Professional Documents
Culture Documents
SUBMITTED TO
BY
OCTOBER 2009
AGAINST
CLIMATE
CHANGE
2.0 ABSTRACT
This is a fifth progress report on implementation of the Fight against Climate Change-Choma/
Chigwere Biogas Project. It is the second report for the 2009/ 2010 financial year and covers
activities, which have been undertaken in implementing the project from July to October 2009.
The main activities carried out during this period were:
The funding of the project for the current financial year 2009/ 2010 was made in the month of
August 2009 and the sum amounted to MK5, 978,048.95.00.
The technical work is being undertaken by Mzuzu University staff and some hired labour.
Project supervision is carried out by Mzuzu University staff.
2
climate and enhanced food production, biogas plant operation and safety. Participants were
also conducted around the biogas plant and the kitchen units where demonstrations were
carried out to emphasis on various points.
3.5 Training
Mr Collen Zalengera attended a four week Environmental Management Course in July
2009. The course was organised by ESAMI and took place in Lilongwe, Malawi.
3.6 Identification of potential Sites for the Construction of Next Eight Biogas Plants
Members of the technical team held several consultative meetings with traditional leaders,
Dairy Farming Associations committee members, dairy farmers and prospective
beneficiaries of the project from within Choma, Doroba and Chigwere Areas. These are
some of the ongoing meetings being carried out during the implementation of this project.
The main objective of these particular meetings was to identify sites for the construction of
the next eight-biogas plants.
The first meeting was held on 7th October 2009 at Kawindula Bulking Centre (with the
people of Chigwere Area) and the second meeting was held on 28 th October 2009 at
Doroba Bulking Centre (with the people of Doroba Area). The last meeting is expected to
take place at Lukonkhowe Bulking Centre on the 4 th November 2009 (with the people of
Choma Area).
During the consultation processes, the communities identified potential beneficiaries after
the technical team briefed them with regards to the requirements of a potential site for a
biogas plant installation. During these two consultations a total of eleven (two from
Chigwere area and nine Doroba area) potential beneficiaries were identified. This number
is in addition to the people who expressed interest during the consultations last year.
The total number is therefore expected to be higher than last year. This is an indication
that interest in the project is increasing all the time.
household with six cows to collect the initial feed on their own. This would therefore risk
the uptake of the technology by the community once funding has come to an end.
The requirement of a herd of six cows to sustain the daily operation of a 3m 3 biogas
plant is risky. If the number of cows is less than six then there would not be enough
dung for normal operation of the plant.
There are problems amongst households in the community to adopt a communal
cooking systems and communal ownership of the biogas plants. Ideally each would
want to own their own plant.
Reduce the size of the biogas digesters to be constructed in the second phase from
3m3 to 1.5m3. A 1.5m3 would require less feedstock both for initial feeding and for daily
operation. It is envisaged that smaller plants would enhance uptake of the technology
after external funding has come to an end.
Each of the plants will be owned by individual households who will be responsible for
daily operation of the plant. This will enhance ownership of the plant thereby reducing
the risk of plant failure due to social problems in the communal set up.
Eight plants will be constructed (instead of four) in the second phase and six plants
(instead of three) in the third phase) each of capacity 1.5m 3 biogas. This change will
not have any effect on the number of beneficiaries and overall gas yield. The total
number of beneficiaries and the total gas yield will remain the same as projected in
the initial project plan. This will, however, ensure a wider coverage of the area than
the current set up.
9.0 CONCLUSIONS
Commissioning of plants 2, 3 and 5 will be done as soon as the plants are ready.
Construction work of the next eight plants in the Choma, Doroba and Chigwere areas will start
as soon as consultations with the communities are complete and the potential sites have been
identified.
10.0 APPENDICES
Appendices 1, 2, 3 and 4 attached.