Professional Documents
Culture Documents
9.
9.1
Introduction
Scope Definition and Management: The scope statement defines what is and what not part of the
project is. The Scope Management Plan outlines the key activities for managing the scope
throughout the duration of the project. This area of focus also includes the change management
process.
Work Plan/Schedule and Schedule Management: The project work plan/schedule identifies the key
tasks, activities, timelines, and resources defined for project execution. The Schedule Management
Plan identifies the activities for managing the schedule throughout the duration of the project.
Directing and Managing Project Execution: This includes Project Management Office (PMO)
activities to oversee project execution, as well as the coordination of delivery across various teams
and work streams.
Monitor and Control Project Work: The process of tracking, reviewing, and regulating the progress
to meet the performance objectives defined in the project management plan.
Perform Integrated Change Control: Closely related to scope management, this is the process of
reviewing all change requests, approving changes, and managing changes to the deliverables,
organizational process assets, project documents, and project management plan.
Close Project or Phase: The process of finalizing all activities across all of the project management
processes to formally complete the project or phase.
9.1.1
Purpose
Page 9-1
application of multiple stakeholders and project management plans, including risk and issue, change,
schedule, and communications management.
The goal of the Integration Management Plan is to establish a consistent, integrated process for initiating,
planning, executing, controlling, and closing the project. Effective integration management will require
that the Business Operations Solution (BOS) project management team achieve the following objectives:
1. During project startup, tailor, maintain, and execute project plans and processes
2. Establish, clearly communicate, and maintain the projects organizational structure
3. Involve all relevant project stakeholders (internal and external) in the definition, maintenance, and
execution of the projects management processes
4. Establish and maintain the projects technical and administrative environment
5. Integrate and coordinate all project plans and processes
6. During project shutdown, execute the projects plans and processes for closure activities
9.1.2
Scope
The scope of the Integration Management Plan encompasses all project management processes and
activities. As such, the execution of this plan spans the entire duration of the project from startup to
closure, applies to all project staff, and includes most project activities, including but not limited to the
following:
Requirements Specification
Design Specification
Software Development
Technical Documentation
Data Management
Page 9-2
9.1.3
Definitions
This section lists terms and acronyms specifically applicable to this document.
Table 9-1: Integration Management Terms and Acronyms
Term/Acronym
Definition
1.
BOS
2.
CCB
3.
4.
5.
PMP
6.
PMO
7.
Quality Management
8.
Status Report
Scope Statement
Work Plan
9.
10.
Page 9-3
9.2
The process steps for Integration Management align closely with A Guide to the Project Management
Body of Knowledge (PMBOK Guide) Fourth Edition process groups of initiate, plan, execute, control,
and close.
With the successful integration of administrative, supporting, and delivery processes, the following
activities may be ensured:
Reinforcing ownership and accountability at all requirement levels and making sure project conforms
to schedule and budget
Establishing effective identification and reporting metrics that support decision-making and corrective
action planning
Page 9-4
9.3
These plans, along with the baseline schedule and cost model are stored in the projects SharePoint
repository.
Continually monitoring and controlling scope according to the Scope Management Plan
Tracking and reporting status regularly according to the commitments within the Communication
Management Plan
Preparing and submitting to the Exchange the deliverables needed to implement the BOS. These
deliverables are set forth in the project schedule, which captures and enables tracking of the progress
of the project
Staffing, training, and managing team members in accordance with the Staffing Management Plan
Generating project data for status reporting and metrics
Managing requirements definition, modifications, and adherence with respect to the design and
development of the BOS in alignment with the Requirements Management Plan
Issuing and completing change requests according to the Change Management Plan
Managing risks and issues proactively per the Risk and Issue Management Plan
Evaluating project progress and collecting lessons learned at regular intervals
Page 9-5
Monitoring the progress of planned and unplanned work according to the Schedule Management Plan
and schedule
9.3.7
Outputs
Status reports
Change requests
9.4
The Xerox PMO and Quality Management (QM) team will have primary responsibility for ensuring the
project teams adherence to the expectations set forth in this plan. The Xerox PMO is responsible for
coordinating the project management activities referenced in this plan and will perform the duties noted in
the Roles and Responsibilites section below. The Xerox QM will provide guidance and feedback to the
PMO and other project stakeholders to help ensure all project lifecycle phases are delivered in
accordance with established standards, Exchange staff expectations, and contractual requirements. The
QM team will perform these duties in alignment with the responsibilities denoted below. In addition, the
QM team will execute quality control and assurance activities as described in chapter 13 of the Project
Management Plan Quality Management.
Page 9-6
The Xerox PMO will institute a variety of control mechanisms to facilitate project integration and help
ensure the success of the BOS effort. These controls include a wide range of items and mechanisms
including:
Status Reports
Status Meetings
Schedule Forecasts
Staffing Forecasts
Financial Forecasts
Financial Controls and Procedures (e.g., time reporting, budget, budget to actual reports)
Scope Baseline
9.5
To manage and support the integration management processes and activities for the Exchange BOS
Project, a variety of individuals and roles will be involved. The following sub-sections identify the roles, as
well as detailed responsibilities.
9.5.1
Roles
Support, execution, and oversight of integration management processes and activities include a wide
spectrum of roles, including the following.
Xerox PMO
Page 9-7
Workstream Leads
9.5.2
Responsibilites
To complete the activities and processes in this management plan, the following responsibilities must be
assumed by the individuals and teams identified in the Roles section above. The Executive Steering
Committee determines how responsibilities are allocated to project resources and the PMO updates the
roles, responsibilities, and deliverables accordingly.
Table 9-2: Integration Management Responsibilities by Role
#
1.
2.
Role
Executive Steering
Committee/Sponsors
Xerox Project
Management Office
Role
3.
4.
Independent Verification
and Validation (IV&V)
Team
Page 9-9
Role
5.
Xerox Quality
Management Lead and
Team
6.
7.
Workstream Leads
9.6
The following table identifies the applicable tools and methods that will be used to execute project
management and integration activities.
Table 9-3: Integration Management Tools
Tool/Method
1.
Microsoft Office
SharePoint
Description
A repository used to retain artifacts. All stakeholders with
authorized access to the projects SharePoint site can
review the content of the projects artifacts.
Page 9-10
Tool/Method
2.
Microsoft EPM
3.
Microsoft Word
4.
Risk/Issue Log
5.
A SharePoint database which captures open items or todo items which are not risks or issues.
6.
Status Report
7.
Deliverable Expectations
Documents
8.
Project Checklists
9.
Project Templates
10.
9.7
Description
Standards
The following section identifies the applicable standards applied to the integration management process
for the Exchange. Adhering to these standards and diligently performing the activities they reference will
help to ensure effective integration across the Exchange BOS Project.
Page 9-11
Standard
Plan Reference
Professional Responsibility
Professional Responsibility
Page 9-12
Standard
Plan Reference
3.2 Training
See Project Start-up Procedure
Estimate the project effort and cost for the work products
and tasks based on estimation rationale.
Page 9-13