Professional Documents
Culture Documents
/Q.&S3
1J
-IV
COO-4211-3/2
MASTER
Clark University
Worcester, Massachusetts
U. S. DEPARTMENT OF ENERGY
Division of Buildings and Community Systems
-TjacncworTHisDoct
DISCLAIMER
This report was prepared as an account of work sponsored by an
agency of the United States Government. Neither the United States
Government nor any agency Thereof, nor any of their employees,
makes any warranty, express or implied, or assumes any legal
liability or responsibility for the accuracy, completeness, or
usefulness of any information, apparatus, product, or process
disclosed, or represents that its use would not infringe privately
owned rights. Reference herein to any specific commercial product,
process, or service by trade name, trademark, manufacturer, or
otherwise does not necessarily constitute or imply its endorsement,
recommendation, or favoring by the United States Government or any
agency thereof. The views and opinions of authors expressed herein
do not necessarily state or reflect those of the United States
Government or any agency thereof.
DISCLAIMER
Portions of this document may be illegible in
electronic image products. Images are produced
from the best available original document.
NOTICE
This report was prepared as an account of work sponsored by the United States
Government. Neither the United States nor the United States Department of Energy, nor
any of their employees, nor any of their contractors, subcontractors, or their employees,
makes any warranty, express or implied, or assumes any legal liability or responsibility for
the accuracy, completeness or usefulness of any information, apparatus, product or process
disclosed, or represents that its use would not infringe privately owned rights.
This report has been printed directly from copy supplied by the originating organization.
Although the copy supplied may not in part or whole meet the standards for acceptable
reproducible copy, it has been used for reproduction to expedite distribution and
availability of the information being reported.
COO-4211-3/2
Distribution Category UC-97d
1978
CLARK UNIVERSITY
950 MAIN STREET
WORCESTER, MASSACHUSETTS
01610
PREPARED FOR
THE U . S . DEPARTMENT OF ENERGY
UNDER CONTRACT NO. E C - 7 7 - C - 0 2 - 4 2 1 1 . A 0 0 1
PREPARED BY
CLARK UNIVERSITY
THERMO ELECTRON CORP.
FITZEMEYER AND TOCCI, INC.
BOZENHARD COMPANY
SHEPHERD ENGINEERING
NEW ENGLAND ELECTRIC SYSTEM
L. G. COPLEY ASSOCIATES
V*
CONTENTS
Volume I;
1.
2.
3.
4.
5.
Final Report
Introduction
Institutional Documentation
2.0 Introduction
1
5
5
2.1
2.2
2.3
5
5
6
8
2.4
Corporate Power
Interchange Terms
Financing
Air Pollution Impact
2.5
11
2.6
12
2.7
Labor Relations
12
13
3.0
Introduction
13
3.1
13
14
20
22
4.0
4.1
4.2
4.3
22
22
22
22
Introduction
Mechanical
Electrical and Grid-Connection
Architectural
4.4
Utility Tie-in
24
4.5
24
4.6 Monitoring
Financial Analysis
25
27
5.0
Introduction
27
5.1
Capital Costs
27
5.2
28
5.3
29
5 .4
5.5
Evaluation of Investment
Generalization to Other Sites
34
36
Volume II:
Appendices
39
2B
46
Utility Contract
2C
2D
109
3A
3B
3C
4A
116
119
123
Treatment Systems
74
132
147
152
160
4E Architectural Design
4F Utility Tie-in Specifications
4G Noise and Vibration Analysis
5A Project Effort and Capital Cost Analysis for
170
180
186
5B
193
205
TABLES
Volume I:
2.4-1
2.4-2
3.3-1
4.6-1
5.1-1
5.2-1
5.2-2
5.3-1
5.3-2
5.3-3
5.3-4
Final
9
9
.21
26
28
28
29
30
31
32
34
82
90
91
92
99
100
190
191
196
200
201
203
204
207
209
210
211
FIGURES
Volume I:
3.1-1
3.1-2
3.1-3
3.1-4
4.3-1
5.3-1
5.3-2
Final Report
2C-1
2C-2
2C-3
2C-4
2C-5
iii
FIGURES
Volume II;
(continued)
3C-1
3C-2
3C-3
3C-4
3C-5
4A-1
4A-2
4A-3
4A-4
4A-5
4D-1
4D-2
4D-3
4D-4
4E-1
4E-2
4E-3
4E-4
4E-5
4E-6
4E-7
4F-1
4F-2
4F-3
4G-1
5A-1
5A-2
TV
173
174
175
176
177
178
182
183
184
189
195
202
-1-
1.
INTRODUCTION
return of 15-20%.
(5) There appear to be no institutional or environmental problems that
would prevent operation of the system as planned.
In this report we provide an update on a number of issues that were
incompletely resolved in the Phase I report.
In Section 2 we provide additional documentation on institutional
basis to Clark when the ICES is not generating; it also describes terms for
sale of power by Clark to the utility.
(3) We are assured that we can obtain adequate financing through a 6-7%
interest HEFA tax-exempt bond issue. This makes the proposed ICES financially
viable for the University.
grams at 3% interest rate, and are currently exploring these with help of
Worcester's Congressman Early.
(4) We have had new worries about air pollution because of the introduction of short-term standards for nitrogen oxide concentrations; however,
it now appears that the plant will not violate either new or existing federal
and state regulations.
(5) There are no other serious environmental problems.
(6) There are, in addition, no problems with building codes, zoning and
fire ordinances.
In Section 3 we provide a preliminary design analysis that clearly
defines our choice of engine and provides revised operating data in light
of additional load profile studies.
(1) A Sulzer #6 oil burning 1405 KW diesel with ebullient cooling and
exhaust gas heat recovery is the system of choice.
(2) The engine and heat recovery system should be housed in a separate
building in close proximity to the existing boiler and steam distribution center.
(3) As a result of summer load studies we have determined that the engine
as specified can be operated with a capacity factor of 90%, instead of the
Phase I estimate of 85%.
In Section 4 we present a summary of our preliminary design package.
This includes sufficient detail to make a much more reliable estimate of capital
and construction costs. Major items included here, but not previously, are
a fuel treatment facility, preliminary design of a building, preliminary layouts
of equipment, including a cooling tower on the roof of an existing building.
-3-
-4To prepare for a final decision to go ahead with the project Ce-xpected
late August, 1978), the University will apply this summer for financing under
two federal energy conservation loan programs. Clark will also seek the
necessary permits from the Massachusetts Department of Environmental Quality
Engineering, and will begin those aspects of final design necessary to ensure
that construction can begin June, 1979.
2.
-5INSTITUTIONAL DOCUMENTATION
2.0
Introduction
These critical issues were (1) whether the University has the
Corporate Power
Interchange Terms
Clark and the Massachusetts Electric Company have agreed on terms for
interchange along the lines described in our Phase I report.
Letters from
-6able. The agreement empowers Clark to use directly as much of the ICES
electricity output as Clark needs. Only when the ICES output is insufficient
for the Clark demand will Clark purchase electricity from Massachusetts
Electric.
Clark has two options for purchases, but must choose one for
iary service rate is in effect at the time. At present Clark would guarantee
a minimum monthly payment based on its contracted demand and would make all
purchases under one of the regular retail rates. Because Massachusetts
Electric has informed us that they expect this auxiliary rate to change in
the near future and because Clark wished for terms which would be defined
over the twenty year life of the contract, Massachusetts Electric has
offered Clark a second option. This option would require that Clark pay a
monthly charge for distribution capacity based on contracted demand, and
pay for all purchases under a retail energy rate, C-22, or the equivalent.
The monthly charge would go from $1.00/kw to $2.00/kw in five years, then
remain fixed at $2.00/kw.
When Clark makes more electricity than it can use, the excess will be
sold to the utility for a price closely approximating the cost of displaced
fuel.
This price depends on time of day; thus there will be two prices, one
for weekdays from 7:00 A.M. to 11:00 P.M., the other for the remaining times.
For convenience, the price will be factored into two pieces, a multiplier
times the average wholesale fuel cost. There will be two multipliers, one
for peak and the other for off-peak sales.
has estimated the peak multiplier to be 1.45, and the off-peak multiplier to
be 1.25.
Financing
-7Tables 1.2.4-2 and 1.2.4-3), this program could provide financing at 3% for
half the project cost. The program has been funded again this year and final
regulations should be published very soon. Another program covering all
university buildings is administered by the Office of Education; it was not
funded last year, but funds have been released for it this year. This program
will also make some matching grants. We are prepared to submit applications
for either program the moment final regulations are published, early this
summer.
Because federal financing is not certain, we have spent considerable
effort in seeking approval for a HEFA bond issue. We have retained an
investment broker, Marsom Pratt of Adams, Harkness and Hill, to handle
the bond issue. Mr. Pratt is investment counsel to HEFA.
In 1976
he developed the successful bond issue for Clark's new Student Activities
Center and he is confident that a HEFA bond issue can be developed for the
ICES and that it will be approved by HEFA.
higher interest rate than the 5% we paid on the public issue for the Student
Activities Center. The interest charges will not exceed 7% in any event.
HEFA approval for the bond issue must come in two stages. We have obtained
preliminary approval for the bond issue.
This may offer even better terms than the HEFA bond issue.
Under this plan an investor would own the facility and lease it to Clark. He
would be able to offer good terms because he could take advantage of
tax benefits, investment tax credit, accelerated depreciation, etc., which
do not apply to the University.
-8-
We are
2.4
The net effect of the proposed Clark ICES is to increase air pollutant
emission in the immediate neighborhood of the University, and to decrease
emission at more distant utility power plants.
in Appendix 2C, A summary of effects may be read from Tables 2.4-1 and
2.4-2 indicating annual and peak emission rates.
With respect to published federal standards Worcester is currently a
non-attainment area in three pollutants: particulates, CO, and oxidants.
Worcester is an attainment area for two other pollutants: SO- and N0 2 .
(There are no standards for HC.)
Act Amendments of 1977 require a permit from local authorities for new sources
emitting over 100 tons per year of the non-attainment pollutant.
under 100 tons are unregulated.
Sources
requires that new sources emitting over 250 tons of a given pollutant not
affect ambient levels beyond a certain "significant increment of deterioration." Sources under 250 tons are unregulated.
A glance at Table 2.4-1 shows that under the present definition, all
non-attainment pollutants emitted by the ICES are under 100 tons annually,
and all attainment pollutants are under 250 tons annually.
It is for this
-9-
System
so 2
CO
HC
Particulates
25
54
79
0.5
1.0
1.5
l.S
155
39
-15
179
24
11.2
0.7
0.5
2.3
-0.3
-0.9
3A
11.6
1.9
N0
Present system
Utility boiler
Clark boiler
System impact
36
78
114
3.2
4.7
ICES System
Utility boiler
57
56
-22
System impact
ii
Clark diesel
Clark boiler
*may be overestimate
System
Tabl e 2.4-2:
so2
N0 2
CO
HC
Particulates
'
Present system
Clark boiler
4^0
3.7*
0.02
3.5
1.8
5.3
3.2*
0.02
5.0
0.8
0.4
8.2
0.8
0.4
0.02
ICES System
Clark boiler
Clark diesel
Total
'may be overestimate
-10of certain EPA designated computer .modeIs, and interpretation of results obtained from these in light of existing hourly maxima.
In anticipation of the forthcoming EPA hourly maximum standards we have
been working with Ed Benoit, Chief of the Central Massachusetts Air Quality
District.
We have
subsequently measured NO emissions from our boilers and obtained values less
than 1/4 those in Tables 2.4-1 and 2.4-2; however, these measurements were
made while the boiler was burning gas and do not include NO production from
bound nitrogen in residual oil. Maximum hourly effects of the combined Clark
system on six sensitive targets in the near neighborhood ranged from 50 to 300
3
3
/igms/m . The peak concentration from the diesel plume is nearly 200 /ug/m .
3
If the forthcoming EPA standard i s set at 200 jug/ra the project appears t o be
in trouble. According to Benoit, who has considerable modelling experience,
3
200 Aigm/m would place in jeopardy nearly every new NO- source of 100+ tons in
urban Massachusetts. Benoit has, however, assured us that we have no d i f f i c u l t y
with other a i r quality regulations (see l e t t e r dated April 5, 1978, in Appendix
2D).
Further complicating the picture is the fact that recently, under intense
community pressure, the Massachusetts Department of Environmental Quality
Engineering (DEQE) has issued an order halting construction of a 22 MWe,
six-diesel, total energy plant being built by Harvard University in downtown
Boston.
The impact of this project, which has total NO- emissions about
certain "sensitive" targets such as homes for the aged, and hospitals.
3
Added to ambient hourly maxima of 300 to 400jug/m , the Harvard project
was believed to be capable of producing hourly maxima in the range of 5003
600 iUg/m at certain downtown Boston locations. The principal finding of
DEQE Regional Environmental Quality Engineer McLoughlin in the Harvard
University case is that existing federal NO- regulations are tqo lax, and
allow the possibility of serious health effects. A proper interim safety level,
3
according to McLoughlin, is 200jug/m hourly maximum. It is for this reason
that Harvard's project was disallowed.
3
At present the Massachusetts DEQE interim standard 200 jugm/m will not
apply to sources of less than 250 tons annually (see E. Benoit letter dated
May 2, 1978, Appendix 2D) and hence the Clark project will not be affected by
EPA standard (which will supercede the interim Massachusetts Standard), the
Clark project will require review.
Appendix 2D) that there will be no difficulty if the EPA standard falls in the
3
range 470 - 940 jugm/m , now under consideration (March 27, 1978, Federal
Register).
A further change in air pollution regulations is the forthcoming EPA
emission standards for diesel engines. These are the responsibility of the
diesel manufacturer and so will not affect Clark except insofar as they limit
the availability or performance of engines. The EPA draft proposed standard
calls for a limit on NO
concentrations and
This effluent will contain less than 80 ppm oil, 600 ppm sodium
chloride, 70 ppm lead, 50 ppm calcium chloride, 5 ppm potassium, and 50100 ppm magnesium.
-12Noise. Noise from the plant will not change ambient levels as described
in section 4.5 and Appendix 4G.
Increased oil deliveries. The number of oil deliveries will be increased
about 50% from the present 120/year.
campus, but not in the adjacent heavily commercial Main Street area.
Construction.
We have been assured that the proposed ICES design can meet all
building code, zoning, and fire regulations.
Labor Relations
closely involved in the planning for the ICES and we anticipate no laborrelated difficulties in plant operation.
For the construction of the plant, Bozenhard said that he foresees no
problems with local unions. The job has been budgeted for union labor and
would be bid by union-affiliated contractors.
relations are good.
-13-
Introduction
it is ebulliently cooled, burns //6 oil, and produces about 1400 KW of electricity. With the #6-burning engine, we need one more subsystem for
the conceptual design, a fuel treatment system.
In the next section, 3.1, we present our new results on thermal demand,
and describe the electrical and thermal outputs of the new diesel.
In sec-
tion 3.2 we review the Phase I choice of system and then give our reasons
for selecting the Sulzer engine and the new location.
In section 3.3 we
describe the changes needed in the conceptual design to accomodate the new
engine and location.
3.1
The electricity load profile presented in our Phase I report was based
on several years of recorded data.
with the previous records, we have not altered our estimated electricity
load profile. The profile contains an estimated contribution from the new
gym; the estimate is consistent with preliminary data from the first month
the gym has been in use.
The thermal load profile presented in the Phase I report used estimated
summer thermal demands. We now have data on thermal demand for this summer
and this changes somewhat our previous estimate. We have found that at
present summer thermal demand is considerably more uniform than we had
estimated.
of the new gym and our estimate is consistent with preliminary data. The
added demand in summer nights means that we will be able to operate the ICES,
at part load, for many summer nights, and the overall output of the system
will be somewhat greater than our previous estimate.
-14We repeat the electric load profile and present our new thermal load
profile in Fig. 3.1-1.
outputs of the Sulzer 1405 kw engine. Except for summer nights and brief
periods for maintenance, the engine operates at full load continuously.
The
overall fuel saving we expect is about 300,000 gals/yr oil saved by Clark and
the electric utility.
demands with the ICES output. Fig. 3.1-3 shows the total annual fuel savings
produced by the ICES (approximately 8000 barrels/year).
This location is
choice is that it adds significantly to the capital cost of the project (see
section 5.1 and Appendix 5A).
enough for Clark's heat demand simply do not make enough electricity to
finance them.
Gas turbines suited to our size burn distillate oil and have
-15-
Fig. 3.1-1:
. 1500
1000T
500 -
2000
Sfl 10
4000
6000
8000
Annual Hours at Power Level P or Greater
'f / / / / / /
/
2000
// // // A / y iesel/
/Heat Output of p
4000
6000
8000
-16-
ELECrRICtTy
(Million
Ku)h)
SO
100
(SO
ZOO
ZfO
ClourK electric
300
dema.nd
I
1
K&f&tt
I HEAr = 77 B&tu
-i
^
2 ^4
4.5
6.5*
Q.H
20
*ID
HEAT
60
So
(Billion Biro)
CoVvENVOhJM
Fig. 3.1-2. Yearly Energy Balance
100
ICES
17-
(THouSAMPS of BARRELS)
FUEL
$*
ts
10
Ar
Ar aARK
7/7 h
: . . s.
*
ZO
i
2f
r
uriury
77/7
31% FoL
SAVING.
ko
8o
Ho
ItO
FUBL
Fig. 3.1-3.
(BBtu)
FUBL
T~
(IOOO'<S Of
/r
10
BARRELS)
ZO
~~T"
T"
zr
30
-I
35"
T
BOILER
r.c */%
...;...BOILER ;.
43% INCREASE
CoNVEMtloNfM
1
Qo
VEMAtJp-
1
9>o
1
l(>o
no
FUEL
(BBto)
CoU^EMriDA)A^
SYSTEM
Fig. 3.1-4.
1M lUl BUfWED
yM
loo
Z.C.E.S. RUS
BOILER.
-19a steam heating system and it would be prohibitively expensive to make the
modifications needed for heating some buildings with hot water. There are
two advantages to burning residual oil; it is significantly cheaper, and
it is in the national and regional interest not to add to the pressure on
the demand for light oil and gas. Grid-connection obviates the need for
multiple engines,as we don't have to follow Clark's electrical demand and
as we are not considering engines large enough to require extensive variation of heat output.
and a 1500 KW engine made by Cooper Bessimer, Superior model 40-X-16. The
Sulzer engine is normally water cooled, not ebulliently cooled; however,
the Sulzer Company assures us that the alterations are minor ones and that
they are happy to maintain their standard one-year guarantee. The Superior
engine normally burns distillate oil; the manufacturer, Cooper Energy Systems,
is willing to modify the engine to burn residual oil. They too will maintain
their one-year guarantee, with the proviso that the fuel entering the engine
be carefully monitored to ensure strict limits on sodium and vanadium in
the fuel.
Since both manufacturers are confident that the modifications will not
impair the performance of the engines and since they will guarantee the
engines, we feel that both engines are viable options. Since they offer a
significant economic advantage over the distillate-fired engine, we would
prefer one of them as the generator for the grid-connected ICES.
It is
-20We chose the Sulzer engine in preference to the Superior for the following reasons. (1) We believe that the burning of residual oil is a more sensitive modification than the change to ebullient cooling.
laboratory and field experience with burning #6 oil in that engine. That
experience is summarized in Appendix 3A. (2) Sulzer places slightly less
stringent limits on vanadium and sodium than Superior. (3) The Sulzer engine
gives a slightly better return on investment (see section 5.3). (4) The
Sulzer engine is smaller and will be easier to install.
