You are on page 1of 5

Q 1 A restaurant Manager is concerned about the

temperature of the food items being served. He never


wanted the food to be warmer than 160 degree F and cooler
than 147 degree F. He decided to do a study of the samples
for 10 days and collected three servings and recorded the
temperatures. Following is the samples and the readings
Sample
no
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.

Readings
150
140
145
150
130
140
150
155
160
150

160
150
150
150
155
140
150
155
160
160

155
155
150
155
150
145
150
160
160
165

The following values are given


Sample size
2
3
4

D3
0
0
0

D4
3.267
2.575
2.282

A2
1.880
1.023
0.729

Develop charts and comment on the process .

Q2. A control Chart for fraction non conforming is to be


established with the centre line at 0.07 (p=0.07).How large
the sample size should be to so as to have a non zero value
of LCL.
Q 3. A company produces micro-oven components on mass
basis. At some production point 10 samples of 100 each
were collected . They were categorized as Good or
Defective ., and the number of defectives were as
follows: 18,19,8,15,17,12,19,1, 15, 17. Construct a p chart
with 3 sigma limits and comment on the process .
Q4. A company produces chips on mass production basis.
At some production point 10 samples of 50 each were
collected and the no. of defects found were as follows:
9,10,4,9,8,6,9,8,7,5 . Construct a p chart with 3 sigma
limits and comment on the process .
Q 5. Control chart for mean and range are to be set up on
the measurements of diameter of a shaft . Samples were of
size 4. After 30 samples were taken it was found that the
mean value of dias were 7515 . The mean value of ranges
were 360. The customer wanted that the diameter of the
shafts should be within 250mm +/- 10mm. It is given that
for n=4, A2 =0.729, D3= 0, D4= 2.282.
Determine the control limits . What is the probability of
rejection by customer ?

Q6. Forecast for the month Feb =100 units. Actual demand
for Feb is 90. if alpha = 0.12, what should be forecast for
March ?
Q7. The data given in the table are the timestudy in an
operation of existing two elements :
Element 1 :
0.1
4
0.1
5

0.1
4
0.1
9

0.1
5
0.1
7

0.1
5
0.1
3

0.1
8
0.1
4

0.2
0
0.1
7

0.1
9
0.1
8

0.1
7
0.1
7

0.1
7
0.1
6

0.1
8
0.1
6

0.1
4
0.1
4

Element 2 :
0.09 0.06 0.05 0.06 0.07 0.06 0.06 0.06 0.07 0.09
0.06 0.07 0.07 0.08 0.07 0.07 0.07 0.06 0.06 0.06

0.07
0.07

During the time study the 1st element was rated as 90% and
second at 120% .Total allowance to be given for the
operation is fixed at 12%. Determine the standard time for
the operation.
Q 8. ABC company purchases metal bars , for which annual
demand is 4500 units. It requires Rs 75 to place one order .
The interest cost is 18% per anum and other costs for
holding inventory is 7% per anum. The price in the market
is as below :

Unit

Price/ Rs unit

1.299
60
300.499 50
500
40
and more
What is the optimum quantity of order with this price
break ?
Q9. A company uses packages of plastic tapes to create
layouts . About 200 packages are consumed each year . The
supplier gives quantity discount as follows
Unit

Price/ Rs unit

1-99
100
100- 499 95
500
90
and more
if the company has a 35% carrying cost per year and spends
about Rs 300 per order determine the right order quantity.
Q 10 A print shop company manufactures its own envelops
. For a production rate of 2000/hour the set up cost is Rs
7500. Average demand for envelopes is 10,000 per
month.Annual cost for holding inventory is 15%.
Envelopes cost Rs 500/ 1000 units in the market. A
working months average is 160 hours.

a) what is the economic production quantity in months


supply ?
b) If the company buys the envelopes , and the order
processing cost is Rs 500 , what should be the
optimum order quantity?
c) If the set up time is 2 days , what is the reorder
point ?

You might also like