OH Asset Network QA Checking Process- Under Stage-2:


All feature layers and their respective fields should be
compared with Standard PGDB.
Give space between values and voltage where ever its
applicable i.e. HV side, LV side. Voltage rating
All the Data/deliverable should be Zone 44 only.
Consistency should be checked in all feature classes and
all fields.
Substation code, Substation name and Feeder code,
Feeder Name should be entered where ever applicable,
should maintain consistency while entering.
DISTRIBUTION TRANSFORMER
1. The following variables in the feature class
2. Feature Attribute Table (FAT) Consistency to be
maintained:
a. DT_Code: Check for duplicates and blank.
b. DT_Name: Spelling Consistency and Check for
duplicates and blank.
c. Voltage: To be abbreviated in the Heading(label of the
field) voltage (V)
d. Step, Adapted Tap, Max Tap and Min Tap to be in
Numeric.
e. If Availability of Capacitor is yes then check the KVAr
Rating of the Capacitor Bank, If No need to be update
as NA.

Navayuga Infotech
Page 1 of 9

Proprietary and Confidential

RAPDRP Tamil Nadu ||

f. If Number of AB Switches is available than check the


AB Switch Voltage and AB Switch Type.

3. Cross checking with DT FAT with Distribution Structure FAT


a. DS code in DT FAT should be same as DS code in DS
FAT.
b. DT name in DT FAT should be same as DS name in DS
FAT for corresponding DTs.

DISTRIBUTION STRUCTURE (DS)

1. Cross checking with Distribution Structure FAT with


Distribution Transformer FAT.
a) DT1_Code should be same as DT_Code in DT FAT.
b) Classification should be same as Tran Mount in DT
FAT.

2. If No. Of Distribution Transformers is updated then check


the transformers is available on that structure or not and
Check the DT Codes availability of the Transformers.
3. If No. Of. AB Switches is available then check the AB
Switch Voltage and AB Switch Type.

Navayuga Infotech
Page 2 of 9

Proprietary and Confidential

RAPDRP Tamil Nadu ||

POLES
1. Pole number should not be duplicated.
2. Check for pole Type information with the asset design
3.
4.
5.
6.

7.
8.

document.
If pole classification is HT or LT then only corresponding
network lines should be connected.
If pole classification is both then both HT and LT network
lines can connect.
Height and Pole_Loc should be verified.
If Street Light updated as No, Then Type of Light field
should be NA, If Street Light updated as yes then Type of
Light should be updated as mentioned in possible values.
Type_Supp can only have STAY WIRE or STUD or NO.
HT_LT_Shac should be YES/NO.
HT Line

9. Classification must be HT/ EHT.


10. Line_Type should be OH or UG.
11. Check for voltage values and its flow.
12. Pole from and Pole To fields should be updated.
13. Phase_Wire should be 3 phase.
14. Depending on the Condu_Type and Condu_Name, size

should be checked as per asset design document.


15. Check the OH Line Height in meters for OH conductors
only, and check for depth if any UG conductors.
16. In general OH Line Height in meters on any pole will be
Pole height-1.
LT Line

17. Voltage should be either 230 V or 440 V. depending on the

line connected.
18. Pole from and Pole To fields should be updated.

Navayuga Infotech
Page 3 of 9

Proprietary and Confidential

RAPDRP Tamil Nadu ||

19. Phase should be R/Y/B or RYB depending on the Phase of

the conductor.
20. Depending on the Condu_Type and Condu_Name, size
should be checked as per asset design document.
21. Check the OH Line Height in meters for OH conductors
only, and check for depth if any UG conductors.
22. In general OH Line Height in meters on LT pole will be Pole
height-1
23. For BOTH poles it will be pole height-2.
24. DT_Name and DT_Code should be entered in same
manner as in DT FAT and the DT wise network also
verified.

BUSBAR

25. Type should be INDOOR/OUTDOOR.


26. Voltage should be corresponding connected HT_Line

voltage.
IMPLANTLINE
27. Type should be HT or LT.
28. Status should be SERVICE or NOT IN SERVICE.