Each of these is a small consideration, but taken together they lead
to a preference for the Sulzer engine. This preference could be reversed
by a continuing decline of the dollar relative to the Swiss franc, which would
make the Sulzer still more expensive than the Superior engine.
3.3
In Appendix
used in the boiler system, the //6-burning engines have appreciably lower
fuel costs, about 5.5 mills/kwh less than the //2-burning engine described
in Phase I.
-21-
Table 3.3-1:
Fuel
Sulzer
Superior
#6
#6
1405 kw
1500 kw
Thermal Output
4.0xl06 Btu/hr
5.3xl06 Btu/hr
1.3xl06 Btu/hr
2.5xl06 Btu/hr
2.7xl06 Btu/hr
2.8xl06 Btu/hr
Electrical Efficiencies
34%
31%
Thermal Efficiencies
39%
43%
Heat Pate
10,010
Btu/kw
11,060
Btu/kw
6,110
Btu/kw
6,260
Btu/kw
-224.
DESIGN PACKAGE
4.0
Introduction
mechanical, including
We describe our
preliminary design for each component briefly and refer to the appendices
for more detail.
4,1
Mechanical
The major mechanical items are the diesel engine and generator, jacket
heat recovery system, exhaust heat recovery system, fuel supply system, and
fuel treatment system.
3C
The design, control and operation of the other mechanical systems are described
in detail in Appendix 4A.
Appendix
provision
of adequate lighting to the new building under normal and emergency conditions,
operation of motors for a large number of mechanical components, and compliance with Mass. Electric requirements for the grid-connection.
The equip-
ment needed to meet each of these demands is described, with outline specifications, in Appendix 4D.
4.3
Architectural
Second,
First of
Our equipment
near the focal point of the campus, it must not intrude too much on the open
space that is available, and its design must be compatible with the neighboring structures, including Jonas Clark Hall, the Goddard Library, and the new
Goddard Memorial.
number of the Clark Trustees and other members of the Clark community felt
that this building would not be satisfactory because of its mass, particularly
-23-its'.
v-?
o p
O'
ra
I
tl
I noun
tjr^romMF M M
My*ra*n, -
4>
FT
S ^
CBKMTM C I * T d X ( * t * U .
M3TOA
7 \
1
COMT
A OL PRMEL.
-+K-
L33 7
JUCfttT VjtR IftU l 5 / l
HEAT ElCHMUD- I
EkKAU5T SHEKEL
-t^
SI
-ff
-ET
r - i ~-
I JLCKE7 WTt
/ / REKHmT M O U R E .
- >
OKtl*
^?
^ vaju=ti
I CL-x^OLJtc
t-a.
",.
_Lt-
-JACKET '
y
1
T
/
e c u s re
IJUST P-_*MTS
t^TtT"
3 'I3"s~
M>aiMMU<TYP>
ft=i-
=E*
^
ET
rrr
llm
ZJf
k-
at
A-A
wSSBTcTJJSricTrTCBJf
Figure 4.3-1
Equipment Layout
h r r- hsrf ri-
-24its height. The height of the building had been determined by the need to
provide adequate clearance over the exhaust gas run shown in Fig. 4.3-1.
We have recently ascertained that a straight exhaust run would be possible
from either the Sulzer or the Superior engine at little or no additional
cost.
approximately 10' above grade on. the west side of the building and 20'
above grade on the east side, an overall reduction in building volume of
about 40%.
Since the new height is at the top of the indentation shown in Figures
4E-.4 through 4E-7 in Appendix 4E, a new design for the building envelope
is necessary.
crossed with the new dimension, and that it will be possible to make.a new
design that fits well into that part of the campus.
4.4
Utility Tie-In
15 psig steam lines; steam from the waste heat boiler must be tied to the
existing 125 psig lines; residual oil must be supplied to the diesel from
the existing oil tanks. A new light oil fuel tank and distribution system
must be supplied for starting and stopping the diesels.
Details of the
Noise and vibration are critical issues for the Clark ICES since the
facility is to be located in the center of the Clark campus and since it
will be in a building attached to Jonas Clark Hall, a major four-story
classroom building.
is a 90-year-old building with 18" thick brick walls, and the existing
heating plant in the basement has had adequate noise and vibration isolation.
vibration. The present ICES design will meet our design objective of
making no significant increase in ambient noise levels anywhere the campus
is used.
-254.6
Monitoring
the boiler and ICES and ambient levels at Clark University are of interest.
The
require the addition of ambient CO and N 0 2 sampling, as well as source measurements of particulates, S0_, CO, and NO-.
for monitoring.)
(2) Monitor the heat of combustion of residual oil.
of residual oil varies widely.
To check whether
our fuel treatment plant is working properly and to obtain accurate information
on residual oil operating costs, it is important to measure these impurities
on a routine basis before and after fuel treatment.
(4) Monitor performance of diesel engine.
requires a continous record of useful heat and electrical output of the ICES.
This may be done by metering fuel and water feed lines.
(5) Monitor sector heat loads.
and heat loads requires knowledge of sector heat demand within the university.
Sector heat demand may be measured by metering condensate return for six
divisions of the University.
The preliminary cost estimate is given in Jable 4.6-1.
-26Table 4.6-1:
Monitored variable
Monitoring equipment
Method
Equipment
Cost
so 2
NO2
$11,000
$500
CO
$2,000
$500
particulates
$3,000
$500
so 2
periodic measurement on
fuel by Clark
N0 2
CO
Heat of combustion
$500
$ 8,000
$500
$500
periodic measurement by
Clark
$500
'10,000
$500
Engine performance
fuel use
heat rate
Fuel contaminants
$17,000
$500
2,000
500
Totals
500
$53,000
$5,500
-27-
5. FINANCIAL ANALYSIS
5.0 Introduction
In their November evaluation of the proposed ICES, the Clark Trustees
agreed to the following investment criteria:
(1) The ICES should be 100% financed from savings, using an external
source of capital.
(2) The expected payback period, including principal and interest
should be 10 years or less.
(3) There should not be large risks associated with uncertainties in
future economic conditions.
In November 1977 we showed that the proposed ICES met these requirements.
At this writing, after a considerably more detailed analysis, and despite
significant changes in some economic parameters, we confirm this conclusion.
We discuss capital and operating costs in the next two sections. In
Section 5.3 we compare the ICES with the conventional system and show that
the
payback period is 9.4 years and the internal rate of return is between
14 and 15%. We also discuss the sensitivity of our model to various assumptions
about key parameters, and conclude that the
e.g. the extreme bounds of the payback period are 15 and 5 years, respectively.
In Section 5.4 we discuss other features of the ICES which make it an attractive
investment for Clark.
Detailed cost
breakdowns are given in Appendix 5A. The total capital cost to Clark, beginning
with phase III is $1,460,000 for the Sulzer based system.
In addition we
expect to request DOE to fund the following demonstration capital cost items.
(1) Grid-connection at about $41,000, as per the original RFP.
(2) Monitoring equipment at about $53,000, as per the original RFP.
(3) Demonstration-related aspects of the power plant building, providing
accessibility to the public, at about $28,000.
(4) Fuel treatment system, at about $95,000.
Sulzer Engine
895
287
60
223
1,465
41
53
28
95
217
Superior Engine
823
287
60
223
1,393
41
53
28
95
217
The first three are straightforward outgrowths of the present demonstration program. The fourth is discussed in more detail in Appendix 5A. We
believe that fuel treatment should be considered a demonstration cost, at
least in part, because sodium (accounting for most of the capital cost) is a
regional problem only, and because there will be major economics of scale when
use of heavy oils in engines becomes widespread. For example, a fuel treatment
facility of ten times the capacity would only cost about twice as much.
5.2 Fuel and Maintenance Costs
Fuel costs with heat credit for the two candidate engines are evaluated
in Table 3.3-1 and Appendix 3C. They are summarized in Table 5.2-1:
Table 5.2-1: Fuel cost and heat credit (mills/kwh)
Engine
Fuel cost
Sulzer 1405 KW
257o
Superior 1500 KW
27.7
Heat credit
9~77
12.0
Yearly Cost
Sulzer
Diesel engine
Superior
$42,500
$41,400
Fuel treatment
3,800
7,100
Miscellaneous
TOTAL
9,000
9,000
$55,300
$57,500
5.6 mills
5.5 mills
system has a first year operating savings of $162,000, and a net savings after
payment of financing costs of $20,000. By the tenth year these savings project
to approximately $240,000 and $100,000 respectively in constant 1980 dollars.
The present estimates are little different from those obtained in November, as
shown in Fig. 5.3-1.
We have examined the sensitivity of the projected savings to the values of
our base case parameters. In Table ; 5.3-4 we list the key parameters and the
sample variations we have used to test the sensitivity of the savings. Figure
-30-
Table 5 . 3 - 1 :
Variable
Rate of inflation
6%/VT
$3.00/MBtu
#6 oil
$2.50/MBtu
4.7*/kwh
2.7*/kwh
2.4*/kwh
first year:
$18,000
after 5 years:
$36,000
1.2
Plant lifetime
20 years
6.9xl06 kwh/yr
75%
6.9xl06 kwh
6.5xl06 kwh
0.4xl06 kwh
4.
4.6xl06 kwh
U.lxlO 6 kwh
6.
12.5X106 kwh
7.
Capacity factor
90%
8.
6%
9.
8%
HEAT
10
10.
11.
11x10
3xl0
Btu
10
Btu
FUEL SAVINGS
12.
10 Btu
4x10
-32Table 5.3-3
FIRST YEAR (1980) BASE CASE CALCULATION
Sulzer Engine
A. Capital Cost
B. Interest Rate
C. Annual Capital Cost ($K)
D. Annual Fuel Cost
E. Annual 0 M
F. Annual Heat Credit
$1,650,000
6%
141,000
278,000
70,000
108,000
G. Operating Cost (D + E - F)
H. Conventional Electricity Cost
326,000
I. Clark Sales
114,000
J. Purchases
K. Total Credits (H + I - J)
L. Net Operating Savings (K - G)
M. Net Savings (L - C)
N. Payback (years)
0. Internal Rate of Return
240,000
38,000
402,000
162,000
21,000
9.4
14.5%
.-33-
1988
VeAfl
Fig. 5.3-1:Base case net savings expressed in constant and
current dollars.
MO
-345.3-2 shows the variation of the Sulzer engine savings with each of the changes.
The total variation is taken to be the square root of the sum of the squares of
each individual variation. The savings are always positive, even the total
variation; hence the risk inherent in the ICES investment appears acceptable.
Table 5.3-4: Sensitivity Analysis
Key parameter
Base value
0.75
0.06/yr
1.2
0.06/yr
Inflation rate
Variation tested
0.85
0.03 - 0.07/yr
1.35
0.0 - 0.12/yr
0.3 $/kwh
$200,000
0.06/yr
5.4
0.03 - 0.09/yr
Evaluation of Investment
The anticipated 15% internal rate of return with the reasonable assurance
of positive net savings is enough to make the grid-connected ICES an attractive investment for Clark.
as
remaining half are subject to inflation. Thus the costs using the ICES
will rise much more slowly than costs for the conventional system as oil
prices go up. Of course, costs would decline less rapidly if oil prices
dropped, but we consider that much less likely.
Furthermore, by generating
rates will change in the next year, as the DPU has required utilities to
introduce time-of-day rates.
Furthermore, the
University does not have much flexibility for shifting more electric use to
the nighttime and so it could be hurt by very high peak rates.
-35-
200
interest
rate
boiler
efficiency
to
u
id
rate struct,
multiplier
oil price
escalation
per year
inflation
rate
total varia
tion (r.r>.s)
(excludes
.
rate struct*
loo
O
O
oo
C71
G
at
J
(A
o
o
increased
credit for
export of
power
10
bo
capital cost
Cd
CO
0>
too0.3*/kW]
$200,000 ,'
under ,'^/'/.
run " ~ * 0 / /
overrun
80
90/80
90/80
90/80
YEAR
Fig. 5.32: Sensitivity of savings for the Sulzer engine
burning #6 oil.
90
5.5
The analysis of the previous two sections shows that the proposed ICES
is a reasonable investment for Clark University at this point. It is interesting
to consider how important the DOE contribution is to this conclusion. There
are
Clark's base capital cost is $100,000 to $200,000 less than it would cost Clark
to design and build the plant without DOE participation.
are within the range of uncertainty of capital costs considered in our sensitivity analysis.
The answer to the second question is that DOE participation has been
essential to Clark's resolution of most institutional issues, and hence Clark's
willingness to continue the project. We have repeatedly found in dealing
with Massachusetts Electric, with the Department of Public Utilities, with
the Attorney General, and most recently with the Department of Environmental
Quality Engineering that Clark's case represented a first-of-a-kind test
case.
It is quite clear that under these conditions the Clark trustees would
soon have lost heart had it not been for the support of DOE.
In addition it is
unlikely that Clark would have been prepared to make extensive engineering
comparisons of alternative systems before knowing that the project was feasible,
yet these comparisons were essential in finding the most suitable configuration
for a facility like Clark.
Assuming, then, that the Clark ICES is built, we believe that a number of
important precedents will have been established which will make the installation
of subsequent facilities considerably easier. The technical comparison of
useful by carefully documenting its performance, its impact on the utility and
its environmental effects.
/
-38-
VOLUME I I
APPENDICES
-39-
Appendix 2A
Letter
on Financing
from
Marsom B. Pratt
Senior Vice President
Adams, Harkness and Hill, Inc.
and
Letters on Utility Tie - In
from
Mary Joann Woods Reedy
Assistent Attorney General
Commonwealth of Massachusetts,
Richard W. Mirick
University Counsel
(two letters)
and
William Cadigan
President
Massachusetts Electric Company
-40-
5 5 COURT
STOCK
rxCHANC.lS
STREET
BOSTON, MASSACHUSETTS
OaiOS
'617!
227-5500
T c i t x 3 4 0 S I S ADAMS BSN
April 6, 1978
Marsom B. Pratt
ypnior Vice President
JUrv^ivnk
c.': i\ip.s<;/b. B>-(>-'n, "ri'-.xl and Winter
ii
41-
THE
COMMONWEALTH
OF
MASSACHUSETTS
BUILDINQ
0210B
rRAN cm x. a t L L o m
ATTORNEY
1INIML
Sincerely,
7uln %^-Aj^
MJWR/kah
-42-
W O R C E S T E R , M A S S . OiGOS
GI7
799-0541
November A, 1977
Richard W. Mirick
RWM/pjb
Enc.
-43-
Massachusetts Bedric
William J. Cadigan
Prttktonl
-44-
-45-
WORCESTER CENTER
WORCESTER, MASS.
BI7
016O8
799-0541
G E O R G E H. M I R I C K ( I 9 I O - I 9 S 3 )
J O H N M. R I E D L
J O H N O. MIRICK
R I C H A R D G. S M A L L
M a r c h 2 0 , 1978
RWM/abm
Richard W . Mirick
-47AGREEMENT dated as of
University, a Massachusetts university of higher education, hereinafter called "Clark", and Massachusetts Electric Company, a Massachusetts corporation, hereinafter called the "Company".
ARTICLE I.
BASIC UNDERSTANDINGS.
-48-
Where not inconsistent with this Agreement, the Company's Terms and
Conditions as on file and in effect from time to time shall apply.
copy of the Terms and Conditions in effect and on file with the
Massachusetts Department of Public Utilities at the date of the execution
of this Agreement is attached hereto and incorporated herein by reference.
ARTICLE II. EFFECTIVE DATE AND TERM.
The term of this Agreement shall commence as of 12:01 A.M. on the
earlier to occur of (1) the commercial operation date of the Plant, as
mutually agreed upon by the parties, or (2) sixty days following the date
on which Clark shall first make delivery of electricity through the
Interconnection Point, as hereinafter defined, (the "Commencement Date"),
and shall extend, until terminated by either party giving the other six
(6) months' written notice specifying the date of termination; provided,
however, such date of termination shall not be earlier than twenty (20)
years after the aforesaid Cjcmmencement Date.
Notwitlistanding the foregoing, however, if at any time during the tenr. of
this Agreement the Plant fails to operate for a period of more than ninety
(90) days due to causes beyond Clark's immediate control and Clark determines that it will no longer operate the Plant in the future to meet its
electric energy requirements, then upon thirty (30) days written notice
to the Company this Agreement shall terminate and Clark shall commence to
take service from the Company under the Company's then effective Large
Power Rate as on file with the Department of Public Utilities or such
other rate as may then be most applicable.
-49-
-50-
-51-
PLUS
(2) For all electricity delivered during hours other
than those specified in (JL) above, a price in nulls
per kilowatthour equal to the Company's estimate
of the incremental cost of fuel for such other hours.
For the purpose of (1) and (2) above the Company's incremental
cost of fuel for the specified hours shall be determined by multiplying
the average cost of fuel during the preceding month of the Company's
wholesale supplier, New England Power Company (NEP), determined in
accordance with NEP's FERC Electric Tariff as on file and as effective
from time to time, times a multiplier reflecting the estimated relationship
between NEP's average and incremental cost of fuel for the specified "
hours during the current year as determined from incremental cost
studies performed annually by New England Power Service Company, NEP's
and the Company's service company affiliate. The Company shall make
available for Clark's inspection records relating to the incremental
cost studies utilized in determining the above referenced multiplier.
-52-
(1)
and
-53-
-54-
Rate as on file and in effect from time to time shall apply throughout the
remainder of the term of this Agreement.
(C) Bills for amounts due under this ARTICLE IV shall be rendered
monthly to the respective parties and shall be due and payable upon
receipt thereof. When all or any part of the bill shall remain
unpaid for more than twenty-five days after the receipt thereof,
interest at the simple rate of one and one half percent (1 1/2%)
per month shall accrue from the date of receipt until the date
of payment on either (1) such unpaid amount or (2) in the event
the amount of the bill is disputed, the amount finally determined
to be due and payable. For purposes of this paragraph the date of
receipt of a bill shall be presumed to be three days following the
date of mailing, unless the bill is delivered rather than mailed,
in which case the date of receipt shall be the same as the date of
55
ARTICLE V.
I^m!aO3NNECTI0N RESPONSIBILITIES.
. Without'limiting
the foregoing, said metering equipment shall include two digital pulse
recorders.
-56-
Both parties shall comply with any reasonable request of the other with
regard to sealing of meters, the presence of a representative of the other
party when the seals are broken and tests made, and other matters affecting
the accuracy of measurement of electricity delivered.
If at any time the metering equipment is found to be inaccurate
by more than two percent (2%) up or down, the Company shall cause it
to be made accurate and the meter readings for the period of inaccuracy
shall be adjusted to correct such inaccuracy so far as the same can
be reasonably ascertained.
-57-
ARTICLE VII.
ACCESS TO PLANT.
-58-
-59-
CLARK UNIVERSITY
By_
By.
CLARK UNIVERSITY
Vice President
OR
ARTICLE IV (B) (2)
Title
By_
Title
By_
Title
'-60-
MASSACHUSETTS ELECTRIC
COMPANY
AVAILABILITY
Service is available under any applicable filed rate of this Company
for Auxiliary Service, sometimes referred to as Standby or Breakdown Service,
and more fully defined as service available at all times to a Customer having
another source of power, electrical or mechanical, from which to supply his
requirements of light, heat or power, or a portion thereof. Where such other
source is used only in case of failure of the Company's service, the Company's
service shall not be considered as Auxiliary Service.
