You are on page 1of 4

NCMA TEK

Provided by:
Cinder & Concrete Block Corporation
National Concrete Masonry Association
an information series from the national authority on concrete masonry technology

FLOOR AND ROOF CONNECTIONS TO


CONCRETE MASONRY WALLS
Keywords: connections, floor systems, hollowcore,
joists, ledger, loadbearing concrete masonry, pocket,
roof systems, trusses
INTRODUCTION
Floor and roof systems for use with loadbearing structural concrete masonry walls serve three primary functions:
they transmit the vertical dead load and live load to the bearing
walls; they function as diaphragms, transmitting lateral wind
and seismic loading through the walls to the foundation; and
they act to support the walls from out-of-plane loads. In
addition to these structural functions, floors and roofs should
provide a satisfactory barrier to the transmission of sound,
fire, and heat. The many types of floor and roof systems in use
today are designed to satisfy all of these requirements in an
economical manner.
CONNECTIONS
The transfer of loads between diaphragms and walls
requires the proper design and detailing of the connection
linking these elements. Connections critical to the integrity
of a structure. The connections detailed herein address
minimal requirements. Additional requirements may be
necessary in some locals, particularly where earthquake and
high wind forces are to be resisted. The four primary types of
connections, each having specific advantages, include:
Direct Bearing Connection The direct bearing connection is often the simplest type of connection. This connection is used at the top of concrete masonry walls or when a
change in wall thickness provides a ledge with sufficient
bearing area as shown in Figure 1.
Pocket Connection A pocket connection consists of
framing the floor or roof system into a void in the masonry
wall. This detail is used when masonry continues above
(either as part of the wall or as a parapet) the connection
location and eccentricity is to be minimized. Care must be
taken to insure that the use of a pocket does not interfere with
the continuity of the vertical reinforcement in the wall.
Hanger Connection When it is desired to maintain the
continuity of the wall for structural, aesthetic, or construction reasons, a wall hanger can be used to suspend the roof or

TEK 5-7A
Details

floor system. Hangers are generally anchored to a wall


through a joint and into a bond beam. However, hangers
approved for direct attachment to the surface of a masonry
wall are also available.
Ledger Connection As with hangers, ledger connections minimize the impact on the continuity of a masonry
wall. A ledger connection reduces the necessary pre-planning and does not unduly impact the masons work as opposed
to a pocket connection; thereby reducing the number of field
modifications.
Note: Most of the connections herein depict flashing for
water penetration resistance which should be used in all exterior
walls. Normally flashing is not provided in interior walls.
FLOOR AND ROOFING SYSTEMS
Several materials are common to roof and floor construction. Wood, concrete, and steel are among the most
frequently used framing materials in these applications.
Wood Systems
Wood framed floors and roofs are common in residential and low-rise construction. It is imperative when constructing a wood-framed system that it not be in direct
contact with the concrete masonry. Wood in contact with
masonry materials may absorb moisture present in the concrete masonry causing the wood to rot. To prevent the
resulting unwanted decay, the lumber used should be pressure-treated, naturally decay resistant, or have a moisture
barrier placed between the wood and the concrete masonry.
Steel Systems
Steel-framed roofs using steel bar joints are very common in commercial structures because they are capable of
spanning long distances. Steel bar joists typically use pocketed or ledger connections to concrete masonry walls. Proprietary systems that use concrete masonry units as a filler
between the steel joists are also available.
Concrete Systems
Concrete slabs can take many forms, including prestressed, precast, and cast-in-place construction. Depending
upon the size and number of stories associated with a given

TEK 5-7A 2001 National Concrete Masonry Association (replaces TEK 5-7 and TEK 17-5 )

(2001)

Superstructure
Blocking or band joist
Toenail or tie as required
Solid or filled masonry
unit to support flashing
Stop flashing at
inside of faceshell
Void/pocket
Fire-cut end of joist
(as required)

Wood joist
Sill (pressure treated
or provide moisture barrier)
Anchorage as required
Reinforced bond beam
Concrete masonry wall

