DC Power System
Installation Manual
Version 4.1R01M01
ZTE CORPORATION
NO. 55, Hi-tech Road South, ShenZhen, P.R.China
Postcode: 518057
Tel: (86) 755 26771900
Fax: (86) 755 26770801
URL: http://ensupport.zte.com.cn
E-mail: support@zte.com.cn
LEGAL INFORMATION
Copyright 2010 ZTE CORPORATION.
The contents of this document are protected by copyright laws and international treaties. Any
reproduction or distribution of this document or any portion of this document, in any form by
any means, without the prior written consent of ZTE CORPORATION is prohibited. Additionally,
the contents of this document are protected by contractual confidentiality obligations.
All company, brand and product names are trade or service marks, or registered trade or service marks, of ZTE CORPORATION or of their respective owners.
This document is provided as is, and all express, implied, or statutory warranties, representations or conditions are disclaimed, including without limitation any implied warranty of
merchantability, fitness for a particular purpose, title or non-infringement. ZTE CORPORATION
and its licensors shall not be liable for damages resulting from the use of or reliance on the
information contained herein.
ZTE CORPORATION or its licensors may have current or pending intellectual property rights or
applications covering the subject matter of this document. Except as expressly provided in any
written license between ZTE CORPORATION and its licensee, the user of this document shall
not acquire any license to the subject matter herein.
ZTE CORPORATION reserves the right to upgrade or make technical change to this product
without further notice.
Users may visit ZTE technical support website http://ensupport.zte.com.cn to inquire related
information.
The ultimate right to interpret this product resides in ZTE CORPORATION.
DOCUMENT INFORMATION
Serial No. SJ-20100726164139-001
Revision No. 1.0
Revision Date: 20100802
Safety Precautions
Safety Precautions
Read the safety instructions before any operation of the equipment. The safety precautions mentioned in this manual only serve as a supplement to the local safety
codes.
Only trained professionals are allowed to install, operate and maintain the equipment. ZTE bears no liability to the consequences incurred by violation of the general safety operation requirements, or violation of the safety standards for designing,
manufacturing and using the equipment.
Safety Signs
describes the safety signs in this manual.
Safety Signs
Safety Signs
Meaning
Danger: Indicates an imminently hazardous situation, which if not avoided, will
result in death or serious injury. This signal word should be limited to only
extreme situations.
Warning: Indicates a potentially hazardous situation, which if not avoided,
could result in death or serious injury.
Caution: Indicates a potentially hazardous situation, which if not avoided,
could result in minor or moderate injury. It may also be used to alert against
unsafe practices.
Electric shock: There is a risk of electric shock.
Precautions
Dangerous High Voltage!
l
Observe the local safety codes during the equipment installation. The installation personnel must be qualified for high voltage and AC power operations.
Never wear any conductive object, such as watch, hand chain, bracelet or ring
during the operation on the equipment.
Safety Precautions
Avoid short circuit during operation. The ZXDU58 S151 system is a power supply product with constant DC voltage.
Do not connect any positive terminal to negative terminal. Do not connect any
non-grounding terminal to the ground.
Turn OFF all the breakers and switches before connecting or disconnecting a
power cable.
Before connecting a cable, make sure that the cable and its label are in accordance with the requirement.
Before performing any operation on battery, read the safety precautions in the
battery manual
Connect the battery cables according to the instructions. Avoid short circuit and
electrolyte leakage.
