Building Construction Technology I

Practical Session no. 3


09.04.2012

Who is responsible for?


-

Issuing a solution/permit for removing buildings,


( The inspection
)*
Administrative supervision over the implementation of the Law on Spatial
Planning and the regulations issued under that act,
( The Ministry ) *
the legality of the actions of authorities and persons with public
authorities relating to the Spatial Planning and building,
( The Ministry ) *
Running the Construction dairy,
( Site engineer
assistant ) *
Ensuring the needed machinery,
( the Contractor ) *
Maintaining the building during its lifetime,
(The Investor)
Maintaining the building after its lifetime,
(The customer )
To give a report ( positive/negative ) on the condition of the building or its
part and will be responsible furthermore for it
( The
Reviser )
Suppling investors with all information about the defects and irregularities
before the construction phase
( The
Supervisor )
Determining whether the survey of the building done by the person
authorized to conduct tasks
( The Supervisor )
Determining whether the contractor meets the requirements for
performing construction activities
( The Supervisor )
To design a project to comply with the building location permit, to meets
the essential requirements for the building and to comply with the
provisions of this Law and special regulations.
( The Designer )
Performing at least half the work necessary for construction and the
building.
( The
main Contractor )
Remove all temporary structures before obtaining the use permit
( The
Contractor )
Make plan of common temporary and temporary work sites
( The
Contractor )
Mark the construction site with prescribed markings&signs
( The
Contractor )
Draw up a written declaration of executed works and the building
maintenance conditions
( The
Contractor )

Obtaining usage permit for the building


( The Investor )
Preserving relevant documents and projects for the construction of with
the amendments marked and changes as long as building exists ( The
Investor )
Obtaining Survey project of the building until the start of construction
works.
( The Investor )

Define the: *
-

Construction: (object created by constructing works, connected to


ground, performed from building products with common installations and
equipment, or integrated complex with facility or equipment as well as
technical - technological units or solo installations connected to the
ground. )
Construction Works: (Performing constructional and other works
(preparation, land, and structural, installation, finishing and mounting of
construction products, plant or equipment) with which new buildings are
built, existing buildings are reconstructed, removed or maintained. )
Constructing: (the process of designing,
constructing, usage and removal of the construction (building), everything
that is related to the constructing of the new buildings can be applied in
an appropiate way to reconstructing, maintance and removal of the old
buildings. )
Construction site: (is a place,land or buildings (including other areas
that are temporarily occupied ) needed to execute the construction works
or the application of appropriate building technology and security, on
which to build, reconstruct, remove or perform maintenance work
building).
Maintenance of buildings: (Performing constructional and other
works to preserve the essential requirements of a building during its
lifetime, with which does not change the compliance with the conditions at
the location of the building in accordance with which it is built. )

Construction site shall be marked with: (name 4 things or more) *


-

Name of investors, the designer, contractors and persons carrying out


construction supervision
Name and type of buildings that is being built
The name of the authority issuing the document upon which to build

Classification code, register number, date of issue and validity of the act
upon which to build
An indication that it is a cultural property that is the national monument

Contractor on construction site must have: (name 8 things or


more) *
-

The decision on registration in court register, or crafts license.


Approval for performing the construction and performance of and the
contract on the association contractors under special legislation.
Act on appointment of chief site engineer, site engineer and works
manager.
Act on appointment of supervisor or principal supervisor.
A decision on building conditions, confirmation of the main project, or
construction permit from the conceptual or main project.
Performing projects with the opinion of chief designer of the project and
certified by the reviser that Requested it in a report on the control of the
main projects requested , for the previously constructed part of the
building , construction and other works that are in progress with all
amendments.
Reviser's report on completed inspection of the execution project if
required.
Construction Diary.
Evidence of compliance for construction products installed.
Evidence of compliance by a special law for the installed equipment.
Identifications of Compliance for certain parts of certain construction
essential.
Special requirements according to law and quality evidence that is
requested by the law, special regulation or project to collect during the
execution of construction work and other commitments and
implementation of control procedures for the previously constructed part
of the building and construction and other works in progress.
Survey project of the buildings.
Other documents, licenses and permits for which special regulations
stipulates that the contractor after the start of construction of the building
must have at the site.