You are on page 1of 40

Carolina

The UNIVERSITY of NORTH CAROLINA at CHAPEL HILL

CAMPUS MASTER PLAN UPDATE


Approved March 22, 2006

Carolina

The UNIVERSITY of NORTH CAROLINA at CHAPEL HILL

TABLE OF CONTENTS
Executive Summary
3
2001 and 2006 Plans
6
Campus Master Plan Update
8

North District
8

Southeast District 10

Southwest District 12

Open Space Network & Pedestrian Circulation 14

Transportation System 18

Utilities
23

Area Calculations for Proposed Buildings
26

North District
26

Southeast District
28

Southwest District
32

Campus-wide Calculations
35

Pedestrian Bridges
35
Acknowledgements
36

CAMPUS MASTER PLAN UPDATE


Approved March 22, 2006

The UNIVERSITY of NORTH CAROLINA at CHAPEL HILL

Caudill Laboratories encourage interdisciplinary collaboration.

Arts Common will better connect UNC to Chapel Hill.

Hinton James North is one of several new residence halls in the


south campus.

Rams Head Center is home to a mix of student amenities.

CAMPUS MASTER PLAN UPDATE

Executive Summary
In 2003, the University of North Carolina at Chapel Hill initiated the process to update the 2001 Campus
Master Plan. In the course of updating the 2001 Plan the University discovered that approximately
fifty percent of the sites proposed by the Plan were under construction or in design and planning. The
University is constructing over six million square feet of new buildings and rehabilitating nearly a million
square feet of existing space. This significant implementation of the 2001 Plan is made possible by funding
from the North Carolina Higher Education Bond Referendum and University based funding sources.
The 2001 Master Plan was developed collaboratively by faculty, staff, students, administrators, and campus
neighbors both immediate and regional, and these four principles guided their efforts:
Support the Universitys mission.
Export qualities of McCorkle and Polk Places to the south campus.
Enhance the Universitys intellectual climate.
Support local and regional planning strategies.
Highlights of the Universitys progress in implementing the 2001 Campus Master Plan include:
Arts Common: The first phase of this project is already under construction. Arts Common will better
connect UNC to downtown Chapel Hill, provide much needed updated performing arts space, and create
new open space in the northwest quadrant of campus.
Science Complex: The first phase of this project is complete; Caudill Laboratories and Chapman Hall
accomplish a major objective of the Master Plan by encouraging collaboration among the many disciplines
across the College of Arts and Sciences. These two laboratory buildings add 270,000 gross sqaure feet of
wet and dry laboratory space, offices, and classrooms.
Rams Head Center: Rams Head is conveniently located for students living in the north and south
campuses and is home to a mix of amenities where they can eat meals, buy groceries, or exercise.
A key design feature of the center is a green roof atop a 700 space parking deck. The green roof helps
to manage stormwater on the site, and is also a plaza that creates a crucial link in the pedestrian route
between the north and south campuses.
Campus Infrastructure Improvements: Most of the improvements recommended in the 2001 Plan have
been implemented. Expansion of campus utilities, such as new steam and chilled water plants, enables the
campus to better accommodate demands of new and renovated buildings. The addition of four parking
decks allows reclamation of surface parking lots for academics and open space.

The UNIVERSITY of NORTH CAROLINA at CHAPEL HILL

The green roof at Carrington Hall is a favorite place to study and helps manage stormwater runoff.

Historic buildings like the Campus Y are a legacy for


the future.

Memorial Grove is one of the many open spaces that have been improved since 2001.

CAMPUS MASTER PLAN UPDATE

South Campus: Additional student housing has been built in the south campus - nine new residence
halls and nine new married student apartment buildings. Not only do these buildings bring more students
to this part of campus, but they better define the streetscape and open spaces of the south campus making
it friendly to pedestrian traffic. Scheduled to be completed in 2007, the new Student Academic Services
Building will bring student services and a major new plaza for student activity to the heart of the
south campus.
Campus Historic Preservation: A commitment to preserve historic buildings as a legacy for future Carolina
students has resulted in restoration and re-use of several well-loved buildings. One example is the Campus Y.
Long underutilized and once slated for demolition, this building has been extensively renovated and now
offers a faculty-student lounge, seminar rooms, University and student offices, as well as a coffee shop.
Environmental Strategy: Growing awareness of sustainability issues has led to a closer examination of energy
and resources used throughout the campus. New initiatives since 2001 include the Sustainability Office,
stormwater management program, tree replacement, water re-use, thermal storage for chilled water, free public
transportation, re-cycling, and additional on-campus student housing. The Campus Sustainability Report
includes more information on this topic and is available on-line:
http://sustainability.unc.edu/office/News/UNC%20Campus%20Sustainability%20Report%20%202005.pdf
Open Space Planning: A number of projects that contribute to the improvement of campus open space
are complete or in progress. Construction of Rams Head, Arts Common, Bondurant Hall, Bell Tower,
Student Academic Services, the parking deck at Cobb-Joyner and Global Education each contribute to the
commitment that the University made in the 2001 Plan to create additional open space on the campus.
Through the course of the Campus Master Plan Update the University has confirmed the original tenets of
the 2001 Plan, and recognized that the implementation of the development program has been successful. The
Update also reveals that the development of the campus since 2001 approaches the responsible capacity of the
land. These objectives will support the Universitys mission driven growth:
Build Carefully Capacity on main campus is limited. The remaining growth potential is about four
and a half million gsf. Of that, fewer than ten building sites, totaling less than one million gsf are
unassigned. Best advantage must be made of the remaining opportunities for buildings and parking.
Strategic Renovation Renewal of existing facilities will be required to meet the ongoing needs of
main campus.
South Access Road Main campus growth continues to be concentrated in south campus, and
requires improved access to the area. If financed by public funds, the administrative process for the
necessary south access road is expected to take ten years or more; work must begin now to meet this
future need.
Carolina North This mixed use development is critical to the Universitys future; its development
will ease current space constraints and support new research and business relationships.

