Professional Documents
Culture Documents
INSTRUMENTATION OF
LIMESTONE STA
INTERNSHIP REPORT ON THE
INSTRUMENTATION OF
LIMESTONE STA
(a)
(b)
(c)
(d)
Drain Valve:
A transformer has drain valve at the bottom to replenish oil and drain out to flush
tank and check for internal corrosions.
Conservator Tank:
Then comes entire Transformer tank that is filled with oil. It has two purposes.
a) To cool down and reduce extra heat.
b) Act as an insulator.
Transformer core is made up of steel laminations. To achieve high level of precision and
to control vibrations and sound level the proper cutting of plate is need to be done and
special care is taken out when stacking the laminations.
Bushings:
The high voltage conductors that pass through the grounding wall of a
transformer are known as bushings of a transformer.
The insulator and the external connections must have the strength to withstand
the short circuit.
Bushings are low cost compared to the high voltage assets that protect. Bushing
failures can have substantial consequences to the transformer, human safety and
environment.
Serious consequences could be occur when porcelain bushes fails. Shards of
porcelain could be launched and cause potential risks to the human safety and
surrounding objects.
The transformer oil is contaminated once it comes in contact with the atmosphere
The transformer oil can also be ignited and cause problems for the human safety
and environment
Breather:
When the insulation oil of the transformer cool down, oil retracts.
During retraction process, fresh air is sucked from the atmosphere through
breather.
i.
ii.
If the dust particles are allowed the oil of the transformer gets contaminated.
Therefore oil cup is used to collect dust particles when the air is sucked by the
breather.
Buchholzs Relay:
It is a mechanical device
By heating of the arc isulating material is destroyed and gas is released. So there
was need to collect the gas bubbles from the transformer to a place where quality
and quantity of the gas can be estimated.
So for this purpose buchollz named scientist gave the idea and this relay is
known by his name as buchollzs relay.
This relay is fitted in the pipe connecting the transformer tank with the
conservator tank.
It consists of two main floats.
When both the floats sink ,each of them short circuits two contacts by closing a
circuit so the fault could be detected.
It is also be capable to detect the low magnitude fault such as inter turn
To test the function of the relay move the with skrew driver in anticlockwise
direction till the slot on the test key point towards the T/L position.
Both the floats will operate and mercury switch of upper and lower float will show
continuity.
During transportation or storage of the relay,the test key should remain in T/L
position.
During topping up of transformer oil the test key should remain in T/L position.
b) S (Service):
During commissioning of the relay the key should remain in service position.
TSUN 6338
20600246
2000 kVA
52C
3
A
50Hz
ONAN
27580W
Dyn 11
6300/415 V
183.3/2782.4 A
8.12 %
Cont.
53C
3 sec
Volts
Termi
nal
B
Tap
Changer
Connection
LOW VOLTAGE
Positi
on
Connect
ion
Volts
Termina
l
6615
6457.
5
DELTA
6300
6142.
5
5985
s
A5
C5
A4
C4
A6
C6
A3
C3
A7
C7
A4 B5
C4
A6 B4
C6
A3 B6
C3
A7 B3
C7
A2 B7
C2
B4
1
B6
2
B3
3
STAR
415
B7
4
0
a
b
c
B2
5
KVA:
Volts at NO LOAD:
It has HV and LV voltages. HV side is known as primary side and LV side is known as
secondary side.
It tells that how much the primary side and secondary side will vary depending upon the
load factor.
The HV side does not vary unless and until we adjust switching tapes.
.
It has LV voltages of 6300 rated voltages. While the standard voltages at LV side are 415
volts.
Current (Amperes):
Phase:
Connections:
HV side is delta connected having voltage and currents at positions
Type of Cooling:
It is of two types.
o Frequency:
Rated frequency is 50Hz.
o Weight:
Oil weight
Core and oil assembly weight
Liftable weight
1050kg
17000kgs
2355kg
Switching positions are at 360 round shaped circle starting from 1 to so on.
When we select position 1 the voltages are 145206V and current is 39.8A respectively.
The main purpose of positioning is to vary the HV side voltages depending on the load.
But these varying voltages are in the limit and we can vary to a small limit at each
postion means not in the limit of 1000V.
This variations of voltages at each position is set by the manufacturer.
