Installation Schedule - Start

0 days

Mon 8/9/14

Mon 8/9/14

Mechanical Install

8/9

46 days

Mon 8/9/14

Wed 29/10/14

Final layout work

4 days

Mon 8/9/14

Thu 11/9/14 2SS

Cao Duong

IP check

2 days

Thu 11/9/14

Fri 12/9/14 2SS

USG

Prepare & review contract

3 days

Sat 13/9/14

Tue 16/9/14 2SS

USG Boral,Cao Duong

Prepare & review schedule

12 days

Sat 13/9/14

Fri 26/9/14 2SS

USG Boral,Cao Duong

USG Boral,Cao Duong

Sign contract

1 day

Fri 26/9/14

Fri 26/9/14 5,6,7

Cao Duong

Cao Duong

Manufacturing drawings MCM Tank

4 days

Wed 24/9/14 Sat 27/9/14

Cao Duong

10

MCM Tank - usg boral approval

1 day

Mon 29/9/14 Mon 29/9/149

USG Boral

USG Boral

11

Manufacturing drawings MCM platform

2 days

Sat 27/9/14

Mon 29/9/148

Cao Duong

Cao Duong

12

MCM platform - USG Boral approval

0.5 days

Tue 30/9/14

Tue 30/9/14 11

USG Boral

USG Boral

13

Manufacturing drawings MCC platform

0.5 days

Tue 30/9/14

Tue 30/9/14 11

Cao Duong

Cao Duong

14

MCC Platform - USG Boral approval

0 days

Tue 30/9/14

Tue 30/9/14 13

USG Boral

15

Bureau Veritas approval

10 days

Tue 30/9/14

Sat 11/10/14 12,14

USG Boral

16

MCM Tank fabrication

8 days

Tue 30/9/14

Wed 8/10/1410

Cao Duong

17

MCM Platform - fabrication

12 days

Tue 30/9/14

Tue 14/10/1412

Cao Duong

18

MCM Platform - handrails

12 days

Tue 30/9/14

Tue 14/10/1417SS

Cao Duong

19

MCC Platform - fabrication

5 days

Tue 30/9/14

Mon 6/10/1414

Cao Duong

20

Lifting cage fabrication

10 days

Tue 14/10/14 Sat 25/10/14 17

Cao Duong

21

Locate MCM tank

1 day

Thu 9/10/14

Thu 9/10/14 16

Cao Duong

22

Install MCM platform

3 days

Tue 14/10/14 Fri 17/10/14 17

Cao Duong

23

Handrails & Finishing

5 days

Fri 17/10/14

Thu 23/10/1422,18

Cao Duong

24

Install MCM dosing skid

1 day

Fri 17/10/14

Sat 18/10/14 22SS+3 days

Cao Duong

25

Install MCC platform

3 days

Mon 6/10/14 Thu 9/10/14 19

Cao Duong

26

MCC Handrails & finishing

2 days

Thu 9/10/14

Sat 11/10/14 25

Cao Duong

27

Install hoist

2 days

Fri 17/10/14

Mon 20/10/1422

Cao Duong

28

Install lifting cage

3 days

Sat 25/10/14

Tue 28/10/1420

Cao Duong

29

Install MCM recirculation pump

1 day

Fri 17/10/14

Sat 18/10/14 22

Cao Duong

30

Install MCM recirculation pipework

3 days

Sat 18/10/14

Wed 22/10/1429

Cao Duong

31

Install MCM tank mixer

2 days

Fri 17/10/14

Mon 20/10/1422

Cao Duong

32

Install bulk bag discharge equipment

3 days

Sat 25/10/14

Mon 27/10/1431

Cao Duong

33

Install MCM tank instruments

1 day

Thu 23/10/14 Fri 24/10/14 23

Cao Duong

34

Install MCM tank blank flanges

2 days

Fri 24/10/14

Sun 26/10/1433

Cao Duong

35

Install MCM pipework to mixer

3 days

Wed 22/10/14 Sat 25/10/14 30

Cao Duong

36

Install compressed air to bulk bag equipment

2 days

Tue 28/10/14 Wed


29/10/14

32,35

Cao Duong

37

Install water supply, valve & meter to MCM


tank

3 days

Thu 23/10/14 Sun


26/10/14

23

Cao Duong

38

Foam water pump delivery

0 days

Fri 10/10/14

Fri 10/10/14

USG Boral

39

Install Foam Water pump

1 day

Fri 10/10/14

Fri 10/10/14 38

Cao Duong

40

Install water supply to foam water pump

3 days

Sat 11/10/14

Tue 14/10/1439

Cao Duong

41

Install 90% of new soap lines

3 days

Wed 15/10/14 Fri 17/10/14 40

Cao Duong

42

John Fall on site

0 days

Mon 22/9/14 Mon 22/9/14

USG Boral

43

Final design vibration rollers

5 days

Mon 29/9/14 Fri 3/10/14 42

TBC

44

Fabricate vibration rollers

10 days

Sat 4/10/14

Wed 15/10/1443

TBC

45

Mount new mixer outlet

1 day

Thu 25/9/14

Thu 25/9/14

46

IT

26 days?

