Professional Documents
Culture Documents
Introduction
Located in the Emirate of Sharjah, United Arab Emirates, the
Sajaa onshore gas field is a Thamama Group limestone
reservoir ranging from 11,000 to 13,000 feet true vertical
depth (3350 to 3960 meters). Bottomhole temperature ranges
from 260 to 310 degrees Farenheight (126 to 154 Celcius) and
bottomhole pressure from 1100 to 1900 psi (75 to 129
atmospheres). This paper contains lessons learned from the
project to date by the various authors directly involved with
this unique and highly successfull Underbalanced Coiled
Tubing Drilling project.
Background
In April of 2002 the concept was conceived to utilize UnderBalanced Coiled Tubing Drilling (UBCTD) to unlock
additional rate and reserves by exposing additional net pay
with multilateral wellbores from the existing well stock in the
Sajaa field. A full year of evaluating and planning ensued and
in April of 2003 drilling for first well began. This full year of
Front End Loading (FEL) was key to the success of the project
and was marked by several milestones or stage gates on the
way to start of operations. FEL included multiple tasks along
parallel paths to bring the project from concept through
financial sanction and finally to start-up. Key tasks within the
FEL were:
Concept Identification:
A peer assist was held with internal and external industry
experts to discuss the technical options that might achieve the
multilateral objectives. The two principal outcomes of the peer
assist identified the basic technical concepts along with the
Basis of Design:
A concept basis of design paper (SPE IADC 87146 by P. V.
Suryanarayana; et.al.) provided the equipment sizing and
parameters. The design was necessary to prepare tenders and
this effort looked at the following requirements and
sensitivities:
Tender:
The tender was structured into seven major service envelopes
and one additional envelope for all required minor services.
Tender invitations allowed the option for a service provider to
bid on an individual envelope or to submit a bid for any (or
all) seven envelopes. Tender responses were evaluated on their
technical merit as well as their safety and environmental
www.petroman.ir
SPE/IADC 92513
Start-up:
A Putting it all Together paper (SPE / ICoTA 89644 by R.D.
Pruitt, et.al.) provided detailed information about the UBCTD
kit. The initial rig up was slow; as expected. Time was taken
to establish safety expectations, train the crews and conduct
walk-throughs of the entire site with everyone involved in the
operation. Early in the project there were significant
equipment failures of both the surface and downhole
equipment. These failures led to several important learnings
so the team could systematically eliminate other problems as
operations progressed. The most important learning was that
the operator must walk the talk on safety when an
unscheduled event occurs. It is essential for the operator to
stop all operations and allow service providers the space and
time to resolve technical issues safety. The lesson is to not
rush through problem solving.
Fabrication:
Drilling Program:
Assurance:
Mobilization:
Most of the required equipment was sourced locally. Three
exceptions were: Coiled Tubing with internal electric cable;
Bottomhole Drilling Assemblies; and the Surface Separation
package. The separation package was mobilized by sea from
the Far East, drilling assemblies manufactured in Celle
Germany, and the coiled tubing built in Houston, USA.
Themes
The rest of this paper will discuss the many learnings along
the course of the project.
Vision
A safe and long-term drilling campaign for unlocking rate and
reserves was the vision. It was recognized at the onset that a
multiple well program was required for the best chance of
proving the concept. The team just said no to the one-off
program approach. Planning for success included tendering for
a 10 well campaign with triggers for early termination if
needed after the first three wells. Planning for long-term
success also allowed better position to negotiation campaign
extensions. This approach with each service provider was time
consuming, but educational as both parties had learned what
their true costs were in terms of both people resources and
equipment.
www.petroman.ir
SPE/IADC 92513
400
350
Total Hours
211
150
145
111
113
79
50
250
100
360
300
200
Figure 1
91
82
77
56
72
64
78
76
75
59
49
0
Sajaa 3 Sajaa Sajaa 7 Sajaa Sajaa 4 Sajaa Sjaa 32 Sajaa
15
16
26
17
Sajaa
21
Sajaa
15
Sajaa
26
Sajaa
19
Sajaa
07
www.petroman.ir
SPE/IADC 92513
Plan-Do-Learn-Evaluate-Share
The hallmark of this project has been the extraordinary degree
of collaboration among the four major service companies.
