Professional Documents
Culture Documents
Introduction:
subjected
to electrical
on Name
and Name
of
the
TIN
who
had
out
the
electrical
safety safety
audit
M/s.
UCO
ZONAL
No.328,
audit represented
UCO electrical
was
bank
during
conducted
audit schedules
the audit
BANK,
Ramesh Narayanan,
Jan Mr.Rama
OFFICE, 14th
Mahendra Rao,
Thambu 2015 and
Chetty
Street,
safety
Chief Safety
Officer
India
3.0
Physical Inspection
Conducting Test and Measurement
Discussion with Safety & Electrical personnel
Examination & Review of Records/ Document
First Floor
Second Floor
Third Floor
Fourth Floor
departments
UPS room, Office area
Retail Loan section, computer centre,, general
Fifth floor
Sixth floor
office
Trainees hostel, dining hall, doctors room
RTC Principals cabin, class room, conference
room, faculty room
11 kV
2072
1 x 500 kVA, 11/0.415 kV, Oil filled
type
RMU with Oil switch in incoming
Type of HT breaker
Audit phase
Audit Objectives
The key focus of the electrical safety audit were as below:
Assessment
Assessment
Assessment
Assessment
Assessment
Assessment
Assessment
Assessment
Assessment
of
of
of
of
of
of
of
of
of
Based on the details collected during the pre-audit meeting, the available
electrical system was studied in depth and key nodes were identified for the
purpose of carrying out measurements of electrical parameters.
Audit findings in brief
Assessment of Electrical Panel room
The RMU has been installed way back in 1970 i.e., about 45 years ago
The consumer side breaker is again an age old HT oil switch with fuse.
o Considerable oil spill was evident on the floor. This implies that the
oil is leaking though the joints or elsewhere from the oil tank.
There is a very much possibility that this oil leak can lead to
reduction in oil level in the switchgear tank and this can lead to
serious arcing and explosion hazard during fault interruption
Narrow,
congested
poorly
and
o The ratings of the fuse elements are not legible and given the age of
the installation the fuses should have deteriorated.
o The rupturing capacity of the fuse element is not evident.
Transformer room
o The transformer room is located adjacent to the HT switchgear
room in the ground floor of the premises.
o The 11000 / 415 Volts transformer is oil filled type and is
installed during 1970 and has outlived its codal life.
o Considerable oil spill / leak is observed from various part of
the transformer tank / tap changing box / cable termination
box etc., which indicates the poor health condition of the
transformer.
Oil spill
leaks
o The burnt oil drain line at the bottom of the transformer tank is
seen directly connected to the normal drain, which is not correct.
The oil should be drained into an oil soak pit instead of directly
being discharged to a normal drain. There is very much probability
that the oil in flame can float around the top layer of the water and
spread the flame.
o Secondly this is also against the Pollution control norms.
Burnt
oil
drain
pipe
discharging into drain
directly
o The inspection of these earth pits revealed that the earth electrodes
and earth interconnecting flats / strips have also been highly corroded.
o The bolts and nuts in the earthing termination are also highly
corroded.
Earth electrode
traceable
not
Assessment of DG set
The backup power supply requirement for this building is achieved by means of
a 250 KVA emergency DG set. This DG set is located outside the building close
to car parking area.
One the day of audit it was observed that this DG set was running even though
utility supply was available. When enquired it came to be known that though
the installed capacity of the transformer was 500 kVA, the contracted
maximum demand is only 250 kVA. Further, the permitted demand is still
lower than the contracted demand. Hence, in order to ensure that the
consumed demand does not exceed the permitted maximum demand, this DG
set was also being used as PEAK LOAD SHAVING purpose i.e., it is being used
to meet the additional electrical load of AC plants.
It was also observed that this DG set is being operated for about 6 hours every
day and more hours during summer months as this DG set primarily supports
AC plants.
Though the practice of using DG set for Peak Load shaving is a general
procedure prevailing in HT consumers, but such practices are restricted to
absolute minimum as the per unit energy cost for a DG set is almost twice that
available from utility.
The output power of this DG set is terminated on to a manual change-over
switch. It is observed this change over switch is only an OFF LOAD type i.e., a
switch which is not meant to be operated when load current is flowing through
and should be operated only after ensuring that the loads connected to it are
switched OFF and no current is flowing through the switch.
