Professional Documents
Culture Documents
This Post lists a set of key questions which must be asked before designing a
planning solution based on Oracle Planning modules (Oracle MRP/ASCP) in discrete
Manufacturing environment. The list may not be exhaustive but highlights important
areas which must be well understood before starting the solution design phase. Few
notes have also been included to emphasize important points.
What is the required Forecasting level ? i.e. item, customer, bill-to or ship-to customer
location. Higher the forecasting level, higher would be the forecast accuracy but the
lower level forecast visibility might be lost, hence it needs to be decided optimally.
What is the Forecast bucket to be used ? e.g. days in short term, weeks in mid term,
periods in long term? Bucket must be set optimally
What is the Forecast consumption level item, customer, bill-to or ship-to customer
location: this need to be aligned with forecast level.
What are the Forecasting rules to be deployed? statistical (for multiple periods) or
Focus (single period)?
5
6
7
8
9
10
11
12
13
Note: Overconsumption creates additional demand line (after exhausting backward and
then forwards days)
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
Are any order modifiers being used? Fixed, min, max order qty, fixed days supply?
Is there a requirement for kit/phantom items planning?
Is there a scenario where both purchasing and in-house manufacturing has to be enabled
for certain items ?
35
Are there any bulk items? i.e. not to be individually issued to jobs, rather to floor
stock expense accounts
36
Is there a scenario for shrinkage rate? i.e. some amount will be scrapped or wasted so
planning plans more: total demand = original demand planned order shrinkage+discrete
job shrinkage (on supply side)
37
38
39
40
41
42
43
44
45
Note: Acceptable early days item parameter in case of advance receipts, controls
rescheduling out feature to avoid very frequent reschedule-outs and decrease
nervousness of planner by having little extra stock in ahead
46
Note: The planning process considers past due supply and demand as if it were due
today (in
other words, the start date of the plan)
47
48
Note: Over-write option only decides over-writing of firm orders, planned orders
anyway are over-written (i.e. all existing entries deleted), plan never creates firm
order automatically-always planned.. Firm can be done manually in workbench.
Note: lead time percent (generated from calculate mfg lead time program)is used to
schedule material requirements at a particular operation and to plan capacity
requirements at a particular operation
49
Note: Dynamic lead time calculation based on fixed and variable lead times (computed
by BOM calculate lead time programs)
50
51
52
53
54
Note: post-processing lead time for the item is added to the dock date to determine the
planned receipt date
55