Contents
Safety Precautions .................................................................. 3
Part I Overview ........................................................................ 7
1 Overall System Structure ....................................................... 7
2 Environment Requirements .................................................... 8
3 Installation and Commissioning Flow ...................................... 8
4 Tools Preparation.................................................................. 10
Part II Hardware Installation ...................................................... 11
5 Installing Cabinet .................................................................. 11
Cabinet Installation Position .................................................. 11
Installing Cabinet in Position .................................................. 12
6 Installing Battery Pack ........................................................... 13
Checking and Cleaning Batteries ............................................ 13
Installing Batteries into Cabinet .............................................. 14
7 Connecting Electrical Cables.................................................. 16
Precautions in Electrical Connection ....................................... 16
Connecting Grounding Cable ................................................. 17
Connecting AC Input Cables.................................................. 18
Connecting Battery Cables .................................................... 19
Connecting DC Output Cables ............................................... 20
8 Connecting Sampling Cables ................................................. 22
Connecting Battery Temperature Sampling Cable ...................... 22
Connecting Relay Sampling Cables ........................................ 24
Part III System Commissioning ................................................. 26
9 Performing Electrical Check ................................................... 26
Checking for Short Circuit ..................................................... 26
Checking AC Input Voltage.................................................... 29
Checking Battery Voltage ...................................................... 31
10 Starting Rectifiers and Monitoring Unit .................................. 32
Slots Configuration .............................................................. 32
Starting and Checking Rectifiers............................................. 32
Starting and Checking Monitoring Unit ..................................... 34
11 Setting Parameters in Monitoring Unit.................................... 36
Operation Interface .............................................................. 36
Entering Ctrl Main Menu ....................................................... 36
Setting System and Battery Parameters ................................... 37
Parameters to be Set in System Commissioning .................. 37
Modifying Parameter Value.............................................. 39
Setting Output Relay ............................................................ 40
12 Charging Batteries .............................................................. 41
Part I Overview
Part I Overview
Overall System Structure ........................................ 7
Environment Requirements ..................................... 8
Installation and Commissioning Flow ......................... 8
Tools Preparation .................................................. 10
The ZXDU58 S151 system is mainly composed of the rectifiers, monitoring unit, AC
and DC distribution units and battery packs. Refer to Figure 1-1.
Figure 1-1 ZXDU58 S151 Internal Structure
Part I Overview
Environment Requirements
The ZXDU58 S151 is applied indoors. The requirements for the environment are as
follows:
1. No conductive dusts or corrosive gases; no explosion hazard, no shake or jolt.
2. In the AC power distribution box, a breaker should be available to power the
ZXDU58 S151 system.
The AC input breaker of the power distribution box that powers the ZXDU58
S151 system should meet the requirements: The AC input mode of the ZXDU58
S151 system is: three-phase five-wire (L1/L2/L3/N/PE). The rated phase voltage
is 220 V. The maximum AC input phase current is 25 A.
3. The grounding busbar is available for the ZXDU58 S151 system and the grounding resistance meets the requirements in the engineering specifications.
4. In the equipment room, the temperature, humidity and air pressure meet the
requirements stated in Table 2-1.
Table 2-1 Requirements for Temperature, Humidity and Air Pressure
Item
Requirement
Operating
temperature
Relative
humidity
Air pressure
Part I Overview
1. Install the system.
a. Install the cabinet.
b. Install the battery packs.
c.
Caution:
Perform electrical check to avoid any accident. Make sure that all the electrical cables are correctly connected.
b. Start the rectifiers and monitoring unit.
c.
Caution:
Set the parameters according to the situation of the installation site. Correct parameter settings are very important to ensure that the monitoring unit
functions as expected.
d. Charge the batteries.
Charge the batteries before they are put into use for the first time.
e. Connect the loads to the ZXDU58 S151 system.
3. Shut down and start up the ZXDU58 S151 system.
a. Shut down the system.
Applicable scenario: The ZXDU58 S151 system can be shut down when the
system debugging is finished, but not put into use.
Warning:
The ZXDU58 S151 system shutdown will cause the loads power-off. Once
the ZXDU58 S151 system is put into use, do not shut down the system without permission!
b. Start up the system.
Applicable scenario: The ZXDU58 S151 system need be started up after it
is shut down.
Part I Overview
Tools Preparation
During the operations, such as equipment installation, uninstallation and maintenance, users should prepare the recommended tools and instruments listed in Table
4-1.
Table 4-1 Tools and Instruments
10
Installing Cabinet
When placing the cabinet, there must be a certain space between the cabinet
front & back side and other non-heat source obstacles, thus facilitating heat
dissipation and equipment maintenance.
