Professional Documents
Culture Documents
1. Introduction
There exist many causes for which the teams stop being accessible, be this due to adjustments, maintenance, absence
of personnel, recuperation of levels or model changes, the problem is that all the stops in which the equipment are not
accessible are losses for the companies. For these cases Shigeo Shingo developed a method to change die on one of the
presses which are used to form the parts at TOYOTA, for which changes used to last up to 4 hours. His objective was to
reduce this time to have more accessible time on the machines. From this is that SMED (Single Minute Exchange of Die)
surged at a minute to change a die.
ISBN: 97819384960-0-4
57
When the time of change is high, the production lots are large and so, the investment in inventory is high. But when
the time of change is insignificant, the necessary quantity can be produced daily, almost totally eliminating the need
to invest in inventories.
2.
The rapid and simple methods of change eliminate the possibility of errors in the adjustments of tools and
accessories. The new methods of change sustancially reduce defects and suppress the need for inspections.
3. With rapid changes, the machines capacity can be increased. If the machines functions seven days a week, 24 hours
a day, one option to have more capacity, without buying new machines, is to reduce its change and preparation time.
58
59
4.1.2
Once that the referent points to Step 0 have been assured, one proceeds to follow the road by the eight step route,
continuing with the planning stage, step 1 is initiated in which the following activities are developed:
1.1 Document each Element of the Model Change, Step by Step.
1.2 Determine each Element of Time and Register the Information
1.3 Graph Data of Start-up and Establish a Challenge of Improvement.
1.4 Document Each Element Visually.
4.1.3
Step 2 consists of the development of the activities that are shown following:
2.1 Register Internal y External Activities.
2.2 Separate Internal- External Activities.
4.1.4
This step refers to converting the developed work while the machine is not functioning, a job that can be done while
the machine is functioning, so that the change of internal and external activities can be done. These steps are developed by
the application of various techniques such as:
3.1 Apply the technique of the 5 Whys.
3.2 Apply the technique of ECRS.
3.3 Use verification tools.
4.1.5
The parallel activities are independent from each other and can be developed simultaneously, in this manner
according to the experts: The time of change can be reduced to less than half doing parallel activities:
4.1 Develop Parallel Activities.
4.2 Develop Gantt Diagrams.
4.1.6
To optimize the internal activities, the one that represents a restriction for all the system like a bottle neck should be
considered in the first place. In this sequence all activity can be reduced up to 10 minutes. The activities that are developed in
this step are:
5.1: Apply Procedures of Improvement
5.2: Apply the Methodology of the 5S.
5.3: Apply the Methodology of the ECRS.
4.2 Phase 2. Do
4.2.1
Continuing with the PDCA circle, one passes to the implementation of Step 2, developing step 6 which properly
constitutes the undertaking of the improvement activities; to the side, are described the tools to advance in the development
of the SMED methodology. The activities to develop in this step are the following:
6.1: Making a Performance Plan
6.2: Undertaking the Plan.
Step 7 makes sure that all the improvements are being performed and controlled integrally. This step corresponds to
step 3 of the PDCA circle which has as its function the assurance of the validation and verification of the process, for the
development of Step 7 the following activities are listed:
7.1: Make an Operation Sequence Worksheet.
7.2: Graphs of the Times of Change.
7.3: Develop a Program of Audits.
7.4: Form an Analysis of Costs-Benefits.
60
Step 8 has as its objective to assure the standardization of the methodology in all the areas and assure the correct
application and diffusion for the quick change model, to develop step eight the following activities are listed:
8.1: Formulate the Work Instruction.
The concept of SMED introduces the idea that in general any change of machine or initiation process should last no
more than 10 minutes, a concept related to CMED, and more advanced, this is a One-touch Exchange of Die, (OTED), which
postulates that the changes should be done in less than ten seconds, and with a formula that a change of model could be done
in one touch, that is to say, pressing a button.
This Investigation, is part of a continuous improvement process (Kaizen) and proposes the in depth investigation for
the application of model changes at one touch through continuously increasing improvements; kaizen is in reality a
philosophy of life. Assume that each aspect of our lives merits constant improvement. The philosophy of Kaizen permits
improving all the aspects in the organization including the personal wellbeing and teamwork.
4. References
Hay, E. J. (2003). Justo a tiempo. La technical Japanese que genera mayor ventaja competitiva. Groupo Editorial Norma.
Jeffrey, L. (2004). Las claves del xito de Toyota 2 Edicin. Mxico: Editorial Gestin 2000 - 2006
Jeffrey, L. (2002). The Toyota Way, New York, U.S.A: McGraw Hill.
Huntzinger, J. (2002). The Roots of Lean: Training within Industry- the origin of Kaizen, Association of Manufacturing
Excellence, 18(2): 9-22.
Villaseor and Galindo (2008). Villaseor Alberto, Galindo Edber (Eds.). Conceptos y reglas de Lean Manufacturing.
Mxico: Editorial Limusa.
Womack, J., Jones, D. and Roos, D. (1990). The machine that changed the world: thestory of lean production. New York,
U.S.A.: First Harperennial Ed.
61