Professional Documents
Culture Documents
Rev 3
SAIC NUMBER
SAIC-W-2038
WBS / BI / JO NUMBER
EQUIPMENT ID NUMBER(S)
EQUIPMENT DESCRIPTION
REV. NO.
30-Jun-08
DATE APPROVED
QR NUMBER
WELDCONTRACTOR / SUBCONTRACTOR
EQPT CODE
SYSTEM ID.
PLANT NO.
MH's SPENT
TRAVEL TIME
ITEM
No.
ACCEPTANCE CRITERIA
REFERENCE
PASS
FAIL
N/A
Instructions for Approval (Responsibilities) ... Quality Managers shall see Notes 1 & 2 at end of this checklist
A1
For shop and all field fabrication IK, NEW WPSs & PQRs are
prepared* and submitted using the correct SA Welding Forms:
A) Attachment 1 - SAES-W-011/012 WELDING PROCEDURE
SPECIFICATION (ATTACHMENT A, PAGES A1, A2, A3, A4, A5)
B) Attachment 2 - SAES-W-011/012 WELD & LINE DESCRIPTION
TABLE (ATTACHMENT B).
For New Procedures (Master Set), follow Attachment 3 rules.
C) If previous CSD-approved WPS is reused. See Section C.
SAES-W-012,
Para. 7.1.2
A2
All WPSs & PQRs shall conform to the latest edition of the relevant
Code (API STD 1104 or ASME SEC IX, as appropriate).
SAES-W-012,
Para. 7.2.1
A3
SAES-W-012,
Para. 7.1.3 & 4
A4
SAES-W-012,
Para. 7.1.10
A5
Originals of all test records, mill certificates, etc. including records from
independent test laboratory are available for review by SA.
SAES-W-012,
Para. 7.1.11
A6
SAES-W-012,
Para. 7.2.5 a)
A7
SAES-W-012,
Para. 7.2.5 b)
A8
For all automatic welding & any process with pulsing, the WPS shall
include all applicable equipment and controller parameter settings.
SAES-W-012,
Para. 7.2.6
B1
SAES-W-012,
Section 7.4
B2
SAES-W-012,
Para. 7.5.1
Review & Submittal of Existing WPS (CSD Previously Approved) ... Quality Manager Checklist (Action & Review)
C1
Page 1 of 4
SAES-W-012,
Para. 7.1.1
RE-INSP DATE
Rev 3
ITEM
No.
SAIC NUMBER
SAIC-W-2038
WBS / BI / JO NUMBER
ACCEPTANCE CRITERIA
REFERENCE
30-Jun-08
DATE APPROVED
QR NUMBER
5-Nov-08
WELD-
CONTRACTOR / SUBCONTRACTOR
PASS
FAIL
N/A
Review & Submittal of Existing WPS (CSD Previously Approved) ... Quality Manager Checklist (Action & Review)
C2
SAES-W-012,
Para. 7.1.1
C3
Each Weld and Line Description Table (Att. B) must be complete and
show line designations (service), materials, joints, & WPS used for
the NEW APPLICATION.
SAES-W-012,
Para. 7.1.4
RE-INSP DATE
Note: CSD HAS IDENTIFIED 6 SELECTED VARIABLES FOR CLOSE REVIEW OF WPS (MOST COMMON CAUSE OF WPS REJECTION)
C4
SAES-W-012,
Para. 7.1.1
C5
Per QW 403 & 450, Check Thickness range, comparing the old and new
application.
SAES-W-012,
Para. 7.1.1
C6
Per QW 403, Check Pipe Diameter range, comparing the old and new
application.
SAES-W-012,
Para. 7.1.1
C7
Per QW 407 & Service Application (Form Page A1), Check PWHT,
comparing the old and new application.
SAES-W-012,
Para. 7.1.1
C8
Check Service & Materials (scope) for Hardness Reqmts, comparing the
old and new application.
SAES-W-012,
Para. 7.1.1
C9
SAES-W-012,
Para. 7.1.1
Note: The following revisions apply to all existing WPS. QA/QC Mgrs. shall take immediate action for revision as needed.
C10
As referenced,
Contact CSD on
any welding
technical
questions
SAES-W-012,
Para. 7.1.1
C11
As referenced,
Attachment 3,
Contact CSD as
needed to verify
SAES-W-012,
Para. 7.1.1
Page 2 of 4
Rev 3
SAIC NUMBER
SAIC-W-2038
WBS / BI / JO NUMBER
C12
As referenced,
Attachment 3,
Contact CSD as
needed to verify
SAES-W-012,
Para. 7.1.1
C13
As referenced,
Attachment 4,
Contact CSD as
needed to verify
SAES-W-012,
Para. 7.1.1
C14
WPS using Internal & External Field applied FBE Coatings shall be
CSD approved. The process shall be GMAW STT or GTAW to assure the
following criteria: All weld joints including adjacent areas to be FBE coated
either Internal or External shall be ground smooth and free from burrs,
weld spatter, sharp edges. Weld toes shall be merged smoothly and
rounded with no sharp undercuts. Weld cap or internal root protrusion
shall not be more than 1.5 mm. WPS provides adequate field
instruction.