RATE
The charge for electricity shall be computed under the Rate applied
with this Provision, but not less than $1.75 per month per KVA of contractual
transformer capacity.
TERM OF AGREEMENT
The agreement for service under this rate will continue for an initial
term of one year if electricity can be supplied to a Customer without an
uneconomic expenditure by the Company. The agreement may be terminated at
any time on or after the expiration date of the initial term by twelve months'
prior written notice; provided, however, the Customer by written notice to the
Company may terminate Auxiliary Service at any time should the Customer permanently abandon the operation of his own source of power.
Effective
December 1, 1971.
-61-
per
per
per
per
KWH
KWH
KWH
KWH
First
Next
Next
Next
Xcs of
Minimum Charge
Zero Use
$1.87
=
$2.00
MASSACHUSETTS ELECTRIC
COMPANY
GENERAL RATE C-22
AVAILABILITY
Service under this rate is available for all purposes.
No service will be furnished hereunder to a Customer for resale in whole
or in part within the territory of the Company, except to a Customer who was
engaged in reselling electricity furnished by the Company on April 21, 1958 who
may continue to resell, but only under the same circumstances or conditions, in
the same location and to the same extent as such Customer was reselling on said
date.
MONTHLY CHARGE
$1.87
6.016
5.416
4.306
3.116
M. D. P. U. No. 374
Sheet 2
MASSACHUSETTS ELECTRIC
COMPANY
GENERAL RATE C-22
MINIMUM CHARGE
$1.87 per month.
However, If the KVA transformer capacity needed to serve a customer
exceeds 25 KVA, the minimum charge will be increased by $1.75 for each KVA
in excess of 25 KVA.
BIMONTHLY BILLING
The Company reserves the right to read meters and render bills on a
bimonthly basis. When bills are rendered bimonthly, the charge for the initial
block, the kilowatt-hours stated in each block and the Minimum Charge shall be
multiplied by two.
TERMS AND CONDITIONS
The Company's Terms and Conditions in effect from time to time, where
not inconsistent with any specific provisions hereof, are a part of this rate.
-64-
M. D. P. U. No. 266
Sheet 1
I lASSACliHSETTS ELECTRIC
COMJ'ANY
PURCHASED POWER COST ADJUSTMENT
PROVISIONS
herein is the Primary Service for Resale Rate of the New England Power Company
as from time to time on file and effective with the Federal Power Commission,
exclusive of any adjustment for cost of fuel applicable thereto.
Upon any increase in the wholesale price the Company may at its option
Increase any one or more of the prices In applicable rates of the Company by
an amount not exceeding the applicable Purchased Power Cost Adjustment.
Upon any decrease in the wholesale price the Company will decrease the
prices under its applicable rates by an amount equal to the Purchased Power
Cost Adjustment.
Any adjustment of the prices under the Company's applicable rates shall
be In accordance with a notice filed with the Department of Public Utilities
setting forth the amount of the applicable Purchased Power Cost Adjustment,
the amount of the increase or decrease, if any, to be made in each of the
prices under these r.itcs, and the effective prices under the rates as so adjusted.
The notice shall further specify the effective date of such adjustment, which
-65-
M. D. P. U. No. 266
Sheet 2
MASSACHUSETTS ELECTRIC
COMPANY
PURCHASED POWER COST ADJUSTMENT
PROVISIONS
shall be not earlier than thirty days after the filing of the notice, or
such other date as the Department may authorize.
The Company may file such notice with the Department with respect to
any increase in the wholesale price at any time, but the effective date of
the adjustment of prices under its applicable rates shall not be earlier than
the effective date of such wholesale increase. The Company will file such
notice with the Department with respect to any decrease in the wholesale price
not more than seven days after the effective date of such decrease or the date
on which the Company shall have received notice of such decrease, whichever
is the later.
If the Company receives any refunds from New England Power Company
representing excess amounts collected over the rates subsequently allowed by
the Federal Power Commission, the Company will make an equitable adjustment of
such refunds with its customers whose rates are affected by the Company's
Purchased Power Cost Adjustments in such a manner consistent with the applicable
provisions of Chapter 164 as may be approved by the Department.
The amount of
any such refund by the Company shall not be greater than any applicable excess
amount collected by Massachusetts Electric from its customers.
The operation of this Purchased Power Cost Adjustment clause is subject
to all powers of suspension and investigation given to the Department by
Chapter 164 of the General Laws.
Effective
<
M. D. P. U. No. 379
Cancelling M. D. P. U. No. 360
Sheet 1
MASSACHUSETTS ELECTRIC COMPANY
STANDARD FUEL CLAUSE
The amount of the charge made by the Company for each kilowatt-hour
of electric energy consumed by the customer, as determined under the Monthly
Charge section of each rate or the equivalent rate section of Street, Private
and Traffic Signal Lighting rates, will be adjusted, for each successive
period of three successive billing months, by the applicable Average Fuel
Adjustment Rate per kilowatt-hour for such period.
The Average Fuel Adjustment Rate per kilowatt-hour applicable to any
period will be equal to the^ amount, either positive or negative and
expressed in mills and fractions thereof, which is the quotient of:
I.
the estimated Total Fuel Charge of New England Power Company (NEP)
for such period plus (or minus) the Adjustment for Past Differentials between fuel costs incurred and fuel revenues collected by
the Company,
divided by
II.
The Average Fuel Adjustment Rate, as so determined for any such period
consisting of three successive billing months, shall be applied to increase or
decrease the price of each kilowatt-hour of electricity billed in the same
period.
As used above, the "Total Fuel Charge" of NEP means the sum of the
estimated aggregate amount of fuel charge (or credit) which will be applied
to the power purchased by the Company from NEP over a period of three successive
billing months, and an amount equal to the product of $.01400 per kilowatt-hour
(representing that portion of the cost of fuel to NEP which is included in
the energy charge per kilowatt-hour set forth in NEP's Primary Service for
Resale Rate) times the estimated kilowatt-hours to be purchased by the Company
from NEP over the same period, and
the "Adjustment for Past Differentials" means the aggregate difference
in amount (whether positive or negative) derived by subtracting from the total
charges on account of cost of fuel incurred by the Company (plus or minus any
prior period reconciling adjustments) over the four billing months prior to
the three successive billing months in which an Average Fuel Adjustment Rate
will be in effect, the total revenues derived by the Company from the application
of the Average Fuel Adjustment Rate in effect during each of said four prior
months. The total charges for cost of fuel and the total fuel adjustment
revenues so derived shall consist of actual charges and revenues for the first
three of said four prior months and estimated charges and revenues for the fourth.
M. D. P. U. No. 379
-67-
Sheet 2
In the event that conditions affecting the price and/or supply of fuel,
which are actually experienced or reasonably to be anticipated during the
period when an Average Fuel Adjustment Rate is in effect,, indicate that the .
total charges on account of cost of fuel incurred and to be incurred by the
Company during said period will vary by ten percent (1.0%). or more above or
below fuel revenues collected and to be collected under such Average Fuel
Adjustment Rate, the Company may apply to the Department of Public Utilities
for approval and authorization of an appropriate interim increase or decrease
in such Average Fuel Adjustment Rate, to be applicable during the remainder
of said period.
If at any time changes or revisions in the fuel adjustment clause
applicable to NEP's Primary Service for Resale Rate become effective in
accordance with law, the Company will propose appropriate changes or revisions
in this Standard Fuel Clause, to the extent they may be necessary, and submit
them to the Department for approval.
Effective
July 1, 1977
MASSACHUSETTS ELECTRIC
COMPANY
TERMS AND CONDITIONS
M. D. P. U. No. 338
Sheet 2
MASSACHUSETTS ELECTRIC
COMPANY
TERMS AND CONDITIONS
6.
The customer shall furnish and install upon its premises such
service conductors, service equipment, including oil circuit
breaker if used, and meter mounting device as shall conform with
specifications issued from time to time by the Company, and the
Company may seal such service equipment and meter mounting device,
. and adjust, set and seal such oil circuit breaker and such seals
shall not be broken and such adjustments or settings shall not be
changed or in any way interfered with by the customer.
11.
-70MASSACHUSETTS ELECTRIC
COMPANY
M. D. P. U. No. 338
Sheet 3
_ 71 _
M. D. P. U. No. 338
Sheet 4
MASSACHUSETTS ELECTRIC
COMPANY
TERMS AND CONDITIONS
17.
The Customer may change from the rate, under which he is purchasing electricity to any other rate applicable to a class
of service which he is receiving, provided that the change
shall not be retroactive, nor reduce, eliminate or modify
any contract period, provision or guarantee made in respect
to any line extension or other special condition; nor, except
during the first year of electric service to any Customer,
cause such service to be billed at any rate for a period less
than that specified in such rate. A Customer having changed
from one rate to another may not again'>change within twelve
months or any longer contract period specified in the rate
under which he is receiving electric service.
18.
19.
The Company shall have the right of access at all reasonable times
to the premises on which its meters, other applicances and equipment are located for the purpose of examining or removing the same.
20.
The Customer shall not permit access for any purpose whatsoever,
except by authorized employees of the Company, to the meter or
other appliances and equipment of the Company, or interfere with
the same, and shall provide for their safekeeping. In case of
loss or damage to the Company's property the Customer shall pay
to the Company the value of such property or the cost of making
good the same.
21.
Temporary service is service which will not continue for a sufficient period to yield the Company adequate revenue at its regular
rates to Justify the expenditures necessary to provide such service. Temporary service will be supplied if the Customer shall
make such payment or payments, in addition to the payments for
electricity at the regular rates, as may be reasonable and Just
in each case.
22.
-72-
M. D. P. U. No. 338
Sheet 5
MASSACHUSETTS ELECTRIC
COMPANY
TERMS AND CONDITIONS
for any other reason to maintain uninterrupted and continuous
service; provided, however, that if the Company is unable for
any of the causes enumerated above to supply electricity for a
continuous period of two days or more, then upon request of
the Customer, the Demand Charge, if any, shall be suspended
for the duration of such inability.
The Company shall not be liable for damage to the person or
property of the Customer or any other persons resulting from
the use of electricity or the presence of the Company's appliances and equipment on the Customer's premises.
The Company may, provided it has spare generating and transmission capacity, supply electricity for trial purposes at
other than its regular rates. The period for the trial must
be not longer than is necessary for the demonstration and must
be specified in the agreement.
Service supplied by the Company shall not be used to supplement or relay, or as a standby to any other service except
under the terms of the Auxiliary Service Provisions or unless
the Customer shall make such guarantees in respect to the payment for such service as shall be just and reasonable in each
case. Where such service is supplied, the Customer shall not
operate its plant in parallel with the Company's system without the consent of the Company, and then only under such conditions as the Company may specify from time to time.
At any location where electricity was being furnished under any
rate of the Company for resale in whole or in part on April 21,
1958, and where, since that date, (1) there has been a change
in the identity of the Customer being served at such location,
or (2) if the same Customer is still being served at such location, resale in any respect is no longer being carried on under
the same circumstances or conditions or to the same extent as
on the above date , electricity shall no longer be available for
resale under any rate of the Company to the Customer being served
at such location; provided, however, that if, after notice to any
such Customer that electricity is no longer available for resale,
such Customer has failed or refused to rewire the building or
buildings within which resale is being carried on, or to apply
to the Company for the installation of separate metering equipment
for each tenant therein, or to make any other necessary changes
or otherwise refused to allow the Company to serve each tenant
at such location as an individual customer of the Company, the
Company may proceed as hereinafter provided:
-73-
M. D. P. U. No. 338
Sheet 6
MASSACHUSETTS ELECTRIC
COMPANY
TERMS AND CONDITIONS
Six months after the date of such notice to such Customer, and
thereafter until satisfactory arrangements are made as set forth
above for such changes as are necessary to enable resale at such
locations to be discontinued, the Company may charge for all
electricity sold at such location under its then filed block
type General Rates as though there were as many individual
meters installed as there are tenants in the building or buildings involved, plus one additional meter for each building to
cover electricity for building use, and as though each of
such meters showed the same energy use, the totals of which
would be equal to the registration shown on the master meter.
If such Customer fails or refuses to furnish to the Company
the exact number of tenants to whom electricity is being
resold at such location, the Company may substitute, for such
number, its best estimate of the number of such tenants.
Where a municipality under sec. 22C of G.L. c. 166 votes to
adopt a bylaw or ordinance forbidding new installation of
overhead facilities, the differential in rates charged to
customers in such municipality shall be determined in accordance with the Company's "Underground Rate Differential Provisions Pursuant to G.L. c. 166, sec. 22L for Municipalities
Adopting G.L. c. 166, sec. 22c" as from time to time filed by
the Company and approved or permitted to become effective by
the Massachusetts Department of Public Utilities, which
provisions are hereby incorporated by reference herein.
Effective
October 9, 1974.
-74-
APPENDLX 2C
Draft Environmental Impact Assessment
May, 1978
-75DRAFT
Environmental Impact Assessment
May, 1978
Environmental Impact Assessment (E.I.A.) of the proposed contract
EC-77-C-4211, "Demonstation of a Grid-Connected Integrated Community
Energy System" at Clark University, Worcester, Massachusetts.
Submitted in accordance with the National Environmental Policy Act of
1969 and according to the guidelines promulgated by ERDA on December 8, 1976,
and published in the Federal Register, Volume 42, Number 17,
January 26, 1977, pp. 4826-4833.
Submitted to: Department of Energy
Chicago Operations Office
9800 South Cass Avenue
Argonne, Illinois 60439
Contents
I.
II.
III.
IV.
V.
VI.
VII.
Introduction
76
76
81
93
A.
B.
93
96
97
98
Positive
Negative
1. Construction short term
2 . Operation long term
102
Description of Alternatives
.105
Conclusion
.106
-76-
I. Introduction
The more efficient use of energy is an urgent national challenge. Nowhere is this need greater than in New England, where the energy prices and
reliance on imported energy supplies are the highest in the country.
In
a diesel generator and make use of the engine's waste heat in the University's
steam heating system.
Grid-connection adds flexibility by permitting Clark to buy and sell electricity, and thereby makes possible about 40% of the energy savings.
Similar systems have a proven record of safety, technologic success,
energy conservation, and economic savings in many European countries.
II. Description of the Proposed Action
The proposed ICES consists of a diesel generator with waste heat recovery
and auxiliary equipment, to be installed in a building attached to Jonas Clark
Hall.
Figure 2C-1 shows the campus and the location of the proposed plant
at Jonas Clark.
following elements:
(a) Engine-Generator. A Sulzer engine Model 8 ASL 25/30 driving a 1405
kw three-phase generator will be installed.
residual oil, and produces exhaust gas at full load at a rate of 24,272 lbs/hr
at 767 F.
77-
Tenuis
Courta
A nd
..
Athletic Field
1 Downing Administration
Center
2 A twood Hall
3 A cademic Center
4 Geography Building
5 Jefferson Hall
6 A lumni Gymnasium
7 Science (Bio-Physics)
Building
8 Jeppson Laboratory
9 Jonas Clark Hall
10 Robert Hutchings Goddard
Library
11 Bullock Hall
12 Potter Laboratory
13 Dana Commons
14 Dana Dormitory
15 Hughes Hall
16 Florence Residence
17 Student Activities Center
Location of proposed p l a n t
-78SULZER ENGINE
8 ASL 2 5 / 3 0
Fig.
2C-2
ENVIRONMENTAL ASSESSMENT
NO
gr/HPH Cas N0 2 )
T*
IS
N
(3
/%
/
<?
8-
CO gr/HPH
HC gr/HPH
05
5*
LOAD
75-
/oo^
-79Fig. 2C-3
SULZER ENGINE
SOOT
8 ASL 25/30
mg/HPH
4/0-
35*-
\
/
7-
\
\
fiS-
X
\
AS
jro
LOAD
SOOT EMISSIONS
-80bypass valve to control steam pressure, level controls, and high and low water
alarms.
jacket cooling system will release steam to the 15 psig heating lines. Any
steam not required by the 15 psig University system will be condensed in a
radiator condenser.
No. 2, distillate oil, is used for starting and shutting down the
No. 6 oil storage tank and a buried 2000 gallon No. 2 oil storage tank. Two
fuel oil transfer pumps will be required, one for No. 2 oil and
one for No. 6 oil. These pumps will be located in the diesel plant building.
The No. 2 pump will take oil from the No. 2 tank and pump to a 300 gallon
day tank in the diesel plant. The No. 6 oil transfer pump will pump the
No. 6 oil from the buried tank to an elevated 600 gallon oil storage system.
From this point an engine driven pump will pump the oil to the engine.
The 120 GPH integrated heavy fuel treatment system will perform the
following operations:
1. Heating the raw fuel.
2. Injection of demulsification agent.
3. Centrifugal desalting and sludge removal reducing water-soluble
metallic salts such as sodium, potassium, lead, calcium, etc.
4. Neutralizing vanadium via magnesium sulfonate.
5. Filtering, pumping, and transferring from residual to distillate
oil use.
The purpose of the system is to reduce the sodium and vanadium content
of the residual fuel prior to combustion to <5 and <30 PPM, respectively.
The effluent from this treatment system is 99% water and 1% oil, and contains
a concentration of metal salts. The oil will be recovered in a skimming tank.
-81The effluent to the sewer will not exceed 18 gallons/hr and will contain less
than 80 ppm oil, approximately 600 ppm sodium chloride, 20 ppm lead, 50 ppm
calcium chloride, 5 ppm potassium, and 50-100 ppm magnesium.
(d) Exhaust System.
boiler, will be discharged through a silencer into a 20" steel exhaust stack.
This stack brick load will rise 95 feet from the plant floor, topping Jonas
Clark Hall by about 30 feet. At full load gases will be expelled into the
atmosphere at 325 F at a velocity of approximately 63 ft/sec. Pollutants will
leave the flue at the rates shown in Table 2C-1.
(e) Cooling System.
on the roof of Jonas Clark Hall to dissipate the heat from the oil and air
coolers on the engine and also to serve as an emergency cooling system for the
engine jacket if steam cannot be used by the Clark heating system.
This cooling
tower is dry and therefore will have no emissions. Noise rating of the fans
is 85 db or less within 3 ft. of the fans.
(f) Powerhouse. The engine, generator, auxiliary and control equipment
are housed in a concrete and brick annex to Jonas Clark Hall.
The building,
windows on the two sides away from the entrance. The building is connected
to the boiler room in Jonas Clark Hall by a fire resistant door.
III. Description of the Existing Environment
For the purpose of evaluating the proposed system's environmental impact,
the existing environment is described below.
(a) The Present Energy System.
the northwest quadrant of the basement of Jonas Clark Hall (Fig. 2C-2).
It
-82-
TABLE 2C-1 .
Rate of pollutants produced by Diesel
Pollutant
Rate gr/sec
NOx
4.96
CO
0.77
HC+
0.36
Particulates
0.02
S0
1.82
Btu/yr. The steam and hot water are piped through a network of
The boilers
can be adapted to burn either residual (#6) or distillate (#2) oil, or natural
gas.
Exhaust from the boilers is vented through a stack mounted on the north
side of the building and rising 36 feet above the roof of Jonas Clark Hall.
Emission of critical pollutants at peak loading is 3.7 gr/sec of NO
and 4.0
gr/sec of SO-. Oil is delivered on campus by tanker truck and stored underground in two 20,000 gallon tanks. The boiler operations are inspected periodically and meet all local, state, and federal regulations. They are operated
by specially licensed personnel.