However, it was observed that this change over switch is being used an ON
LOAD change over switch i.e., it is being operated with the LOAD ON, which is
strictly prohibited and extremely dangerous. When enquired it was stated by
the DG set operator that the existing switchgears in the main panel are of
obsolete type and many often do not work.
Secondly it was observed that the cable terminations at this the change-over
switch board was shabby. It was also observed that cable looping was done at
the bus side, which is totally not acceptable.
The earth fault relay in the DG panel was also observed to be non-functional
Thirdly, it was also observed that the cables from the DG set were protruding
into the car parking and maneuvering area. There is a very high probability
that this cable can entangle to the bumper of any of the car and get pulled out.
This will lead to a very dangerous situation and can lead to unimaginable
catastrophes.
.
The 415 Volts LV power supply is further distributed from the main LT panel to
an auxiliary panel board. In addition to this auxiliary LV panel several switches
were observed to have been mounted on the walls of the switch room. The
cables to these switches and as well as the cables from these switches to the
loads were also observed to have been run haphazardly manner. The cable
terminations are also not done in correct manner. Such cabling and
terminating methods can give rise to totally unsafe condition.
AC Plant room. Here again it was observed that the panel room was totally in a
mess with cluster of panels, most of them dysfunctional.
Most of the electrical connections were precariously done and dangling across
the length and breadth of the LT panels.
The cable terminations were observed to have been made in a totally
unacceptable manner.
Assessment of UPS
The power backup to data servers, work-stations and associated passive
networking and communication devices have been achieved by host of smaller
rated UPS spread across various floors. All these UPS are under Annual
Maintenance Contract with a external agency.
All the UPS rooms were inspected and glaring unsafe practices were observed
as below
o The batteries were both of Vented Type Lead Acid (VLA) and as well as
Valve Regulated Lead Acid type (VRLA).
o The battery and the UPS were located in the same room.
o The UPS cum battery room were poorly ventilated.
o Many of the batteries were observed with passification due to reaction of
hydrogen crystals and sulphuric acid in the batteries. Continuation of
such condition is likely to lead to further corrosion of the battery
terminals leading to loosening of cable terminations. This inturn can lead
to sparking and flashover leading to fire accident.
The Flooded or Vented Lead Acid batteries give off hydrogen and oxygen gas.
The hydrogen gas being lighter rises to the top most point like ceilings and
other enclosed space. If the battery room does not have good ventilation then
the hydrogen gas concentration builds up. A 4 % concentration in the air forms
an explosive mixture. The institution of Electrical and Electronics Engineers
(IEEE) have defined the permissible of Hydrogen gas concentration. As per
IEEE recommendations, the maximum permissible concentration of hydrogen
gas is only 1 %. Thus all the UPS battery rooms need to be provided with
adequate mechanical forced ventilation. The guideline given by m/s. Exide for
hourly air exchange volume as below
Q = 0.05 X n x I (Cu.mtr/hr); where
Q = Air volume required for the room
n = No. of cells and
I = Value of the current.
Assessment of Pumps
Presently the Metro water is being received into a underground main sump.
From the main sump, the water is being pumped into a secondary sump and
then to overhead tank.
Pump room No.1
The primary pump is a jet pump located near the compound wall abetting
the road.
ageing
The pump starter is mounted in an inconvenient position inside this
pump room.
No guard is available for the Vee Belt.
The motor pulley has considerably worn out
No body earth connection is available for the pumpset.
The wiring / cabling is precarious
room.
The live wires of the start / run capacitors are bare
No body earth connection is available for the pumpset.
The wiring / cabling is precarious with many number of joints
300-500-750 Lux
300-500-750 Lux
300-500-750 Lux
The lighting in the various office areas in various floors of the building have
been accomplished by combination of FTL and CFL light fixtures. The spot
illumination levels were measured using lux meter at random spacing of the
office areas.
The illumination levels observed at various locations in all the floors is
available vide annexure
It is observed that the illumination levels measured in all the floors were
considerably lower than the NBC recommended values.
There is thus a need for improving the illumination in all the office areas.
in
front
of
the
main
electrical
HT,
recommended practice
of keeping the
exists
high
probability
that
the
down
with
materials
totally
by
persons
who
holds
the
valid
particulars
of
DG
set
running
and
Recommendation in brief
compact
compartmentalized
versions.
Immediate
11
12
Attachments
1) Filled in formats
2) Photographs
3) Illumination measurements
****
Krishna
Engineers & Consultants
Company Profile
Credential
Performance
Association