The LV side voltages remains irrespective of the selected positions.
(a)
(b)
Transformer Testing
http://www.hiload.pk/browse.php?u=rY%2BT6%2BTuvOD4vBAySnz%2F5qjKSx8K1%2BM
%2BqZKmSgTrEwg4vHES51Z6&b=29
The oil works as insulating material and serves as coolant (exhaust heat being
produced in transformer).
The breakdown voltage is the voltage reached at the time of the first spark
appears between the electrodes.
The test is carried out six times on the same cell filling and the electric strength of
the oil is the arithmetic means of the six results obtained.
What should be Break Down Voltage values for the following Transformers?
1. 22/0.4kV, 1000kVA
2. 0.4/125 KV, 160.9 KVA
3. 132/6.3 KV, 26 MVA
Above three transformers having different voltages. Take Higher side Voltages
1. 22,000 V
2. 125, 000 V
3. 132, 000 V
According to IS 6792:1992, BDV value should be
30 kV Minimum: Transformers up to 72.5 kV
40 kV Minimum: Transformers from 72.5 kV up to 170 kV
50 kV Minimum: Transformers from 172 kV up to 420 kV
The BDV value should be greater than 40 KV (Voltage is 125,000 V, greater than
72,500 V)
The BDV value should be greater than 40 KV (Voltage is 132,000 V, greater than
72,500 V
65 kV
Such types of variation are often seen and cause confusion whether the unit is ready for
operation or not.
One common reason for variation in result is insufficient time gap between oil samples.
Instead of 5 minutes, time gap between each sample should be around 15-20 minutes.
The techniques used for oil sampling follow the guidelines of international recognized
standards that are known as:
Bottle Sampling:
Ensure that the stopcock is attached to the syringe and attached the flinch tubing
to the stopcock
Set the stopcock at position 1 and push on the plunger
Note: Pulling on the plunger may results in formation of bubbles
Set stopcock at position 3 and press the plunger to swill the oil into the container
Then open the stopcock and fill the syringe up to 50mm,close stopcock and
remove the tubing, pack the syringe immediately into box, unblock the adopter,
install the sealing kit of sampling port
Remember that the oil remaining oil into the tubing and adopter should be flush
through to the waste container
When due to some reasons gases are not dissolved in the insulating liquid they
evolve in the form of bubbles.
These bubbles find their way to the conservator through the pipe.
So these bubbles are removed by the Bucholz relay before they reach the
conservator tank and contaminate the oil.
The Bucholz samples are taken from the gas sampling device.
In case if device is not available samples are taken directly from the buchholz
Buchholz can be sampled either for oil or gas
If Bucholz contains humiliated gas then it need to be sampled and gas can be
released using variety of samples
We can use either glass syringes or gas sampling bags
First task is to accumulate gas through the buchholz into the sampling device
TO take samples through the sampling device open the bottom port of the
sampling device and allow the oil to drain,Notice that the oil level in the device
decreases
Now the sampling device is full of gas close the bottom port
Once the gas is collected in the device retrieve the gas by attaching the sampling
tubing to the top port of the sampling device and connect the sampling container
either the glass syringe or sampling bag
Now open the top port valve of the sampling device to release
Notice that the oil level will rise again as the gas is pushed out from the device
Note that all the gas is released by opening the top valve port till the oil start to
flow out through the tubing
DGA analysis is not for determining the quality of oil in the transformer.
It is carried out to determine any abnormalities in the internal winding or
formed and due to this energy the long organic oil chain is getting broken.
As a result so many gases is formed such as CO2, C2H4, C2H2, C2H6,
C3H6, C3H8, CH4, CO, H2, O2, N2 etc.
The principal or key gases associated with each type of issue are shown below:
Hydrogen (H2): generated by partial discharges
and arcing
Methane (CH4): generated by relatively low elevated
temperatures (150 C).
Acetylene (C2H2): generated by arcing.
Ethane (C2H6): generated by high temperatures
(<300 C)
Ethylene (C2H4): generated by high temperatures
(>300 C)
Carbon Monoxide (CO): generated by oxidation of
cellulose insulation
Carbon Dioxide (CO2): generated by oxidation of
cellulose insulation
Example:
Gas
Concentration in ppm
H2
28
O2
173831
N2
593952
CH4
C2H4
C2H6
C2H2
C3H6+C3H8
CO2
615
CO
124
Permissible Limits:
transformer
In your Transformer none of the above limit is exceeded.
