Professional Documents
Culture Documents
Deltares, Technical University Delft, chair person Dutch CUR Task group Design Guideline
Piled Embankments
2)
Deltares and Technical University Delft
P.O. Box 177, 2600 MH Delft, The Netherlands, Suzanne.vanEekelen@Deltares.nl
The last years have brought decision support systems to quantify the impacts of choices,
making the selection process more transparent. A case study for the widening of the
highway A2, and in addition several successful examples show that a contractor is
stimulated to offer innovative solutions such as piled embankments when the principle
sets requirements for construction time, protection of vulnerable objects or a period of
maintenance for the contractor.
When design guidelines for these innovative solutions become available, like the
recently introduced Dutch Piled embankment Design Guideline, the application of these
techniques is further stimulated and the public demands are more easily fulfilled.
However, cars and trains were developed and the need for road and
railroads grew. So, the Dutch were faced with the problem of raising sand
embankments on ground that should be considered unsuitable. A project
that finally succeeded was the construction of the railroad between Gouda
and Schoonhoven, see figure 1.
FIG. 1
1942
Need for wider and more reliable roads in the thirties of the last century,
source: www3.picturepush.com/photo/a/2223576/1024/Friese-B-nummerstrucks/12515.jpg
FIG. 2
Since the thirties of the last century, the need for more reliable and
wider roads increased with the development of more reliable diesel engines.
Keverling Buisman and his co-workers at the Dutch Institute for Soil
Mechanics developed several construction methods to build roads in the soft
Dutch polders (Heemstra, 2008). They for instance developed the road on a
lightweight embankment (dried peat), the road on piles (concrete slabs on
timber piles) and embankments reinforced with fascines. In order to prevent
rotting of the fascines, these mattresses needed to remain completely below
ground water table during their service life.
FIG. 3
and demands
The choice for a method for road construction on soft and compressible soil
has serious implications for both construction phase and operation of the
road. Road users want the road to be available as soon as possible and do
not accept delays due to maintenance works.
In addition, when building in densely populated areas, owners of
nearby underground infrastructure or facilities do not want the construction
works to damage their property. However, the principal often has a limited
budget that is fixed in an early stage of the project.
These demands often are contradictory, as indicated in Table 1. The
table compares the impacts of three categories of construction methods
commonly used in the Netherlands. Prefabricated vertical drains are the
default option, combined with some extra meters of sand loading as
temporary surcharge. The temporary surcharge will reduce creep
settlements during the service life of the road. The Beaudrain and IFCO
methods use a combination of underpressure in the drains and forced
dewatering to apply a temporary surcharge to the soft soil, adding to the
effect of the sand surcharge. The principle of both piled embankments and
Expanded Polystyrene (EPS) embankments is to prevent the compaction of
the soft soil, thus eliminating settlements. Although EPS is also a good
construction method, this will not be considered further in this paper.
TABLE 1
Impact of
construction
method
Construction time
Maintenance
Construction costs
Damage to nearby
structures
Beaudrain or IFCO
method with
temporary
surcharge
medium
frequent - medium
medium
can be avoided by
careful execution
Piled embankment /
EPS embankment
short
none
high
unlikely
generally more expensive for the principal. In the example of the N210,
strict requirements were set for creep settlements and the availability of the
existing very vulnerable road during construction. With these requirements,
and with inclusion of 20 years of maintenance in the contract, the piled
embankment came out as the most reliable solution with lowest overall cost.
Another example is the piled embankment of the railroad in Houten. Here,
very limited construction time was available, and with a vulnerable
foundation next to the railroad, an innovative solution was necessary. The
piled embankment again came out as the most reliable solution with lowest
overall costs.
However, the definition of lowest overall cost is not straightforward.
This is illustrated in the next paragraph for the widening of Dutch national
highway A2.
3.2 Case
FIG. 4
for the contractor in dealing with other stakeholders. The last is a shared
concern of contractor and principal, and it is only logical that also revenues
and the losses are shared.
Various projects in the Netherlands show what can be reached with the
changing attitude of the authorities. In the case of N210, the strict
requirements for availability and integrity of the existing road, and the
responsibility for the maintenance for the first 20 years, forced contractors
to offer innovative solutions. Lightweight EPS foam allowed the nearby 2
km long N475 to be reconstructed within a month, a bonus/penalty system
stimulating fast construction. The lightweight solution was hardly more
expensive than the traditional construction. A piled embankment turned out
to be more expensive because the logistics were less suitable for that
location. In both cases, the principal gave priority to the interests of the road
user. And in both cases, the additional costs of innovative construction
methods turned out to be limited.
4
REFERENCES
CUR, 2010 Design Guideline for Piled Embankments, CUR report