Professional Documents
Culture Documents
J
Langwell
Estate
Hydro
Electric
Scheme
Outline
Construction
Method
Statement
st
24
January
2014
Revision
A
Eugene
Craig
Eugene.craig@dhghydro.com
07786
401194
INDEX
1
INTRODUCTION
...........................................................................................................................
3
2
SITE
ESTABLISHMENT/COMPOUNDS/DELIVERY
AREA
.........................................................
3
3
ACCESS
TRACK
IMPROVEMENT/CONSTRUCTION
..................................................................
4
4
DAM
CONSTRUCTION
ON
LOCH
A
CHROISG
.........................................................................
6
5
INTAKE
CONSTRUCTION
ON
GARBH-ALLT
..............................................................................
8
6
PIPELINE
......................................................................................................................................
10
7
POWERHOUSE
CONSTRUCTION
..............................................................................................
12
8
OUTFALL
PIPELINE
AND
OUTFALL
CONSTRUCTION
.............................................................
13
9
GRID
CONNECTION
...................................................................................................................
14
10
11
DEMOBILISATION ................................................................................................................... 16
Introduction
This
document
describes
the
Outline
Construction
Methods.
Further
detailed,
specific
Construction
Method
Statements
must
be
submitted
by
the
Contractor
(once
appointed).
Some
specific
hazards
and
other
considerations
have
been
identified
by
the
Designers.
These
are
listed
under
each
activity
and
must
be
included
in
the
Risk
Assessment
and
Method
Statement
for
that
section
of
the
work.
For
the
avoidance
of
doubt,
this
must
not
be
assumed
to
be
a
complete
list
and
the
team
undertaking
the
Risk
Assessment
should
address
any
other
hazards
which
could
impact
the
work.
2.1
Summary of Works/Methods
2.2
The Method Statements which have been identified for this work are:
Method
Statements
will
be
in
place
prior
to
any
work
commencing
on
this
activity
and
shall
address,
as
a
minimum:
the
preparation
for
and
delivery
of
plant
and
materials
to
the
area
in
question
the
establishment
of
the
initial
means
of
access
to
the
site
the
type
and
establishment
of
a
temporary
welfare
facility
(until
such
time
that
the
full
welfare
facilities
may
be
established)
Public
Access
and
Safety
Hazards
which
will
be
considered,
as
a
minimum,
in
the
associated
Risk
Assessment
will
include:
3.1
Summary of Works/Methods
The
following
sections
give
brief
outline
procedures
for
the
access
works.
3.1.1 Existing
access
track
from
Langwell
Lodge
to
the
intake
area
This
track
is
long
established,
is
made
of
a
firm
gravel
running
surface
and
is
generally
in
very
good
condition.
The
following
works
are
proposed:
Levelling
and
re-grading
where
required
Formalisation
of
existing
passing
place.
Creation
of
new
passing
places.
These
will
be
kept
to
minimum.
3.1.2
A
short
new
section
of
track
will
be
installed
from
the
existing
track,
near
the
intakes,
at
Grid
Ref
220395,902505
to
the
pipeline
route.
This
will
provide
a
direct
access
route
for
positioning
of
the
pipe
and
access
by
installation
machinery.
The
track
shall
be
formed
by
stripping
of
the
top
soils
and
laying
a
temporary
firm
running
surface
on
taram.
This
track
shall
be
fully
removed
post
construction
and
the
area
fully
reinstated.
3.2
The Method Statements which have been identified for this work are:
Access
Track
Method
Statement
Method
Statements
will
be
in
place
prior
to
any
work
commencing
on
this
activity
and
shall
address,
as
a
minimum:
The
repair
and
improvement
of
existing
access
track
The
installation
of
temporary
river
crossing
The
creation
of
new
access
track
to
the
powerhose
Hazards
which
will
be
considered,
as
a
minimum,
in
the
associated
Risk
Assessment
will
include:
the
safety
of
road
users
the
safety
of
pedestrians
the
prevention
of
debris
being
deposited
on
public
highway
the
prevention
of
debris
polluting
any
nearby
watercourse
4.1
Summary of Works/Methods
The
construction
of
the
dam
and
intake
on
the
Loch
aChroisg
present
the
greatest
risk
of
river
contamination.