Electric power is supplied by Massachusetts Electric Company, a member
of the New England Electric System.
13,800 volt utility line.
located on the north side of Jonas Clark Hall near the heating plant. Electricity is distributed from this point throughout the campus. Peak electrical
demand is approximately 1500 kw, and total use is about 6 x 10 kwh/yr. Most
of this electricity has been generated in utility boilers burning imported
residual oil.
(b) Jonas Clark Hall.
campus (Fig. 2C-1).
northwest corner, the basement also houses a gym, craftshop, gameroom, three
small laboratories, and lavatory.
-84-
Maui St w
mmm
1 Downing Administration
Center
2 Atwood Hall
3 Academic Center
4 Geography Building
5 Jefferson Hall
6 Alumni Gymnasium
7 Science (Bio-Physics)
Building
8 Jeppson Laboratory
9 Jonas Clark Hall
10 Robert Hutchings Goddard
Library
11 Bullock Hall
12 Potter Laboratory
13 Dana Commons
14 Dana Dormitory
15 Hughes Hall
16 Florence Residence
17 Student Activities Center
-85-
Although the sound levels inside the b o i l e r room are high (85-95 d e c i b e l s ) ,
the b u i l d i n g ' s thick brick walls, the b o i l e r room's brick c e i l i n g , and soundproofing reduce the sound levels immediately outside the b o i l e r room to the
ambient level.
major.
This r e s u l t s
from 1965 to 1975, the University's t o t a l energy costs rose from $81,000 t o
$560,000.
$444,000, showing that Clark's efforts to respond t o these pressures have been
determined and effective.
-86-
zo
is a.
s
10 g
i
4 \
Xs
'75
'70
B0
yfAR
Figure 2C-5.
-87-
Some of
these structures are single family residences, but most contain several r e n t a l
units.
Main S t r e e t ,
On i t are
the a r t e r y .
Clark's r e l a t i o n s with the surrounding community are generally p o s i t i v e .
The primary issues of community-University conflict are a l l related t o University
expansion.
Although the University added 140 new parking spaces in 1976 and 200 spaces in
1977, the problem i s s t i l l not e n t i r e l y resolved.
the apartments in the area surrounding the campus.
88
be an issue in the future. Significantly, the proposed ICES installation will
not affect any of these areas of Universitycommunity conflict.
(e) Metropolitan Worcester. The city of Worcester, the secondlargest city
in New England, has a population of approximately 170,000 and more than 6 million
people live within 50 miles of the city.
The population
has declined as the more affluent have moved to the suburbs, textile and related
industries have closed, the tax rate has continuously increased, urban renewal
programs have met with only partial success, abandoned buildings degrade older
.neighborhoods, etc.
more effective and actually reversed many of the negative trends. The city
center is being revitalized, and the exodus of people and industry has slowed;
newer service industries are expanding.
Clark is one of eleven colleges and universities of the Worcester Consor
tium for Higher Education.
employers in the city.
But further
-89is presently a non-attainment area for particulate matter oxidants and carbon
monoxide.
Other air pollutants are not as critical; however, air pollution must
One measuring
quality at Clark is usually somewhat better than at the downtown (New Salem
Street) station. Table 2C-2 summarizes some of the available information on
ambient air-quality.
(g) Ambient Noise. Noise levels on the campus and in its vicinity vary
greatly.
measurements, taken mostly in the daytime, range from 52 dbA in the dormitory
quadrangle to 95 dbA in the boiler room and on Main Street when heavy trucks
pass.
The sound level on the campus varies considerably with time of day as
well as location.
the lowest ones and are used as the base ambient sound level.
-90Tablie 2C-2
so 2
Year
ppb
.Aigm/m
1971
1972
1973
1974
1975
1976
1977
Quarter
76
76
68
63
57
-43
4
3
62 -68
46
62
50
55
44
43
51
62
40
40
58
32
43
61
39
45 - 42 - 35
2
13
15
12
16
11
- 8
6
3
2
4
3
8
3
9
4
1
1
4
2
3
4
14
14
6
13
12
8
1
Month
June
July
Aug.
Sept.
77
77
77
77
Max. hour
Max. day
75
110
72
48
49
44
46
32
105
170
100
70
Annual Mean
Max . 24 hours
2
. -"jm/m
f
60
49
44
300
151
176
19
1
3
2
0
0
50
94
55
176
485
273
3
50
8
0
18
1
Source:
Central Massachusetts
Air Pollution District.
-91-
Table 2C-3
Location
95
95
75
70
70
68
65
55
55
Dormitory quadrangle
52
a.
-92Table 2C-4
Baseline Sound Data
Average Sound Levels
*
Location
Time
dBA
8am
11am
5pm
2am
65
67
65
60
60
54
54
42
62
60
58
46
58
" 60
58
51
53
52
50
44
68
70
70
49
55
55
50
46
57
56
56
50
9
Btu to 170.2 x 10
21%--a reduction of 309,000 gallons of oil. Net energy savings are even greater
since that much oil need not be extracted, transported, and refined.
The maintenance of the financial strength of the University.
The cost of
fulfilling the energy requirements at Clark in 1977 was $450,000. This amounts
to approximately 20% of the amount spent on faculty salaries at the University.
Reducing these figures by 21% would be a very positive economic impact.
Clark is a private university and tuition costs have increased dramatically
over the last decade. Already many people can't attend for financial reasons.
The savings from the ICES will help to reduce further tuition increases, maintain
the University's ability to compete for the most qualified students, and, hopefully, renew opportunities that were previously closed due to high tuition rates.
Clark now benefits from a declining block rate pricing structure for electricity.
The savings of the ICES will be larger if proposals for a more uniform rate
structure go into effect.
The creation of an energy conservation demonstration facility in Massachusetts.
Establishment of a grid-connected
It is
located on 1-90 and 1-290 and has a functioning train station and airport. Over
50% of the region's population lives within 50 miles of the Clark campus. Second,
the University has established an impressive record in monitoring and recording
its energy use patterns. The Science, Technology, and Society Program at Clark
has devoted three issues of its journal to energy use at the University.
Finally,
oppor-
tunity for students to obtain data relevant to many research projects from the
monitoring systems. The operation of the plant will most likely spur much new
student interest in energy conservation, pollution control, and the viability of
ICES.
The creation of an informed citizenry will aid in the creation and effec-
-95research opportunities.
and its impact on the utility would be very useful to utility planners.
The expenditure of approximately one million dollars in one of the most
economically depressed regions of the country.
involve the dispersal of a million dollars in the national economy. The money
will help to generate jobs in a region where unemployment has been most persistent
and severe.
ICES acts as a stimulus for other installations (as is expected); the positive
effect on regional employment levels would be even more significant.
A reduction in the emission of some air pollutants. The ICES will reduce
total oil consumption by 309,000 gallons. This savings will be in reduced burning
of residual oil by Massachusetts Electric generating stations, and will lead to
a reduction in particulate emissions by 3.3 tons/year and S0 2 emissions by 24.1
tons/year.
Reduction in the negative environmental impacts of the extraction, processing,
and transport of fuels. The 309,000 gallons of oil conserved reduces the negative
effects of drilling, refining and transporting oil. This positive impact is not
very significant, but it is a factor that should be considered when evaluating the
decisions that may encourage or discourage the wide use of ICES.
Installation
Presently, approximately
75% of New England's residual oil is from foreign sources charging $13.50 a
barrel.
At this rate, the ICES would save nearly $100,000 per year, a small
amount when compared to the billion dollar trade figures, but still a savings,
and one which could be generalized.
A reduction in political vulnerability.
It will
tions will occur when relatively few students will be on campus, and the inconvenience will affect a reduced number of individuals. There is no direct contact between the construction site and neighboring private residences, and it
is not anticipated that Clark's neighbors will be inconvenienced.
Noise. None will be generally confined to the site itself. Scheduling
of noisy activities so as to reduce their effects, the use of heavy duty mufflers
on construction equipment, and the screening effect of the surrounding buildings
will keep the noise at a minimum.
Additional traffic. Along Downing Street and at the site on the north side
of Jonas Clark Hall, increased traffic will have some disruptive effect since
Jonas Clark Hall is the center of the campus and trucks and equipment will
approach through Downing Street. The inconvenience of heavy machinery on the
compact campus will be greatest in the early stages, when the excavation equipment,
dump trucks, and cement trucks are on campus.
Aesthetic impacts. Unavoidable noise and unsightliness will persist throughout construction.
Every effort is being made to schedule the most disruptive construction maneuvers
when the university is not in session.
Particulate emissions. Dust and other particles will be generated during
construction. Although these emissions will not be significant, they are mentioned here because of Worcester's particulate problem.
In summary, the negative environmental impacts of the construction phase
are mainly inconveniences.
construction be undertaken during the summer months when the University is not
in session.
as well
as annual and short-term S0 2 concentrations. However, they showed that there can be
significant short-duration concentrations approaching 200 /ig of NO
per cubic
meter from the diesel plume at critical points in the Worcester area. Because
of the small size of the Clark facility (less than 250 tons of NO
emitted per
year) Clark will not be subject to the Massachusetts DEQE limit of hourly concentrations of 200 ug per cubic meter; however, Clark is likely to be subject to
new EPA short-term NO
99
Table 2C5
Estimated Air Pollution ImpactPresent System and Proposed GridConnected
ICES .
Annual Emission (in tons/year)
System
SO,
NO
x
CO
HC^
+
Particulates
Present System
Utility boiler"
Clark boiler
Totalc
36.7
77.6
114.3
25.5
54.0
79.5
0.5
1.0
1.5
1.5
3.2
4.7
ICES System
,
Clark diesel
Clark boiler
Utility boilere
Totale
56.9
55.5
22.3
90.1
155.2
38.6
15.5
178.3
11.2
0.5
2.3
.9
1.9
Net Change
At Clark
% Changef
Auto equivalents^
Clark + Utility11
% Change
Auto equivalents
34.8
45.0%
24.1
21.0%
139.8
259.0%
2796.0
98.8
124.0%
1976.0
24.1
24.1
0.7
.3
11.6 '
24.1
10.9
1090.0%
45.0 155.0
24.1
10.1
673.0%
NA
45.0 144.0
NA
.4
12.0%
2.8
60.0%
a. Based on generalized data for utility boilers burning residual oil with an ash
content of 0.04% (by weight), sulfer content of 1.0% (by weight), weight of 7.83
lbs. per gallon, 148,000 Btu per gallon and a Btu to kwh ratio of 10,050 to 1.
Assumes the consumption of 6.9 x 10 kwh per year.
b. Based on the use of residual oil with the same characteristics as specified
in note a and a boiler efficiency of 75%. A ssumes a thermal load of 110 x 10*
Btu per year. Preliminary measurements indicate that NO figures may be too
high by as much as a factor of four.
c. Carbon monoxide levels (less than 0.1 tons) are considered negligible here.
d. Based on the manufacturer's specifications and the use of #6 residual oil with
an ash content of 0.04% (by weight), sulfur of 1% (by weight), a weight of 7.83
lbs per gallon, and an energy value of 148,000 Btu per gallon. A ssumes operation
at full capacity for 7884 hours per year (90% capacity factor).
e. Assumes reduction in utility generation of 11 x lQr kwh/year; other assumptions
as in note a.
f. The percent change for carbon monoxide is meaningless since basically none
was emitted previously.
g. Auto equivalents (in numbers of auto?) are included to provide a means of eval
uating the relative significance of the net changes. They are based on EPA's
estimates for the average emissions of motor vehicles operating in the U.S. in
1976.
h. The Clark + Utility figures represent the net additional emissions of the Clark
ICES and net reduction in the emissions at New England Electric System's residual
oilfired generators. A ssumes a net reduction in NEES' oil consumption by
740,000 gallons per year.
-100Table 2C-6
Estimated Peak Rates of Air Pollutants Output
at Clark
NO
Present System
Clark boiler
4.0
3.7
ICES System
Clark boiler
Clark diesel
Total
3.47
1.82
5.29
3.2
4.96
8.16
Net Change
in gr/sec
in %
41.3
32
CO
*
*
+4.5
121
HC+
Particulates
0.0001
0.007
0.021
0.0001
0.77
0.77
0.006
0.36
0.366
0.019
0.02
0.039
0.8
NA
0.4
NA
0.018
85
may be s e r i o u s l y o v e r e s t i m a t e d
-101these standards. Noise inside the plant will require the use of ear-protectors
for those working there. To insure that vibration is kept to a minimum the foiuw
dation of the diesel engine and generator will be independent of the buildings
and equipped with vibration dampers.
Liquid effluent. Oil treatment equipment will produce an effluent not exceeding 18 gallons/hr.
less than 80 ppm oil and approximately 600 ppm sodium chloride, 70 ppm lead,
50 ppm calcium chloride, 5 ppm potassium and 50-100 ppm magnesium.
This effluent
will not adversely affect water pollution or the operation of the Blackstone
Pollution Abatement District Sewer Plant.
Increased presence of oil delivery trucks. At present there are approximately
123 deliveries per year.
deliveries per year, an increase of 445,000 gallons of fuel, nearly 50%. Aside
from their visual and olfactory impact, the increased presence of 8000-gallon
fuel trucks carries with it an element of risk. The increased presence of
these trucks is, however, significant only on the Clark campus and Downing
Street. Other streets, including Main Street, are major truck arteries and
56 more trucks per year will not be noticeable.
Visual and physical impact of the ICES building.
and concrete ICES building, the 95 foot brick stack and the cooling unit will
affect the appearance of Jonas Clark Hall and the campus. It will be most
noticeable in the area between Jonas Clark, Atwood Hall, and the Goddard
Library.
which will soon be under construction. The strong architectural statement made
by the memorial will be the focal point of the area and thus the plant will be
in the background.
It should be noted that the ICES' negative impacts are mostly con-
tained within the Clark University campus. As a result, almost all of the
negative impacts are experienced by the same people who benefit from the more
significant positive impacts. Negative impacts on third parties, such as the
local community, except for NO
Aside from these specific factors, it is also important that the ICES
not conflict with any policies and programs of federal, state, and local governments.
The relevant items and the steps that have been undertaken in response
impact analysis are presented in Chapter III, U.S. Energy Research and Development
Administration, Part 711 - Guidelines for Environmental Review published in the
Federal Register, 26 January 1977, pp. 4826-4833. These regulations require
that an Environmental Impact Assessment (EIA) be written as specified in Part
711 - 25 of the regulations. This document is a preliminary draft of an EIA
based on the present state of knowledge of the Clark ICES installation. This
that, based on presently available data and pending more detailed analysis,
the project would not be in -violation of present air pollution regulations
(see letter in Appendix 2D).
Representatives
of the EPA noise pollution branch in Boston also have been contacted. They
stated that the Commonwealth's standards either meet or exceed theirs and would
I-
-104be acceptable.
Building Codes. The applicable building codes are contained in Article
II, "Heating Equipment and Appliance Mounting, Clearances and Connections,"
of the State Building Code.
are subject to the provisions of Chapter 146 of the Massachusetts General Laws
and Acts as amended.
require the approval of.certain boilers and pressure vessels by the Board of
Boiler Rules of the State Department of Public Safety.
is permissible under Section 15A (6) of the code. The ICES installation was
discussed with Mr. Remmer, Commissioner, Dept. of Building Code Inspection,
City of Worcester. He stated that the project would not violate existing
zoning regulations (see letter in Appendix 2D).
Planning and Development was also contacted to insure that the installation did
not interfere with the plans and programs of that agency.
the project would not affect their plans. The Worcester Redevelopment Authority,
an agency that operates in the vicinity of the Clark campus, has also indicated
that they have no objection to the ICES installation (see letter in Appendix 2D).
To conclude, the Clark ICES proposal does not conflict in a significant
manner with any specific legal and institutional requirements or the plans and
policies of related governmental agencies. On the contrary, these entities all
support the ICES proposal on the basis of the positive impacts such a system
-105would have on energy conservation and the economic welfare of the community.
The advice of the regulatory personnel has been of great assistance to the
Environmental Impact Assessment Group. The Group will continue to seek their
advice and opinions in the future.
VI. Description of Alternatives
There are four sets of alternatives open to Clark University:
(1) to
continue with present practices; (2) to institute additional strong conservation measures to reduce energy demand; (3) to install a totally independent
integrated energy system; or (4) to select a different grid-connected ICES
system.
Continue with present practices. This alternative would have no environmental impacts at Clark University; it would, however, continue unabated the
use of oil within the New England area. This would, therefore, be contrary to
the national and regional objective of fuel conservation.
Furthermore, it
campus not connected with the existing electric grid have been investigated in
-106several studies. Such systems have generally the same advantages as a gridconnected ICES. Costs, however, are higher, as system reliability must be
achieved by the installation of standby units. Our Phase I study shows that
the costs of interconnection, including standby charges for electricity, are,
lower than those of standby units.
an additional 60% oil savings resulting from electricity sales to the utility.
Different grid-connected ICES." A large number of alternative ICES installations, including differently sized diesel units, steam turbines and gas
turbines, were investigated in Phase I.
efficiency and technologic risk.
efficiency and rate of return but also higher initial cost. On environmental
grounds few differences can be ascertained except that larger units are likely
to increase aesthetic problems and air pollution but reduce oil consumption.
On economic grounds, larger units, in addition to increasing initial cost,
represent higher opportunity cost and larger risks.
VII.
Conclusion
Based on the previous section of
Significant
-107(3) Most community environmental effects of the project are negative, but small.
The output of NO
level in parts of
-108-
-109-
APPENDIX 2D
Letters on Environment and Codes
from
Edmund G. Benoit
Chief, Air Quality Control Section
Commonwealth of Massachusetts
(2 Letters)
Michael J. Burke
Assistant Commissioner of Public Works Engineering
City of Worcester
George P. Beringer
District Chief, Fire Prevention Division
City of Worcester
and
Norton S. Remmer, P.E
Commissioner, Department of Code Inspection
City of Worcester
(2 Letters)
-110-
TEL
(6171 7 9 1 - 3 6 7 2
April 5, 1978
Clark Universlty
950 Main Street
Worcester, Massachusetts
Attn:
01610
2.
3.
h.
EGB:mlk
cc: DAHM-R.Donovan
Edmond G. Benoit
Chief, Air Quality Control Section
Ill
Hy 1 , 1978
"HboO**.
*j4Hauac4iaet&> CMOS
Clork unlvorttty
950 Miln Stroot
Worcester, MttMchuMttt 01*10
Attnt Horry Schwartz, professor, Invlronmntol Affairs
-112-
TELEPHONE
(617) 798-8151
EXT8. 2S5. 292. 2 8 5
JZ./MJB/EH
MICHAEL J. BURKE
Asr'r. Commissioner of Public Works
Engineering
"
"
Mr. " I n g a r e l l i
Engineering
-113CITY OF WORCESTER. M A S S A C H U S E T T S 0 1 6 0 5
FIRE D E P A R T M E N T
141 G R O V E S T R E E T
SAVE YOUR
ETT
AND
HOME
BUSINESS
PREVENT
FIRES
Nov 1, 1977
Mr. Basil Kimball
Chief Engineer
Clark University
950 Main St.
Worcester, Mass 01610
Dear Mr. Kimball:
State law requires that any additional flammable
fluid to be stored at your installation, requires
that your present license for storage of fuel oil
be ammended to include the additional deisel fuel
oil, you intend to store and use. This can be
accomplished by notifying the City Clerk at City
Hall.