If anything exceeded, then we can go for analysis of fault.
Normal
Modest Concern
H2
100
101-700
Major
Concern
Imminent
Risk
Transformer
Results as
mentioned
above
701-1800
>1800
28
CH4
C2 H
C2 H
50
121-400
401-1000
>1000
36-250
51-80
>80
50
51-100
101-200
>200
50
66-100
101-150
>150
351-570
571-1400
>1400
124
2500-4000
4001-10000
>10000
615
C2 H 6
CO
200
CO2
5000
Remarks:
Normal:
In this condition it is stated that below this level indicates that the transformer is
Modest Concern:
Within this range indicates greater than normal combustible gas concentrations.
Any individual
investigated.
Check either any trend is present or not.
combustible
gas
exceeding
specified
levels should
be
Major Concern:
immediately.
Take immediate action to establish a trend, as faults are probably present.
Imminent Risk:
Within this range indicates excessive decomposition of Beta Fluid and cellulose.
Continued operation could result in failure of the transformer.
Our Results:
The results shown here illustrates that the transformer is healthy and is in proper
working condition.
None of the limit is exceeded, so there is no need to go for the analysis of the
fault.
The following examples are extreme but serve to illustrate how the dissolved gas-in-oil test can be used
to highlight active problems.
EXAMPLE 14
The utility suspected that the magnetic shunt pads attached to the inside of this transformer tank had
come loose and were either touching the core (layered steel structure around which the copper winding is
installed) or were coming very close. The result was intermittent unintentional core grounding and stray
flux causing localized overheating of the oil.
EXAMPLE 25 It was suspected that a single line to ground through-fault caused the failure of this
transformer. The fault was of enough energy to destroy one of the windings. Acetylene was a predominant
gas possibly indicating that arcing may have occurred. The acetyleneto-ethylene ratio indicated the
problem could be either high temperature overheating of the oil, arcing or both. The problem was likely in
the winding because it involved cellulosic materials, as witnessed by the comparatively high carbon
monoxide and carbon dioxide concentrations.
EXAMPLE 35 A technician noticed that this transformer was enveloped in a cloud of steam during a
rainstorm. This prompted an investigation where it was found that the temperature indicator pegged. It
was estimated that the temperature in the unit had been greater than 200C. It was discovered also that
the unit became highly overloaded during some switching functions due to current imbalances in the three
phases. The condition probably existed on and off for two years. An internal investigation found the
cellulosic paper used as an insulant was brittle and crumbly. Again, the key gas indicators for this
condition were carbon monoxide and carbon dioxide.
Oil testing is an important part of a utilitys electric apparatus condition assessment. As these cases
illustrate, dissolved gas-in-oil analysis is the most important diagnostic test for detecting a wide range of
problems
Hydrogen
H
Status
Methane
CH4
Acetylen Ethylen
Carbon
Ethane
e
e
monoxide
C2 H
35
C2 H
50
C2 H6
65
Carbon
dioxide
CO
CO2
350
2500
Normal
100
120
Modest
concern
101-700
121-400 36-250
Major
Concern
701-1800
4011000
51-80
101-200
101150
571-1400
4001-10000
Imminent
Risk
>1800
>1000
>80
>200
>150
>1400
>10000
2500-4000
__________________
Fault Gases:
Since these gases can reveal the faults of a transformer, they are known as "fault
gases".
http://www.aunblock.pk/browse.php?u=O%2B8ZmSVMS9ju
%2F5IY62tXxrkNPCtfWhbDwwgx9S7t%2Bk2D9tJMHEQp&b=29
Sampling Equipments
Sampling Flask:
Lid of the flask has the rings that are fixed between the glass and the plunger to
covered properly
Sampling Rack:
Used to hold the sampling flasks
It has a clip and tubing and at the back it has a wrench to hold the gas cylinders
Part 2:
How to do Sampling:
Remove the black vinyl cap and attach tygon tubing
Start the CO2 gas to flow
Insert the tubing from the cylinder into the flask
Flush the area between the o-rings with CO2 la
The present maintenance trend is to reduce cost, which in some cases means
lengthening the intervals of time to do maintenance or eliminating the
maintenance completely.
