Professional Documents
Culture Documents
Specification EXH-DG-1317
December 1989
Page 1 of 3
Chevron
Specification EXH-DG-1317
Source
Process Engineer
Process Engineer
Process Engineer
Section 2200
Local Surveys
Operating Representative
Other factors the manufacturers will follow up on to refine their designs, are:
Water quality
Plant life expectancy
Continuous or cyclical operation
Size or plot limit preference
How operating costs will be evaluated
Environmental restrictions
Page 2 of 3
December 1989
Chevron
Specification EXH-DG-1317
2.
3.
To these requirements, the purchase order should also require the manufacturer to supply the
appropriate data so that a CTI Acceptance Test under ATC-105 can be performed (and appropriate
equations to financially penalize the manufacturer, if the tower does not meet "design.")
December 1989
Page 3 of 3