SAES-H-201,
Para. 7.2.2
C15
CSD approved WPS with essential variables that include the restriction
of electrodes (Per Attachment 5) are "noted":
A) G Designated Electrodes are restricted to the exact brand & type
specified on the PQR & WPS.
B)
WPS & PQR with Impact Toughness Reqmts use the same brand name
& type GMAW electrode, SAW flux & FCAW electrode.
C)
Change in filler metal or deposit chemistry from A-No. 1 to A-No. 2
(ASME SECT IX) Note: Requalify Sour Service Procedures
WPS Notes shall specify that substitutions are not allowed and exact
brand name and type consumable shall be used.
Plan Consumable substitution approvals by CSD. Do not wait until
designated & required consumables are gone.
SAES-W-012,
Section 7
30-Jun-08
DATE APPROVED
QR NUMBER
5-Nov-08
WELD-
CONTRACTOR / SUBCONTRACTOR
WELDING PROCESS CONTROL PROCEDURE (COVERS ALL WELDING RELATED ACTIVITY OTHER THAN THE WPS)
D1
Welding related activities other than the actual WPS are identified and
controlled (Special Construction Process) by Procedure. Option exists for
a single procedure (Welding Process Control) or multiple procedures
covering the remaining elements in Section D below.
A single Procedure is recommended for efficiency . All SAIC are
referenced in this procedure. Use the specific checklists.
SAEP-1160 Weld ID & Tracking System (Database) required.
D2
SAIC-W-2038
D3
SAIC-W-2039
D4
SAIC-W-2040
D5
SAIC-W-2008
D6
SAIC-W-2045,
SATR-W-2011
D7
SAIC-W-2055
D8
SAIC-W-2047
D9
SAIC-W-2048
SATR-W-2006
Page 3 of 4
Schedule Q,
Attachment VI,
Special Process
Tables
Rev 3
SAIC NUMBER
30-Jun-08
DATE APPROVED
QR NUMBER
SAIC-W-2038
5-Nov-08
WBS / BI / JO NUMBER
D10
SAIC-W-2049
D11
SAIC-W-2050
SATR-W-2007
D12
SAIC-W-2051
D13
SAIC-W-2056
D14
SAIC-W-2057,
SATR-W-2014
WELD-
CONTRACTOR / SUBCONTRACTOR
Remarks:
NOTES: 1) See Section "C" regarding Existing WPS (whether approved or not). Follow all specifics. Contact CSD on any technical matter
related to Welding. Contact your Project Inspection Representative on any checklist question for Welding. QA/QC Mgr. Action Required!
2) QA/QC Mgr shall ensure a detailed Welding Process Control Procedure per Section D is established. See item D1.
Certain procedure elements (heat input, wps monitoring, associated forms, etc) are also provided as applicable to scope.
3) Alignment Tolerances & Disposition of Repairs shall be addressed during Pipe Stringing. See SAIC-W-2048.
4) Structural steel welding (AWS D1.1 related) on Pipelines shall utilize SAIC-M-2012. See SAIC-M-2012.
ATTACHMENTS: 1 - SAES-W-011/012 WELDING PROCEDURE SPECIFICATION (ATTACHMENT A, PAGES A1, A2, A3, A4, A5)
Attachment 2 - SAES-W-011/012 WELD & LINE DESCRIPTION TABLE (ATTACHMENT B)
Attachment 3 - SAEP-352 Welding Master Set Preparation & Approval (Instructions)
Attachment 4 - NACE RP-0472 Table 2: Process/Filler Material Combinations Exempt from Weld Deposit Hardness Testing
Attachment 5 - WPS PROCEDURE VARIABLES (SAES-W-012, Section 7.4)
Attachment 6 - SAES-W-012 TABLE 4A/4B - PREHEAT TEMPS. VERTICAL DOWN SMAW BUTT WELDS (NOTICE OF ERROR IN SA STDS)
REFERENCE DOCUMENTS: 1. SAES-W-012, Welding Requirements for Pipelines, (31 December 2002)
2. SAEP-352, Welding Procedures Review and Approval, (31 May, 2003)
Contractor / Third-Party
Saudi Aramco
Construction Representative*
PMT Representative
T&I Witnessed
QC Record Reviewed
Work Verified
T&I Witnessed
QC Record Reviewed
Work Verified
T&I Witnessed
QC Record Reviewed
Work Verified
QC Inspector
PID Representative
Performed Inspection
QC Supervisor
Name, Organization,
Initials and Date:
Y = YES
Page 4 of 4
N = NO F = FAILED