Tue 23/9/14

Wed 22/10/14

47

Spec IT requirements

3 days

Tue 23/9/14

Thu 25/9/14 48SS-3 days

HCM IT

48

Order IT items

21 days

Fri 26/9/14

Mon 20/10/1449SS-21 days

HCM IT

49

Install IT

7 days

Tue 14/10/14 Tue 21/10/1450SS-7 days

TBC

50

Test remote connection

1 day?

Wed 22/10/14 Wed 22/10/14

TBC

4 days

Fri 31/10/14

Mon 3/11/14

USG Boral

51

SHUTDOWN LINE 2

Cao Duong
USG
USG Boral,Cao Duong

Cao Duong

30/9
USG Boral
Cao Duong
Cao Duong
Cao Duong
Cao Duong
Cao Duong
Cao Duong
Cao Duong
Cao Duong
Cao Duong
Cao Duong
Cao Duong
Cao Duong
Cao Duong
Cao Duong
Cao Duong
Cao Duong
Cao Duong
Cao Duong
Cao Duong
Cao Duong
Cao Duong
Cao Duong
10/10
Cao Duong
Cao Duong
Cao Duong
22/9
TBC
TBC

HCM IT
HCM IT
TBC
TBC

Cao Duong

52

Remove existing Foam skid

0.5 days

Fri 31/10/14

Fri 31/10/14

Cao Duong

53

Locate and fix down new foam skid

0.5 days

Fri 31/10/14

Fri 31/10/14 52

Cao Duong

54

Reconnect foam skid pipe connections

1 day

Sat 1/11/14

Sat 1/11/14 53

Cao Duong

55

Connect foam water pump

1 day

Sun 2/11/14

Sun 2/11/14 54

Cao Duong

56

Final connect MCM to mixer

0.5 days

Mon 3/11/14 Mon 3/11/1455

Cao Duong

57

Rearrange IBC positions

1.5 days

Sat 1/11/14

Sun 2/11/14 53

Cao Duong

58

Finish soap lines

0.5 days

Sun 2/11/14

Sun 2/11/14 57

Cao Duong

Cao Duong

59

Install compressed air to 2x soap valves

0.5 days

Sun 2/11/14

Sun 2/11/14 58SS

Cao Duong

Cao Duong

60

Modify forming table

4 days

Fri 31/10/14

Mon 3/11/1444,52SS

TBC

22.63 days

Thu 9/10/14

Mon 3/11/14

61

Electrical Installation

62

Install MCC panel

2 days

Thu 9/10/14

Sat 11/10/14 25

TBC

63

Install new cable trays

5 days

Sat 11/10/14

Fri 17/10/14 62

Elec Installer

64

Pull cables

5 days

Fri 17/10/14

Thu 23/10/1463

Elec Installer

65

Terminate MCM cables

3 days

Thu 23/10/14 Sun 26/10/1423,26,64

Elec Installer

66

Terminate power cable

1 day

Sun 26/10/14 Sun 26/10/14

Elec Installer

67

Power on for MCM testing

0 days

Sun 26/10/14 Sun 26/10/1466

USG Boral

68

Power Off to complete foam

0 days

Fri 31/10/14

Fri 31/10/14 51SS,76

USG Boral

69

Terminate foam system cables

1 day

Sat 1/11/14

Sat 1/11/14 68FS+1 day

Elec Installer

70

Terminate cables to forming table

1 day

Sun 2/11/14

Sun 2/11/14 60FS-2 days

Elec Installer

71

Power On for foam

1 hr

Mon 3/11/14 Mon 3/11/1465,66,69,70

Elec Installer,USG Boral

72

Modify HMI

3 days

Fri 31/10/14

Future Option

8 days

Mon 27/10/14 Mon 3/11/14

4 days

Mon 27/10/14 Thu 30/10/14

73

74

Commissioning
MCM

Sun 2/11/14 51SS

75

I/O & rotation checks

2 days

Mon 27/10/14 Tue 28/10/1467

USG Boral

76

Sequence test

2 days

Wed 29/10/14 Thu 30/10/1475

USG,USG Boral

1 day

Mon 3/11/14 Mon 3/11/14

77

Foam & Vibration Rollers

78

I/O & rotation checks

0.5 days

Mon 3/11/14 Mon 3/11/1471SS

79

Sequence test, calibration, make foam

0.5 days

Mon 3/11/14 Mon


3/11/14

0 days

Tue 4/11/14

80

Ready for commissioning trials

Project: Next Gen - Installation

Task

Split

Cao Duong
Cao Duong
Cao Duong
Cao Duong
Cao Duong

TBC

TBC
Elec Installer
Elec Installer
Elec Installer
Elec Installer
26/10
31/10
Elec Installer
Elec Installer
Elec Installer,USG Boral
Future Option

USG Boral
USG,USG Boral

78

Tue 4/11/14 79

4/11

USG,USG Boral

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Page 1

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Slippage

16 Nov '14
S

You might also like