However,
correct
procedures
and
construction
methods
greatly
reduce
this
risk.
The
SEPA
guide
Engineering
in
the
water
environment
good
practice
guide:
Temporary
construction
methods
(WAT-SG-29)
has
been
applied
to
the
methods.
The
following
sections
give
brief
outline
procedures
for
the
dam
construction.
Once
fully
cured,
the
coffer
dam
will
be
moved
to
divert
water
through
the
scour
valve
within
the
chamber
in
the
northern
side
of
the
dam
- The
entire
flow
will
then
pass
through
the
scour
valve.
Dam
construction
PHASE
2
southern
dam
wall
and
wingwalls
- Excavation
of
the
dam
area
down
to
bed
rock
some
bed
rock
may
need
to
be
removed
to
gain
sufficient
depth
- Rock
dowels
drilled
and
installed
as
required
- The
floor
slabs
will
then
be
cast
in
concrete
- Once
cured,
the
main
dam
wall
will
be
shuttered
and
cast
with
reinforced
concrete
- Wing
walls
will
be
completed,
tied
into
the
banks
- Bank
and
bed
scour
protection
(gabions
and/or
boulders
in
concrete)
will
be
completed
Installation
of
fittings
- Intake
screens
fitted
- Sluice
gates
installed
and
locked
off
- Access
hatch,
safety
railing
and
stilling
wells
fitted
Re-watering
- The
working
area
will
be
cleared
of
any
loose
debris
before
re-watering
- The
compensation
plate
can
then
be
installed,
thus
completing
the
dam,
and
the
area
upstream
will
fill
up
and
then
flow
over
the
screens
Reinstate
&
make
good
Outline
construction
drawings
for
the
Dam
are
given
in
Appendix
D1.
4.2
The Method Statements which have been identified for this work are:
Method
Statements
will
be
in
place
prior
to
any
work
commencing
on
this
activity
and
shall
address,
as
a
minimum:
the
flow
diversion
works
associated
with
the
dam
the
excavation
work
for
the
dam
wall
and
wells
the
installation
of
formwork
for
the
reinforced
concrete
walls
and
wells
the
installation
of
the
reinforcement
steel
the
mixing,
placing
and
compaction
of
the
concrete
the
installation
of
the
intake
screen
Hazards
which
will
be
considered,
as
a
minimum,
in
the
associated
Risk
Assessment
will
include
the
prevention
of
falls
into
unattended
excavations
the
prevention
of
falls
into
watercourses
the
prevention
of
pollution
of
the
adjacent
watercourses
(slippage,
sediment,
cement,
refuelling).
See
Environmental
Management
Plan
the
prevention
of
watercourses
inundating
the
works
COSSH
assessments
for
fuels
and
cement
5.1
Summary of Works/Methods
The
construction
of
the
intake
presents
the
greatest
risk
of
river
contamination.
However,
correct
procedures
and
construction
methods
greatly
reduce
this
risk.
The
SEPA
guide
Engineering
in
the
water
environment
good
practice
guide:
Temporary
construction
methods
(WAT-SG-29)
has
been
applied
to
the
methods.
The
following
sections
give
brief
outline
procedures
for
the
intake
constructions.
- Clean
rock
will
be
used
to
backfill
the
upstream
side
of
the
intake.
This
will
accelerate
the
natural
process
of
sediment
build
up
and
bring
forward
the
time
at
which
sediment
is
transported
over
the
intake
and
down
the
river
again.
