outline method statement for the proposed works identified under Contract 1. The
The contractor will comply with environmental constraints as outlined in the Contract
Documents and Construction Method Statement.
Contractor to liaise with SEPA regarding timing of rock armour works and
implement appropriate flood warning measures during the works.
Contractor to conform to environmental constraints contained within the Contract
published by SEPA.
Contractor staff to wear appropriate PPE at all times during site operations.
Contractor shall not deviate from their submitted and approved detailed method
statement without prior written authorisation from the Engineer.
Contractor will be responsible for reviewing all services within each element of
Contract 1. Appropriate warning signs and goal posts to be placed either side of
services in close proximity.
Welfare unit will be on site for the duration of the works.
The Contractor will be directed to follow all relevant and specific requirements of
the scheme' s SEPA Licence, which will be referred to in the Works
Specification.
On contract award the Contractor will provide detailed method statements prior
to the construction work.
Note: There are no proposed in- channel works for this element of the works.
0 Mouchel 2014 -
1-
Contractor to prepare a detailed method statement for the proposed works for
erecting an RC Floodwall around the perimeter of the Bowling Green, which shall
include [ as a minimum] the following requirements:
Contractor to set up site preliminaries including offices /messes and site boundary
safety fencing around the bowling green, parts of the access road and parking
area. All appropriate access permissions to be acquired from affected landowners.
Contractor to conduct trial pits (hand dug) to confirm the locations of existing
services and take reasonable measures to protect services affected by the works.
Contractor will commence site clearance operations, this will include removal of
vegetation, garden furniture, garden path surfacing, slabs and the contents of
sheds either to be carefully stockpiled for re -use or disposed of in a licensed tip.
Contractor will commence demolition operations consisting primarily of
removing an existing brockwork boundary wall and two existing timber sheds.
The Contractor will adopt safe methods of working to ensure the existing wall
and sheds will not be prone to collapse during demolition operations. The
contractor will also have special measures in place as directed by SEPA
guidelines to prevent any demolition debris and other pollutants entering the
watercourse. This will include ensuring all construction plant and storage areas
will be set back from the watercourse and river banks.
Contractor will excavate foundations for the proposed flood wall. Foundations are
required for excavations. Where possible, existing turf t/opsoil will be stockpiled
and re -used.
Contractor will erect the proposed flood wall reinforcement, shuttering including
expansion joints, and cast concrete in -situ. All formwork will be checked for
leaks/ bleeding during pouring operations and any identified instances of grout
egress will be immediately plugged and cleaned away. The contractor will ensure
all surplus concrete /grout is transported away from the site and disposed of in a
licensed tip.
After the flood wall has cured sufficiently, the concrete set beneath existing
ground levels will be waterproofed with layers bituminous coating applied by
roller or brush. The wall will then be clad in brickwork. Material spills of
New sheds will be installed to replace the existing. The landscape and garden
paths /furniture etc will be restored.
The contractor will remove all trace of the preliminary items including temporary
fencing, messes and stores.
Other requirements:
units in accordance with the Contract Special Requirements to capture any leakage
from plant
0 Mouchel 2014 -
2-
iimolAchel ill
Contractor shall develop a detailed method statement for rock armour bank protection
works, which shall include ( as a minimum) the following requirements:
Access to the site will be via the road access to the Playing Field and Playing
Field Pavilion.
When using access roads banksman will be aware of pedestrian movement and
make sure site traffic passes safely.
Construction work for the lower half of the revetment atibeneath river bed level
Using an excavator place foundation and toe scour rock below outfall.
Install surface water outfall and protect with rock armour.
halfway up the bank. Continue along the entire length of the revetment.
Repeat process for the upper part of the bank.
At the downstream end tie into the existing bank profile once Playing Field
Pavilion and Scottish Water outfall have been removed.
Re- profile and seed soil behind with appropriate amenity mix.
a
Contractor shall develop a detailed method statement for sheet pile installation at
Sheet piling location to be set back from river bank as per drawing 10330641600 -001.
Contractor to keep all plant remote from East Pow Burn. Machinery is not
permitted to enter the East Pow Burn for Contract 1 sheet pile installation works.
Sheet piles are set back approximately 11 metres horizontally from normal flow
channel, which shall provide a sufficient buffer strip for pollution prevention.
0 Mouchel 2014 -
3-
ground level to ensure no utility services or tree root will be damaged by piling
operations.
prevent sediment run -off into the Burn as a result of site works, rainfall or any
other external factor. Any excess material will be removed from site and either
recycled on a separate project or taken to an appropriate facility.
Contractor to install piling platform and install piling equipment on platform.
Contractor to ensure accurate pile installation via use of any proprietary
template /guide structure for the particular product used.
Contractor to install sheet piles sequentially using a crawler rig (or approved
equivalent) and the appropriate driving methodology and pile protection to the
designed depth and to the top of sheet pile wall levels required in the Contract.
Contractor to liaise with the Engineer throughout sheet pile installation and
highlight any locations where difficulty is encountered installing piles through the
alluvial strata.
Contractor shall undertake water sampling downstream of the sheet piling works
as directed by the Engineer, in accordance with SEPA and Vector Aerospace
requirements.
Contractor shall take cognizance of all overhead obstructions at, and on the
approaches to, the site within the detailed method statement.
Contractor shall provide measures for recording wind speeds during sheet pile
installation and include within the detailed method statement a procedure for
Contractor shall reinstate the grassed area and security fence on Vector
Aerospace land to the satisfaction of the Engineer.