I can foresee no problem in this area, and I
would suggest you ammend your license at your
convience.
Respectfully yours,
ree P. Berineer
George
Beringer
Dist Chief, Fire Prevention Division
-114-
COMMISSIONER
November 3, 1977
Within those
-115-
01904
> t
TELEPHONE 617 7 9 8 4 1 1 1
COMMISSION!*
Zoning.
2.
3.
4.
5.
-116-
APPENDIX 3A
Engine Operating Experience and Guarantees
-117APPENDIX 3A
Engine Operating Experience and Guarantees
Operating Temperature
The Sulzer candidate is standardly equipped with a low-temperature (less than
200 F) water-jacket cooling system.
ebulliently cooled.
Fuel
Both manufacturers have had extensive experience burning distillate oil in
their candidate engines. We believe that the issue of residual-oil experience
is most important.
Sulzer's experience with heavy-oil-burning engines is considerable,
since they have about 50% of the market for large marine engines. They also
have heavy-oil experience with engines of the same design as the one
proposed for Clark. They have run a 6-cylinder ASL 25/30 engine in the
laboratory from 1969-1972. They accumulated 1130 hours of operation, 880
on heavy fuel and 250 on distillate oil during break-in, starting and stopping.
The sodium/vanadium content of the fuel varied between 13ppm/76ppm and 27ppm/
173ppm.
Measurements of wear were made after 300 hours of operation with the
27/173 Na/V fuel. The chromium-plated top piston ring had wear of about
.00l5inch/1000 hours. Liner wear was .0004 to .0008inch/1000 hours. No wear
could be measured on valves or the piston ring grooves. According to Sulzer,
rate of wear on piston ring, and liner drops to about'1/3 of the initial rate
after about 5000 hours. Assuming this change is linear for the first 5000
hours and remains constant thereafter, the wear on the top piston ring would
be .005 inch after 5000 hours and .0075 inch after 10,000 hours. The liner
wear would be .00133 to .0027 inch after 5000 hours and .0019 to .0038 inch
after 10,000 hours. From these values, Sulzer has predicted the lifetimes
of^various components. These predicted lifetimes are presented in Appendix
5B, Table 5B-1, where they are used to estimate maintenance costs for the engine.
In addition to the test engine, two ASL 25/30 engines have accumulated
A further consideration
was that the vanadium content in the available fuel had increased, and they
were not set up to treat vanadium.
wear on valves and other engine parts was not appreciably different for #2
and #6 oils, except when there were high vanadium levels in the oil (unfortunately the spokesman could not say definitely what a high vanadium level was).
There was an increase in maintenance costs for such components as injectors,
fuel pumps, and other fuel handling equipment.
To summarize, Sulzer has experience operating their candidate engine with
residual fuels; Superior does not. Sulzer does not have experience with the
ebullient cooling of their engine while Superior does.
Both manufacturers
have considerable experience burning heavy fuels in other engines, but Sulzer's
experience is probably more extensive as they are the larger company.
Guarantee Terms
Both companies offer us their standard guarantee.
the engine for 12 months from the commissioning of the power plant. The
guarantee applies to an ebulliently cooled, residual-oil-burning engine, but
the engine must maintain limits of sodium/vanadium of 15ppm/50 ppm. The
guarantee covers repair or replacement of defective parts; the details of the
guarantee can be negotiated at the time of purchase. The guarantee will not
cover normal wear, improper maintenance, incorrect operation, etc.
Superior's guarantee is similar.
-119-
APPENDIX 3B
Plant Descriptions
-120APPENDIX 3B
Plant Descriptions
I. ENGINES
A. Sulzer Engine
The Sulzer engine i s Model 8 ASL 25/30 ( i n - l i n e c y l i n d e r s ) .
eight cylinders, 900 RPM, and i s rated at 1984 bhp at 100% load.
generator output at 100% load i s 1405 kw.
available as a residual o i l engine.
The
I t has
of s e r v i c e .
Both the Superior and Sulzer jacket and a i r cooler w i l l be cooled
by g l y c o l - t o - a i r r a d i a t o r s .
B. Superior Engine
The Superior engine is Model 40-X-16 (V type).
900 RPM, and is rated at 2120 bhp at 100% load.
It has 16 cylinders,
100% load is 1500 kw. The engine has a brake mean effective pressure of
141.4 psi at 100% load and is turbocharged. As currently available it does
not use heavy oil. Cooper Energy Systems has advised that with modifications
the engine will be suitable for residual oil.
The following design changes would be necessary to make it capable of
burning residual oil as fuel:
1. Injection pumps would require special clearanced plungers and barrels
and a bypass to allow an adequate flow of oil through the pump for cooling.
2. The injection nozzles would require special clearances in the area of
tho valve and seat.
3. The injection nozzle tips would require low sac volume and an orifice
size selected for the particular fuel used.
4. The fuel would require pre-treatment including, as a minimum, water
washing and centrifuging, as well as preheating to reduce its viscosity
and make it easier to treat. We would select one of the commercially
available fuel treating systems. The treated fuel would require additional filtration at the engine and possibly further heating before and
after filtration, depending upon viscosity.
-1215. The fuel system would allow the engine to start and stop on No. 2 diesel
fuel and transfer to residual operation after the engine is running.
This would ensure that there was no #6 oil in the engine when the block
was cool.
6. Corrosive metallic alloys in the fuel might need to be reduced. Many
residuals contain extremely high sulphur and water content which, under
the right conditions, can form corrosive acids.
7. The crankcase would need a high total base number (TBN) lubricating oil
and more frequent oil changes. The high TBN oil has high alkaline
reserve, preventing acid build-up and minimizing corrosion in the crankcase.
The manufacturer would like to have a minimum of one month available for
testing an engine with the residual fuel selected.
II.
A. The new diesel plant will utilize the existing deaerator, condensate
system and feedwater pump of the University boiler plant.
B. A new waste heat boiler rated at approximately 2500 lb/hr at 125 psig
saturated steam will be installed.
control steam pressure, level controls, and high and low water alarms.
C. The ebullient jacket cooling system consists of supply and return piping
to a steam reservoir separator. The reservoir/separator will have level
controls and high- and low-level alarms. Make-up water will reach the
system via a water softener.
by a modulating steam valve which will release the steam to the 15 psig
system.
2, distillate oil, is used for starting and shutting down the engine. The
oil storage system will consist of an existing 20,000 gallon No. 6 oil
storage tank. Two fuel oil transfer pumps will be required, one for No. 2 oil
and one for No. 6 oil. These pumps will be located in the diesel plant
building.
The No. 2 pump will take oil from the No. 2 tank and pump to
-122will pump the No. 6 oil from the buried tank, to the oil treatment system.
After treatment, the oil will be pumped to an elevated 600 gallon oil
storage system.
From this point an engine driven pump will pump the oil
to the engine.
FUEL TREATMENT SYSTEM
A 120-gallon-per-hour fuel treatment system will be necessary to
ensure that sodium and vanadium content of fuel does not exceed the limits
required to maintain the engine guarantee described in Appendix 3A. The
system will remove sodium by washing the fuel and will neutralize the
corrosive effects of vanadium by forming non-corrosive orthcr-magnesium
vanadate.
this report.
ELECTRICAL SYSTEM
The diesel generator will generate power at 13,800 volts. It
will operate continuously, in parallel with the Massachusetts Electric
Power System.
tied into a new switchboard located in the diesel plant. The 13,800V
power will be fed (via the new switchboard) to the Goddard Library via
two buried conduits. At the distribution system in Goddard, the power,
which can flow into or out of Clark, will be metered in each direction.
-123-
APPENDTX 3C
Performance of the Candidate Systems
-124-
APPENDIX 3C
Performance of the Candidate Systems
For each diesel generator considered, heat balance data were obtained
from the engine manufacturer in terms of Btu per bhp-hr. The heat balance
parameters given by the manufacturer were:
Work Output
Jacket Water
Lubricating Oil Cooling
Exhaust Gases, Flows and Temperatures
Exhaust Latent Heat
Radiation and Unaccounted
This data was then used to obtain system heat balances, showing the amount of
125 psig and 15 psig steam flows.
A characteristic of diesel engines is that performance (i.e. heat
balance in terms of Btu/kwh) is fairly constant down to about 50% of design
load and then drops off substantially.
at 50%
load.
-125-
FICURE 3C-1
Schematic for Diesel
Heat Balance
Input
v
y'
Diesel Engine
Hi
H
a+ %
>
y'
Input
)
Supplemental
Boiler
To Heating
System
PROPOSED SYSTEM
Input
*
Boiler
+ H
CONVENTIONAL SYSTEM
_^
"7
To Heating
System
-126-
EHR
value
(Btu'lb
fuel
>
CD
where
EHR = engine heat rate (Btu/kwh) = fuel input per electrical output
The total fuel per kwh used by the proposed system is then obtained by
adding boiler fuel used to supplement the engine thermal output:
where
F,
H.
E
n,
=
=
=
=
The total fuel used by the conventional system is just the boiler fuel required
to obtain the required thermal output.
"h
=
CS)
cs
%
Subtracting equation 3 from equation 2 results in the desired incremental
heat rate (HR):
H,
F
HR = EHR + - 2 - - -(4)
nbE
E
= EHR - - 2 nbE
We see-from equation 4 that the term H./n. is the useful thermal output
(from the exhaust and cooling jacket) generated by the diesel. It replaces boiler fuel which would have had to be utilized in a conventional
boiler. This fuel is therefore credited to the diesel.
Another key parameter is the cost of fuel attributable to generation
of electricity. This is the cost of fuel for running the system less the
cost of fuel that would be used in the existing boiler to make up the heat
output of the candidate system. This can be expressed
-127-
f = f
x EHR - - 2 - B 2 .
(5)
where
f
Btu)
EHR = fuel input to engine (or high pressure boiler for a steam
turbine) (Btu/kwh)
f,
H,
n.
The derivation of equation 5 is similar to that for the heat rate, equation
4.
When the same type of fuel is used for both the engine and the boiler,
or when the costs for these fuels are equal, f is simply the fuel cost
multiplied by the heat rate.
The performance data for the two engines, the Sulzer 1405 kw and the
Superior 1500 kw, at full and half-load, are shown in Figures 3C-2 to 3C-5.
afc23.LBS
I3I.LBS
314.8 h
108. LBS
2.k82*IO fe BTU/HR
HEAT ABSORBED
El7.LB3
I27.2F <
H-X
DEAERATOR
2W7.LBS
I3fc.7b
Z754 LBS
178.0 h
ZIO.OF
242721BS
7G7F
ifih
RETURNS
RETURN
TANKS
325 F
-t
131.LBS
137.0b-1 fc9.0F
. BOILER
BLOWDOWK
13ILBS
324.8 h
15.0PSIG STEA M
WloA.Oh
1322 LBS
M P
178.0 b
BASED QN 857. EFFICIENCY BOllEfi
I983.9*.344*ia900 - *5IG II93-2M7 tt7f2+l.30,O*
H E A T R A T E
FUEL COST
HEAT RATE
FUEL COST
1405.-gr.0
4,565 * ' 2 . 5 0 / 1 0 * - ' . 0 1 6 4 / K W H
^ "
G5G5-rrm
F i g . 5C -2
Heat Balance:
S u l z e r , 100% Load
*I65SZ5D
ao
i
.5I.LBS
I0I3.LBS
TO HEATING SYSTEM
923.LBS
42.LBS
J00.LB5
127.2 F
.03fexlOfe BTU/HR
HEAT ABSORBED
DEAERATOR
064. LBS
780h
210.0 F
H-X
RETURN
TANKS
I3764.L65
G26F
BOILER
BLOW DOWN
51. LBS
324.8h
51.LBS
137.0 h-169.0 F
28b
RETURNS
I022.LBS
I36.7h
325 F
138 h
915.LBS
I78.0h
15* Thermo
97
WMS Bectron
coi.po.t.oN
0.85
687-18.0
= 7195 * *2.50/lO f e = '.OI799/KWH
.=7195^Fig. 3C-3
Heat Balance:
Sulzer, 50% Load
DRAWN
J WALKER
101
sl Avenue
CHICKED
EMIMEER
507.LOAD 47TAMB.
SULZER 8CYL.MOD.ASL25/30
' 992BHP-900RPM
.
EKW = C>87
TITLC:
i J 4. LBS
-:-"sO. LBS
I25.0P3IG
2570.LBS
1193.Oh
\;.'8h
- * - TO HEATING SYSTEM
2442.LB5
133 h
110. LBS
262. LBS
2.74xlO t BTU/UR
HEAT A BSORBED
127.2 F
DEAFIRATOR
Ri4.LBS
173.0 h
Q)
210. OF
24.I92.L&:
708 F
-^t
I78.0h
1500-35
= ^.01706/KWH
BOILL'R
BLCV DOWN
Is-;. LBS
3i;.3h
2576. LBS
^ Thermo
fc Electron
"
2 . 2 O x . 4 O 4 x , 8 / 9 0 O - 2570 x , , 9 3 . 0 ^ 7 0 4 x , 2 7 . 2 , 2.54x,0^
FUEL COST = 6824 * ^ . S O / l O 6
H E A T R A T E =
RETURN
TANKS
134. LBS
137.0b-169.0 F
RETURNS
H-X
2704. LBS
136.6 F
325 F
23 h
=6824
Fig. 3C4
Heat Balance:
Superior, 100% Load
DRAWN
CHECKED
EMGIf
J.WALKER
TITLE: A
C SE H
l007oLCAD-/l-"AMa
SUPERIOR I6CYL. M ' X 4 0 *
2120 BIsP - 9 C ?PM
SIZE1 DRA WING NUME^
f~T
125.0 PSIG
48.LBS
.20 xio fe BTU/HR
MEAT ABSORBED
14 LBS
127.3F
DEAEPATOR
"
I33h
28 ^
RETURNS
H-X
1184. LBS
136.3F
RETURtIS
TAtlKS"
;l
w
^^7
I 17.56SLBS
BOIL'.R
BLCV. DWM
58.0 LBS
I37 0h-I69.0F
600 F
. 5 s ; .as (
* 32'i J h
*i
1517. LBS
178.Oh
. 7 3 z , jgntfpjw
FUEL **r*tJOiUaJwH
&AT$STE
fZ Electron
t"'"
- 78c KWH
M
Fig. 3C-5
Heat Balance:
Superior, 50% Load
Avenue
DRAWN
J ' M.-XR
CHECKED] ZHQIHEE
TITLE:
CALZ H
507.LCAD-^7'F
SJ~ERICR ",-CfL M : :
iC53\Br^' re
x|$>
I.
SHE |
DRAWING
:7|Wr
NUMbwH
-132^
APPENDIX 4A
Design Descriptions for the
Steam, Fuel,and Fuel Treatment Systems
-133-
4A.0
Introduction
In this
appendix we give the design descriptions for the Steam, Fuel and Fuel treatment systems.
4B and 4C, and the electrical design and specifications are given in 'Appendix
4D.
-'
The basic equipment layout is shown in Fig. 4A-1.
4A.1
Steam System
the following controls: 1) -TVC-1 and TC-1 - Engine jacket fresh water
temperature control valve and temperature controller; 2) PCV-1 - Fifteen
pound (15 psig) steam pressure control valve; 3) PS-1 - Fifteen pound
(15 psig) ebullient steam pressure switch which both activates the jacket
water back-up heat-exchanger glycol circulating pumps and operates the solenoid
valve S-l, sending a signal to PCV-2; 4) S-l - Solenoid valve; 5) PCV-2 Pressure control valve permitting jacket fresh water to flow through the jacket
back-up heat exchanger, thereby controlling the steam pressure from the steam
generator; 6) TS-1 - A temperature switch which on high jacket temperature
puts PCV-2 on temperature control using a solenoid valve SV-2 and TC-U 7)
SV-2 - solenoid valve; and 8) TCV-2 and TC-2 - Glycol temperature control valve
and controller which will have a set point just below the lowest jacket
fresh water return temperature, preventing the return of very cold water to
the jacket.
The fresh water loop is kept pressurized by means of the jacket water
expansion system.
jacket loop 50-100 psi above the saturation temperature of the fresh water.
At 100% load, the fresh water temperature leaving the engine will be controlled
at 266 F and the return temperature will be. 257F.
Assuming the normal pressure in the 15 psig header, the set point of
\-a~
(Oil
\oW
Mt-MOGM.
134-
T
u-dPH
I I*""
S
MUTMK--^/'T\
*'C**^
rfT^y
MOTO cormoL m a
UMNjaTSUIKH
it.
ro^M
tor/ t U T MB DUCT
*-
-tee
-i
/
/
Ptgure 4A4
JUL
I*, i ' *
A-A
NOIfOMBMlTICB
an aapaiiai awrrv
5 o a I'M a"
,TJ
PCV-1 will hold set pressure and TCV-1 will hold 266F at the engine fresh
water outlet. When the header pressure upstream from-PCV-1 rises to 18 psig,
PS-1 will operate SV-1, allowing the header pressure to pass to PC-2 opening and
modulating PCV-2 and simultaneously starting a jacket water back-up glycol
circulating pump.
fresh water pump through two parallel loops, the tube side of the 9team
generator and the back-up heat exchanger.
pick up as much of the heat load as necessary to maintain the jacket fresh
water temperature at 266 F.
The jacket
water back-up heat exchanger glycol pump will then shut down and PCV-2
will go to the closed position.
The purpose of TCV-2 is to. prevent the return jacket fresh water from
falling below approximately 245F.
on the jacket when the back-up jacket water-to-glycol heat exchanger is in service.
Waste Heat Boiler
125 psig by means of a gas bypass valve installed between the gas pass division
partition on the inlet end (top) of the boiler.
-138-
-137-
of $20,000.
' ,. ..
4A.2
oil from the engine fuel oil pumps and, secondarily, as a reservoir for the
booster pumps.
The booster pumps pump the oil via the end heater and viscosimeter to the
engine fuel-oil and metering pumps to the combustion chamber.
senses viscosity
T he viscosimeter
Assuming the oil viscosity at 100F as above, the oil' viscosity entering
the engine fuel oil pumps would be above 60 ssu, which will correspond to a
temperature of 180 F leaving the end heater.
the mixing tank will not be in
the engine pump can maintain the 115F temperature in this vessel.
The unit will be started on diesel oil by operating valve "A" to the
diesel oil position.
..-..
To effect the transfer from diesel oil to residual oil, valve "A"
should be gradually transferred to residual oil and the temperature leaving
the end heater gradually increased.
engine fuel-oil pumps to bind "and seize, damaging pumps and cam shaft components-
-139-
After complete transfer to residual, the diesel oil fuel system may be shut down.
To shut down after having operated on residual oil, the heat tracing system
shown in Fig. 4A-3 should be turned on. Valve "A"-should gradually be transferred
to diesel oil, avoiding any sharp changes of end-heater temperature and thereby
avoiding engine pump damage.
should be flushed out prior to shut-down, after which the heat tracing system
may be shut down.
-140-
4A.3
The 120 GPH integrated heavy fuel 'treatment system can perform the
following operations:
1. Heating the raw fuel.
2. Injection of demulsification agent.
3. Centrifugal desalting and sludge removal resulting in reductions of
water-soluble metallic salts such as sodium, potassium, lead, calcium,
etc.
