There are two ways to do the IP new site intergration,one is USB Flash Drive for GBTS
Commissioning , the other one is SMT for GBTS Commissioning.
For USB Flash Commissioning ,you only need an USB,and put the BTS configuration file in the USB
accurately,then you plug the USB to the BTS;For the SMT commissioning ,you need connect to the BTS by a
laptop , then you can do the config of the BTS by SMT software.
About the two methods ,we recommend the USB commissioning ,if the USB commissioning is not
working ,you can use the SMT commissioning.
Step
Work procedure
The power for the BTS is OK and the BTS is power on;
Check the CWO status with CWO engineer, the port for BTS
should be defined in the transmission side;
Transmission for the site is OK,ping test from RTN or GPON to the
BSC gateway is OK;
2015-3-29
1 , 12
File
Transmission
configuration file
usb:\BTS3900 GSM\Stie0\TranCfg.ini
5.Check the status of the GBTS,make sure the GTMU board is power on and working nomal;
6.Put the USB flash into the USB port of the GTMU,
7.Do not remove the USB flash drive during the period from plugging in the flash drive to the duration of
normal operation of the base station. Otherwise, the file load or parsing fails.
Commissioning
Phase
Status of the
Indicator on the
USB Flash Drive
Duration
Steady on
About one to
two seconds
Blinking
About ten
seconds
Steady on
About three
seconds
2015-3-29
2 , 12
Commissioning
Phase
Status of the
Indicator on the
USB Flash Drive
Duration
Blinking
About three
seconds
Steady on
If this status
remains for
more than
one minute,
the upgrading
is successful.
8.Check with BSC integration team whether the BSC can Ping to the BTS IP.
2015-3-29
3 , 12
2.Use an Ethernet cable to connect the BTS and the laptop. One end is connected to the ETH port on the
GTMU of the main cabinet, and the other end is connected to the Ethernet port on the a laptop).
3.Run the SMT software.
4.Obtaining the Site Management Rights by click the Site Management Right and then click Get.
2015-3-29
4 , 12
5.In the left pane of the SMT System window, select Site. In the right pane of the window, double-click
IP over FE Static IP.Confirm the static IP network, and then click OK.
6.In this dialog box,set the IP addresses of the BTS and BSC and other related parameters step by step like
2015-3-29
5 , 12
below, the parameters in the red box are the same to all the sites,the parameters in the yellow box are different
to different sites.Click Config Para to complete the settings of the IP addresses and VLAN parameters.
2015-3-29
6 , 12
7.Click the Config Router tab. On the Config Router tab page, set the route of the BTS, as shown
in the below picture.Every site we need add 3 router, first one goes to BSC DEVIP, other one goes to
IPCLK1,the last one goes to IPCLK2.
Add the router to BSC like below:
2015-3-29
7 , 12
2015-3-29
8 , 12
2015-3-29
9 , 12
11.Click the Query tab. On the Query tab page, click Query to query the static IP addresses.
Make sure all the parameters are correct according to the IP design.
2015-3-29
10 , 12
12.Click the Board in the left panel ,then click Board Management,then right click GTMU board,choose
Board Reset to reset the site.
13.After the site reset,you should contact the BSC intergation ,check whether they can PING to the BTS
IP, if the site is up,you can see the board is OK.
If the site is UP, also you should check with the BSC interation whether there are any alarms in the BTS and
Clear all the alarms.
2015-3-29
11 , 12
2015-3-29
12 , 12