Professional Documents
Culture Documents
Project Management
Pre-Project and
Project Initiation
Phase
J.S.Javier October 2014. All Rights Reserved.
Project Beginnings
Business Case
Definition
Justification
- 2-
Definition
Execution
Closeout
Idea
Business
Case
Phase 1
Phase 2
Phase N
System
Development Life
Cycle
Authorization
Pre-Project
Project
- 3-
- 4-
- 5-
- 6-
- 7-
- 8-
- 9-
F1
F2
Ft
Time Period
PV1 = F1 / (1 + r) 1
PV2 = F2 / (1 + r) 2
PV t = Ft / (1 + r) t
Present
J.S.Javier October 2014. All Rights Reserved.
- 10-
- 11-
Sample Problem 1
ABC Company is evaluating two IT projects, each with the projected cash
flows as shown below :
Year
1
2
3
4
5
Project 1
14,000
14,000
14,000
14,000
14,000
Project 2
28,000
12,000
10,000
10,000
10,000
Project 1 will require an initial investment of $42,000, while Project 2 requires $45,000.
If the cost of capital to ABC is 10%, which project will they prioritize ? Compare using
the NPV method as a basis for your recommendation.
J.S.Javier October 2014. All Rights Reserved.
- 12-
- 15-
Payback Period
The exact amount of time required for the project
to recover its initial investment as calculated
from the cash inflows
For annuity cases, this can be found by
dividing the initial investment by the annual
cash inflow
For mixed stream, the yearly cash inflows
must be accumulated until the initial
investment is recovered
The elapsed time required for accrued benefits
to overtake accrued and continuing costs
J.S.Javier October 2014. All Rights Reserved.
- 16-
- 19-
- 20-
Project Charter
- 21-
Project Charter
- 22-
- 23-
- 24-
- 25-
Project Boundaries
- 26-
Organizational Structures
Describes the set-up of project units in an
organization and establishes the authority
of the project manager
It constrains the availability or terms under
which resources become available to the
project
- 27-
Functional Manager
Functional Manager
Project Coordination
Functional Manager
Staff
Staff
Staff
Staff *
Staff *
Staff
Staff
Staff *
Staff *
Characteristics :
Each unit is responsible for carrying out a
specific, similar set of activities
- 28-
Project Organization
Project Manager
Chief Executive
Project Coordination
Project Manager
Project Manager
Staff
Staff
Staff
Staff
Staff
Staff
Staff
Staff
Staff
Characteristics :
Each unit operates to complete a different project
Some organizations have separate support units and systems
per project unit (e.g. HR and Purchasing), while others have
common support units and systems
J.S.Javier October 2014. All Rights Reserved.
- 29-
Functional Manager
Project Coordination
Functional Manager
Functional Manager
Staff *
Staff
Staff
Staff
Staff *
Staff
Staff *
Staff *
Staff *
Characteristics :
Project team composition comes from different functional units
Maintains many of the characteristics of a functional organization
Project Manager role is more of a coordinator or expediter than that of a
manager
J.S.Javier October 2014. All Rights Reserved.
- 30-
Functional Manager
Project Coordination
Functional Manager
Functional Manager
Staff *
Staff
Staff
Staff
Staff *
Staff
Project
Manager
Staff *
Staff *
Characteristics :
Project team composition comes from different functional units
A member under a functional unit has an official management position with
low to moderate authority as a project manager
J.S.Javier October 2014. All Rights Reserved.
- 31-
Manager of Project
Managers
Functional Manager
Functional Manager
Functional Manager
Project
Manager
Staff *
Staff
Staff
Project
Manager
Staff
Staff *
Staff
Project
Manager
Staff *
Staff *
Staff *
Project Coordination
Characteristics :
Project team composition comes from different functional units
Maintains many of the characteristics of a project organization
A member under a functional unit has a project management position with
moderate to high authority for a project manager
J.S.Javier October 2014. All Rights Reserved.
- 32-
- 33-
Relative Authority of PM
- 34-
IT Manager
Project Manager
QA Team
Counterpart IT Staff
Systems Analysts
System Owner
Support Team
Programmers
Technology Group
- 35-
- 37-
- 38-
- 39-
Characteristics of Stakeholders 1 of 2
May exert influence over the
project, its deliverables, and
the project team members
May be internal or external
to the project
May have varying levels of
responsibility and authority
when participating on a
project and these can
change over project lifetime
May have adverse impact
on the project objectives
J.S.Javier October 2014. All Rights Reserved.
- 40-
Characteristics of Stakeholders 2 of 2
Stands to gain or lose through
the success or failure of the
project
Provides funding for the project
Has invested resources in the
project
Participates in (works on) the
project
Is affected by the outputs or
outcomes of the project
Is in the chain of accountability
- 41-
Chain of Accountability
A hierarchy of people who signs
off to approve the project in some
ways and are viewed as taking on
some accountability for the project.
As such, they may see themselves as
stakeholdersand feel that they have
the right to exert influence on the
project, if they sense the need.
- 42-
- 43-
- 46-
- 47-
- 48-
- 49-
Assessment Information
Major Requirements, Main Expectations, Potential
Influence in the project, Phase with most interest
Stakeholder Classification
Internal / External, Supported / Neutral / Resistor,
etc.
PMBOK Guide, 4 Ed., 2008, Sec. 10.1.2, p. 250
th
- 50-
- 51-
- 52-