Professional Documents
Culture Documents
ON
INFRASTRUCTURE DEVELOPMENT
(PGPM 14)
SUBMITTED TO:
NATIONAL INSTITUTE OF CONTRUCTION
MANAGEMENT
& RESEARCH (NICMAR) PUNE.
SCHOOL OF DISTANCE EDUCATION
(SODE)
By
Mr. abc
(PGDPM)
Reg.no.-abc
PGPM14
Page 1
INFRASTRUCTURE
DEVLOPMENT
PGPM14
Page 2
CONTENTS
SR.NO.
1
2
3
4
5
PGPM14
DESCRIPTION
ASSIGNMENT.
PUBLIC PRIVET PARTNERSHI:
OPTION OF PPP:
WHAT IS BOT?
CASE STUDY: MUMBAI METRO
Page 3
PAGE NO.
4
4
5
6
9
ASSIGNMENT:
Public Private Partnerships refers to arrangements, typically medium to long
term, between the public and private sectors whereby some of the services
that fall under the responsibilities of the public sector are provided by the
private sector, with clear agreement on shared objectives for delivery of
public infrastructure and/ or public services. A PPP is generally a contract or
agreement to outline the responsibilities of each Party and clearly allocate
risk. In a BOT arrangement, the private sector designs and builds the
infrastructure, finances its construction and owns, operates and maintains it
over a period, often as long as 20 or 30 years. This period is referred to as
the "Concession" period. Such projects provide for the infrastructure to be
transferred to the Government at the end of the concession period. There are
a number of major parties to any BOT project, all of whom have particular
reasons to be involved in the project. The Contractual arrangements between
those parties, and the allocation of risks, can be Complex. Explain in detail
structuring of BOT projects.
PGPM14
Page 4
The diagram below illustrates the continuum of options for involving the
private sector in the provision of infrastructure delivery.
At the left are supply and service contracts, which tend to be of short
duration and requireless private commitment than the options higher in the
continuum. The private
contractor is not directly responsible for providing the service, but instead for
performing specified tasks, such as supplying inputs, constructing works,
maintaining facilities, or billing customers. At the left are the longer term
arrangements which require significant private sector commitment.
OPTION OF PPP:
There is a range of options for involving private sector participation that vary
with regards to ownership, operations and maintenance, financing, risk
allocation and duration. A summary of these options can be viewed in Table
1.
Table 1: Allocation of key responsibilities under the main private
sector participation options
Option
Asset
Operatio
Ownersh ns
and
ip
Maintena
nce
Service
Public
Public and
contract
Private
Managem Public
Private
ent
contract
Lease
Public
Private
PGPM14
Capital
Invest
ment
Commer
cial Risk
Duration
Public
Public
1-2 years
Public
Public
3-5 years
Public
Shared
8-15
years
Page 5
Concessi
on
Build
Operate
Transfer
Divestitur
e
Public
Private
Private
Private
Private
and
public
Private or
private
and
public
Private
Private
Private
Private
Private
Private
25-30
years
20-30
years
Indefinite
(may be
limited
by
license)
Service contract
Under this option, the private sector performs a specific operational service
for a fee, for example meter reading, billing and collection.
Management contract
In this option, the private sector is paid a fee for operating and maintaining
a government-owned business and making management decisions.
Lease
Under the lease option, the private sector leases facilities and is responsible
for operation and maintenance.
Concession
Under concessions, the private sector finances the project and also has full
responsibility for operations and maintenance. The government owns the
asset and all full use rights must revert to the government after the specified
period of time.
WHAT IS BOT?
BOT is the terminology for a model or structure that uses private investment
to undertake the infrastructure development that has historically been
5
undertaken by the public sector. In a BOT project, a private company is
given a concession to build and operate a facility that would normally be
built and operated by the government. The private company is also
responsible for financing and designing the project. At the end of the
concession period, the private company returns ownership of the project to
the government (although this need not be the case). The concession period
is determined primarily by the length of time needed for the facilitys
PGPM14
Page 6
revenue stream to pay off the companys debt and provide a reasonable rate
of return for its effort and risk.
The table provided below reviews the BOT option and its variants, describes
some characteristics of these different procurement arrangements and
depicts the relationship between these different procurement methods and
the financing of the project.
Characteristics
The service provider is
responsible for design and
construction, finance, operations,
maintenance and commercial
risks associated with the project.
The service provider owns the
project throughout the concession
period
The asset is transferred back to
the government at the end of the
term, often at no cost.
PGPM14
Page 7
Page 8
PGPM14
Page 9
PGPM14
Page 10
stockshallbeprocuredfromCSRNanjing.Thelandforthedepothasbeentakenonalongterm
leasewhichisrenewablefromtheownersoftheland.TheSPVholdstheexclusiverightstodevelop
and use the land for the MRTS Project
15.3 Current Status
TheconstructionhascommencedfromFebruary,2008andtheprojectachievedfinancialclosurein
October 2008.The completion date for the project construction is expected by mid 2011.