4. Neutralizing corrosive vanadium via magnesium sulfonate.
5. Filtering, pumping, and transferring between residual and distillate oil.
The system will reduce the sodium and vanadium content of the fuel as
follows:
Influent Oil (representative values)
Sodium
Vanadium
200 PPM
200 PPM
Effluent Oil
< 5 PPM
<30 PPM
is first mixed with the fuel in a mixer. The fuel is then centrifuged. The
single-stage centrifuge separates and removes water-soluble and nonsoluble
sodium, potassium, lead, calcium and magnesium.
(kinematic)
The effluent is 99% water with the above metallic soluble plus
approximately 1% oil. This oil is removed in a skimming tank where the oil
content is reduced to less than 80 PPM.
After the centrifuging, the vanadium is treated. Organic vanadium is
extremely corrosive in high-temperature areas of an engine.
very soluble in water, it is difficult to remove.
Because it is not
-141-
2. Inhibition of Vanadium:
Dosage
Source
Identification
3.2/1 mg/Va
Tretolite
Tretolite KI-16
*Hfrl
trTl*TTNT
n*o~i
*-
auppcy
-142-
QMTlMUOvS
rrpi
STM
So P^*/
4 ^
^ ^ = - ^ - 1 - D O
3f
<fl3
I
*4eo
V*
HX
TOSUJM6
M/C
Vp/
ft
-"too
T *.
nNMlttlTlOM
tEEAGENT 0eOM|
l(8 CWSTOr*t^ J
n>sLuoe
TAMtC#l300
\WTGW\rrTEKT OOMTipVOOS
-_
Igoo I
^^p^^3=^-/fc^Nl
SlUBfrC TRC SK
I goo I
*l3O0
rtKr*>-JH]ftJ
#sio
Figure 4A4
-143-
PROCESS LINE
A-KmAftf I ' N E
-**-
~f
L>*
"*!
2-W
A Y SA N'T^.RV VA uVE
A
W/ IR A CTUA TOR
T
>-CH
_ jffi
i
~~h\
ill i
, *?
MOTORIZED LINE R L T E R
>-W-i
GATE VA LVE
-tg9-
PNEUMATIC BA LL VA LVE
GLOBE VWtVE
2 - W A Y PLUG VA LVE
1CJPLIN3
>
PUSHBUTTON
FUNNEL
5PRAY NOZZLE
|S]
PRESSURE SWITCH
IDPSI
DIFFERENTI
A L PRESSURE SWITCH
01
LIMIT SWITCH
T H E RA
M L SWITCH
El
FLOW SWITCH
IS)
FLO
A T SWITCH
RED LIGHT
GREEN LIGHT
TEMPERATURE
CONTROLLER
_^_J
LINE BLIND
*****
y ^ l t
NEEDLE VELVE
DAMPER VA LVE
J 4 l w BA CK PRESSURE VA LVE
^"T"*
TURBINE PUMP
HEATER OR COOLER
SIPHON OR PIGTAIL
TRANSDUCER
A,
TEMPERATURE CONTROLLER
CONDUCTIVITY CONTROLLER
LEVEL CONTROLLER
INDICA TING
j U K ^ f a f a n PROPORTIONING PUMP
/
CT
,. .
^
a
'
S
X
>
FLOW RECORDER
FLOW INDICA TING CONTROLLER
FLOW RECORDING CONTROLLER
STANDARD CUBIC F T
TEMPERATURE
CONTROLLER
PSIG MA X
PRESSURE RECORDING
CONTROLLER
*F MA X
FLCW GPM- RATED CA PA CITIES
FLOW/HR : RATED CA PA CITIES
RECORDING
PRESSURE T R A N S M I T T E R
TEMPERATURE
T RA N S M i T T E R
VENT
FLOW T R A N S M I T T E R
COMBINATION INSTRUMENT
W / T W O SERVICES
FLAME A RRESTER
ITEM NUMBER
DRAIN
Ul)
*-m-<
HIGH L E V E L A L A R M
Figure 4A5
CONTROLLER
>~Qi
PRESSURE
H RECORDING CONTROLLER
DR
HthT
POSITIVE PUMP
L E V E L INDICA TOR
>~~-Cy~i
INDICA TOR
ALARM BELL
3-W
A Y SOLENOID VA LVE
I
!
TEMPERATURE
CENTRIFUGAL PUMP
ALARM HORN
2-W
A Y SOLENOID VA LVE
DUPLEX S T R A I N E R
VALVE INTEGRA L
ANGLE VA LVE
HH
J(J)~*
tSo^t
)(
)&
CHECK VA LVE
RELIEF V*LVE
A IR SWITCH
>
ACCUMULATOR
SIGHT GLASS
TANK VENT
DIVERSION BA LL VA LVE
(7.
!/PUNTED 'NSTSLVENT
SlSN
A L CONVERTER
ORlFiCE
^\E_
(5g
THERMOSTATIC A IR VENT
^0i
^A?K3AGM SEA L
' F Q M RA T Q P .
T5C--CONDENS
A TE
A
M VlETIC
H)
THERMOMETER W/WELL
SAMPLE VA LVE.6A TE
BALL VA LVE
-f5-
(Mj
THE3MOWE LI-
PEDi^ER
REV^TOFLEy
ELECTRICAL .INE
H>-5
FLOW METER
-1444A.4
based on having not more than a 10" H-0 pressure drop between the ambient
and engine exhaust flange. The engine connection is 18". Therefore, we
will utilize 18" pipe and fitting between engine and boiler and between
boiler and exhaust silencer.
1.
a.
0.75
b.
1-18" 90
.23
c.
Expansion joints
.23
d.
.11
Total K
2
W v
A 2 x 2.093 x 105
K = 1.32
W = 24,272
v = 30.9 ft3 at 767F
A = 224 in2
AP1
2.
1.10" H 2 0 (W.G.)
3.
4.
Pressure drop through 20" pipe downstream from boiler just before stack:
4' of 20" pipe
1 expansion joint
1 sudden enlargement
Total
K = 1.13
W = 24,272 l b s / h r
v = 19.77 f .3
t3/lb
A = 291.0 in
0.03
.10
1.00
1.13
.60
1.00
1.60
1227
AP = (3.01)^g = 4.57
The pressure drop through the boiler with the internal gas bypass
open (used to control steam pressure) as quoted by the manufacturer
is 2" H20 (W.G.).
The total pressure drop through the exhaust system is
4.57 + 2 + 6.57
At both temperatures the total exhaust system pressure drop is
less than the maximum allowable.
Inlet Air System Pressure Prop
The engine manufacturer has stated that the maximum allowable pressure
drop between ambient and the diesel inlet flange connection shall not
exceed 4" H 2 0 (W.G.).
146
The major components making up the inlet air system are as follows:
1) oil bath type air filter; 2) inlet air silencer; and 3) 20" O.D. pipe
between air filter and engine.
Oil bath type of air filter. A ir mass flow rate into engine at
100% load is 24,272 lbs/hr. A t 90 F this corresponds to an air volume
of 5603 CFM. The manufacturer's performance curve gives a AP of:
APj = 1.06" H 2 0 (W.G.)
Inlet air silencer. This is a 20" American air filter unit.
Face velocity is 2773 ft/min at 90 F pressure drop:
AP 2 = 0.6
20" O.D. pipe between roof and engine.
590 Elbows
108 feet of 20" O.D. pipe
Sudden contraction at engine
Sudden contraction of filter
Expansion joints
K = 0, ,74
K = 0. ,96
K = 0. ,5
0. ,5
0. 3 _
3, ,0
AP = *'
A2
W 2 vv
x 2.093 x 10 5
Ap
(291) x 2.093 x 10 D
= 1.38" H 2 0 (W.G.)
Total System Pressure Drop
AP
aK
= p
+ p
1 2
+ p
*3
-147-
APPENDIX 4B
Equipment and Instrument List
-148APPENDIX 4B
EQUIPMENT AND INSTRUMENT LIST
4B.1
will be used to control the steam pressure in the ebullient cooling system.
The control valve will be a Fisher Controls Design ED 3" equal percentage
valve ANSI Class 125 lb. The valve will be equipped with a Fisher Controls
657 type actuator and a Type 4160 Controller mounted on the valve. The
valve is selected to pass 2600 lbs/hr of 15 psig steam with a 2 psi
pressure drop.
>
The valve will be used to maintain the primary loop jacket water
temperature at 266 F.
Controls Design ED 3" equal percentage 300 lb. design. The valve will be
equipped with a 657 type actuator and a type 2560 controller for mounting
on the valve.
Pressure Control Valve and Pressure Controllers - PCV-2 and PC-2.
The valve will be used as a backup to PCV-1 to control the ebullient steam
pressure.
3" equal percentage 300 lb. design and a Type 4160 Receiver Controller for
mounting on the valve.
Glycol Temperature Control Valve and Controller - TCV-2 and TC-2. The
purpose of this valve and controller is to hold the glycol temperature to a min
imum of 245F while the backup heat exchanger is in service. The pressure
control valve will be a Fisher Controls Design ED 3" equal percentage 300
lb. design with a Type 4160 Receiver Controller for mounting on the valve.
Level Control Valve and Level Controller on the Jacket Steam Generator
- LCV-1 and LC-1. This will be a Fisher Controls Design ED 1" restricted
trim equal percentage valve and Fisher 2502-249 pneumatic level controller.
Level Control Valve and Level Controller on the Jacket Water Steam
Generator - LCV-2 and LC-2. This will be a Fisher Controls Design ED 1"
restricted trim equal percentage valve and a Fisher 2502-249 pneumatic
level controller.
1500 kw,
2120 BHP; 900 RPM; 16 cylinders; 10 inch bore; 10.5 inch stroke; residual
oil fuel; engine suitable for generating steam from jacket heat at 15 psig.
Electric Generator.
1500 kw, 80% power factor, 900 RPM, 3 phase, 60 Hz, 13,800 V.
The generator
gas flow:
temperature; 2516 lbs/hr steam flow; 150 psig design pressure; 125 psig
working pressure; designed and stamped in accordance with ASME Code Section VIII.
Choice of boiler based on the above performance requirements and the
existing operating pressure of Clark steam distribution system.
A further con-
sideration leading to selection of a vapor phase boiler was that this design
takes a minimum amount of floor space.
Diesel Jacket Unfired Steam Generator.
erator are as follows:
308 GPM at
A primary loop (diesel jacket fresh water) and secondary loop (15 psig
steam system) were selected because the engine manufacturer required that the
jacket cooling water system be maintained under a positive pressure to prevent
water from flashing into steam in the jacket of the engine.
unfired steam generator is taken from the engine heat balance, Appendix 3c.
Air Cooled Glycol Radiator and Surge Tank.
two separate horizontal sections, the diesel air cooler and lube oil cooler
Performance
requirements for the air and lube oil cooler section are: 390 GPM glycol
flow; glycol temperature in: 118.9 F; glycol temperature out: 107.6F;
air temperature to unit:
93 F.
back-up glycol to air heat exchanger are: 370 GPM glycol flow; glycol
temperature in: 246 F; glycol temperature out: 237F; air temperature
to unit: 93F.
Both sections will be designed for 50 psig. The size of the units
is taken from the engine heat balance, Appendix 3C. We decided to use
glycol in both systems to eliminate the potential for freezing.
An air
shall be a skid mounted unit completely piped and wired, and automated.
The capacity of the unit is 120 GPH. The unit shall have the capability
of reducing the sodium level from 200 ppm to <5 ppm and the free vanadium
level from 200 ppm to <30 ppm.
Fuel Oil Pumps: Two Heavy Oil Transfer Pumps; Two Heavy Oil Engine
Pumps; One Distillate Oil Transfer Pump; One Distillate Oil Day Tank Pump;
One Leak-off Tank Pump. These seven pumps will be duplicates. They will
be IMO DeLaval Fuel Oil Pump Series 3EB, 2 to 9 GPM, 150 psig.
One Air Compressor and Two Air Compressor Receivers.
Compressor
capacity is 25 CFM (free air), 250 psig discharge pressure, 900 RPM,
7-1/2 BHP. The unit will have a belt-driven compressor drive motor and
belt guard.
240 gallons. The air receivers have been sized for six consecutive starts.
of air at 95F is .36 psi. The sound attenuation shall be not less than
the following:
Octave Band Center
Frequency - Herti
Attenuation dB at
4000' FPM
Exhaust Silencer.
125
8
250
15
500
21
1000
27
2000
27
4000
23
5000
17
provided by this
31.5
63
125
250
500
IK
2K
4K
8K
Attenuation dB
12
30
35
32
26
22
23
25
28
-153APPENDIX 4C
OUTLINE SPECIFICATIONS
One (1) Sulzer ASL 25/30 Diesel Engine
1. Power Rating - 1405 kw, 1983.9 BHP
2.
3. Number of Cylinders - 8
4.
5.
6.
7.
a.
b.
8.
9.
10.
11.
12.
Flywheel
b.
Speed governor
c.
Safety governor
d.
e.
f.
g.
h.
Piping on engine
i.
j.
k.
1.
Alternative Engine:
3. Number of Cylinders - 16
Bore - 10 inches
5.
6.
7.
a.
b.
8.
9.
10.
11.
Flywheel
b.
Speed governor
c.
Safety governor
d.
e.
f.
g.
h.
Piping on engine
i.
j.
k.
1.
m.
Skid
Rating - 1875 KVA, 1500 kw, 80% P.F., 900 RPM, 3 phase, 60 Hz, 13,800 V
2.
3.
4.
5.
6.
7.
8.
b.
c.
d.
1.
2.
Performance
a.
b.
c.
d.
e.
Maximum gas drop through unit - 6.0 inches H-0 at 24,272 lbs/hr
3.
4.
b.
c.
d.
e.
f.
g.
h.
General Description
The tube bundle will be multipass "U" tube construction. The
tube bundle will be immersed in water from the building heating
system.
tubes.
Steam
3.
b.
c.
d.
e.
The diesel air cooler and lube oil cooler section and the diesel jacket
back-up cooling section.
The air handling units will be located beneath the units forcing air
vertically upward across the coils.
1.
Performance
a.
b.
-157One (1) Air Cooled Glycol Radiator and Surge Tank (continued)
2.
Design
Both sections will be designed for 50 psig.
b.
c.
d.
The bearing frame contains one ball bearing inboard and two ball
bearings outboard.
e.
f.
c.
d.
be equipped with an inlet air filter and have a dual control system.
The compresor will be Quincy Model D-340 or approved equal.
Two (2) Air Compressor Receivers
Design pressure - 275 psig
Each receiver will have a capacity of 240 gallons each.
Each unit
will be equipped with a base ring, inlet and outlet connections, gauge
connections, and drain connections.
125
250
500
1000
2000
4000
5000
15
21
27
27
23
17
Exhaust Silencer
A Model M41, size 20", Maxim Exhaust Silencer or approved equal
shall be furnished.
bore axis, i.e. the flow shall be straight through the unit. The maximum
allowable pressure drop through the unit shall not exceed 1.25" H 2 0 (W.G.)
at a flow of 24,000 lbs/hr, at a gas temperature of 350F.
Also, the
The sound
attenuation provided by this unit shall not be less than the following:
Band Center
Frequency Hz
31.5
63
125
250
500
IK
2K
4K
8K
Attenuation dB
12
30
35
32
26
22
23
25
28
-160-
APPENDIX 4D
Electrical Specifications, Including Grid Connection
-161i
APPENDIX 4D
ELECTRICAL SPECIFICATIONS, INCLUDING GRID CONNECTION
4D.1
Scope of Work
The work covered by this specification shall include all labor,
material, equipment and services to construct and install the
complete electrical systems in accordance with the National
Electric Code and State and Local Requirements, and as shown on
the plans and specified herein.
This work shall include the following:
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
4D.2
Specifications
Primary Service
The primary service will be 13.8 KV Delta, 60 cycles, ungrounded
system, starting from the Goddard Library existing service board and
extending to the new building 13.8 KV generator set. This is shown
on the site plan, Fig. 4D-1.
Primary duct system shall consist of two 4" I.D. Type II, direct
burial plastic conduits encased in concrete with rigid conduit
adapters and fittings at the manholes and existing padmount substation.
All terminations, splices and Kenetron Test are to be made only by
Technicians experienced in this work and by a company approved by
the Engineers, such as Hub Cable Company, Medford, Massachusetts.
Existing Substation Padmount
The Electrical Contractor shall furnish and install a 400 ampere, 3
pole, fused Square "D" switch in section two to feed the new motor
control center.
The feeder from the existing substation shall be four (4) #500 MCM4" C and one (1) 4" C spare, encased in concrete.
System of Light and Power
Primary distribution system shall be 13,800 volts, three phase, three
wire, 60 cycles, A.C.
Secondary distribution system shall be 120/208 volts, three phase,
4 wire, 60 cycles, A.C.
-162-
, TRANSFORMER
T^TT^
NEW METERING
t RELAY
METERING AND
RELAY CONTI
WIRING
BATTERY CHARGER
BATTERIES
2-4'SPARE
CONDUITS TO
UANHOL-C
-SHELVING
FEEDER A
PRIMARY CABLE-
SE
FEEDER Tt
-PRIMARY
CABLE
txwfflur
3aMANHOLE COVER
COVER JO BE
INSCRIBED ELECTRIC
(MADE
-/
BRICK HEIGHT
TO SUIT GRADE
CONDITIONS
PULLING
IRONS
INSTALLED^
IN MANHOLES
ON ALL WALLS
V'
""Wi~
RIGID
STEELCONDUIT
^INSTALL
INSULATEO 01
GND BUSHINGS
AND GND TO
ROD
BARE COPPER
H*
10 LONG COPPER
GROUND ROD
JERICA N
PRECAST
MANHOLE'A-10
CABLE RACKS
TYPICAL FOR ALL
(<)WALLS
EXISTING TELEPHONE
CONDUITS TO BE
REPLACED
Ot^
SITE PLAN
SCALE i
.sco-
CABLE RACK
MANHOLE DETAILS
30"MANHOLE
ic
\4
COVER
y\.
SITE PLAN
PROPOSED ICS.
PLANT
DOE CONTRACT NO. ECTT-C-02-42H
CLARK
UNIVERSITY
9 5 0 MAIN STREET WORCESTER, MASS
OI&JO
HANDHOLE
Figure 4D-1
SCALE
r-50.0"
,-.i
SHEPHERD
ENGINEERING
4 9 6 PARK
A\ENUE
WORCESTER,MASS
0IGI0
INC
DRWt
E-l
NO
Type RHW or THW shall be used for all distribution wiring, as indicated
on the drawings.
164-
HOLOPHANE
HOLOPHAME
HOLOPHANE
HOLOPHANE
HOLOPHANE
HOLOPHANE
DEVINE
I9II-P0-I20V.C-2-C6-IT5W-METAL
HALIOE
l*l-PD-l20V-C~l-Ct-l30WJHC
(LESS BALLAST)
C*-TP-PX-2/T9W-INC
4IT-420VB2S-IT3W-METAL HALIOE
IHI-WL-l20V<-2-C6-IOOW-METAL
HALIOE
7200-4 -2/kOW-TI2
FGia-VIS-MV-IT}W-E2-MV
tt
''
CONTACTOR WITH
MAW CONTROL MOUNTED
IN THE COVER
I2
3Ek
Figure 4D-2
Floor PlanLighting
SCALE'/4-l
SCALE
it
ipf'
HelO
DATE
SHEPHERD
EN
G INElRINt
INC
)9S PARK AVENUE
WORZCSTlR,\l*SS
OHIO
OHIO
OWS NO
E-3
-165SIAINLESS
STEEL
WATERPROOF
NEMA4
DISCONNECT
SWITCHES
SMOKE OCTCCTORS
TO EXISTING
HPtyUpjO
PANEL
ONTROL MOUNTED
HE COVER
FA
**
0ETICT7RS
LIGHTING
AND
RECEPTACLE PANEL
100A MAIN CIRC BR
12 20A IP CIRC BR
120/20
V
tojt
MAIN CIRC BR
SO 0 TYPE LA
400
AMPERES.