The ZXDU58 S151 position should comply with the specifications shown in Figure 5-1.
Figure 5-1 Position Requirements
The vertical distance between the cabinet top and a cabling rack should be equal
to or larger than 300 mm.
The installation position should be able to bear the weight of the ZXDU58 S151
equipment and batteries.
11
Steps
1. Prepare four M12 X 100 expansion bolts.
2. Drill four holes (70 mm deep) with the same dimensions as the cabinet holes at
the bottom.
3. Install the four M12 X 100 expansion bolts into the holes (leave 30 mm of the
bolt above the ground).
4. Remove the feet of the cabinet.
5. Mount the ZXDU58 S151 on the floor and into the expansion bolts.
12
Steps
1. Check each battery according to the following requirements. If you find any
damaged battery, replace it with a new one from the same manufacturer and of
the same model.
a. Check the battery appearance. Check whether there is battery leakage or
the battery is damaged.
13
The voltage (absolute value) of a battery is less than 10.8 V (this value
is just for your reference) indicates that the battery is damaged.
2. Wear protection gloves and clean the cable connection ends and connection
plates with dry and clean soft cloth.
Caution:
l
Dirty contact will cause sparks because the temperature on the terminal is
raised.
The direction of the connecting terminals of the battery cells should be outward.
The distance between the internal walls and the surface of the battery packs
must be greater than 10 mm. The connecting terminals of the battery cells
should not contact the internal walls of the cabinet to avoid short circuit to eliminate the risk of fire.
Caution:
There might be electric shock in the battery installation process. It is recommended
to wear protection gloves and use insulation tools.
Steps
1. Place four 12 V battery cells into the battery rack at the bottom.
2. For each battery pack, install connecting plates and leave one disconnected.
Caution:
The connecting plates must be connected reliably. Poor contact will raise the
temperature on the battery connection terminals.
15
Turn off the AC input breaker of the power distribution box that powers the
ZXDU58 S151 system. Put a warning sign beside the AC input breaker to avoid
unintentional power-on. For example, DO NOT turn on!.
Before connecting any electrical cable to a breaker, make sure that the breaker
is turned off.
Fully insulate the tools, such as screw driver and spanner, to avoid short circuit.
For example, wrap exposed metal parts with insulation tape.
Take off any conductive object, such as watch, hand chain, bracelet or ring.
Wear protective gloves to avoid electric shock.
It is recommended to use copper-core cable as AC cable and bunched yellowgreen copper-core wire as PE cable. Cable size should match the load.
To use a uniform color for the cables, choose black color. Mark the cables with
heat-shrink tube to avoid confusion. The requirements for cable color may vary
in countries. Please observe the local rules for cable color.
DC cables, AC cables and signal cables should be laid separately. If they cannot be laid separately, the distance between various cables in the same trough
should be at least 200 mm.
16
In top cabling mode, cabling rack should be used and the vertical distance between the rack and the top of the cabinet should be at least 300 mm; in bottom
cabling mode, the cables should be laid in hidden trough and the width of the
trough should be less than the distance between the installing holes of the cabinet.
The distance between cable route and heating flue should be more than 1 m.
Caution:
Connect the grounding cable to the nearest grounding point. The PE length cannot
exceed 30 m. The grounding cable should be laid as short and straight as possible.
Context
Figure 7-1 Connecting Grounding Cable
Steps
1. Connect the PE cable to the PE busbar of installation site.
17
Put a warning sign beside the AC input breaker of the equipment room that powers
the ZXDU58 S151 to avoid unintentional shutdown. For example, ZXDU58 S151 is
in operation. DO NOT turn off!.
Steps
1. Turn OFF the AC input breaker that powers the ZXDU58 S151.
2. Turn OFF the AC input breaker of the ZXDU58 S151 system.
3. Connect the phase wires.
18
Caution:
l
Context
Figure 7-3 Connecting Battery Cables
Steps
1. Turn off all the battery breakers.
2. Connect the cables of battery pack 1 strictly according to the following sequence.
19
Caution:
There is a detection cable installed on the connection terminal of the battery
breaker. In the process of connecting the negative cable, you must fix the
loose detection cable.
b. Connect the positive cable to the working ground busbar (+).
c.