The utility, or company, realizes some savings on manpower and material by
lengthening the maintenances cycle, but by doing this, the risk factor is
increased.
A few thousand dollars for a maintenance program could save your utility or
company a half-million dollar transformer.
Inspection:
The volts per turn available in large transformers is quite high and hence a
change of even one turn on the LV side represents a large percentage change in
the voltage.
Also the LV currents are normally too large to take out the tapping from the
windings. LV winding being the inner winding in a core type transformer adds to
the difficulty of taking out of the taps.
Hence irrespective of the end use for which tapping is putt, taps are provided on
the HV winding.
Buck-Boost Arrangement:
In this arrangement the tap positions are changed when the transformer is taken out of
the circuit and reconnected.
b) The load is still connected to the transformer or On Load Tap Changer (OLTC):
In this arrangement taps are changed without the interruption of the load current
As there is no permission of switching off the transformer during tap changing. The
tapping arrangement is placed in separate diverter tank attached to electrical power
transformer main tank.
Inside this tank, the tap selectors are generally arranged in a circular form. The diverter
switches have contacts operating in rapid sequence with usually four separate make and
break units.
This method employs an auxiliary reactor to assist tap changing. The reactor has a
center tapped winding on a magnetic core.
The two ends of the reactor are connected to the two bus bars to which tapping
switches of odd/even numbered taps are connected.
When only one tap is connected to the reactor the shorting switch S is closed minimizing
the drop in the reactor.
The reactor can also be worked with both ends connected to two successive taps. In that
case the switch S must be kept open.
The reactor limits the circulating current between the taps in such a situation. Thus a
four step tapped winding is used for getting seven step voltage on the secondary (see
the table of switching).
Tap
1
Switches Closed
1,s
1,2
2,s
2,3
3,s
3,4
4,s
4,5
5,s
Major Objection:
The major objection in this scheme is that the reactor in the circuit is always generating extra
loss.
In order to maintain the continuity of supply the primary winding is split into two parallel
circuits each circuit having the taps as shown in Fig. 44.
Two circuit breakers A and B are used in the two circuits. Initially tap 1a and 1b are
closed and the transformer is energized with full primary voltage.
To change the tap the circuit breaker A is opened momentarily and tap is moved from 1a
to 2a. Then circuit breaker A is closed.
When the circuit A is opened whole of the primary current of the transformer flows
through the circuit B.
A small difference in the number of turns between the two circuit exists. This produces a
circulating current between them.
Next, circuit breaker B is opened momentarily , the tap is changed from 1b to 2b and the
breaker is closed.
In this position the two circuits are similar and there is no circulating current.
Note: The circulating current is controlled by careful selection of the leakage reactance.
Generally, parallel circuits are needed in primary and secondary to carry the large current in a
big transformer. Provision of taps switches and circuit breakers are to be additionally provided to
achieve tap changing in these machines.
In this case a separate transformer is used to buck/boost the voltage of the main
transformer. The main transformer need not be having a tapped arrangement.
This arrangement can be added to an existing system also.
Fig. 42 shows the booster arrangement for a single phase supply. The reverser
switch reverses the polarity of the injected voltage and hence a boost is
converted into a buck and vice versa.
The power rating of this transformer need be a small fraction of the main
transformer as it is required to handle only the power associated with the injected
voltage.
Note: One precaution to be taken with this arrangement is that the winding must not be
open circuited. If it gets open circuited the core (B in fig) gets highly saturated.
In spite of the small ratings and low voltages and flexibility, this method of voltage
control costs more mainly due to the additional floor space it needs. The methods of
Moving Coil Voltage Regulators:
Voltage regulation discussed so far basically use the principle of tap changing
and hence the voltage change takes place in steps.
Applications like a.c. and d.c. motor speed control, illumination control by
dimmers, electro-chemistry and voltage stabilizers need continuous control of
voltage. This can be obtained with the help of moving coil voltage regulators.
Fig. 45 shows the physical arrangement of one such transformer. a, b are the two
primary windings wound on a long core, wound in the opposite sense. Thus the
flux produced by each winding takes a path through the air to link the winding.
These fluxes link their secondaries a2 and b2.A short circuited moving coil s is
wound on the same limb and is capable of being held at any desired
position.This moving coil alters the inductances of the two primaries.