Installation
of
fittings
- Intake
screens
fitted
New
replacement
footbridge
installed
- Small
bridge
landing
pads
cast
- Bridge
lifted
into
place
and
secured
- Access
ladder
to
intake
installed
Re-watering
- The
working
area
will
be
cleared
of
any
loose
debris
before
re-watering
- The
compensation
plate
can
then
be
installed,
thus
completing
the
weir
- The
large
diameter
temporary
bypass
pipe
will
be
blanked
off
to
divert
water
through
the
intake
/
constructed
compensation
notch
- the
area
upstream
will
fill
up
and
then
flow
over
the
screens
Reinstate
&
make
good
Outline
construction
drawings
for
this
Intake
are
given
in
Appendix
D2
5.2
The Method Statements which have been identified for this work are:
Method
Statements
will
be
in
place
prior
to
any
work
commencing
on
this
activity
and
shall
address,
as
a
minimum:
the
flow
diversion
works
the
excavation
work
for
the
intake
the
installation
of
formwork
for
the
reinforced
concrete
walls
and
wells
the
installation
of
the
reinforcement
steel
the
mixing,
placing
and
compaction
of
the
concrete
the
installation
of
the
intake
screens
Hazards
which
will
be
considered,
as
a
minimum,
in
the
associated
Risk
Assessment
will
include
the
prevention
of
falls
into
unattended
excavations
the
prevention
of
falls
into
watercourses
the
prevention
of
pollution
of
the
adjacent
watercourses
(slippage,
sediment,
cement,
refuelling).
See
Environmental
Management
Plan
the
prevention
of
watercourses
inundating
the
works
COSSH
assessments
for
fuels
and
cement
Pipeline
6.1
Summary of Works/Methods
10
HPPE
is
a
relatively
strong
material,
which,
if
the
ground
conditions
are
good,
can
be
buried
directly
without
the
need
for
imported
backfill.
If
the
ground
conditions
are
poor,
imported
backfill
material
might
be
required
to
prevent
damage
to
the
pipeline.
The
general
ground
conditions
are
good
at
the
site
and
the
need
for
imported
backfill
is
expected
to
be
very
limited.
It
is
not
expected
that
any
pipeline
trench
section
will
remain
exposed
for
more
than
4-5
days.
If
a
trench
section
is
left
open
overnight
a
ramp
access
will
be
left
to
allow
any
animals
that
may
enter
the
trench
to
escape.
Care
will
be
taken
to
ensure
the
pipeline
does
not
affect
the
drainage
nature
of
the
land.
Where
the
pipe
crosses
under
side
streams
or
through
any
particularly
wet
areas,
clay
bungs
will
be
installed
as
appropriate
to
prevent
running
water
scouring
along
the
pipe.
6.2
The Method Statements which have been identified for this work are:
Method
Statements
will
be
in
place
prior
to
any
work
commencing
on
this
activity
and
shall
address,
as
a
minimum:
the
excavation
of
pipe
trenches
and
pits
including
temporary
storage
of
materials
the
measures
to
ensure
trench
stability
the
procedures
for
inspection
of
trenches
the
jointing
of
pipes
the
laying
of
pipes
the
bedding
and
backfilling
of
pipes
the
reinstatement
of
trenches
the
testing
of
pipework
Hazards
which
will
be
considered,
as
a
minimum,
in
the
associated
Risk
Assessment
will
include
the
prevention
of
falls
into
unattended
excavations
the
prevention
of
spoil
or
materials
accessing
the
trench
the
prevention
of
pollution
of
the
adjacent
watercourses
(sediment,
refuelling)
see
Environmental
Management
Plan
the
prevention
of
excessive
crossings
of
watercourses
by
vehicles
the
prevention
of
trench
collapses
due
to
vehicles
working
adjacent
the
prevention
of
flooding
of
the
trenches
from
ground
or
surface
waters
the
avoidance
the
disturbance
to
the
designated
areas
of
archaeological
interest
(see
Environmental
Management
Plan)
COSSH
assessments
for
fuels
and
cement
11
Powerhouse Construction
7.1
Summary of Works/Methods
The
powerhouse
is
sited
away
from
the
river
and
does
not
involve
any
de-watering
works.