3 PHASE, 3 POLE
FIRE ALARM
TYPICAL FA STA
HORN4 A 0 LAMP
SYSTEM
TV JUNC
U0NIT0R
SOX
STORM
SOCAGE EJECTOR
4
SPARE
<
SPARE
SUE
9/
1.
ai
2
2
12
12
12
)
3
10
It
'4
It
M
o
a
2
2
19
2 TRAHSF PUMP
M
IT
__s
2
2
>4
0
0
It
( EHUNf
HUPP*
20
PUMPPfA
21
22
PUMP
<fi
V}
PUMP Pi
PUMPP4
PUMP PI
'/!
>>>
''1
PUMP Pi
CENTRIFUGE
2*-
AIR COMPRESSOR
"/?
23
24
27
SPARE
21
2t
30
31
SEWACE EJECTOR
STORM PUMP
32
>l2
SPARE
31
6
2
1
NO
,,
,
,.
"
30
GO
GO
11
it
12
7 SECTION
STARTER
PURPOSE
i
EXISTING eAN
W / f l / W TO BE
,
,.
,
"
i,
GO
60
60
60
,
'
I,
"
,,
n
13
'
ra
n
n
,1
11
IS
ii
ii
40
'
,
l_
ra
,,
"
,1
,i
>
,|
40
11
>'
"
70
'
"
,,
20
IS
1,
"
"
i,
li
ACCESSORIES
HOA H.0T CONTTRAN AUX
YES
Jl._
YES
COW
1,
1,
,,
,,
LOCA'ION OF
TELfPHONE
ll
II
7
TYPICAL
SMOKl
0ETICHIR-,
I,
,1
1L.
JTAPPROX
Tl
EXISTIN
G
ll
LINES
,.
SK,3 MOUNTED
PUMPS P6.P6-A
P3I.P4J Pi PT
AND P6 1/2HP
EACH
CNTRIFUGF 6HP
jr
,.
,
II
-H-
i,
,
,,
3 SETS
NO
0TUR
PLM0VE07
1,
- if-,
&
ll
j.y^&m
MCC
,i
,,
II
"
L , v
T~f\
CAMERA
II
T'/,
,1
'.
,
,1
II
"
'
,
,1
I,
II
1,
, .
//
I _
'J
JACKET WATER
CIRC PUMPS
JACKET MM I ER
BACK-UP HJ EXCHR
GLYCOL CIRC PUMPS
LEAK OFF
NOTE
TANK PUMP
SECTION
MO 1
()
l'/2 HP
SECTION
r<
NO 2
TV
CAMERAS
10 MANHOLE
SEE SITE PLAN
TRANS
TV MONITOR
IN 3011 LR RM
POWER FLOOR
~L
TV JUNC
EXISTING lOOOKVA
EXHAUST
BOX
FAN
Ef <^
EXHAUST FAN If
POWER FLOOR
Floor PlanPower
PLAN
TV CAMERA SYSTEM
EXISTING
BOILER
eOlLlf
OIG PO
ROOM
SPARE-rc
Figure 4D-3
PLAN
^4-10
ONI
SCALl
sz./L
JO EXISTING MOTOR
CONTROL
CENIIR
BOILIR "!
~ ' \ :~ )
SCALE
,\k*r
l/t
10
DATE
"-W:H/9"B
SHEPHLRD
EN
G INEERIN
G
496 PARK AVENUE
WORCLSTER,MAiS
OHIO
INC
E-2
166
MASS.ELEC CO
FEEDER 41
EXISTING crs
600fi
ELEC
CONTRACTOR SHALL
FURNISH
AND INSTALL
AUX CTS TO
CHANGE SETTING
TO
400/5.
I FE
EXISTING
4/b COPPER
(i*
OUT
RELAYS
UN
it
RELAYS
11
G TS
L_.
LINE,
SIN
PILOTLINE
RELAY
TRANSFORMER
TRIP CONDUIT
FOR 12-41
METIRim
TRIP CIRCUIT
FOR
52-20
i.-, . J
r-J
r~"
TRIP
CONOUITS
FOR 12-41
AND 52
20
Jml l&6--EI]
.J L.
RECORDING
MAG NETIC
TAPE UNIT
\JSA->
rrrn
.;<
FEEDER
}'4/>-l5kv
CABLE
IOOKVA
TRAHSF
r /i
X
COPPER
4'CONOUIT
Hi
--i
rxi
r-'
I
I
I
I
I
I
L J
~l
i
I300KW
I3BKV
GENERATOR
GENERATOR
CONTROL
PANEL
GODDARD LIBRARY
EXISTING SUBSTATION
AND NEW METERING
CONTROL FOR NEW
ICES PLANT
Figure 4D4
FEEDER
FEEDER
X
V
i
i
rxn
MOTOR
CONTROL
CENTER
LJ
4 SOOMCM
4'C
JONAS CLARK
EXISTING SUB-STATION
AND NEW MOTOR CONTROL
CENTER IN ICES PLANT
DISTRIBUTION CENTER
PROPOSED ICES
PLANT
DOE CONTRACT NO ECTT-C
02-4211
CLARK
UNIVERSITY
9 3 0 MAIN
STREET-WORCESTEHMASS
Ji-i
SCALE
fi'l
DATE
MARCH '9TB
SHEPHERD
G
EN INEERIN
G
4 9 6 PARK AVE
WORCESTER MASS OIG IO
E-4
-167Panels for lighting and small power shall be NQOB with thermal magnetic, bolt-on circuit breakers and NEMA interrupting capacity as
required and mounted in the motor control center.
Safety switches shall be Square "D" heavy duty type, fused or unfused,
as required.
Receptacles shall be duplex grounded type, 20 ampere capacity.
Switches for general lighting shall be the quiet type, 20 ampere.
Device plates shall be brushed stainless steel.
Emergency Lighting
Emergency lighting shall be provided in the new addition, as shown in
Fig. 4D-2. The feed shall be extended from 20 ampere circuit breaker in
the Boiler Room emergency panel.
Fire Alarm System'
The Electrical Contractor shall furnish and install a complete supervised,
closed-circuit, double-supervised, zone-indicating, manual and automatic
fire alarm system with standby batteries, as shown in Fig. 4D-3.
Telephone System
Electrical Contractor shall furnish and install new empty conduit for the
existing New England Telephone manhole, all as designated on the electrical
site drawing.
The existing service conduit shall be removed. Existing raceways may be
cut and re-routed under the floor slab to the existing junction box.
Power
All motors will be furnished and installed by others, wired and connected
by the Electrical Contractor, as shown in Fig. 4D-3.
The Electrical Contractor shall furnish and install all starters, contactors,
safety disconnects, thermal switches, remote and local control switches,
relays, timers, toggle switches and pilots, unless otherwise shown.
The Electrical Contractor shall furnish and install all interlock wiring
required for all motors, controls and alarm circuits.
Motor Control Center
The Electrical Contractor shall furnish and install a Square "D" model
four, or equal, motor control center, complete with all fusible disconnect
switches, starters, selectors and switch controls for operating motors and
auxiliary contacts for interlocking of motors and remote controls. This
is shown in Fig. 4D-4.
Metering and Relay Control to Monitor the Parallel Feeder Load Between
Clark University and Massachusetts Electric Company
A pilot wire terminal at the University shall be connected to the existing
pilot line control cable, making a three-terminal line, as shown on the
site plan, Fig. 4D-1, and the Distribution Center Plan, Fig. 4D-4.
-169!&
1
1
1
1
6
1
1
1
1
1
6
3
Device
Function
Type
Range
Style #
87PW
Pilot Wire
HCB
4-15
67-51
Dir. Over
current
0.5-2.5
292B930A10
1575394
508A468G01
291B318A09
288B571A12
55-140
55-140
55-59.5
55-65
55-140
1875508
1875512
671B287A15
291B995A12
1875512
27
59
81-U
81-0
59N
CV-5
Transformer
W2 Switch
RC Milliammeter
CR-7
CB-2
CV-5
KF
CF-1
CV-5
4/1
-170-
APPENDIX 4E
Architectural Design*
4.3,
The new specifications and drawings were not available at press time.
-171APPENDIX 4E
ARCHITECTURAL DESIGN
4E.0
Introduction
There were two primary requirements of this architectural design:
It was our
mass of the building above grade, where it would tend to overpower the
structure in its relation to other buildings on the campus. The site
plan is shown in Fig. 4E-1. The main floor plan is shown in Fig. 4E-2.
The upper part of the generator room will contain an observation deck
along the north wall and a recessed, sheltered observation window along the
east wall.
other equipment and a large removable panel in the south wall to provide
access to machinery.
tion and cross sections of the proposed building are shown in Fig. 4E-4 - 4E-7.
-172-
SITE
PLAN
Figure 4E-1
S i t e Plan
-173-
:_i
rr:
l-
an c-
FLOOR
LOWER
Figure 4E-2
LEVEL
PLAN
-=_
II
i . . .._o- ^ po ^OPCSL'^
i.~)on-''
. iiICES
J,.
P-^S -1
CL_A'j!< U V E R I T Y
^x:.'/'
174-
/ /
7 /
V/ .
rs;. A . s
/ / /
\>' 7 7 li
FLOOR
UPPER
LEVEL
Figure 4E-3
PLAN
Jti
paopc&zD
CLA:^
\cz PLANT"
u\.vE3f--:7Y-
175-
j
1
'
7 i
i
tir-
r_
L,
f 4
i"
-r
L. _ J
,1
IF
'
EAST
H
Figure 4E-4
East Elevation
'
ELEVA TION
-r
E-CVA TO^
(4 . i - PROPOSED
ft-ASK
VOf5C6TtQ
!CCS
P-A VT
UNVC-25""Y
Miee
~^-
176-
I
:TCCT
HX-DOMr-AXf!
1 - . , \ :. t - 9 1 - T &
i anon
ST,uonasni.
IwesF-
SOUTH
- = . <=
Figure 4E-5
NORTH
South and North Elevations
., ,
V ><>'
7TI7fc
^vfcito c ^ . n c
MCf-^-f'
.
"KOQTM ...^ ..SOUTH l_evA T:N
PROPOSED ices PLA ST_
'CL.A.Q^ USJTVE.,2S:TY : "
wonoeren
M i n .
-177-
c_n
EJ
3S2~0\.
Figure 4E-6
A A
CnOSS
QSC-QV.
BB
n^TDAQ^TrAX^^-KT3
. l<mt> ! &UI_D'NG
|_ - C * - L '
I
-J
CAJKI^L.
CQOS5
3CCOSS
uisi":v:Q5.,"rY
1781
ct
"-fl
-_l
[ i_..
c=n
-,
m
T
MeriikMl!
^ruDt
T_>^,rJtfBrrr
crayy* a e e r p s i
^T^3~3
cc
'
Figure 4E~7
C~A?PC
ICES
PL.A S.T
uwr^TY
-1794E.2
Architectural Specifications
The following outline specifications describe the construction as
presently planned;
and
over east observation deck; standard asbestos felt or asphalt felt and
gravel roofing; windows framed with aluminum tube and multiple glazed for
acoustical attenuation; steel or aluminum doors and removable panel,
gasketed and double glazed; strip aluminum louvers permitting random locations for inlet or outlet air; an internal envelope of acoustical material
on the underside of the roof and on walls wherever suitable space is
available; painting of piping, steel doors and miscellaneous iron only
no painting of concrete is included; bridge-type, double-beam crane for
minimum vertical clearance, with hook and bridge manually controlled by
continuous chain; tin-clad, four-hour fire door between generator room and
old boiler room is included.
The chimney plan includes a foundation at the boiler room floor
level, tied to the Jonas Clark building and rising to a height of 95',
approximately 30' above the cornice of the Jonas Clark building.
is
The flue
a new 30,000 pound cooling tower; this work will require the removal of
the third floor ceiling and extensive strengthening of the structure of
Jonas Clark.
tower at the present east end of Jonas Clark (this design not fully
developed); also, structural steel will be provided to frame up the side
of Jonas Clark to support condenser water lines.
-180-
APPENDIX 4F
-181. APPENDIX 4F
UTILITY TIE-IN SPECIFICATIONS
4F.0
Introduction
We show in Fig. 4F-1 a si,te plan including all existing utilities.
The floor plan in Fig. 4F-2 shows the necessary utility tie-in described
in this Appendix, and Fig. 4F-3 gives elevation's for major tie-ins. All
work can be done in accordance with federal, state and local regulations.
4F.1 Heating System
Steam lines (existing).
now leaving the existing boiler plant and serving the campus must be
rerouted through the proposed new plant and reconnected to the existing
steam and condensate return lines outside proposed new plant foundation
walls.
Steam lines (new).
now leaving the existing boiler plant and serving two buildings on campus
must be rerouted as shown on the drawings and reconnected outside the new
plant.
Feedwater piping.
tion tank manifold to new feed water tank in proposed new plant complete
with all necessary controls, valves and other accessories.
4F.2
Fuel System
Fuel oil piping systems (existing); The existing fuel oil supply
and return lines and fuel oil gauge lines serving the existing boilers are
presently located in the area of the proposed new plant.
be relocated and run through the new plant and reconnected to the existing
lines outside, the proposed new plant foundation walls.
Fuel oil piping systems (new).
-182-
LEGEND
(HEA T I N G")
-HKS.
-HW.R.
-F.W.
-F.O.S.
-F.OR.
F
GA
V
_f
t
/REM.,.
TO
BE REMOVEO.
NOTE:
REFER TO FLOOR PLAN 'j>W6 VIZ)
FOR NEW PIPE CONN TO EXIST'G
S T E A M SUPPLY
STEAM RETURN
HOT WATER SUPPLY
HOT WATER RETURN
FEEDWATER
FUEL OIL SUPPLY
FUEL OIL RETURN
FILL
GAUGE
VENT
PIPE UP
PIPE DN
NEW PIPING
EXISTING PIPING
GATE VALVE
CONTROL VALVE
G L O B E VALVE
CONN. NEW PIPE TO EXIST'G
FRESH AIR SYMBOL
EXHAUST AIR SYMBOL
EXHAUST FAN
ROOF FAN
SOUND TRAP
AUTOMATIC CONTROL DAMPER
FRESH AIR
FUEL OIL
FEEDWATER
VOLUME DAMPER
(PLUMBING)
GAS
-SANSANITARY
SANITARY (BURIED)
RAIN CONDUCTOR'
RAIN CONDUCTOR (BURIED)
VENT
VENT ( J U R I E D )
P I P E UP
P I P E DN
GATE VALVE
CHECK VALVE
CONN. NEW P I P E TO E X I S T ' G
NEW P I P I N G
EXISTING PIPING
F.C.O.
FLOOR CLEAN OUT
V.T.R.
VENT THRU ROOF
W.tT.
WASTE t TRAP
CO.
CLEAN O U T
F.D.
FLOOR DRAIN
RXJl
ROOF DRAIN
V.
VENT
Site Plan--Engineering
CLARK UNIVERSITY
WORCESTER,
FITZEMEYER t
MASS.
TOCCI INC
Ml(
183-
Figure 4F-2
HALL)
Floor PlanEngineering
PLANT)
FLOOR PLAN
PROPOSED ICES PLANT
CLARK UNIVERSITY
WORCESTER,
MASS.
184-
J1
6AUGE
3* F O S
2 V FOR.
QJ
n^v
Jfc=Jr-4=*A
6 0 X 54
h
i
I. L
1-
^TNT
DATE
J-IJ-Tt
r"-i
KALC
ijif. i'-o*
sunn
F i g u r e 4F-3
AMO pr
fLF
Elevations
|!(..ll\V
ELEVATIONS
PROPOSED ICES PLA NT
CLARK UNIVERSITY
WORCESTER,
A
M SS.
A
M tS.
M3
-185A new No. 2 fuel oil tank, supply and return lines, tank tappings,
gauge, vent, fill connections and all necessary accessories shall be installed.
The new fuel oil supply and return lines shall extend from the
new fuel tank into the proposed plant and tie into the fuel pump furnished
by Thermo Electron.
Gas system.
is presently located in the area of the proposed new plant. This gas
main shall be relocated as shown on the drawings, including all gas meters
and valving.
4F.3
existing boiler plant must be removed and replaced with two new exhaust
fans as indicated on the drawings, on Fig. 4D-3. These fans are to be operated
from reverse acting thermostats with switches for manual operation.
4F.4 Water and Drainage
Domestic water.
the existing mains in the existing boiler plant for use in new plant.
Floor drainage systems. New heavy-duty floor drains with large
sumps and bucket strainers shall be installed with cast-iron pipes extending from each drain to a new duplex sewage ejector.
the ejector shall be extended into the existing boiler plant and connected
to the nearest sanitary main.
roof.
Storm drainage system.
be installed across the new ramp down to the new plant. New cast-iron
piping shall be extended to a new duplex sewage ejector.
The discharge
from the ejector shall be extended into the existing boiler plant and
connected to the nearest sanitary main.
-186-
APPENDIX 4G
-187Appendix 4G
Noise and Vibration Analysis
4G.1.
Noise and vibration are key design issues. This Appendix presents the
results of the acoustical engineering preliminary design analysis. The outline
specifications for mechanical (Appendix 4C) and ventilation systems (Appendices
4D,4F) and for the building (Appendix 4E) all include items pertaining to noise
and vibration control.
The following noise sources were considered in the acoustical design analysis.
The diesel engine emits noise from its casing and from the air inlet on the roof
of Jonas Clark and also from the exhaust stack.
silencer and also a heat recovery boiler which attenuates engine noise. The
engine air inlet is equipped with a silencer.
is a potential leak for in-plant noise such as from the diesel engine casing.
This system will have inlet and exhaust silencers to reduce plant noise and ventilating fan noise reaching the outdoors. The building will be designed to prevent excessive noise escape,
be a special wall construction on the Jonas Clark side to protect classrooms from
excessive noise.
a quiet option unit with slower fan tip speed, or by constructing a noise barrier
around the heat exchanger to take advantagf of its high elevation relative to
critical receptors.
Diesel engine vibration will be controlled by means of an inertia block
foundation isolated from the rest of the building.
Design Criteria
rooms and offices in Jonas Clark Hall; adjacent open space including the proposed
Goddard Memorial, Goddard Library, and Bullock Hall dormitory.
With existing and foreseeable technology for diesel engines it can be expected
that noise levels inside the plant will be in the range 100 - 110 dBA. This
-188assumes extensive sound absorbing surfaces inside the plant on the roof and walls.
There is no known way to reduce these noise levels below 100 - 110 dBA.
These expected noise levels inside the plant are well above the 90 dBA
permitted by OSHA for 8 hours per day employee exposure.
sary to locate the operator's desk and control station outside of the high noise
area.
This is comparable to
the existing noise levels and will permit conversation with a loud voice at a
distance of 3 ft. Telephone use will also be possible. There is no known risk
of hearing damage at 70 dBA.
