BRIDGE CONSTRUCTION

INSPECTOR
Practice Questions

Next

Bridge Inspector
Practice Questions

1. An 8 ft. diameter drilled shaft has a tip


elevation of 197 ft. With a top elevation of
235 ft., what is the theoretical quantity of
concrete for this shaft?
a)
29 cy
b)
58 cy
c)
71 cy
d)
102 cy

Bridge Inspector
Practice Questions

1. An 8 ft. diameter drilled shaft has a tip


elevation of 197 ft. With a top elevation of
235 ft., what is the theoretical quantity of
concrete for this shaft?

CORRECT!

Next

Bridge Inspector
Practice Questions

1. An 8 ft. diameter drilled shaft has a tip


elevation of 197 ft. With a top elevation of
235 ft., what is the theoretical quantity of
concrete for this shaft?
INCORRECT!
The correct answer is C, 71 cy.

Next

Bridge Inspector
Practice Questions

2. Air entrained concrete is highly resistant to


the destructive effects of freeze-thaw
cycling due to the presence of large air
bubbles in the paste.
a)
b)

True
False

Bridge Inspector
Practice Questions

2. Air entrained concrete is highly resistant to


the destructive effects of freeze-thaw
cycling due to the presence of large air
bubbles in the paste.

CORRECT!

Next

Bridge Inspector
Practice Questions

2. Air entrained concrete is highly resistant to


the destructive effects of freeze-thaw
cycling due to the presence of large air
bubbles in the paste.
INCORRECT!
The correct answer is False.

Next

Bridge Inspector
Practice Questions

3. A footing is 8 ft. wide by 13 ft. long. The


bottom of the footing is at elevation 211.00
and the original ground is at elevation
225.00. The finish grade of the deck is
235.00. What is the amount of structure
excavation?
a)
54 cy
b)
78 cy
c)
92 cy
d)
133 cy

Bridge Inspector
Practice Questions

3. A footing is 8 ft. wide by 13 ft. long. The


bottom of the footing is at elevation 211.00
and the original ground is at elevation
225.00. The finish grade of the deck is
235.00. What is the amount of structure
excavation?

CORRECT!

Next

Bridge Inspector
Practice Questions

3. A footing is 8 ft. wide by 13 ft. long. The


bottom of the footing is at elevation 211.00
and the original ground is at elevation
225.00. The finish grade of the deck is
235.00. What is the amount of structure
excavation?
INCORRECT!
The correct answer is B, 78 cy.

Next

Bridge Inspector
Practice Questions

4. The vibrator should not be used to move


concrete laterally.
a)
b)

True
False

Bridge Inspector
Practice Questions

4. The vibrator should not be used to move


concrete laterally.

CORRECT!

Next

Bridge Inspector
Practice Questions

4. The vibrator should not be used to move


concrete laterally.
INCORRECT!
The correct answer is True.

Next

Bridge Inspector
Practice Questions

5. During hot weather concrete placement,


the inspector should
a)

Not worry about wind as it will help to cool the


concrete surface.

b)

Assure that the curing water is as cold as possible.

c)

Take appropriate steps to lower the mix


temperature when it approaches 90F.

d)

Use clear/white plastic as part of the cure process.

Bridge Inspector
Practice Questions

5. During hot weather concrete placement,


the inspector should

CORRECT!

Next

Bridge Inspector
Practice Questions

5. During hot weather concrete placement,


the inspector should
INCORRECT!
The correct answer is D, use clear/white
plastic as part of the cure process.

Next

Bridge Inspector
Practice Questions

6. For footings and seals, the bottom elevation


shown on the plans serves as the lower pay
limit. Should the contractor over excavate
below that limit or should the need arise to
excavate below that limit to attain the
necessary bearing value, the situation must
be corrected in a manner that the
construction Project Manager must approve.
a)
b)

True
False

Bridge Inspector
Practice Questions

6. For footings and seals, the bottom elevation


shown on the plans serves as the lower pay
limit. Should the contractor over excavate
below that limit or should the need arise to
excavate below that limit to attain the
necessary bearing value, the situation must
be corrected in a manner that the
construction Project Manager must approve.