Cavity fill or
other mortar
collection device
1 in. (25 mm)
partially open
"L" shaped head
joints for weeps
at 32 in. (814 mm)
o.c.
Drip edge

Figure 1Direct Bearing Wood Floor Joist (ref. 2)

Sheathing

Wood joist
Pressure treated or
provide moisture barrier
Reinforcement

Cavity fill or other mortar


collection device

1 in. (25 mm) partially


open "L" shaped head
joints for weeps
at 32 in. (814 mm)

Stop flashing at inside


of faceshell
Provide gap or moisture
barrier as required
Blocking or band joist
Sheathing
Wood joist
Toe nail or tie
as required

Drip edge

Sill (pressure treated or


provide moisture barrier)

4 in. (102 mm) unit


(solid or filled) to
support flashing

Anchorage as required
Reinforced bond beam
Concrete masonry wall

Figure 2Direct Bearing Wood Floor Joist

Cavity fill or other mortar


collection device
1 in. (25 mm) partially
open "L" shaped head
joints for weeps
Drip edge
4 in. (102 mm) unit
(solid or filled) to
support flashing

Stop flashing at
inside of faceshell
Joist hanger; fasten
as required by
hanger manufacturer
Sheathing

Grout stop

Concrete masonry bond beam

Figure 5Wood Floor Joist With Pocket

2 in. (51 mm) deep


Cavity fill or other
mortar collection device
1 in. (25 mm) partially
open "L" shaped head
joints for weeps
at 32 in. (814 mm)

Solid or filled
unit to support
flashing
Reinforced
bond beam
Ledger
Sheathing

Drip edge

Grout stop
Wood joist
Joist hanger
Double (shown) or
staggered anchor
bolt as required

Wood joist
Reinforced
bond beam

Figure 6Wood Ledger and Hanger

Figure 3Wood Floor Joist Hanger (ref. 2)

Cavity fill or
other mortar
collection device

Stop flashing at
inside of faceshell
4 in. (102 mm) unit (solid or
filled) to support flashing

Cavity fill or
other mortar
collection device

Concrete masonry wall


Stop flashing at
inside of faceshell
Provide gap or moisture
barrier as required
Notch/pocket

1 in. (25 mm)


partially open
"L" shaped head
joints for weeps
at 32 in. (814 mm)
o.c.
Drip edge
Concrete
masonry wall

Wood truss

Bearing truss hanger;


fasten as required by hanger
manufacturer
Reinforced bond beam

Figure 4Wood Floor Truss Hanger (ref. 2)

1 in. (25 mm)


partially open
"L" shaped head
joints for weeps
at 32 in. (814 mm)
o.c.
Drip edge

Wood Truss
Reinforcement
Bond beam

Figure 7Wood Floor Truss Pocket (ref. 2)

Sloping sheet metal coping


cap with cont. cleat. each side
Grout cores solid at anchor bolts

Wood Nailer with anchor bolts


Attachment strip

Cavity fill or other mortar


collection device

Counter flashing
Sealant

Standard unit with


inside faceshell and
part of web removed

Sill (pressure treated or


provide moisture barrier)
Anchor bolt or
specialty anchor
as required
Bond beam
Concrete masonry wall

Toenail per
code or use
rated connector

Figure 8Wood Roof Truss with Top Plate (ref. 2)

Stop flashing at inside of


faceshell (see TEK 19-2A)
Cant
Parapet flashing
Sealant
Roofing membrane

1 in. (25 mm) partially


open "L" shaped head
joints for weeps
at 32 in. (814 mm)
Drip edge
Solid unit notched
around joist steel
plate with anchor
Grout stop
Reinforced bond beam
Masonry wall

Steel bar joist welded


or bolted to bearing
plate

Figure 11Steel Joist with Pocket (ref. 3, 4, 5)


+
+
+
+
o

Moisture barrier
Uplift connector
as required
Reinforced bond beam
Concrete masonry wall

o
o

Figure 9Wood Roof Truss with Embedded


Strap Anchor (ref. 2)

Isolation joint
1 in. (25 mm) partially
open "L" shaped head
joints for weeps
at 32 in. (814 mm)

Steel bar joist welded or


bolted to ledger angle

Drip edge

Steel ledger angle


bolted to wall
Reinforced bond beam

2 in. (51 mm) min. to 4 /2 in.