The most critical receptors in Jonas Clark Hall are the offices, classrooms
and other teaching spaces. Typical acceptable background noise levels in such
spaces are in the range 35 - 50 dBA.
produced by the ICES plant should not exceed 40 dBA in any offices or teaching
space in Jonas Clark Hall.
some rooms at the east end of the building, but not audible in most of the rooms.
Figure 4G-1 shows some of the existing noise levels measured during the
Environmental Impact Assessment investigations.
levels shown in Fig. 4G-1 are the lowest ambient noise levels measured, i.e. at
night (2:00 a.m.).
Most other locations in the vicinity of the proposed ICES Plant were measured at
about 50 dBA. The only exception to this was close to Jonas Clark Hall where the
boiler room emits 60 dBA.
Our interpretation of these data is that the true night-time ambient noise
level for the Clark University campus is about 42 dBA.
at night outside such nearby buildings as Bullock and Atwood, where it produces
noise levels at about 50 dBA. The existing ambient noise levels are apparently
compatible with campus activities. The Massachusetts DEQEstandards would permit
an increase of 10 dBA over the existing ambient levels.
-189-
y, . - 'J
0 20 40 Go*
Approx. Scale:
1 inch = 50 ft
AMBIENT NOISE
LEVEL - dBA
(Source: Appendix 2C)
LGC
ansa's
excessive noise for the exterior of a dormitory and would greatly detract from
the present tranquil ambience of Clark University.
The Cities of Boston and Cambridge in Massachusetts have established 50 dBA
as the night-time noise limit for residential land uses.
It is our recommendation
that the ICES Plant should not produce noise levels above 50 dBA at a distance of
200 ft., i.e. including the Bullock Hall dormitory exterior.
If the Plant produces noise levels of 50 dBA at 200 ft. then higher noise
levels can be expected closer in.
in Appendix 2C are in the range 50 - 70 dBA, with 55 - 60 dBA being rather typical.
It is our recommendation that the ICES plant should not produce noise levels in
excess of 55 dBA at ground level at a distance of 100 ft. from the plant. This
would protect most of the open space, including the Goddard Memorial. For
accessible locations right next to the Plant we recommend a design noise level
not to exceed 65 dBA.
level of 65 dBA permits easy conversation at a distance of 3 feet and raised voice
conversation at 6 feet.
The preceding recommended acoustical design criteria are summarized in
Table 4G-1.
Table 4G-1. AcousticsDesign Criteria
Location
70 dBA
70 dBA
65 dBA
55 dBA
40 dBA
50 dBA
Vibration produced by the Plant shall not be perceptible directly by human beings
in any teaching or office space in Jonas Clark Hall.
be as developed by Reiher and Meister.
Building Floor Vibration," Sound and Vibration, October, 1974, pp. 34-37.)
-1914G.3.
'
in the other Appendices. Noise calculations have been performed based on this
preliminary design.
>
in Table 4G-2. These calculations are based on the design assumptions incorporated in the other Appendices .describing the building and the Mechanical, Electrical
and Ventilation systems.
As shown in Table 4G-2, the plant is expected to meet the outdoors acoustical
design criteria presented in Table 4G-1. These criteria will assure a plant that
does not interfere with the quiet of the Clark University campus. Note in Table
4G-2 that the two most noisy sources are the diesel exhaust stack and the sircooled heat exchanger. However, three of the other sources listed are also significant.
With proper silencing, the plant ventilation openings are not signifi-
46 dBA
38
45
39
39
47
39
44
48
46
53 dBA
50 dBA
PLANT TOTAL
32
The interior acoustical design criteria presented in Table 4G-1 for Jonas Clark
Hall can be met without unusual construction techniques. This is due to the
massive construction of Jonas Clark Hall.
4G-4.
Curtain wall between the diesel room and the exterior of Jonas
(e) The diesel exhaust stack should be above the roof of Jonas Clark Hall
and be equipped with an i n - l i n e s i l e n c e r inside the plant providing at least
35 dB insertion loss at 125 Hz. The exhaust gases must also be passed through a
completely separate heat recovery b o i l e r before entering the exhaust s i l e n c e r .
The diesel engine must be turbocharged.
(f) The air-cooled heat exchanger must be located on the roof of Jonas Clark
Hall and must not emit noise in excess of 80 dBA as measured at any point within
3 f t . of the unit as delivered t o the s i t e . I t may be necessary to surround the
heat exchanger with a noise b a r r i e r .
-193-
APPENDIX 5A
P r o j e c t E f f o r t and C a p i t a l Cost A n a l y s i s
f o r Phases I I I - V I n c l u s i v e
-194-
Appendix 5A
Project Effort and Capital Cost Analysis for Phases III-V Inclusive
costs to Clark for the project and our proposal for DOE-funded demonstration
costs according to the terms of the original RFP. We have also made an estimate
of the costs to another comparable facility which might wish to duplicate the
Clark project, taking advantage of Clark's experience.
Starting with Phase III we will use a revised organizational structure for
the project, as shown in Fig. 5A-1. The revision will help in maintaining the
construction schedule and segregating demonstration activities. Task assignments
with levels of effort and estimated costs are presented in Table 5A-1.
Our projections for capital costs are summarized in Table 5A-2.
Details of the mechanical costs are given in Table 5A-3. As with the
labor costs, we distinguish between base costs to Clark and proposed demonstration costs to the Department of Energy.
There are
two reasons why we feel that fuel treatment should be, at least in part, a
demonstration cost.
First, the major portion of the capital cost for the fuel
Second, the costs of fuel treatment are much higher now than they will
be when there are more heavy oil diesel and gas turbine facilities. The economics of scale in fuel treatment facilities are illustrated in Fig. 5A-2, which
shows, for example, that the capital cost of a facility ten times as large as
Clark's is only about twice as much.
In Table 5A-4, we summarize labor and capital costs by phase, with Clark's
base costs and DOE demonstration costs.
We have estimated costs for duplicating the Clark project under the following assumptions:
Clark Trustees
Figure
5A-1
Program Administrator
Organizational Chart
Representative
R. Plutnicki
F. Puffer
Coordinating Committee
F. Puffer, L. Iandry, R.
Goble, C. Hohenemser, B.
Kimball, E. Fitzemeyer
Lo Landry
1
Environmental
Monitoring
Demonstration
Schwarz
Jiohenemser
Gottlieb
Goble
-Hohenemser
Clerk of
works
Thermo-electron, Inc.
3 Kimball
Eng^Lneerinf
engnm e
>
TECO
Engineering,
interfac i
Archi-
Fitaemey
.er &
Tocci
Bozen-hard
tect
Electrical
Shep- herd
Sub-contractors
.
-196Table 5A-1
Project Effort and Cost Analysis
Phase/Task
Work
done
by
Engine system
Distribution system
Electrical/non-grid
Architectural
TECO
Clark
TECO
F T
Shep.
Boz.
20.2
11.5
1.4
0.5
6.8
8.7
-
7.0
1.3
0.2
-
1.5
0.5
1.0
-
2. Engineering of monitoring'
system
A. Design specifications
B. Interface engine
C. Interface boilers
D. Air pollution
Clark
TECO
F T
TECO
1.1
0.5
0.2
0.2
0.2
0.3
TECO
2.0
0.7
4. Institutional problems
A. Legal issues
B. Code compliance
C. Air pollution
D. Financing
Clark
Clark
Clark
Clark
5. Grid connection
A. Electrical design
B. Electrical interface
Shep
NEES
0.1
0.1
0.1
2.0
0.5
0.5
0.5
0.5
1.2
1.0
0.2
0.5
0.5
Demonstration information
program
A. Draft summary of planning experience
.9
Clark
TECO
F T
Boz.
Shep.
0.2
0.4
0.1
0.1
0.1
Clark
TECO
1.5
1.0
0.5
-197-
Work
done
by
3.0
2.0
1.0
Clark
TECO
Clark
TECO
F T
11.5
7.0
1.3
Boz
1.4
6.8
0.5
All
20.2
8-5
Shep
NEES
ESTIMATED EFFORT COST
($1000s)
.2
Clark
$71.3 $28.7
TECO
F 5T
9.0
4.2
32.6
Boz.
2.4
.9
Shep.
NEES
115.3
33.8
All
1.0
0.8
-
1.8 .
$6.0
$3.3
-
9^3
1.0
0.2
4.3
$3.0
$14.9
1.3
-
4.8
0.6
24.6
0.5
5.2
1.9
0.1
0.1
0.1
1.5
IA.
0.9
0.1
-
$31.2
$3.7 $11.7
0.3
2.4
0.6
0.5
0.5
6.4
44.5
$75.5
$158.4
Totals
0.5
2.4
0.2
TECO
F T
Clark
2.2
T75
0.7
1.0
3.9
1.8
0.2
1.7
0.4
0.2
1.0
TECO
F T
Boz
Shep
TECO
F T
Clark
1.5
0.5
0.5
0.5
Shep
0.5
0.8
0.2
0.6
0.4
0.4
Work
done
by
5. Construction Reports
Clark
A. Reports of deliveries
B. Reports of installations
C. Daily construction log
6. Demonstration Information
Program
A. Educate local community
B. Prepare report on implications of final design
C. Final draft, planning
workbook
3.0
1.0
1.0
1.0
Clark
Clark
TECO
Clark
TECO
2.2
0.2
0.5
0.5
0.5
0.5
Clark
TECO
0.4
0.2
0.2
TECO
Clark
3.0
1.0
2.0,
Clark
TECO
F t, T
0.4
3.0
3.3
0.7
1.7
0.4
4.9
2.7
0.5
0.2
0.5
Shep
NEES
All
0.8
0.4
9.1
8.8
Clark
TECO
F5T
1.2
3.9
1.6
18.0
20.5
4.5
8.2
1.9
29.4
16.8
3.2
0.7
2.9
53.1
53.0
Shep
NEES
All
5.1
1.6
Boz
Totals
0.2
0.6
-
Boz
$59.8
$53.0
199
Phase/Task
by
TECO
F5T
Shep
TECO
Clark
0.4
0.2
0.6
0.5
0.2
0.2
0.2
0.1
0.2
0.4
3.0
0.5
1.0
0.5
1.0
2. Performance tests
A. Engine monitoring system TECO
Clark
B. Grid connection
Shep
C. Report to DOE
Clark
3. Demonstration information
program
A. Provide display facility
for demonstration site
visits
Clark
B. Prepare educational ma
terial on system
Clark
EFFORT TOTALS PHASE V:
Clark
TECO
F6T
Shep
All
ESTIMATED EFFORT COST
($1000s)
2.0
1.9
0.2
0.2
0.4
'
0.1
0.5
1.2
1.3
0.5
3.0
.1
0.2
5.4
0.2
0.5
6.6
Clark
TECO
F 5 T
Shep
All
TOTALS
3.0
1.2
1.0
2.2
.1^
$32.4
4.3
2.4
39.1
39.1
-200-
Sulzer Engine
895
287
Superior Engine
823
' '
287
60
223
60
223
1,465
1,393
41
41
Monitoring equipment
Demonstration civil costs
53
28
53
28
Fuel treatment
95
95
217
217
-201Table 5A -3
TOTAL MECHANICAL CAPITAL COST
Item
Sulzer 1405 kw
Residual Oil
Model ASL 25/30
Mechanical Costs
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
"26.
27.
28.
29.
30.
31.
32.
33.
34.
35.
36.
37.
$385,411
3,375
27,172
40,000
incl. base price
incl. base price
incl. base price
5,000
63,900
24,925
36,000
incl. base price
6,900
6,900
2,000
4,000
94,500
6,900
4,500
2,300
2,300
1,500
3,000
2,300
10,000
25,000
57,000
25,000
12,000
5,500
4,000
5,700
7,000
5,000
2,500
6,000
35,000
922,583
4-478
ELECTROSTATIC DESALTER
CAPITAL COST vt. CAPACITY
1ppm SODIUM)
100
ii
i i i im
COST OF CLARK'S
RESIDUAL FUEL
TREATMENT SYSTEM
o
a.
<
1.0
3000
11
10,000
Fig. 5A-2
1,000,000
100,000
kW
600
6000
-203-
Table 5A-4
Cost Summary ($1000s) for Phases I-V
Phase
I
II
III
IV
V
158.4
All
223.0
TOTALS
59.4
Capital
147.0
207.0
207
75.5
233.9
1242.0
$1465.0
Labor
TOTAL
1242.0
5.2
51.5
39.1
520-1
$737M
147
217.0
217.0
1569.9
44.3
2202.1
-204-
Starting
from Clark's base cost we add costs for engineering from Phases I and II, which
will be used directly in final design.
coming legal and institutional problems and the costs of the grid-connection.
We then subtract net costs for the special facing for the new building and for
structural modification to Jonas Clark Hall, to give our estimate for duplication
costs when there is no need for extensive fuel treatment.
about $40,000 more than the Clark base cost.
Table 5A-5
CLARK BASE COST & REPLICATION COST
$895 I
212
Special Civil
75
Electrical
(without grid connection)
60
223
Labor
$1,465
Replication Cost
Clark Base Cost
$1,465
DOE Contribution
Engineering
(from phases I&II)
Legal and Environmental
Grid Connection
48
41
-75
$1,494
$ 1,589
-205-
APPENDIX 5B
Operation and Maintenance Costs
-206-
APPENDIX 5B
Operation and Maintenance Costs
Operation and maintenance costs were estimated for the diesel engine,
generator, boiler and accessory equipment.
estimated by Thermo
Electron staff.
4000-6000 hours.
Their
lifting the engine covers, checking valves, and pulling the pistons should
be performed every 6000-8000 hours of operation.
checkups, including labor and replacement parts
etc.) when required, amounts to about $10-12/hp over the life of the engine.
Expected lifetime of engine components is given in Table 5B-1, with estimated
differences between distillate and residual oil use.
commended every
3-4,000
hours of operation.
They
Superior experience has been that the cost of the major overhauls
The
G.E. Krolls, Liquid Fuel Treatment Systems, General Electric Gas Turbine
Reference Library, GER-2484, 1973.
-207-
TABLE 5B-1
TV
i I' Tf.i. 4
26 4 70
SULZPR
07760032
2cks
(30,00048,000)
above 60000
24000-48000
Main bearings:
32000-64000
-208This prevents deposition on the valves and cylinder walls. The amount of additive
required depends on the content of the fuel and the amount that must be removed
prior to use in the engine, amounting to about 3.2 parts of magnesium per part
of vanadium (by weight) removed.
into the engine are listed in Table 5B-2. We see from this table that, according
to manufacturer's experience, the Sulzer engine can tolerate greater limits on
sodium and vanadium.
Table 5B-2, which shows that the cost of Tretolite KI-16 for the Superior engine
is slightly greater than for the Sulzer engine.
Table 5B-3 summarizes the operation and maintenance costs for both the
Sulzer and Superior engines based on the above discussion.
(See next
that the operation and maintenance costs are 5.6 mils/kwh for the Sulzer engine
and 5.5 mils/kwh for the Superior engine.
cost of about 4 mils/kwh for the distillate-fired 1531 kw Fairbanks Morse with
opposed piston described in the Phase I report.
Fouling of the heat recovery boiler for this plant was raised as a potential
problem during our preliminary presentation to DOE at Washington on April 17,
1978, by a representative of the Bureau of Standards. The Bureau of Standards
has monitored the performance of heat recovery from Caterpillar diesels at the
Summit Plaza, Jersey City, New Jersey, plant.
This is a HUD plant having five 675 kw Caterpillar diesel generators. They
are equipped with Vapor Phase Company waste heat hot water boilers.
Operators
have had to remove the five units approximately every two months for mechanical
cleaning of the fire side.
advised that typically the gas temperature from the heat recovery boilers rises
50-75
load and with the hot water temperature in the order of 180-230F.
We believe
(1) low
load (i.e. low gas velocity); (2) low exhaust temperature; (3) poorer combustion
at part load operation; and (4) relatively cold tube surface. None of these
hold for the proposed Clark ICES.
analysis.
-209TABLE 5B-2
MANUFACTURERS' RECOMMENDED LIMITS
FOR VANADIUM AND SODIUM GOING INTO ENGINE
Superior
30 PPM
Vanadium
Sodium
Sulzer
50 PPM
5 PPM
<l/3 Va content
50 PPM)
3.2 lb Mg
lb V
0-504 lb fuel
kwhr
100 lb tretolite
8 lb Mg
$5.00
gal tretolite
gal tretolite
9.25 lb tretolite
= $0.000382/kwhr
3.2 lb Mg
lb V
100 lb tretolite
8 lb Mg
6
gal tretolite
9~25 lb tretolite
$5.00
= $0.000672/kwhr
gal tretolite
210
TABLE 5B3
SUMMARY OF DIF.SEL FNCINE OPFRATION AND MATNTENANCF COSTS
Sulzer
Type 8 ASL 25/30
1368 kwe
Injector Inspection and Repl.icement
Annual Maintenance and Overhaul
(every 68000 hours)*
Periodic Maintenance/Inspect ion**
$ 1,300/yr
Sub Total
Sub Total x 1.25
Tretolite***
$ 1,300/yr
22,000
2,200
Oil
Superior
Model 40X16
1460 kwe
2,200
26,500
8,500
3,100
$34,000/yr
$33,100/yr
42,500/yr
4l,400/yr
3,800
7,100/yr
Total Engine
$4 6,300/yr
$48,500/yr
Total Engine/kwhr
$0.00470 kwhr
$.00462 /kwhr
Includes major overhaul and replacement of all parts over 20 year life of engine.
**Includes oil analysis, replace filters, check fuel pumps, valves, crankcase,
balance cylinder temperatures, etc.
***Based on vanadium content in oil of 85 PPM and treatment with tretolite (8% Mg)
at 3.2 parts Mg/partV and $5.00/gal tretolite.
-211-
TABLE 5B-4
SUMMARY OF SYSTEM OPERATION AND MAINTENANCE COSTS
Sulzer
Type 8 ASL 25/30
1368 kwe
Superior
Model 40-X-16
1460 kwe
$ 46,300/yr
$ 48,50Q/yr
Generator
2,000
2,000
Boilers
1,600
1,600
Pumps
1,500
1,500
2,000
2,000
Miscellaneous
2,000
2,000
Total System
$ 55,400/yr
$ 57,600/yr
Total System/kwhr
$0.00563/kwhr
$0.00549/kwhr
heat recovery steam generating units and have advised that these units are
cleaned generally once per year and never more than twice per year. They say
that they would only use Vapor Phase heat recovery units because of their
ease of cleaning (no finned tubes) and general high quality.
finned tube heat recovery equipment because of the likelihood of plugging and
difficulty, once"fouled, to clean.
We also talked with Cummins-Northeast about the Babson Institute diesel
waste heat recovery plant. This is a Vapor Phase Company waste heat recovery
hot water boiler. The full load gas temperature to the boiler is 875F. The
boiler has been selected so that at maximum hot water duty, the gas bypass
valve is still open, meaning that the boiler is somewhat oversized.
The boiler
operates as low as 40% of design capacity and as high as 80%. The hot water
temperature is maintained at 195-200 F.
twenty months and has not yet fouled sufficiently to require cleaning.
Since the Clark plant is expected to be a base-loaded unit, we would
expect that the availability of the Vapor Phase boiler will be at least as
high as the Witt-Armstrong units discussed above. We anticipate costs associated
with cleaning the fire side of the Clark boiler of no more than $1600/year.