Cem
Concr Res 2010;40:1096105.
[43] TNO-DIANA-BV. Diana users manual release 9.2, Delft, The Netherlands;
2007.
[44] Azenha M. Numerical simulation of the structural behaviour of concrete since
its early ages. PhD thesis. University of Porto, Porto, Portugal; 2009.
[45] Reinhardt H, Blaauwendraad J, Jongedijk J. Temperature development in
concrete structures taking account of state dependent properties. In: Int conf
concrete at early ages, Paris, France; 1982.
[46] Faria R, Azenha M, Figueiras JA. Modelling of concrete at early ages:
application to an externally restrained slab. Cem Concr Compos
2006;28:57285.
[47] Breugel K, Koenders EAB. IPACS report BE96-3843/2001:31-1. Solar radiation:
effect on solar radiation on the risk of cracking in young concrete; 2001.
[48] Kasten F. A simple parameterization of the pyrheliometric formula for
determining the Linke turbidity factor. Meteorl Rdsch 1980;33:1247.
[49] Incropera FP, DeWitt DP, Bergman TL, Lavine AS. Fundamentals of heat and
mass transfer. Wiley; 2006.
[50] Freiesleben Hansen P, Pedersen EJ. Maturity computer for controlled curing
and hardening of concrete. Nordisk Betong 1977;1:1934.
[51] Bazant ZP, LHermite R. Mathematical modeling of creep and shrinkage of
concrete. John Wiley & Sons; 1988. 484 p.
[52] Japan Concrete Institute. JCI guidelines for control of cracking of mass
concrete. JCI; 2011. p. 153.
[53] Couto LT, Oliveira MS, Dias da Silva J, Magalhes AP. New Paradela dams
spillway: design and testing in reduced hydraulic model. 9 Congresso
Nacional da gua. Associao Portuguesa de Recursos Hdricos, Estoril,
Portugal; 2008 [in Portuguese].
[54] CEN. EN 1992-1 European Standard Eurocode 2: design of concrete structures.
Part 1: general rules and rules for buildings; 2004.
[55] CEN. EN 446:2007 grout for prestressing tendons: grouting procedures; 2007.
p. 20.
[56] Costa A. Thermo-mechanical analysis of self-induced stresses in concrete
associated to heat of hydration: a case study of the spillway of Paradela dam.
Master thesis. University of Minho, Guimares; 2011[in Portuguese].
[57] Azenha M, Faria R, Ferreira D. Identication of early-age concrete
temperatures and strains: monitoring and numerical simulation. Cem Concr
Compos 2009;31:36978.
[58] Yeon JH, Choi S, Won MC. In situ measurement of coefcient of thermal
expansion in hardening concrete and its effect on thermal stress development.
Constr Build Mater 2013;38:30615.
[59] Choi S, Won M. Thermal strain and drying shrinkage of concrete structures in
the eld. ACI Mater J 2010;107:498507.
[60] DAloia L, Chanvillard G. Determining the apparent activation energy of
concrete: Eanumerical simulations of the heat of hydration of cement. Cem
Concr Res 2002;32:127789.
[61] Carino NJ, Lew H. The maturity method: theory and application. Structures
congress & exposition. Washington (DC): American Society of Civil Engineers;
2001. p. 15.
[62] Ulm F-J, Coussy O. Strength growth as chemo-plastic hardening in early age
concrete. J Eng Mech 1996;122:112332.
[63] fdration internationale du bton. b Model Code 2010 (nal draft),
Lausanne, Switzerland; 2011. p. 653.
[64] Aitcin P-C, Neville A, Acker P. Integrated view of shrinkage deformation. Concr
Int 1997;19:3541.
[65] Hedlund H. Hardening concrete. Measurements and evaluation of non-elastic
deformation and associated restraint stresses. Doctoral thesis. Lulea University
of Technology, Lulea, Sweden; 2000.
163