Mark the battery number and polarity with labels. For example, mark battery
1 (+) on the positive cable and battery 1 (-) on the negative cable.
The detection cables marked with F1** and F10E* belong to LLVD1, used to
connect secondary loads.
The detection cables marked with F2** belong to LLVD2, used to connect important loads.
Context
The following figure illustrates the procedure for DC output connection.
20
Steps
1. Turn off the loads.
2. Turn off DC output breakers.
3. Connect the negative terminal of a load to one of the load breakers.
21
Caution:
l
22
Caution:
The distance between battery temperature sensor cables and power cables should
be at least 200 mm.
23
Steps
1. Remove the paper cover of a sensor and paste it to the side of a battery of the
battery pack 1.
Make sure that the sensor is reliably pasted.
2. Connect the dual-pin plug to X2 on the SIB.
3. Repeat the step 1 and 2 to install the temperature sensor and the cables of other
battery packs.
l
X14 interface: provides one output relay for faults of the monitoring unit.
X15 to X18 interfaces: provide eight customized output relays for alarms. One
output relay corresponds to multiple alarms.
The connection of alarm output relay sampling cable is illustrated in the following
figure.
Figure 8-3 Connecting Relay Signal Cable
24
Steps
1. Connect one end of the sampling cable to a specified output relay interface.
Select an NO or NC relay.
Caution:
There are two kinds of relay points: NC and NO.
2. Connect the other end of the sampling cable to other monitoring equipment. The
relay points at both ends of the cable must be consistent.
Postrequisite
When there are the following requirements, set the alarm output properties through
the monitoring unit:
l
Set each alarm to its corresponding output relay. Menu path is [Ctrl 1.Setup
Para3.Alarm Para1.Set Alarm Attr.].
25
AC input cables
Battery cables
DC output cables
26
Caution:
Before checking for short circuit, turn off the corresponding breaker. An alarm sound
given by a multimeter indicates that there is a short circuit. In this case, locate the
short circuit and eliminate it before proceeding to the next step.
Steps
and short circuit the two probes. An
1. Turn the knob of a multimeter to
alarm sound given by a multimeter indicates that the multimeter functions normally. Otherwise, replace it with a normal one.
In the AC power distribution box, check the AC input cables for short circuit.
27
Check the negative and positive cables of each battery pack for short circuit.
28
Check the negative and positive cables of each load for short circuit.
Caution:
Strictly follow the instructions below for the equipment safety.
Steps
1. Turn off the AC input breaker in the ZXDU58 S151 cabinet.
2. Turn on the AC input breaker of the power distribution box that powers the
ZXDU58 S151 system.
3. Turn the knob of a multimeter to
4. Measure the AC voltages, as shown in the image below, and keep a record.
29
Acceptance Criteria
Troubleshooting
voltage.
a. Turn off the AC input breaker of the power distribution box that powers the ZXDU58 S151 system.
b. Correct the connection of the cables.
c.
6. Turn off the AC input breaker of the power distribution box that powers the
ZXDU58 S151 system.
30
Steps
1. Install the connecting plate that is leaved disconnected.
3. Measure the voltage of each battery pack, as shown in the image below, and
keep a record.
31
Acceptance Criteria
Troubleshooting
10
Unit
Slots Configuration
The number of rectifiers for each of the phases should be basically identical in order
to maintain phase balance and favor a good radiation. The distribution of the slots
and phases of the rectifiers are shown in Figure 10-1.
Figure 10-1 Slots Configuration
Make sure that there is no short circuit for the AC input cables.
32
AC Input Voltage
Working Status
ZXD1500 (V4.0)
ZXD1500 (V4.3)
Voltage < 80 V
Voltage < 80 V
Steps
1. Turn on the AC input breaker of the distribution box that powers the ZXDU58
S151 system.
2. Turn on the AC input breaker in the ZXDU58 S151 cabinet.
3. Perform the operations below to check whether the rectifier 1 can work normally.
a. Install the rectifier 1 into the rectifier 1 slot.