Atpresent,theconstructionoftheviaductisunderwaywith773pilesbeingdugup.Theconstruction
oftheDepot,SubstationandStationshasalsocommencedalongtherouteoftheproject.Workhas
alsocommencedontheconstructionof2overheadbridgesatAndheriStationandtheWestern
Express Highway.
15.4 Financing Information
Thetotalprojectcostisestimatedat`2,356crores.Theprojectshallbefinancedonthebasisof
aViability Grant of`650 crores contributed by the Government of India (`470 crores being
20%
oftheprojectcost)andGovernmentofMaharashtra(`180croresbeing7.5%oftheprojectcost).
Theremainderistobefinancedby70%debt,30%equity.TheprivateoperatorandMMRDA shall
provide equity contribution of`466 crores in proportion of their equitystake.The private
operatorhasalsoarrangeddebtof`1240croresfortheproject.Thishasbeentiedupfroma
consortium of banks ledby IDBI,Corporation Bank,KarurVysya bank,Canara Bank,Indian
Bank andOrientalBankofCommerce. IIFCL(U.K.)isprovidingtheforeigncurrencyloanforthe
project.
15.5 ProcessAnalysis
Conceptualisation and Feasibility
TheGovernmenthadbeenexploringtheviabilityofvariousmasstransitsystemsthatareefficient,
economicallyviableandenvironmentfriendly.Inthiscontext,adetailedfeasibilitystudywascarried
outundertheIndo-GermanTechnicalCo-operationbyentrustingtheconsultancyworktoTEWET in
association with DE-Consult &TCS,during 1997-2000.
ThestudyrecommendedamasstransitcorridorfromAndheritoGhatkoparaspotentiallybankable
andeconomicallyviable,afterexamininganumberofalternativecorridorsandalignments.Itwas
then decided to bid out the project on PPP basis.
Tomanagethetransactionprocess,aconsortiumconsistingofLouisBergerastechnicalconsultants,
PriceWaterhouseCoopers(PWC),MasonsandEconomicLawPracticeswasappointedin2003-04 to
assist MMRDA.
Procurement
TheprojectwasapprovedbytheGovernmentofMaharashtrainAugust2004andglobalbidswere
invitedinthesamemonthfortheprojectthroughanExpressionofInterest(EoI).Almost150 bidders
responded to the EoI and a pre-bid meeting was held in November 2004.
The suggestions of prospective bidders were incorporated in the agreements being prepared
PGPM14
Page 11
for theproject.Thebidprocessconductedwasessentiallyatwostagebid-process,i.e.technicaland
financialstage.
Only those consortia whose technical bids met the technical criteria were allowed to submit
financialbids.Technicalbidswereinvited fortheprojectinMay2005.Theconsortiathatsubmitted
bids were:
FinancialproposalsweresubmittedinJanuary2006onlybytheRelianceEnergyandIL&FSconsortia.
The Siemens consortium withdrew their bid.
Afterthebidprocess, negotiationscommencedwiththelowestfinancialbidder, i.e. Reliance
EnergyandConnexFrance.VeoliaTransportandHongKongMRTweretheothermembersofthe
consortiumprovidingtechnicalknow-how.FromFebruarytoMay2006negotiationswerecarried
out with the lowest financialbidder.
TheREL-ledconsortiumexpectedanEquityIRRof26%butthegovernmentwasabletonegotiate
foralower returninlinewithinternationalexperience.Theconsortiumfinally agreedonanEquity
IRR of 15% on their investment.This brought down theVGF to `650 crores.
AnapplicationforVGFwassubmittedtotheGovernmentofMaharashtrainJune2006afterthe
successfulbidderwaschosen.TheprojectfaceddelaysinobtainingapprovalforViabilityGap
Funding(VGF)astheprojectwasconceptualizedbeforethemodelconcessionagreementwas
putinplace.ItsconcessionagreementwasbasedonthemodelconcessionagreementofNational
HighwaysAuthority of India.
Moreover,thePublicPrivatePartnershipAppraisalCommittee(PPPAC)atthecentralgovernment
levelhadnotbeenconstitutedtillthattimeandonlytentativeguidelineswereinplaceforthePPP
agreements.Therefore,atthattimevariousoptionstoobtaingrantfundingwereexploredincluding
obtaininggrantfundingthroughtheJnNURMscheme.However,theJnNURMfundswerecapped
at10%oftheprojectcost.TheissuewasfinallyresolvedbygrantofVGFintheformofaspecial
onetimegrantgiventothestate.TheGoIagreedtogiveaspecialgrantof20%oftheprojectcost.
Inaddition,theGoMapprovedagrantof7.5%ofprojectcost.Thedocumentationandapproval
processtooksometimeandthe formal approval forVGFof`650croreswasobtained muchlater by
January 2009.