CORRECT!
Next

Bridge Inspector
Practice Questions

6. For footings and seals, the bottom elevation


shown on the plans serves as the lower pay
limit. Should the contractor over excavate
below that limit or should the need arise to
excavate below that limit to attain the
necessary bearing value, the situation must
be corrected in a manner that the
construction Project Manager must approve.
INCORRECT!
The correct answer is True.
Next

Bridge Inspector
Practice Questions

7. A bridge foundation must bear the weight


of traffic and the considerable weight of the
structure itself. Therefore, its foundation
a)
b)
c)

d)

Must be near the surface to reduce deflection.


Must start out on firm but yielding material.
Is of no particular importance in the bridges
stability.
Relies on structural design, not mass.

Bridge Inspector
Practice Questions

7. A bridge foundation must bear the weight


of traffic and the considerable weight of the
structure itself. Therefore, its foundation

CORRECT!

Next

Bridge Inspector
Practice Questions

7. A bridge foundation must bear the weight


of traffic and the considerable weight of the
structure itself. Therefore, its foundation
INCORRECT!
The correct answer is D, relies on structural
design, not mass.

Next

Bridge Inspector
Practice Questions

8. When excavating inside a cofferdam, the


Bridge Construction Inspector
a)

b)

c)

d)

Need not be concerned with levelness of materials


encountered at the bottom of seal excavation.
Should never feel responsible for monitoring the
positioning of the internal supports for the sheet pile
walls.
Should arbitrarily lessen the seal depth if hard rock is
encountered while excavating for the bottom of seal
elevation.
None of the above.

Bridge Inspector
Practice Questions

8. When excavating inside a cofferdam, the


Bridge Construction Inspector

CORRECT!

Next

Bridge Inspector
Practice Questions

8. When excavating inside a cofferdam, the


Bridge Construction Inspector
INCORRECT!
The correct answer is D, none of the above.

Next

Bridge Inspector
Practice Questions

9. Reinforcing steel in piers and abutments


a)
b)

c)

d)

Is critical to a bridges load bearing strength.


Must be closely checked for specified lap
splice lengths, support and wire tie accuracy.
Must be closely checked for size, shape,
length, spacing and quantity used.
All of the above.

Bridge Inspector
Practice Questions

9. Reinforcing steel in piers and abutments

CORRECT!

Next

Bridge Inspector
Practice Questions

9. Reinforcing steel in piers and abutments


INCORRECT!
The correct answer is D, all of the above.

Next

Bridge Inspector
Practice Questions

10. When placing concrete as part of a bridges


superstructure, the concrete should not be
allowed to drop more than 4 feet.
a)
b)

True
False

Bridge Inspector
Practice Questions

10. When placing concrete as part of a bridges


superstructure, the concrete should not be
allowed to drop more than 4 feet.

CORRECT!

Next

Bridge Inspector
Practice Questions

10. When placing concrete as part of a bridges


superstructure, the concrete should not be
allowed to drop more than 4 feet.
INCORRECT!
The correct answer is False.

Next

Bridge Inspector
Practice Questions

11. A inch High Strength Bolt that is 4


inches long and installed perpendicular to
the connection has a turn requirement in
the Rotational Capacity Test of
a)
b)
c)
d)

1/3 turn
1/2 turn
2/3 turn
1 full turn

Bridge Inspector
Practice Questions

11. A inch High Strength Bolt that is 4


inches long and installed perpendicular to
the connection has a turn requirement in
the Rotational Capacity Test of

CORRECT!

Next

Bridge Inspector
Practice Questions

11. A inch High Strength Bolt that is 4


inches long and installed perpendicular to
the connection has a turn requirement in
the Rotational Capacity Test of
INCORRECT!
The correct answer is B, 1/2 turn.