Each understands that the success of the project depends upon
coordinating their efforts and sharing information regarding
each of their state-of-the-art (and sometimes proprietary)
technology products. They understand that no single service
company can supply all the technology and expertise needed
for the Sharjah project. Hence, success of the project required
a shared success among all the service companies. On a larger
scale, underbalanced CTD worldwide would be directly
affected by success or failure of this project.
BP shared this global perspective and a desire that this project
be an incubator for the development of UBCTD technology.
BP has opened the Sharjah drilling site to visitors from other
oil companies and the project has become a showcase for the
industry. It is also a showcase for future customers of the
technology. In this respect, BP has provided an example of
openness and cooperation. Service providers are expected to
follow this example.
Initially, safety and environmental protection were the top
concerns. The section on the previous page addressed safety.
Minimizing natural gas flaring to the environment was also a
goal. Extraordinary measures were put in place to capture
produced gas and condensate while drilling forward. All
hydrocarbon products are sold to the market on the same day,
which is an amazing accomplishment. This required an extra
www.petroman.ir
SPE/IADC 92513
www.petroman.ir
SPE/IADC 92513
Procedures
7
6
5
Hours
4
3
2
1
0
0
We ll No.
800
Workdays per well
700
Saja a
7 00 .9
3 = 49 da y s
Saja a 15 = 38 da y s
Saja a 7 = 3 8 d ay s
600
Saja a 16 = 23 da y s
Saja a 4 = 2 7 d ay s
500
Total Hours
Saja a 32 = 22 da y s
Saja a 17 - 3 0 da y s
400
Saja a 42 = 20 da y s
300
3 09 .3
2 94 .4
200
2 16 .3
1 92 .9
1 66 .0
1 70 .9
1 54 .8
1 49 .0
1 36 .4
1 16 .3
100
7 8.8
8 7.7
7 3.0
5 1.8
3 7.6
0
Sajaa 3 Sajaa 15 Sajaa 7 Sajaa 16 Sajaa 4 Sajaa 32 Sajaa 17 Sajaa 42 Sajaa 5
NPT Hours
www.petroman.ir
SPE/IADC 92513
Extended Teams
One-year prior to start-up it was clear the Sharjah team needed
help. The project required more expertise than what was
available in Sharjah.
The first extended team was the BP coiled tubing drilling
operation in Alaska, USA. That team provided a ready source
of information about how to get started and helped Sharjah
focus on critical issues related to the reservoir, equipment and
personnel. Although the Alaska reservoir and drilling
operation were different than that in Sharjah, the lesson was
not to re-invent the wheel for the basic concept. The Alaska
team was also a key source of expertise for real time trouble
shooting of complex problems rig-site to rig-site; a best
practice especially for external assurance.
A BP subsurface team of engineers was assembled in the UK
to define the prize. The initial impression about this split-site
team set-up was lack of teamwork. Making use of modern
communication technology helps reduce inherent problems
caused by having split-site teams. A weekly video meeting
keeps the entire team on track with specific issues and
concerns such as candidate selection and choke points in the
hopper-of-opportunities. Drilling priorities are also established
during these joint meetings through a healthy challenge
process. Drilling decision trees are formulated for each
candidate and cover a large range of potential subsurface
issues. These trees create a real sense of joint-ownership and
alignment between the two teams. The trees also reduce
decision time delays associated with split work sites. Rate and
reserve development are always discussed.
Service providers are an important part of the extended team
concept and the key lesson is to get key technical staff as close
to the operation as possible. Workshop proximity related to
the rig site is of critical importantence when sophisticated
technologies are brought in from outside the country. Regular
meetings are held with all major service providers. The
location of these meetings is at the rig site. This provides
visibility of contractor management with their respective
staffs.
Subsurface
The single key subsurface lesson derived from this project is
that the technology works. UBCTD has delivered a substantial
rate and reserve volume from this tight (low permeability) and
pressure depleted gas reservoir. To date, the sustained
incremental production exceeds 140 million scf/d from 19
wells. This is a staggering volume of additional incremental
gas volume from what was previously considered a mature
reservoir. Reservoir access was achieved by drilling multiple
sidetrackes into relatively higher pressures away from the
original motherbore. After nearly 20 months of operations,
there is very little interference between individual laterals or
wells. This learning has allowed the campaign to continue into
the year 2005.
www.petroman.ir
SPE/IADC 92513
References
1.
2.
www.petroman.ir