Caution:
Make sure that no obstacle is blocked in the shutter or air vent of a rectifier
for good heat dissipation.
33
Observe the indicators and make sure that the IN and OUT indicator are
glowing.
d. If the rectifier is not powered (i.e. the IN indicator is off), uninstall the rectifier
and reinstall it. If the symptom persists, replace the rectifier or install the
rectifier into the other rectifier slot.
Prerequisite
The rectifiers are working normally. The rectifiers provide 48 V power to the monitoring unit.
Steps
1. Perform the operations below to install the monitoring unit, as shown in Figure
10-2.
Note:
If the monitoring unit has been installed in the cabinet, proceed to the next step.
34
a. Grasp the handle with one hand. Hold the monitoring unit with another hand
and push it slowly into the monitoring unit slot of the cabinet.
b. Fasten the captive screw to firmly connect the monitoring unit to the backboard.
2. The monitoring unit starts working. Then the PWR indicator of the monitoring
unit glows.
3. After self-test and initialization, the RUN indicator of the monitoring unit glows
and the LCD displays the main menu, as shown in Figure 10-3.
Figure 10-3 Main Menu
Note:
The batteries and loads have not been connected to the ZXDU58 S151 system.
As a result, the monitoring unit gives the DC Loop Break alarm and Bat Loop
Break alarm.
35
11
Unit
Operation Interface
The front panel of the monitoring unit is shown in Figure 11-1.
Figure 11-1 Operation Interface
The components of the monitoring unit front panel are described in Table 11-1.
Table 11-1 Keys of the Monitoring Unit
Category
Key
Function
Single Key
Key Combination
< + Ent>
Steps
1. In the main menu, press
Then
Postrequisite
After entering the correct password, users can enter the Ctrl menu interface, with
1.Setup Para selected by default.
Caution:
Keep a record in Table 11-2 and Table 11-3 for future reference.
37
Table 11-2 provides the system parameters to be set in the system commissioning. Menu path: [Ctrl1.Setup Para1.Sys Para].
Default
Set Value
Requirements
Value
Bat.1 Cap. (Ah)
300 Ah
0 Ah
0 Ah
0 Ah
MainSwitch
No
Det.
AuxSwitch Set
No
Current Date
Current Time
Table 11-3 provides the battery parameters to be set in the system commissioning. Menu path: [Ctrl1.Setup Para2.Bat Para].
Default
Set Value
Requirements
Value
Cur. Limited (C)
0.125C
Equal Func.
Enable
Enable
38
Default
Set Value
Requirements
Value
1-Shut Vol. (V)
45.0 V
44.0 V
Context
Caution:
Do not modify a parameter value without permission. Modifying parameter value will
affect the system operation.
Taking Bat.1 Cap. as an example, Figure 11-3 shows how to modify parameter
values.
Figure 11-3 Modifying Parameter Value
Steps
1. Perform the operations below to enter the Bat.1 Cap. editing interface.
a. Press or to move the cursor or turn pages to locate the parameter to
set.
b. Press Ent to enter the parameter editing interface.
Press Esc to return to the upper-level interface.
2. In the parameter editing interface, perform the operations below to modify the
value. For example, modify the value of Bat.1 Cap. from 300 to 150.
39
Prerequisite
l
Make sure that the level of the alarm whose output relay need be modified is
not Mask.
Except for Total Alarm, the output relay of an alarm of Mask level dose not take
effect.
Context
Taking AC AuxSwitch Off as an example, Figure 11-4 shows how to set output relay
of an alarm.
Figure 11-4 Setting Output Relay
Steps
1. Perform the operations below to enter the 1.Set Alarm Attr. interface.
a. Press or to move the cursor to 3.Alarm Para.
40
Note:
l
3. Perform the operations below to modify the output relay for other alarms.
a. Press Ent to move the cursor the serial No. of the alarm. For example,
move the cursor to 2.
b. Press or to turn pages and locate the alarm to modify the output relay.
c.