CAPACITOR

29. Check for KVAR value entered.


30. Check Phase and voltage values.
31. Status should be SERVICE or NOT IN SERVICE.

FUSE
32. Voltage should be corresponding Connected Lines voltage.
33. Type should be HG FUSE if on HT side, and FEEDER FUSE if

on LT side.
34. Phase should be RYB or R/Y/B depending on connected
lines.
Navayuga Infotech
Page 4 of 9

Proprietary and Confidential

RAPDRP Tamil Nadu ||

35. Status should be SERVICE or NOT IN SERVICE.

SWITCH
1. Type should be HT or LT.
2. Voltage should be corresponding Connected Lines voltage.
3. Status should be OPEN or CLOSE.
4. In general switch status will be CLOSE when placed on HT
lines it will be in OPEN state when placed on LT lines.
5. When switch placed to avoid the looping conditions, it
should be in OPEN state, weather it is placed on HT line or
LT line.
DISTRIBUTION TRANSFORMER ENERGY METER (DTEM)
6. Check for DT code entered as same as in DT FAT.
7. CT_Rat_Avl, CT_Rat_Adp, STR_of_CT is need to be updated.
8. Meter_S_No should be entered and not to be duplicated.
9. TOD slots should be a numeric value.
10.

Meter seal details should be GOOD or TAMPERED.

11.
Current, Voltage, Power_Fact, Frequency need to be
entered.
12.
KW, KVAr, Kwh, KVAh should be entered if Meter is in
working condition.
13.
Physical Status should be SERVICE or NOT IN
SERVICE.

RING FENCE METER (RFM)


14.

RFM_Code should be entered.

Navayuga Infotech
Page 5 of 9

Proprietary and Confidential

RAPDRP Tamil Nadu ||

15.

DS code should be entered same as in DS FAT.

16.
PT_Rat_Avl, PT_Rat_Adp, CT_Rat_Avl, CT_Rat_Adp
should be updated.
17.
Meter_Type, Meter Make, Meter Model, Meter_DOM,
Meter_P_O should be entered if available.
18.
Current, Voltage, Power_Fact, Frequency should be
entered.
19.
KW, KVAr, Kwh, KVAh should be entered if Meter is in
working condition.
20.

Connection type should be OH/UG.

21.
Physical Status should be SERVICE or NOT IN
SERVICE.

SPATIAL CHECKINGS on Assets


Check the direction of Flow for both HT and LT lines
For HT lines the flow direction should be from SS to
Transformer.
For LT lines flow direction should be distributed from
Transformer.
Check DT arrangement.
Check for spatial duplicates (Duplicate objects).
Check the Lines passing through the poles based on pole
classification.
Check weather pole height and OH_Ht_in_m for LT and HT
lines are updated correctly.
Check weather DT code is entered correctly or not for the
LT lines connected to the DTs, by selecting the LT lines
based on DT code
Check for double circuits, by cross checking with the
Photos available.
Check for edge matching with adjacent feeders.

Navayuga Infotech
Page 6 of 9

Proprietary and Confidential

RAPDRP Tamil Nadu ||

Check for Positional accuracy errors w.r.t Geo-referenced


image.
Check for topology errors,
Check for Geometry errors
Need to place switch to avoid looping between the two
different
Check Voltage flow and Phase and wire flow for both HT
lines and
LT lines are needed to be match.

Consumers
Navayuga Infotech
Page 7 of 9

Proprietary and Confidential

RAPDRP Tamil Nadu ||

For the entire consumers, all the mandatory fields need be


filled appropriately.
Street Light Meters/Traffic signal meters are part of the LT
Consumers only.
All the LT consumers should be connect to the LT network
only.
LT Consumers

o Pole ID and DT_Code fields need to be updated.


o Divi_Code , Sec_Code, Dist_Code, Service No is need to be
entered.
o Service No should be combination of Sec_Code+
Dist_Code+ Section number, must be enter.
o Mobile no and LL numbers need be maintained
consistency.
o Service Date is to be entered.
o Consu_Name, Bill_Add is need to be filled accordingly
(Floor_No, Street/Area Name,etc).
o Tariff Code is need to be entered as per the Tariff codes
described in the Document.
o Phase to be entered.
o Sanct_Load, to be entered if possible.
o Meter_S_No, Meter_Loc, Voltage, Status to be updated.
LTCT consumer

o Pole ID and DT_Code fields should be added and updated.


o Divi_Code, Sec_Code, Dist_Code, Service No is need to be
entered.
o Service No should be combination of Sec_Code+
Dist_Code+ Section number, must be enter.
o Mobile no and LL numbers need be maintained
consistency.
Navayuga Infotech
Page 8 of 9

Proprietary and Confidential

RAPDRP Tamil Nadu ||

o Service Date is to be entered.


o Consu_Name, Bill_Add is need to be filled accordingly
(Floor_No,Street/Area Name,etc).
o Tariff Code is need to be entered as per the Tariff codes
described in the Document.
o Phase to be entered.
o Sanct_Load, to be entered if possible.
o Meter_S_No, Meter_Loc, Voltage, Status to be updated.
o Indust_Na need to be entered.
o Phy_Status need to be updated.

Navayuga Infotech
Page 9 of 9