Development
PGPM14
Page 12
ThedevelopmentphaseoftheprojectwasinitiatedinparalleltotheVGFapprovalprocess.Major
milestones achieved in the development phase are presented below:
TheEngineeringandProjectManagementConsultants,aconsortiumofParsonsBrinkerhoff
(USA) and Systra SA (France) joined the team on February 14,2007
SigningoftheConcessionAgreementandShareholdersagreementtookplaceonMarch
7,2007
MMOPLandGovernmentofMaharashtraenteredtheStateSupportAgreementonApril
20,2007
Allmajorcontractsfortheprojecthavebeenawarded.Atpresent,90%oftheRightofWayhasbeen
handedovertoMMOPL.Utilities,mapping,conditionsurvey,andtheworkforutilityshiftinghas
beencompleted. 70%ofthefoundationworkhasbeencompleted.Girderlaunchinghasstarted
atcertainstretches.TheconstructionoftheDepot,SubstationandStationshasalsocommenced
alongtherouteoftheproject. Workhasalsocommencedontheconstructionof2overhead bridges
atAndheri Station and theWestern Express Highway.
15.7 Key Learning and Observations
1. Expeditingthebidprocessiscriticaltoensuringagoodresponsetotheproposal:The
entirebidprocessforchoosingthesuccessfulbiddertookmorethan2years.Thisled
toalessernumberofbidderstobidfortheproject.Similarhurdleswereexperienced
inthebidprocessfortheMetroLine2astheconcessionagreementwasbasedon
themodelconcessionagreement.Thisagreementhoweverhadtobetailoredforuse
forimplementationofametrosystem.Thesedelaysresultedinonlyonebidderfinally submitting a
bid for the project.
2. DelayinObtainingVGFapproval:Therewassubstantialdelayinobtainingapprovalfor
VGFfromtheGovernment.Whilethiswasattributedtothemodelconcessionagreement
notbeinginplace,thePPPAppraisalCommitteenotbeconstitutedandonlytentative
guidelineswithrespectto VGFapprovalbeingavailableatthetime,thisissuewasa deterring factor
for developers and is also likely to have impacted the level of interest in the Phase 2 bid.
3. Delayinapprovalscanpotentiallyderailtheproject:Therewasadelayinobtaining
approvalsfortheoverbridgethatpassedovertherailwaylinefromtherailwayauthorities.
Thishadthepotentialofdelayingtheprojectschedule.Thiswasduetotherailways exploringthe
feasibilityofanotherprojectinvadingthepathofthemetroline.Howevera quick resolution of this
issue ensured that work was able to continue.It is recommended that authorities be
cognizant of all other upcoming infrastructure projects that have the potential to affect
operations of the planned project while bidding out such projects and resolve the same prior
to the appointment of a developer.
4.LandAcquisitionprocesscanleadtoissuesintheproject:Thegovernmentcommittedthat
PGPM14
Page 13
thelandfortheprojectwhichessentiallyconsistsoflandallocatedforthedepotwouldbeprocuredasp
erthelandprocurementscheduleprovidedintheagreement.However,this
landwasunderprivateownershipandunderdispute.Thisexposedthegovernmenttothe risk of
land not being available for the depot thereby bringing in a possibility of derailing
theproject.Theissuewasfinallyresolvedbytheprivateownerofthelandagreeingto allocate 75%
of the land for the development of the project on the condition of the
governmentgrantinghimtherighttotheFloorSpaceIndex(FSI)availableovertheentire
plotoflandfor25%oftheland.Thislandhasbeenprovidedonanominalleaserentto the
concessionaire for the concession period.It is recommended in the future concerns
suchastheseareaddressedbeforetheprojectprocurementstageitselftoensuresmooth
functioning of the project.
5. ClearSpecificationsonAssetTransferontermination:Ontheterminationoftheproject
throughtheeffluxoftime,5yearsbeforetheexpiryoftheconcessionperiodasurveyof the assets
would be carried out to determine whether they are in working condition as
givenintheagreement.Thesurveyistobecarriedoutbyanindependentengineerbased
onascheduleofspecificationsontheconditionofassets.However,thescheduleinthe
concessionagreementdoesnothaveclearandrobustspecifications.Thereisthusarisk of a
difference of opinion between the concessionaire and the government and this can
potentiallyleadtoadispute.Thegovernmentcouldmanagethisbetterbyincorporating clearand
robustspecifications ontheconditionit would wanttheassetsto behanded over to the
government.
6. PublicSupportfortheproject:Foraprojectofthismagnitude,itisimportantforthe
governmentagencytogarneradequatepublicsupporttoensuresmoothimplementation. MMRDA
ensuredadequatepublic support for land acquisitionandroadexpansion activities
byadialoguewiththeaffectedindividuals.Despitetheseefforts,theprojectwas susceptible to
delays and similar difficulties are also being experienced in phase 2 of the project.
7. RoleofGoodProjectPreparation:Theviabilitygapfundingusedintheproject(`650crore)
makesupasignificantcomponent(27.5percent)oftheprojectcost.Thisprojectcosthas
beensharedbetweenthecentralandstategovernments.Theinitialquotesubmittedby
thesuccessfulbidderquotedanamount(`1250crore)whichwassubsequentlyrevisedto
thecurrentfigure throughnegotiations.Thus,thereisanincreasedneedforgoodproject
preparation prior to the procurement process to ensure that the fair bids are received for the
projects.Thiswould eliminate private operators colluding with each other and/or speculative
bids.
PGPM14
Page 14