12
Charging Batteries
41
Context
Caution:
l
Follow the sequence to connect the battery packs: Connect a battery pack with
lower voltage > Connect a battery pack with higher voltage.
Before turning on a battery breaker, set the floating charge voltage (53.5 V, by
default) of the system to a value equal to the voltage of the battery pack. A
large difference between the voltage of the battery pack and the floating charge
voltage of the system can cause sparks, and thereby cause fires.
Steps
1. Before turning on the battery breakers, measure the voltage of the battery packs
and keep a record.
2. Perform the steps below to connect the battery pack with the lowest voltage.
For example, the voltage of the battery pack n1 is 49 V and it is the lowest.
a. Set Float Vol. to 49 V.
Menu path: [Ctrl1.Setup Para2.Bat ParaFloat Vol.]. The figure below shows how to set Float Vol..
42
Then
D 1.5 V
D > 1.5 V
4. After connecting all the battery packs, set Float Vol. to the default (53.5 V) or a
value required by the user.
Result
In the monitoring unit, the Bat Loop Break alarm disappears.
Caution:
Batteries need be charged in equalized (boost) charge mode before they are put into
use for the first time.
Prerequisite
The Ctrl menu has been entered.
Context
Figure 12-1 shows how to start equalized (boost) charge mode.
Figure 12-1 Starting Equalized (Boost) Charge
43
Steps
1. Press to move the cursor to 2. OAM.
2. Press Ent to enter the OAM interface.
3. Press to move the cursor to 4. EQUAL....
4. Press Ent .
Result
l
Succeed! displayed on the LCD means that the operation to start equalized
(boost) charge mode succeeds.
In equalized (boost) charge mode, the EQU indicator glows. The system automatically switches to float charge mode and EQU indicator is off when equalized
(boost) charge mode ends.
Abort! displayed on the LCD means that the operation to start equalized (boost)
charge mode fails because the operation is presently not allowed.
13
Context
48 V loads can be connected to the ZXDU58 S151 system.
Caution:
l
Before turning on the power breaker of a load, make sure that the positive and
negative load cables are not inversely connected.
Steps
1. Turn off the breaker of the load.
2. Turn on the corresponding DC output breaker of the ZXDU58 S151 system.
3. Perform the operations below to measure the DC output voltage and make sure
that the positive and negative load cables are not inversely connected.
a. Turn the knob of a multimeter to
44
c.
Acceptance Criteria
Troubleshooting
42 V to 58 V.
4. Turn on the breaker of the load after making sure that the volage is normal and
the cables are correctly connected.
Result
In the monitoring unit, the DC Loop Break alarm disappears.
45
14
System Shutdown
Prerequisite
l
The ZXDU58 S151 system has been debugged, but not put into use.
Context
Warning:
Do not shut down the ZXDU58 S151 system without permission. The ZXDU58 S151
shutdown will cause the loads power-off.
Steps
1. Turn off all the loads (or use other supply to power the loads). Then the ZXDU58
S151 system works without load.
2. Turn off all the DC output MCBs.
3. Turn off all the battery MCBs to disconnect the batteries from the system.
4. Turn off the AC input MCB.
Then the rectifiers stop working.
With AC contactor configured in the ZXDU58 S151 system, skip this step.
5. Turn off the AC input MCB of the power distribution box that powers the ZXDU58
S151 system.
System Startup
Perform the operations below to start the ZXDU58 S151 system when the system
need be started after shutdown.
Prerequisite
The ZXDU58 S151 system has been debugged.
Steps
1. Turn on the AC input MCB of the power distribution box that powers the ZXDU58
S151 system.
2. Refer to the table below to turn on the AC input switch.
46
Operations
Single MCB
mechanically)
Double AC contactors
(interlocked electrically)
Then the rectifiers start working, and the monitoring unit starts self-check with
the indicators flashing. The monitoring unit starts working normally in about 10
s. Then the PWR, RUN and ALM indicators glow. The LCD displays the DC
Loop Break and Bat Loop Break alarms.
3. Turn on the battery MCB to connect the batteries to the system.
Then the Bat Loop Break alarm disappears.