(114 mm) max. cavity
Sloping sheet metal coping
cap with cont. cleat. each side
Attachment strip
Wood Nailer with anchor bolts
Counter flashing

Wall ties (typ.)

Sealant
Cant
Parapet flashing
Sealant
Roofing membrane

Figure 12Steel Joist with Ledger Angle

Reinforced bond beam


Anchor bolts spaced
as required

Insulation

Cavity fill or other mortar


collection device
1 in. (25 mm) partially
open "L" shaped head
joints for weeps
at 32 in. (814 mm) o.c.
Drip edge
Steel shelf angle

Steel bar joist welded


or bolted to bearing
plate
Reinforced bond beam
Reinforced lintel
Sealant at top of
flashing unless self
adhearing flashing or
tuck into mortar joint

Figure 10Steel Joist Direct Bearing on Cavity Wall

Steel
angle

Decking attached
to steel
angle as
required for
diaphragm
shear transfer

Concrete masonry wall

Figure 13Steel Joist at Sidewall

Cavity fill or other mortar


collection device
1 in. (25 mm) partially
open "L" shaped head
joints for weeps
at 32 in. (814 mm)
o.c.

Stop flashing at inside


of faceshell (see TEK 19-2A)
4 in. (25 mm) unit (solid
or filled) to support flashing
Hooked shear bar grouted
in slab keyway
Topping if required

1 in. (25 mm) partially


open "L" shaped head
joints for weeps
at 32 in. (814 mm) o.c.
Drip edge

Drip edge

Stop flashing at inside


of faceshell (see TEK 19-2A)
4 in. (25 mm) unit (solid
or filled) to support flashing
Reinforcement with hooks
on both ends grouted
into broken core
Topping if required

Grouted cells at
location of
shear bar

Reinforced
bond beam
Grout stop

Cavity fill or other mortar


collection device

Precast hollow core slab


Bearing strip
Hooked bar in wall at shear
bar (not required if vertical
reinforcement at this location)

Reinforced
bond beam

Precast hollow core slab

Grout stop
Hooked bar in wall at shear
bar (not required if vertical
reinforcement at this location)

Figure 14Concrete Hollowcore at Bearing (ref. 3)

Figure 15Hollowcore at Sidewall (ref. 3)

project, one concrete framing system may have unique benefits over another. For example, hollow core prestressed
slabs can be erected quickly, without the need for formwork
or shoring. Where sufficient space is available at the job site,
precast slabs can be formed in stacks on-site, starting with the
roof slab and using the top surface of the lower slab as the
form for the next slab. Once cured, the precast slabs are lifted
to their final location. The use of cast-in-place concrete
floors and roofs, because of the time needed for forming,
pouring, finishing, and curing, requires a building plan which
is large enough to permit the masonry work to progress in one
part of the structure while the floor in another area is completed.

REFERENCES
1. Architectural and Engineering Concrete Masonry Details for Building Construction, TR-95. National Concrete
Masonry Association, 1973.
2. Concrete Masonry Homes: Recommended Practices.
U.S Department of Housing and Urban Development, Office
of Policy Development and Research, 1999.
3. Design for Dry Single-Wythe Concrete Masonry Walls,
TEK 19-2A. National Concrete Masonry Association, 1998.
4. Flashing Details for Concrete Masonry Walls, TEK
19-5A. National Concrete Masonry Association, 2000.
5. Generic Wall Design for Single-Wythe Loadbearing
Walls. Masonry Institute of Michigan, 2000.

Provided by:
Cinder & Concrete Block Corporation
Disclaimer: NCMA and the companies disseminating this technical information disclaim any and all responsibility and
liability for the accuracy and the application of the information contained in this publication.

NATIONAL CONCRETE MASONRY ASSOCIATION


2302 Horse Pen Road, Herndon, Virginia 20171-3499
www.ncma.org

To order a complete TEK Manual or TEK Index,


contact NCMA Publications (703) 713-1900

You might also like