Professional Documents
Culture Documents
Agenda
Case studies
Overview of legal requirements pertaining
to demolition works
CP 11 Code of Practice for demolition
Asbestos Health hazard in demolition
works
Key Findings
1) There were 2 types of PE-endorsed designs for the anchorage
of the hoarding
one for solid ground, the other for concrete ground.
2) The span of scaffold hoarding that collapsed was not erected in
accordance with the PEs design.
3) Wall ties were used as a form of anchorage on the road asphalt
surface instead of concrete block footings.
4) The anchorage distance from the hoarding base was also too
close.
Lessons Learnt
1) Incident could have been prevented if the hoarding and its
anchorage system were constructed according to the PEs
design and drawings.
2) The contractor should appoint a competent person experienced
in the hoarding erection to supervise and control the work on site.
3) The condition of the hoarding should be inspected on a regular
basis, especially after incremental weather conditions.
Key Findings
1) During the demolition of the embedded cooling water stub pipe,
there were no continuing inspections made by a designated
person to detect any hazard resulting from weakened or
deteriorated floors or walls, or loosened materials.
2) The weight of the top portion of the concrete aggravated by the
vibration generated by the pneumatic breaker used in the hacking
process probably caused the sidewall of the concrete to crack
and eventually gave way, resulting in the top right corner of the
concrete falling onto the deceased.
Lessons Learnt
1) Accident could have been prevented if the worker has carried
out the hacking work by standing in front of the block of the
concrete to be hacked instead of going inside the pipe hole
and worked under the block of the concrete to carry out the
hacking.
2) A designated person should be appointed to carry out continual
inspection while the demolition of the embedded cooling water
pipe was being done to detect any hazard resulting from the
work.
3) Appropriate training and briefing should be provided
for workers before they can be deployed to carry out such
demolition works.
All Rights Reserved
Deceased was
standing here
Key Findings
1) When the hacking started, it caused the end of the railing with
the very badly corroded metal leg to swing with great force
and speed. The force could be due to the vibrations
transmitted from the concrete breaker to the railing panel.
2) No Safe Work Procedure for the demolition of railings.
Lessons Learnt
1) Accident could have been prevented if gas cutting was used to
cut the two metal legs and remove the railing panel instead of
using concrete breaker to hack the footings.
2) No worker should be in the vicinity of the operation zone of the
excavator mounted with hydraulic breaker when it is in
operation.
3) The contractor should appoint a competent person experienced
in
the type of demolition work concerned to supervise & control the
work on site.
4) Appropriate training and briefing should be provided for workers
before they can be deployed to carry out such demolition works.
All Rights Reserved
Key Findings
1) Deceased had hacked the partition wall from the bottom section
using a 10-pound hammer.
2) The partition wall was simply resting on the ground and abutted
against the adjacent main wall. There was no interlocking joint
between the partition wall and the main wall.
3) As-built detailed drawings of the toilet walls were not made
available to the contractor prior to the hacking work.
4) In-house demolition procedures were not effectively implemented.
Lessons Learnt
1) Accident could have been prevented if the wall was demolished
in the reverse manner to that of its construction, i.e. the partition
wall should be hacked from the top section and extended down
progressively so as to maintain its structural stability.
2) Workers should be grouped in teams of two or more when
carrying out demolition works.
3) The contractor should appoint a competent person experienced in
the type of demolition work concerned to supervise and control
the work on site.
4) Appropriate training and briefing should be provided for workers
before they can be deployed to carry out such demolition works.