The UNIVERSITY of NORTH CAROLINA at CHAPEL HILL

2001 Campus Master Plan

Existing Buildings

Proposed Buildings

0 100 200 400

CAMPUS MASTER PLAN UPDATE

2006 Campus Master Plan

Existing Buildings

Planned Buildings

Proposed Buildings

0 100 200 400

The UNIVERSITY of NORTH CAROLINA at CHAPEL HILL

Campus Master Plan Update


This revised plan for the campus reflects the remarkable strides made toward realization of the 2001 Plan.
Many changes and new ideas have been implemented, and many more are in progress. The campus has
experienced significant, rapid growth over the past five years, but this pace is slowing somewhat to a more
traditional schedule. The many new buildings and additions will facilitate renovation and maintenance of
existing facilities.
Many findings of the Update are consistent with the 2001 Plan, therefore the two documents are meant
to be used together going forward. What follows are highlights of adjustments to the Plan, organized by
district, with attention to key planning issues that arose in the course of the Update.
North District
1. Arts Common
No underground parking deck, instead surface parking will accommodate service, accessibility,
and employees.
2. Porthole Alley
Updated plans reflect changes in program needs and recognize use constraints.
3. Whitehead Hall
Renovation will accommodate Carolina Inn expansion needs.
4. Science Complex
A larger central quad atop an underground science library is planned.
5. Morehead Planetarium and Science Center
Expansion to the north will accommodate visitor needs and engage with Franklin Street.
6. Davie Hall
Building will be demolished and replaced.
7. Student Housing
Reduced pressure for new housing allows preservation of open space southeast of Kenan and
McIver Halls. Site southwest of Cobb Hall developed as a Parking Deck and Chiller Plant, with
recreational open space.
8. Jackson Hall
Plans for renovation and expansion forthcoming.
9. School of Government
Update makes allowance for future expansion.

CAMPUS MASTER PLAN UPDATE

North District

The UNIVERSITY of NORTH CAROLINA at CHAPEL HILL

Southeast District
1) Ridge Road
Streetscape improvements will promote pedestrian safety.
2) Boshamer Field
Renovation and expansion planned to meet program needs.
3) ROTC
Site reserved for future ROTC facility north of Student Academic Services Building on
Ridge Road.
4) Craige Deck
Three additional levels of parking to be added to existing structure.
5) Central Park South
Outline of area has been adapted slightly to reflect some adjacent programming changes.
Open space will be programmed for passive recreation.
6) Tennis Court Area
A deck with tennis courts on top will replace previous design. Courts will connect to open space
at adjacent Hinton James Community.
7) Skipper Bowles Lot
Programming of area has changed based on housing and athletic needs. Structured parking and
academic or office building replace previous design, while maintaining a viable pedestrian route
through the area.
8) Public Safety Building
Public Safety will be relocated from Southwest District to a site adjacent to Manning Drive deck.
9) South Access Road
See Transportation System.
10) Student Housing
New footprints no longer needed adjacent to Carmichael and Hinton James Residence Halls.

10

CAMPUS MASTER PLAN UPDATE

Southeast District

10

10

11

The UNIVERSITY of NORTH CAROLINA at CHAPEL HILL

Southwest District
1) South Columbia Street
Pedestrian safety improvements will support north-south route through campus.
2) Dental Sciences
Two existing buildings to be demolished and replaced. Project includes a pedestrian bridge that
crosses Manning Drive.
3) 2003 Health Care System and School of Medicine Precinct Study
Study issues included the realignment of Mason Farm Road, clarity of visitor circulation and
parking and flexibility and redundancy of vehicle access:
Right-of-way for fixed-route transit continues to be preserved.
New plaza at pedestrian bridge landing at Mary Ellen Jones building will connect existing
research buildings to improved north-south pedestrian corridor.
4) South Access Road
See Transportation System.
5) Bell Tower
Planned roof-top open space will be replaced with open space at grade.
6) Kenan Stadium
Completion of southeast end of stadium for additional seating is planned. Skybox seating will be
introduced above southwest side.
7) Student Health
Renovation considered, but current Taylor Clinic is inadequate; improved facility desired.
Relocation and redevelopment will be in conjunction with UNC Hospitals plans.
8) UNC Hospitals Area
Expansion of Emergency Room access is planned. Redevelopment will be in conjunction with
replacement of Taylor Clinic and potential additions on north side of Hospital.
9) Public Safety Building
To better utilize this building site, the Public Safety Department will be relocated to the Southeast
District.
10) Utility Plant Sites
Site necessary in south campus for additional chiller plant.
Site necessary for reclaimed water tank to accommodate new reuse water system.
11) Campus Support Facility
Site reconfigured to accommodate a support facility.