4. Turn on the corresponding DC output MCBs connected to loads.
Then the DC Loop Break alarm disappears.
47
Appendix
Appendix
Weight and Dimensions .......................................... 48
Interface Description .............................................. 50
Alarm List ............................................................ 57
15
Weight
Table 15-1 describes the weight of the components.
Table 15-1 ZXDU58 S151 Weight
Item
Specification
Cabinet Weight
Monitoring unit
2.2 kg/pc
ZXD1500 rectifier
Battery weight
Refer to the battery manual. Each cell cannot exceed 62.5 kg.
Dimensions
Figure 15-1 shows the dimensions of the ZXDU58 S151 cabinet. Table 15-2 describes the details.
48
Appendix
Figure 15-1 ZXDU58 S151 Cabinet Dimensions
Specification
Cabinet dimensions
65 mm 70 mm (adjustable)
Dimensions of installation
480 mm 450 mm (W D)
holes at bottom
Diameter of installation holes
12 mm
at bottom
49
Appendix
16
Interface Description
50
Appendix
Table 16-1 Electrical Connection Terminals
Item
Description
AC Input
3P (L1/L2/L3)
DC Output
8*LLVD1 breakers
8*LLVD2 breakers
Battery Input
3*Battery breakers
PE
PE busbar
GND
Note:
The communication ports of the monitoring unit are X19, X20, X21 and X22. X22 is
optional.
l
X19 and X21 are used in RS232 communication mode. X20 and X22 (optional)
are used in RS485 communication mode.
Appendix
Refer to Table 16-2 for the SIB interfaces description.
Table 16-2 SIB Board Interfaces Description
Interface Designation
Pin No.
Signal Definition
Signal Description
X2
T1
Battery 1 temperature
+12V1
X3
T2
Battery 2 temperature
+12V1
X4
T3
Battery 3 temperature
+12V1
X5
T4
Battery 4 temperature
+12V1
X6
TEMP
+12V1
VCC_W
X7
+12V1
Flood alarm
AGND
Analog ground
WATER_IN
X8
+12V1
Smoke alarm
SMOKE_IN
+12V1
X9
AGND
Analog ground
GLASS_IN
AGND
Analog ground
+12V1
AGND
Analog ground
DOOR_IN
Intrusion signal
X11
DOOR1
AGND
Analog ground
Environment temperature
X10
Intrusion alarm
52
Appendix
Interface Designation
Pin No.
Signal Definition
Signal Description
INRLY1
Input relay 1
INRLY2
Input relay 2
AGND
Analog ground
INRLY3
Input relay 3
INRLY4
Input relay 4
AGND
Analog ground
FAULT-NO
FAULT-COM
FAULT-NC
RO1-NO
Relay output 1 NO
RO1-COM
X15
RO1-NC
Relay output 1 NC
Output relays 1, 2
RO2-NO
Relay output 2 NO
RO2-COM
RO2-NC
Relay output 2 NC
RO3-NO
Relay output 3 NO
RO3-COM
X16
RO3-NC
Relay output 3 NC
Output relays 3, 4
RO4-NO
Relay output 4 NO
RO4-COM
RO4-NC
Relay output 4 NC
RO5-NO
Relay output 5 NO
RO5-COM
X17
RO5-NC
Relay output 5 NC
Output relays 5, 6
RO6-NO
Relay output 6 NO
RO6-COM
RO6-NC
Relay output 6 NC
X12
Input relays 1, 2
X13
Input relays 3, 4
X14
Monitoring unit fault detect
53
Appendix
Interface Designation
Pin No.