The sharing of the total applied voltage thus becomes different and also the
induced emf in the secondaries a2 and b2. The total secondary voltage in the
present case varies from 10 percent to 20 percent of the input in a continuous
manner.
The
turns
ratios
of
a1:a2
and
b1:b2
are
4.86
and
10.6
respectively.5/4.86+95/10.6= 10% when s is in the top position. In the bottom
The minimum step size of voltage change obtainable is the voltage across a
single turn.
The conductor is chosen on the basis of the maximum load current on output
side. In smaller ratings this is highly cost effective.
Two winding arrangements are also possible. The two winding arrangement
provides electrical isolation also.
Electrical Maintenance:
(a)
(c)
(b)
(d)
Preventive maintenance:
We can replace the oil filled transformers in most of the substations to avoid the
transformer failure for at least ten years.
Operational maintenance:
Corrective maintenance:
Inspection
Frequency
Item to be
inspected
Inspection Notes
Hourly
Hourly
Ambient
Temperature
Ambient
Temperature
Hourly
Hourly
Oil
Temperature
Load ampere
Hourly
Voltage
Daily
Oil level in
transformer
Daily
Daily
Oil level in
bushings
Leakage of
water into
cooler
Replace if crack or
broken
Daily
If Broken
10
Daily
Relief
diaphragm
Dehydrating
Breather
11
Quarterly
Bushing
12
Quarterly
Oil in
Transformer
13
Quarterly
Cooler for
Check that
temperature rise is
reasonable
Lubricate bearings
Actions required if
abnormal
Conditions
Shutdown the
transformer and
investigate either
persistently higher
than normal
bearing
motors and
operating
mechanisms
worn contacts or
other parts
14
Half Yearly
Oil Cooler
15
Half Yearly
Yearly
Filter or replace
16
17
Yearly
Oil in
Transformer
Oil filled
bushing
Gasket joints
18
Yearly
Cable Boxes
19
Yearly
20
Yearly
SurgeDiverter
s and Gaps
Relays,
Alarms and
their circuits
21
Yearly
22
a) 5 Yearly
b) 7-10
Yearly
Filter or replace
Clean or replace
Earth
Resistance
a )1000 to
3000 kVA
Overall inspection
including lifting of
core and coils
Clean the
components and
replace fuses and
contacts if
necessary. Change
the settings if
necessary
Take suitable actions
if resistance is high
Wash by hosing
down with clean dry
oil
b ) above
3000kVA
Overall inspection
including lifting of
core and coils
Wash by hosing
down with clean dry
oil
S.No
.
Inspection
Frequency
Item to be
inspected
Inspection Notes
Hourly
Load Current
Hourly
Voltage
Daily
Dehydrating
Breather
Monthly
Oil level in
Transformer
Check the
transformer oil level
Quarterly
Bushings
Half Yearly
Non-Conservator
tank
Yearly
Oil in transformer
Yearly
Earth Resistance
Yearly
Relays ,Alarms
and their circuits
Actions required if
abnormal
Conditions
If Silica Gel is
pink ,Change by
spare charge.The
old charge may be
reactivated for use
again
If low top up with
dry oil. Examine
transformer for
leaks
Clean or replace
Improve
ventilation ,Check
oil
Take suitable
actions to improve
quality of oil
Take suitable
actions if Earth
Resistance is high
Clean the
components and
replace contacts
Check relay
accuracy etc.
10
2 Yearly
11
5 Yearly
Non Conservator
Transformers
Internal inspection
above core
Overall inspection
including lifting coils
and fuses if
necessary. Change
the setting if
necessary
Filter oil regardless
of conditions
Wash with clean dry
oil
NOTE:
One of the reasons for failure of distribution transformers is the supply of sub-standard
transformers, which is a result of improper vendor rating and lack of routine test prior to
dispatch by the manufacturer & issue for use. It is therefore proposed as follows:
Maintenance Tests:
Two important tests that could prevent field failure are:
1. Using an infrared scan on a transformer could locate hot spots.
By using this test we could detect system overloads, loose defective
components and damaged switchgears
An infrared camera is used to detect the hotspots
Hotspots are easily eliminated before before they cause failures
IR Thermography technique is used in these cameras
IR Thermography Inspection helps:
Reduce downtime
Lower risk