12

CAMPUS MASTER PLAN UPDATE

Southwest District

11

13

The UNIVERSITY of NORTH CAROLINA at CHAPEL HILL

Open Space Network and Pedestrian Circulation


Open Space Network
Protection and creation of open space was essential to approval of the 2001 Plan. The University has made
significant progress in qualitative improvements to open space through out the campus.
To support quality open space, Chancellor Moeser appointed a task force to inventory and evaluate the
campus landscape. The Landscape Heritage and Plant Diversity Task Force identified and established
guidelines for protection and preservation of heritage trees, significant trees and landmark spaces. The task
forces findings are documented in a written report which also includes landscape design guidelines for new
and renovated spaces and a tree replacement policy, in addition to the tree protection guide-lines already in
place. The final report was reviewed and approved by the Chancellors Buildings and Grounds Committee,
and it is available on-line:
http://www.fac.unc.edu/AboutUs/Grounds/tabid/87/HeritageLandscape/tabid/_83/Default.aspx
A number of improvement projects are complete or in progress. The resulting open spaces from construction
of Rams Head Center, the Science Complex, the Northeast Chiller Plant and Parking Deck, and the Global
Education Building each make a positive difference to the campus - as do renovation of the landscape
around South Building, Gerrard Hall, and Playmakers Theater and new gardens at Memorial, Murphey, and
Saunders Halls. The quality of the open space in and around these projects is dramatically improved, as are
the pedestrian links through them. Other projects that will improve open space that are in planning or under
construction include the Student Academic Services Building, Arts Common, the Bell Tower project, and
Dental Sciences.
Each of these projects has contributed to a bold commitment that the University made in the 2001 Plan to
set aside additional acreage for open space on the campus. The bulk of this commitment will be realized in
south campus in the area currently occupied by Odum Village. The proposed 10 acre park will be larger than
Polk and McCorkle Places combined, and offer relief from the intensity of south campus, as well as storm
water management benefits. The creation of this open space hinges on new construction and renovation of
residence halls that will replace Odum Village.

14

CAMPUS MASTER PLAN UPDATE

Open Space Network

Quadrangles

Streetscape Open Space

Canopy

15

The UNIVERSITY of NORTH CAROLINA at CHAPEL HILL

Pedestrian Circulation
One goal of the 2001 Plan was to strengthen and enrich the connections between north and south
campus. Major strides to achieve this goal are or will be complete within the next few years. The newly
completed Rams Head Center bridges a significant grade change between north and south campus and is
the linchpin of their connection. Renovation and expansion of Bondurant and Carrington Halls facilitate
pedestrian circulation. Soon-to-be completed, the Student Academic Services Building and its associated
pedestrian paths will strengthen the connection from Rams Head south. Finally, the Bell Tower project,
now in design, will create a pedestrian bridge across South Road to better link north campus with the
Health Affairs precinct. Also in design is a new Dental Sciences facility, which will include a pedestrian
bridge across Manning Drive. Completion of these projects will minimize conflict with automobiles from
campus routes from Polk Place to the Thurston Bowles Building. Improved crosswalks along Country
Club Road, South Road, Mason Farm Road, and South Columbia Street have made many intersections
safer for pedestrians. Additional streetscape improvements are planned for Ridge Road, South Columbia
Street, South Road, and Skipper Bowles Drive.
Carolinas pedestrian network continues to be characterized and united by brick walks with low stone
walls. The diagram shows primary paths in red. These paths will be well lit and barrier free; the University
is committed to making as many as possible universally accessible. Secondary paths are indicated in orange.
Improvements to the pedestrian network, especially safety and accessibility, are just as important in this
Update as they were in the 2001 Plan. A new capital project fee will fund a priority list of pedestrian
safety improvements.