The
following
is
the
outline
for
method
for
the
construction
of
the
powerhouse:
Site
preparation
- Removal
and
storage
of
vegetation
and
topsoil
- Excavation
of
foundations
for
pipe
anchor
block,
turbine
sump
and
transformer
compound,
and
for
powerhouse
wall
footings
- If
required,
pumps
will
be
used
to
keep
the
working
area
dry
and
this
will
be
discharged
to
a
settlement
pit
dug
several
meters
away
from
the
burn.
Construction
- Cast
foundations
and
main
floor
slab
- Cast
the
main
retaining
walls
- Build
superstructure
and
roof
- Formalise
hard-standing
area
Reinstatement
and
landscaping
Drawings
of
the
proposed
powerhouse
building
are
given
in
Appendix
E.
7.2
The Method Statements which have been identified for this work are:
Method
Statements
will
be
in
place
prior
to
any
work
commencing
on
this
activity
and
shall
address,
as
a
minimum:
the
excavation
of
the
base
and
foundations
for
the
building
the
installation
of
formwork
for
the
reinforced
concrete
slab
and
sump
the
installation
of
the
reinforcement
steel
the
mixing,
placing
and
compaction
of
the
concrete
the
construction
of
the
blockwork
building
walls
the
construction
of
the
roof
the
installation
of
the
overhead
gantry
the
installation
of
fittings
(doors,
vents,
guttering
etc)
Hazards
which
will
be
considered,
as
a
minimum,
in
the
associated
Risk
Assessment
will
include
the
prevention
of
falls
into
unattended
excavations
the
prevention
of
falls
from
height
the
prevention
of
pollution
of
the
adjacent
watercourses
(sediment,
cement,
refuelling)
see
Environmental
Management
Plan
12
8.1
Summary of Works/Methods
The
outfall
pipeline
runs
from
the
powerhouse
building
to
the
outfall.
The
outfall
itself
will
be
constructed
behind
a
coffer
dam.
The
following
is
the
outline
method
for
the
construction:
Prior
to
construction,
a
coffer
dam
will
be
installed
to
divert
the
burn
towards
the
south
bank
and
away
from
the
main
construction
area.
- Sandbags
will
be
used
to
form
the
coffer
dam
(a
combination
of
individual
sand
bags
and
larger
dumpy
bags
as
appropriate)
- The
coffer
dam
will
be
placed
so
as
to
maintain
as
much
width
in
the
river
as
possible
to
reduce
the
restriction
to
the
water
flow
- If
required,
pumps
will
be
used
to
keep
the
working
area
dry
and
this
will
be
discharged
to
a
separate
settlement
pit
dug
several
meters
away
from
the
burn
- Hay
bales/silt
net
will
be
placed
immediately
downstream
of
the
working
area
to
capture
any
disturbed
sediment
Outfall
construction
- Excavation
of
the
outfall
area
down
to
bed
rock
or
solid
ground
some
bed
rock
may
need
to
be
removed
to
gain
sufficient
depth.
Existing
bed
material
to
be
placed
to
one
side
for
reinstatement
- The
floor
slab
will
then
be
cast
in
concrete
- Once
cured
the
main
outfall
structure
will
be
shuttered
and
cast
with
reinforced
concrete,
around
the
pipes
to
the
turbine
sump
- Wing
walls
will
be
completed,
tied
into
the
banks
- River
bed
reinstated
to
original
level
- Bank
and
bed
scour
protection
(gabions
and/or
boulders
in
concrete)
will
be
completed
Installation
of
fittings
- Outfall
screens
fitted
- Safety
railing
fitted
Re-watering
- The
coffer
dam
can
then
gradually
be
removed
and
water
allowed
to
flow
slowly
past
the
outfall
structure
- Hay
bales/Silt
nets
will
remain
in
place
until
the
water
runs
clean,
and
then
the
coffer
dam
can
be
fully
removed
Reinstate
and
make
good.