Next

Bridge Inspector
Practice Questions

12. The granular wall backfill under an impact


panel should be placed in ______ lifts.
a)
b)
c)
d)

6
12
18
None of the above

Bridge Inspector
Practice Questions

12. The granular wall backfill under an impact


panel should be placed in ______ lifts.

CORRECT!

Next

Bridge Inspector
Practice Questions

12. The granular wall backfill under an impact


panel should be placed in ______ lifts.
INCORRECT!
The correct answer is D, none of the above.

Next

Bridge Inspector
Practice Questions

13. Your bridge has precast bulb-I girders with a

camber of 2 and the deck and rail deadload


together has a deflection of 2. The top flange of
the bulb-I girders is a total of 2 feet wide and your
superelvation is 0.04 ft/ft. With a minimum buildup
required across the entire girder of 1, then the
total buildup at the ends of the beams at the
girder centerline will be ______.

a)
b)
c)
d)

2
2
3
4

Bridge Inspector
Practice Questions

13. Your bridge has precast bulb-I girders with a

camber of 2 and the deck and rail deadload


together has a deflection of 2. The top flange of
the bulb-I girders is a total of 2 feet wide and your
superelvation is 0.04 ft/ft. With a minimum buildup
required across the entire girder of 1, then the
total buildup at the ends of2
the beams at the girder
centerline will be ______.

CORRECT!
Next

Bridge Inspector
Practice Questions

13. Your bridge has precast bulb-I girders with a

camber of 2 and the deck and rail deadload


together has a deflection of 2. The top flange of
the bulb-I girders is a total of 2 feet wide and your
superelvation is 0.04 ft/ft. With a minimum buildup
required across the entire girder of 1, then the
total buildup at the ends of the beams at the girder
centerline will be ______.

INCORRECT!
The correct answer is A, 2 inches.
Next

Bridge Inspector
Practice Questions

14. You have a 6 ft. diameter drilled shaft with


a clearance of 3 from the reinforcement
cage to the side of the shaft. How many
spacers are required at each interval
around the drilled shaft reinforcement
cage?
a)
5
b)
6
c)
7
d)
9

Bridge Inspector
Practice Questions

14. You have a 6 ft. diameter drilled shaft with


a clearance of 3 from the reinforcement
cage to the side of the shaft. How many
spacers are required at each interval
around the drilled shaft reinforcement
cage?

CORRECT!

Next

Bridge Inspector
Practice Questions

14. You have a 6 ft. diameter drilled shaft with


a clearance of 3 from the reinforcement
cage to the side of the shaft. How many
spacers are required at each interval
around the drilled shaft reinforcement
cage?
INCORRECT!
The correct answer is C, 7.

Next

Bridge Inspector
Practice Questions

15. You have a post-tensioned box girder bridge that


will have the tendons tensioned from both ends.
Given the following elongation amounts, what is
the % of elongation per tendon?
20% Actual
Elongation

100% Actual
Elongation

Calculated 80%
Elongation

Bent
1

65

54

Bent
4

6 7/8

a)
b)

103.4%
107.3%

c)
d)

109.4%
121.5%

Bridge Inspector
Practice Questions

15. You have a post-tensioned box girder bridge that


will have the tendons tensioned from both ends.
Given the following elongation amounts, what is
the % of elongation per tendon?
20% Actual
Elongation

100% Actual
Elongation

Calculated 80%
Elongation

Bent
1

65

54

Bent
4

6 7/8

CORRECT!
Next

Bridge Inspector
Practice Questions

15. You have a post-tensioned box girder bridge that


will have the tendons tensioned from both ends.
Given the following elongation amounts, what is
the % of elongation per tendon?
20% Actual
Elongation

100% Actual
Elongation

Calculated 80%
Elongation

Bent
1

65

54

Bent
4

6 7/8

INCORRECT!
The correct answer is C, 109.4%.