16

CAMPUS MASTER PLAN UPDATE

Pedestrian Circulation

Primary Paths

Secondary Paths

17

The UNIVERSITY of NORTH CAROLINA at CHAPEL HILL

Transportation System*
The most significant changes in the transportation elements contained in the 2001 Campus Master
Plan are the provision of parking, and to a lesser degree, planned road improvements. Promoting and
encouraging the use of alternatives to driving alone was strongly recommended in the 2001 Plan, and
continues to be a necessary focus (particularly park-and-ride and transit). Since 2001 there have been
major improvements and successes in these areas: riding Chapel Hill Transit is free to all users and ridership
has increased by over sixty percent, and the amount of park-and-ride spaces has doubled to close to 4,000
and use has increased by over ninety percent.
Parking
The earlier 2001 Plan identified sixteen potential sites for future structured parking, including levels of
parking beneath buildings or underground decks, to compensate for displaced surface parking (estimated
in excess of 5,000 spaces) and provide for growth. The new decks had the potential to add approximately
10,000 spaces, or a net increase on Main Campus of about 4,000 spaces.
Since 2001, four parking decks have been completed (Rams Head, Cobb-Joyner, Jackson Circle, and
Global Education). These four decks have a total of 2,124 spaces. The Update still includes sixteen sites for
parking structures (including the ones completed since 2001). However, there have been some changes in
the proposed locations (the number of spaces in some locations also has changed):
Two underground decks proposed as part of Arts Common and the redevelopment of the Venable
Hall site have been removed from the plans as a result of more detailed design for these sites.
An expansion of the Craige deck is now included, by adding several levels to the existing facility.
A deck shown directly south of the Kenan-Flagler School of Business has been removed from the
plan.
A deck is now included for a portion of the Skipper Bowles Drive parking lot.
A small deck proposed for the lot on the north side of Skipper Bowles Drive opposite the Dean
Smith Center has been removed from the plan, and instead a low deck is now shown on the
tennis courts adjacent to this lot with the courts replaced on the roof.
The Update maintains the net increase of about 4,000 spaces that was provided in the 2001 Plan. Since
2001, experience has shown that the number of parking spaces projected for a site in the Master Plan
is not always achievable when more detailed site planning occurs. To compensate for the expected
discrepancy, the Update identifies potential for more spaces than will actually be built.

18

* Prepared by Martin/Alexiou/Bryson, PLLC.

CAMPUS MASTER PLAN UPDATE

Structured Parking

Existing

Potential Sites (Previously Considered)

Opening Soon

In Development Plan
Potential Sites (Not Previously Considered)

19

The UNIVERSITY of NORTH CAROLINA at CHAPEL HILL

Roads
South Access Road
The 2001 Plan included a new access road from Fordham Boulevard to East Drive. The primary goals for
the road are to provide additional access from Fordham Boulevard and divert traffic from Manning Drive.
While the road is shown in the Update in a somewhat different configuration, it is still needed for the
following reasons:
Traffic on Manning Drive is projected to increase in the future as a result of hospital growth and
additional parking decks in that area.
The level of pedestrian activity on, and particularly the number of pedestrians crossing, Manning
Drive is increasing. Many of these are students in the residence halls around the Ridge Road
intersection. Reducing traffic on Manning Drive would improve pedestrian safety and the general
pedestrian environment.
There is significant congestion at the Manning Drive/Fordham Boulevard intersection in the
afternoon peak period. Traffic leaving the campus at this time and queuing to turn left onto
Fordham Boulevard typically backs up past Skipper Bowles Drive. In addition to increases in
traffic on Manning Drive, traffic also is projected to increase on Fordham Boulevard, with no
capacity improvements planned.
The Update continues to include new buildings along and south of Mason Farm Road. These will
benefit from direct access from Fordham Boulevard.
The 2001 Plan showed a new divided four-lane road approximately paralleling and to the north of Mason
Farm Road. This resulted in a total of six lanes of pavement. While this original concept is still viable, the
following concept is more sustainable and could be constructed mostly on University property by:
Building a single, four-lane divided boulevard by moving existing Mason Farm Road slightly to
the north, using these two realigned lanes for eastbound movement, and adding two lanes on the
north side of the two realigned lanes, separated from Mason Farm Road by a wide landscaped
median, for westbound travel.
Installing sidewalks and planting strips on both sides of the boulevard. On the south
(neighborhood) side, these would partially be located in the path vacated by the existing Mason
Farm Road, i.e., part of the existing roadbed will be redeveloped as a vegetative buffer, planting
strip and sidewalk.

20

CAMPUS MASTER PLAN UPDATE

Proposed Mason Farm Road Alignment - At 1400 Mason Farm Road (Just East of Oteys Road)

Proposed Mason Farm Road Alignment - At 1306 Mason Farm Road (Just West of Oteys Road)

21

The UNIVERSITY of NORTH CAROLINA at CHAPEL HILL

Most new road construction would be on the north side of existing Mason Farm Road. In addition to
allowing more area for vegetation than the six-lane option, this option also retains more buffer between
the road and the new student housing.
Bell Tower Connector
The 2001 Plan included a new road connection from a proposed parking deck on what is now the Bell
Tower surface lot to Manning Drive. More detailed studies for the Bell Tower site have resulted in a
smaller deck being proposed, avoiding the need for a second access connection (which was intended to
supplement the existing access from South Road).
Transit
Effective transit services, at both the local and regional levels, are critical to the functioning of Main
Campus given the constraints of the road system and parking limitations. The parking plan developed for
the 2001 Plan assumed that fixed guideway transit (rail or bus) would enter the campus from Durham or
Research Triangle Park, and connect to other local transit services. The transit corridor was dedicated for
this purpose. Regional transit has since suffered a setback with the loss of federal funding for the initial
rail line segment between Durham and Raleigh, but the corridor is being retained as new options for
improved regional transit are explored. The University will continue to support initiatives for more and
enhanced transit, as it helps reduce parking needs, removes traffic from the campus streets, and provides
mobility options for the campus population.
The Update continues to preserve a corridor for rail or bus rapid transit. The corridor starts at Fordham
Boulevard just east of Mason Farm Road and terminates in the area of the Hospitals.