Outline
construction
drawings
for
the
outfall
are
given
in
Appendix
F
13
8.2
The Method Statements which have been identified for this work are:
Method
Statements
will
be
in
place
prior
to
any
work
commencing
on
this
activity
and
shall
address,
as
a
minimum:
the
flow
diversion
works
to
accommodate
the
pipe
and
discharge
chamber
the
excavation
for
the
pipe
and
discharge
chamber
the
jointing
of
pipes
the
laying
of
pipes
the
bedding
and
backfilling
of
pipes
the
reinstatement
of
trenches
the
installation
of
formwork
for
the
discharge
chamber
the
installation
of
the
reinforcement
steel
for
the
discharge
chamber
the
mixing,
placing
and
compaction
of
the
concrete
for
the
discharge
chamber
Hazards
which
will
be
considered,
as
a
minimum,
in
the
associated
Risk
Assessment
will
include
the
prevention
of
falls
into
unattended
excavations
the
prevention
of
falls
into
watercourses
the
prevention
of
pollution
of
the
adjacent
watercourses
(sediment,
cement,
refuelling)
see
Environmental
Management
Plan
the
prevention
of
watercourses
inundating
the
works
COSSH
assessments
for
fuels
and
cement
the
prevention
of
spoil
or
materials
accessing
the
trench
the
prevention
of
excessive
crossings
of
watercourses
by
vehicles
the
prevention
of
trench
collapses
due
to
vehicles
working
adjacent
the
prevention
of
flooding
of
the
trenches
from
ground
or
surface
waters
the
avoidance
the
disturbance
to
the
designated
areas
of
archaeological
interest.
See
Environmental
Management
Plan
Grid Connection
9.1
Summary of Works/Methods
The
grid
connection
is
to
be
provided
in
full
by
SSE
and
all
construction
method
statements
shall
be
provided
by
SSE..
9.2
The Method Statements which have been identified for this work are:
14
Grid Connection Method Statement Buried Line and Substation Works (SSE)
Method
Statements
will
be
in
place
prior
to
any
work
commencing
on
each
activity.
Hazards
which
will
be
considered,
as
a
minimum,
in
the
associated
Risk
Assessment
will
include
the
organisation
and
management
of
multiple
sub-contractors
on-site
the
systems
to
ensure
sub-contracted
staff
are
competent
and
qualified
the
exclusion
of
unauthorised
or
inexperienced
persons
in
the
work
areas
the
prevention
of
falls
from
height
the
prevention
of
electrocution
the
prevention
of
burns
the
prevention
of
fire
lifting
heavy
machinery
manual
handling
10
10.1
Summary of Works/Methods
This
work
involves
the
installation
of
the
turbine,
generator,
control
system
and
grid
connection/protection
equipment.
This
is
specialist
work
and
will
be
carried
out
by
specialist
contractors.
All
works
are
contained
within
the
powerhouse
building
and
do
not
present
any
environmental
or
public
hazards.
10.2
The Method Statements which have been identified for this work are:
Method
Statements
will
be
in
place
prior
to
any
work
commencing
on
each
activity.
Hazards
which
will
be
considered,
as
a
minimum,
in
the
associated
Risk
Assessment
will
include
the
organisation
and
management
of
multiple
sub-contractors
on-site
the
systems
to
ensure
sub-contracted
staff
are
competent
and
qualified
the
exclusion
of
unauthorised
or
inexperience
persons
in
the
work
areas
the
prevention
of
falls
from
height
lifting
heavy
machinery
manual
handling
the
prevention
of
electrocution
the
prevention
of
burns
the
prevention
of
fire
15
11
Demobilisation
The
site
will
be
demobilised
only
after
there
has
been
consultation
with
the
landowner
and
stakeholders
regarding
the
final
reinstatement
and
timescales/standards
agreed
for
any
matters
requiring
further
attention.
Areas
which
will
be
discussed
shall
be
final
condition
of
existing
tracks
reinstatement
of
hard-standings
formerly
used
for
storage,
welfare,
etc.
reinstatement
of
fences
and
gates
reinstatement
of
pipe
route
reinstatement
of
surface
water
control
measures
general
site
tidiness
(litter,
etc.)
on-going
safe
visitor
access
16