Signal Definition
Signal Description
RO7-NO
Relay output 7 NO
RO7-COM
X18
RO7-NC
Relay output 7 NC
Output relays 7, 8
RO8-NO
Relay output 8 NO
RO8-COM
RO8-NC
Relay output 8 NC
Not used
RXD_1
Receive Data
TXD_1
Transmit Data
Not used
GND_1
Ground
Not used
Not used
Not used
Not used
10
GNDP
Protection ground
11
GNDP
Protection ground
485A1
RS485 signal A
485B1
RS485 signal B
DCD
RXD_2
Receive Data
TXD_2
Transmit Data
DTR
GND_2
Ground
DSR
RTS
Request To Send
CTS
Request To Clear
10
GNDP
Protection ground
X19
Serial port 1 (RS232 interface)
X20
Serial port 1 (RS485 interface)
X21
Serial port 3 (RS232 interface)
54
Appendix
Interface Designation
X22
Pin No.
Signal Definition
Signal Description
11
GNDP
Protection ground
485A0
RS485 signal A
485B0
RS485 signal B
VCC
HUM_IN
Humidity signal
GND
Digital ground
48V+
Not used
48V-
X23
Environment humidity
X24
48V power input
Note:
The IP board is an optional component that is installed according to the user requirement.
The IP board interfaces are shown in Figure 16-3.
Figure 16-3 IP Board Interfaces
Appendix
Table 16-3 Interfaces Description
Interface
Pin No
Signal Definition
Interface Description
X1
GND
+12V
X2
voltage
Standard JATG interface, used for
downloading applications.
X3
X4
RS485_B
In
RS485
communication
RS485_A
X6
RS232_RXD
RS232_TXD
RS232_GND
In
RS232
communication
The RS 232
IP board Dual In-line Package (DIP) switches are described in Table 16-4.
Table 16-4 IP Board-DIP Switches Description
DIP Switch
Description
S1
56
Appendix
DIP Switch
Description
S3
Used to set working mode of the RS232 port, as shown in Table 16-6.
S2[2]
S2[3]
Baud rate
OFF
ON
OFF
9600 bps
ON
ON
OFF
4800 bps
OFF
OFF
ON
2400 bps
ON
OFF
ON
1200 bps
The baud rate of two communication terminals should be consistent, otherwise the communication will fail.
The maximum baud rate supported by the monitoring unit is 9600 bps.
S3[2]
S3[3]
S3[4]
Description
ON
ON
OFF
OFF
OFF
OFF
ON
ON
17
Alarm List
Alarm Type
Default Level
Default
Description
Relay
1
Total Alarm
Ignore
A1
An alarm occurs.
AC Aux SW Off
Minor alarm
A2
AC Main SW Off
Major alarm
A2
57
Appendix
S/N
Alarm Type
Default Level
Default
Description
Relay
4
AC Power Off
Major alarm
A2
ACArrester Brk.
Minor alarm
A2
AC Under-Vol
Minor alarm
A2
AC Over-Vol
Minor alarm
A2
AC Phase Lost
Minor alarm
A2
AC Current Over
Minor alarm
A2
10
SMR Alarm
Minor alarm
A3
11
SMR Abnormal
Minor alarm
A3
12
DC Under-Vol
Minor alarm
A4
13
DC Over-Vol
Minor alarm
A4
14
DC Loop Break
Minor alarm
A6
15
Minor alarm
A6
16
Bat Under-Vol
Major alarm
A4
17
Bat Over-Temp
Minor alarm
A4
18
1st Shut-down
Major alarm
A5
19
2nd Shut-down
Major alarm
A5
58
Appendix
S/N
Alarm Type
Default Level
Default
Description
Relay
20
DCArrester Brk.
Minor alarm
A2
21
DCBreaker Alarm
Minor alarm
22
Battery Fault
Major alarm
23
Bat Under-Temp
Minor alarm
24
Bat.Temp.Void
Minor alarm
25
Bat.Discharge
Minor alarm
26
Env Under-Temp
Minor alarm
A7
27
Env Over-Temp
Minor alarm
A7
28
Env Under-Hum
Minor alarm
A7
29
Env Over-Hum
Minor alarm
A7
30
Smoke Alarm
Minor alarm
A7
31
Flood Alarm
Minor alarm
A7
32
Intrusion Alarm
Minor alarm
A7
33
Minor alarm
A7
34
Glass Broken
Minor alarm
A7
35
Env.Temp.Void
Ignore
A7
36
Start GEN
Ignore
A8
59