22

CAMPUS MASTER PLAN UPDATE

Utilities*
In 2002, the University completed an Energy Systems Infrastructure Improvements Master Plan. Updates
to this plan were completed in January 2006.
Campus chiller and steam plants are considered models of efficiency for centralized supply systems, and
the University is working to achieve higher levels of sustainability by employing more efficient heating,
ventilation, and air conditioning (HVAC) equipment, energy modeling, and building commissioning. As
a result, building systems are becoming more efficient and more complex, making education of building
occupants as to the most efficient way to use buildings increasingly important.
Implementation of the 2001 Campus Master Plan to date has resulted in a dramatic increase in demand
for service from the campus utility infrastructure. Utility projects completed to meet new needs are
described in the following three sections.
Utility Systems
The most significant change to plans for utility systems since the adoption of the 2001 Plan is the addition
of a reclaimed water system. This system is being planned and implemented in conjunction with Orange
Water and Sewer Authority (OWASA), and will be used to supply makeup water to the cooling towers at
the chiller plants and the Cogeneration Facility. The reclaimed water system requires a water tower which
will be located at the south end of the Manning Steam Plant. The first phase of the project will serve the
North, South, East, and Tomkins Chiller Plants, as well as the UNC Hospitals chiller plants. Later phases
will extend the system to the Northeast Chiller Plant and the Cogeneration Facility. Utilizing reclaimed
water conserves the community potable water supply, and in the future reclaimed water will likely be used
for additional purposes such as irrigation.
Plants

* Prepared by University of North Carolina at Chapel Hill.

23

The UNIVERSITY of NORTH CAROLINA at CHAPEL HILL

The new plant capacities identified in the 2001 Master Plan have largely been completed, although in a
slightly different configuration than originally planned. Additional capacity has been added at the Cobb and
Tompkins Chiller Plants. These improvements have increased chilled water system capacity to approximately
50,000 tons. Further capacity expansions planned at the North and East Chiller Plants have yet to be
completed.
Since the adoption of the 2001 Master Plan, capacity at the Cogeneration Facility on Cameron Avenue has
increased to 750,000 pounds per hour. Additionally, a new 400,000 pound per hour steam plant is nearing
completion on Manning Drive. These projects complete the boiler plant capacity expansion called for in
the 2001 Master Plan.
A new Chiller Plant site at the south end of the Manning Steam Plant has been identified in the 2006
Update to accommodate additional future chiller capacity.
Distribution Systems
The 2001 Plan called for expansion and improvement of the existing distributions systems. A new network,
the South Campus Utility Tunnel, is nearing completion. This walkable tunnel contains steam and chilled
water piping. An electrical ductbank, potable water, and reclaimed water piping systems run in the same
corridor, but not within the tunnel. Additionally, old steam and hot water distribution piping system
upgrades throughout the campus are nearing completion.

24

CAMPUS MASTER PLAN UPDATE

Utility Sites

Reclaimed Water Tank

Chiller Plant

Thermal Storage

Steam Plant

25

The UNIVERSITY of NORTH CAROLINA at CHAPEL HILL

Area Calculations for Proposed Buildings


These square footage charts for each of the three campus districts replace the charts included in the
2001 Campus Master Plan. These charts, like the original ones, give the general intent of the Master Plan
relative to the massing and scale of proposed buildings, and allow the University to plan for the future
based on the environmentally responsible capacity of the land.
The accompanying diagrams identify each proposed building by letter-number combination. The letter
relates to each of the respective geographical districts. N represents North District, SE is Southeast District,
SW is Southwest District. The letter B is used as an abbreviation for pedestrian bridge. The charts identify
building use, size, massing, and height.
Proposed Buildings, North District

26

CAMPUS MASTER PLAN UPDATE

Area Calculations for Proposed Buildings - North District


Calculated
From 2006 Plan
Area Calculations for Proposed Buildings - North District
Calculated From 2006 Plan

Building Number
N 1
N 2
N 3- NOT USED
N 4
N 4.1
N 5- BUILT
N5.1- NOT USED
N 6- NOT USED
N 6.1
N 7
N 8- NOT USED
N 9- BUILT
N 10- BUILT
N 11- BUILT
N 12- BUILT
N 13- BUILT
N 14- BUILT
N 15- NOT USED

Building Use
ACADEMIC
ACADEMIC

Number of
GSF Per Floor Floors
Total GSF
Phasing
10,000
4 40,000 Light Grey
1,800
4 7,200 Orange

ACADEMIC
ACADEMIC

10,600
8,100

4 42,400 Orange
4 32,400 Orange

ACADEMIC
ACADEMIC

4,100
16,250

3 12,300 Orange
4 65,000 Light Grey

N 16
N 17
N 17.1
N 17.2- NOT USED
N 18- BUILT
N 19- BUILT

ACADEMIC
ACADEMIC
ACADEMIC

*
*
*

N 20

SUPPORT

15,000

N 21
N 22
N 23
N 24- NOT USED
N 25
N 26 - NOT USED
N 27
N 28 - NOT USED
N 29
N 30 - NOT USED
N 31- NOT USED
N 32- NOT USED
N 33- BUILT
N 34- BUILT
N 35- BUILT
Northern Precinct Subtotal

ACADEMIC
SUPPORT
PARKING

25,000
4,667
69,600

HOUSING

6,800

3 20,400 Orange

HOUSING
HOUSING
SUPPORT

3,000
6,100
3,300

3 9,000 Orange
3 18,300
2 6,600 Orange

max. 6
max. 4
max. 2

174,000 Orange
22,400 Orange
51,400 Orange

1 15,000 Orange
*4 75,000 Orange
3 14,001 Light Grey
3 208,800 Orange

Building Details/
Parking Numbers

Remarks

* Varies
ROTC Site
Science Library Pavilion * Varies
Science Library Stacks * Varies

Connector from Inn to


Whitehead

* 3 floors above ground and 1


Davie Hall Replacement floor below ground
Morehead Planetarium
3 levels below ground
600 spaces

814,201

27

The UNIVERSITY of NORTH CAROLINA at CHAPEL HILL

Proposed Buildings, Southeast District

28

CAMPUS MASTER PLAN UPDATE

Area Calculations for Proposed Buildings - Southeast District


Area Calculations for Proposed Buildings - Southeast District
Calculated
From 2006 Plan
Calculated From 2006 Plan

GSF Per Number of


Floor
Floors
Total GSF
Phasing
30,700
4 122,800 Orange

Building Details/
Parking Numbers

Building Number
SE 1

Building Use
ACADEMIC

SE 2
SE 3
SE 4
SE 5- BUILT
SE 6- BUILT
SE 7- BUILT
SE 8- NOT USED
SE 9- BUILT
SE 10- NOT USED
SE 11- NOT USED
SE 12 - ROTC
SE 13
SE 14
SE 15- BUILT
SE 16
SE 17
SE 18- NOT USED
SE 19- BUILT
SE 20- BUILT
SE 21- BUILT
SE 22- BUILT
SE 23- BUILT
SE 24- NOT USED
SE 25- NOT USED
SE 26- NOT USED
SE 27- NOT USED
SE 28- BUILT
SE 29- BUILT
SE 30
SE 31
SE 32- NOT USED
SE 33- NOT USED
SE 34- NOT USED
SE 35- NOT USED

ATHLETICS
ACADEMIC
SUPPORT

3,000
6,800
4,000

2 6,000 Orange
3 20,400 Orange
3 12,000 Orange

ACADEMIC
ACADEMIC
HOUSING

5,000
12,500
10,200

4 20,000 Light Grey


3 37,500 Orange
4 40,800 Orange

UTILITY
ACADEMIC

15,000
31,250

2 30,000 Orange
4 125,000 Orange

SILS

ACADEMIC
PARKING

23,500
80,500

4 94,000 Orange
3 241,500 Orange

Skipper Bowes

PARKING/
REC SPORTS

48,100

2 96,200 Orange

230 Spaces
Rams Head Rd Deck

ACADEMIC
ACADEMIC
ACADEMIC

11,600
17,000
23,000

4 46,400 Orange
4 68,000 Orange
4 92,000 Orange

SE 36
SE 37- NOT USED
SE 38
SE 39
SE 40

Remarks

Sports Medicine Center


Alumni Center Addition

SOG
15,000 tons

730 spaces

29

The UNIVERSITY of NORTH CAROLINA at CHAPEL HILL

Area Calculations for Proposed Buildings - Southeast District continued


Area Calculations for Proposed Buildings - Southeast District continued
Calculated
From 2006 Plan
Calculated From 2006 Plan

Building Number
SE 41- NOT USED
SE 42
SE 43
SE 44- BUILT
SE 45
SE 46- NOT USED
SE 47- NOT USED
SE 48- NOT USED
SE49- NOT USED
SE 50- NOT USED
SE 51
SE 52- BUILT
SE 53- BUILT
SE 54- BUILT
SE 55- BUILT
SE 56- BUILT
SE 57- BUILT
SE 58- BUILT
SE 59- BUILT
SE 60
SE 61-BUILT
SE 62-BUILT
SE 63
SE 64
SE 65- BUILT
SE 66- BUILT
SE 67- BUILT
SE 68- BUILT
SE 69 - NOT USED
SE 70
SE 71
SE 72
SE 73
SE 74- NOT USED
SE 75- NOT USED
SE 76- NOT USED

Building use

Building Details/
Parking Numbers

UTILITY
PARKING

10,000
50,600

1 10,000 Orange
4 202,400 Orange

SUPPORT

15,200

4 60,800 Orange

PARKING

98,000

5 490,000 Orange

5 levels above ground

HOUSING

12,500

3 37,500 Orange

APT.

HOUSING
HOUSING

15,700
15,700

3 47,100 Orange
3 47,100 Orange

ACADEMIC
PARKING
HOUSING
HOUSING

40,200
60,600
10,500
12,400

3
3
3
3

SE 77

ATHLETICS

38,600

*125,000 Orange

SE 78
SE 79

ATHLETICS
ATHLETICS

23,400
5,000

*125,000 Orange
1 5,000 Orange

SE 80
SE 81
SE 82
SE 83

ATHLETICS
ATHLETICS
ATHLETICS
UTILITY

SE 84
PARKING
SE 85
ATHLETICS
Southeast Precinct Subtotal

30

Area Per Number of


Floor, gsf Floors
Total Area, gsf Phasing

6,400
51,500
*
max. 2
NA
NA
104,000
5,000

120,600
181,800
31,500
37,200

2 12,800
1 51,500
25,000
NA

600 spaces

Orange
Orange
Orange
Orange

Orange
Orange
Light Grey
Light Grey

3 312,000 Light Grey


2 10,000 Orange
2,724,900

Remarks

1,500 spaces

550 spaces

Kenan Endzone Seats

* 125K GSF total of


SE 77&78
* 125K GSF total of
SE 77&78

Kenan Skyboxes
Eddie Smith Indoor Track
Soccer Stadium
Improvements
Carmichael Addition
Boschemer Stadium Impr* Varies
Reclaimed Water Tank
3 levels added to
existing deck
Craige Deck Addition
Wrestling Center

CAMPUS MASTER PLAN UPDATE

31

The UNIVERSITY of NORTH CAROLINA at CHAPEL HILL

Proposed Buildings, Southwest District

32

CAMPUS MASTER PLAN UPDATE

Area Calculations for Proposed Buildings - Southwest District


Area Calculations for Proposed Buildings - Southwest District
Calculated
From 2006 Plan
Calculated From 2006 Plan
Building Number
SW 1- BUILT
SW 2- BUILT
SW 3
SW 4
SW 5
SW 6- NOT USED
SW 7
SW 8- NOT USED
SW 9- NOT USED
SW 10- NOT USED
SW 11

Building Use

GSF Per
Floor

Number of
Floors
Total GSF

Phasing

Building Details/
Parking Numbers

ACADEMIC
ACADEMIC
ACADEMIC

8,000
9,600
5,400

3 24,000 Orange
3 28,800 Orange
3 16,200 Orange

ACADEMIC

72,000

4 288,000 Light Grey

ACADEMIC

13,400

SW 12
SW 13
SW 14- BUILT
SW 15
SW 16- NOT USED
SW 17

PARKING
ACADEMIC

37,000
7,000

6 222,000 Orange
4 28,000 Orange

HOSPITAL

88,000

6 528,000 Orange

SUPPORT

20,800

4 83,200 Orange

SW 18
SW 19- NOT USED
SW 20
SW 21
SW 22
SW 23- BUILT
SW 23.1- BUILT
SW 24- BUILT
SW 25
SW 26

ACADEMIC

45,200

5 226,000 Light Grey

Student Health
Dental Science
Building addition

HOSPITAL
HOSPITAL
PARKING

26,600
21,200
63,900

8 212,800 Light Grey


4 84,800 Light Grey
4 255,600

730 spaces

ACADEMIC
ACADEMIC

24,800
16,000

4 99,200 Orange
6 96,000 Orange

SW 27
SW 28
SW 29- BUILT
SW 30- BUILT
SW 31
SW 32 - NOT USED
SW 33
SW 34 - NOT USED
SW 35
SW36
SW37- BUILT
SW38- NOT USED
SW39- NOT USED
SW40- NOT USED
SW41- BUILT
SW 42- BUILT
SW 43
SW 44
SW 45
SW 46- NOT USED
SW 47

ACADEMIC
SUPPORT

55,000
3,200

6 330,000 Orange
1 3,200 Orange

ACADEMIC

22,200

4 88,800 Orange

PARKING

51,100

3 153,300 Orange

440 spaces

HOSPITAL
PARKING

64,300
44,800

3 192,900 Orange
3 134,400 Orange

350 spaces

ACADEMIC
ACADEMIC
ACADEMIC

11,000
28,500
30,200

4 44,000 Orange
4 114,000 Orange
4 120,800 Orange

SUPPORT

4,800

3 14,400 Orange

SW 48
SW 49 - NOT USED
SW 50
SW 51- NOT USED

ACADEMIC

18,000

10 180,000 Orange

ACADEMIC

28,400

4 113,600 Orange

SW 52

SUPPORT

13,300

*48,000 Orange

Grounds Facility

SW 53

SUPPORT

14,700

*48,000 Orange

Grounds Facility

SW 54
SUPPORT
Southwest Precinct Subtotal

8,000

*48,000 Orange
3,762,000

Grounds Facility

80,000 Orange

Remarks

Pharmacy

Wrapper Building
710 spaces
Bell Tower Parking
Deck

UNC Imaging
Center

MOB

* 48K GSF total of


SW 52, 53 & 54
* 48K GSF total of
SW 52, 53 & 54
* 48K GSF total of
SW 52, 53 & 54

33

The UNIVERSITY of NORTH CAROLINA at CHAPEL HILL

Proposed Buildings & Pedestrian Bridges, Campus-wide

34

CAMPUS MASTER PLAN UPDATE

Area
Calculations for Proposed Buildings - Campus-wide
Area Calculations for Proposed Buildings - Campus-wide
Calculated
From 2006 Plan
Calculated From 2006 Plan
Total for Proposed Buildings
Northern Precinct
Southwest Precinct
Southeast Precinct
Total Proposed Buildings, gsf

total gsf
814,201
3,762,000
2,724,900
7,301,101

Adjusted Total of New Campus Building Area, gsf


Total Proposed Buildings, gsf
Total Existing Buildings Demolition, gsf
Total Proposed Parking, gsf
Adjusted Total of New Campus Building Area, gsf

7,301,101
7,301,101

Proposed Pedestrian Bridges


From
2006 Plan
Proposed Pedestrian Bridges
Bridge Number
B1
B2
B3
B4
B5
B6
B7
B8
B9

District
N
N
SE
SE
SE
SW
SW
SW
SW

Remarks
Not used
Not used

35

The UNIVERSITY of NORTH CAROLINA at CHAPEL HILL

Acknowledgments
The 2001 Plan was the product of an intensely collaborative process that engaged large numbers in the
campus community, as well as local citizens and officials. A similarly collaborative approach was employed
to produce the 2006 Update. The University is grateful to every person who participated in the process.
Many meetings both internal and external to the University were held to capture and learn from the
experience of the communities on and around campus. Service providers (University and commercial),
faculty, students, administrators, neighbors, visitors and staff were asked to contribute to the Update process
on numerous occasions:
2003
SW Precinct March
SE Precinct Pedestrian Connections August
2004
Community Workshop Sept. 20
Technical Workshop Sept. 21
FPC/FWG Sept. 21
FPC/FWG - Nov. 2
Community Nov. 3
Technical Nov.3
Disabilities Advisory Committee Nov.3
Belltower/School of Medicine/Hospital Nov. 3
Housing Dec. 14
Arts Common Dec. 14
Utilities Dec. 15
Open Space/Pedestrian Connections Dec. 15
Design Team Dec. 15
Parking Dec. 16
Design Team Dec. 16
2005
Chancellor Briefing Jan. 3
Chancellors Cabinet Jan. 11
Deans Council Jan. 13
Hospital/School of Medicine March 7
Utilities March 7

36

Housing/Student Affairs March 7


Parking March 7
Pedestrian Circulation March 7
Phasing and Implementation March 22
Parking - March 22
Bell Tower March 22
Grounds Dept. April 5
Belltower April 5
Housing April 5
Phasing Implementation April 5
Board of Trustees (B&G) April 11
Executive Committee of Faculty Council April 25
Student - April 27
Engineering Information Services May 17
Hospital/School of Medicine May 17
Community May 18
Community May 18
Community May 19
Hospital/School of Medicine May 31
Buildings and Grounds Committee June 2
FPC/FWG June 7
Technical June 7
Athletics June 7
Porthole Alley June 8
Service Areas June 8
Pedestrian Corridors June 8

CAMPUS MASTER PLAN UPDATE

Project Team
Chancellors Cabinet July 19
Chancellors Advisory Committee July 20
Board of Trustees July 28
Board of Trustees Sept. 21
Chapel Hill Town Council Sept. 26
Hospital area Sept. 27
Service Areas Sept. 28
Pedestrian Corridors Sept. 28
Overall Review Sept. 29
Community Oct. 6
Community Oct. 7
FPC/FWG Nov. 15
2006
Facilities Planning Jan. 26
Unresolved Areas Feb. 21
FPC/FWG Feb. 21
Chancellors Cabinet Feb. 28
Chan. B&G March 2
Board of Trustees March 22

The University of North Carolina at Chapel Hill


Jill Coleman
Linda Convissor
Carolyn Elfland
Jonathan Howes
Bruce Runberg
Anna Wu
Ayers/Saint/Gross
Karla Aghajanian
Luanne Greene
Lindsay Harmon
Glenn Neighbors
Amelle Schultz
Naomi Susman
Bynum Walter
Martin/Alexiou/Bryson, PLLC
George Alexiou
Graham James
Andrew Topp
Affiliated Engineers, Inc.
Jerry Schuett

37

The UNIVERSITY of NORTH CAROLINA at CHAPEL HILL

1040 Hull Street


Suite 100
Baltimore, MD 21230
410.347.8500
410.347.8519 fax
www.asg-architects.com

38

You might also like