Professional Documents
Culture Documents
MS- 06B
Rev. A
No
REV.A
Date
2014.3.4
Prepared
LiBO
Checked
Zhong Xiang
Approved
He peizhi
Remark
CONTENT
1.0 Purpose of Method Statement
2.0 Relevant documents and Standards
3.0 Responsibilities for activity Describe within this Method Statement
4.0 Detailed method of carrying out method statement activity
5.0 QA & QC measures
6.0 HSE Measures
Appendix 1 .RETAINING WALL FORMWORK
Appendix.2. Relevant Chinese material specification
Notes
b is the width, H denotes the height, 1:n denotes the slope gradient. The values of b, H and n are
indicated in the drawings of different construction sites.
If the height of the retaining wall is higher than 3.0m, protective railing will be provided.
The embedded depth of retaining wall in cutting areas will be not less than 1.2m, below the shoulder
or the berm of side the ditch and not less than 0.2m below base of the side ditch.
If the retaining wall is in the inclined ground the embedded depth is not less than 1.0m for soil and
weak rock, and the horizontal distance between toe to the embedded ground surface shall be 1.5m to
2.5m. For the hard rock embedment depth will be not less than 1m, the horizontal distance between
toe to the embedded ground surface shall be 0.6m 1.5m. If the gradient of the slope is greater than
5%, the base of the retaining wall will be stepped.
If the wall height is greater than 6m, C20 rubble concrete will be used for the construction. If the
wall height is less than 6m, M10 Cement mortar will be used.
0.1m dia. PVC pipe drain holes will be provided in wall arrange in 2m X 2m grid. The inner end of
PVC pipe is wrapped with geotextile. The first raw of drain holes will be 0.3m higher than ground or
shoulder level. 0.3m thick, filter gravel/sand layer will be constructed between embankment or slope
surface and inner surface of gravity retaining wall. 0.5m thick compacted impermeable clay layer
will be provided in at each ends of the filter layer, 0.5m below from the original ground level at the
bottom and 0.5m from top of the retaining wall.
At the sites where ground water development is high, the filter layer thickness will be increased to
0.5m. At the slopes where it is very hard to excavate (eg: hard weathered rock) or coarse-grained
sandy back fills or slopes the filter later will be omitted.
4.2 Materials
4.2.1 C 20 Rubble concrete
4.2.2 Ladder Rebar (see attached drawing)
4.2.3 100mm dia. gauge 600 or above PVC pipe for drain holes
4.2.4 Gravel and sand filter materials
4.3 Preparation
After the setting out for foundation, the excavation will be carried out until design level reached. The
dynamic cone penetration test, at least 1 per every 30m segment will be carried out to assess the
bearing capacity of in-situ soil. If the bearing capacity is not sufficient, additional excavation will be
carried out to sound bearing strata. The additional excavation depth will be back filled with
compacted rubble stone.
After excavation, the foundation pit will be continuously de water, so the bearing stratum will not
allow getting soaked.
The base trench will be excavated section by section or at different locations. Continuous excavation
of a long section that will influence the stability of Embankment slope is strictly forbidden. The
maximum length of wall section is 30m.
The sections will be separated using settlement joints. The length of section will be 10m or as
specified in working drawings. The base trench will be excavated to the required level and pass the
bearing capacity test prior to the base construction. Formwork will be installed as per the design
drawing. Concrete should be uniformly produced and transported to site by truck mixer.
The concrete will be delivered to site and discharge within one and half hours after addition of
cement to the aggregates. Each batch of concrete delivered will be accompanied with batch ticket
bearing complete batching information. The temperature of fresh concrete will be maintained less
than 32C. The addition of water after initial mixing will not allowed. The concrete that is not within
the specified consistency limits at the time of placement will not be used.
All mixed concrete will be placed and compacted in the formwork, using approved vibrators of the
internal, external, or screed types or combination of thereof depending on the type of Job.
After one layer of concrete 150-300mm rubble layer will be placed on top of paved concrete layer,
and cover with C20 concrete, compact adequately using poker vibrators until voids between rubbles
fully occupied with concrete. The maximum particle size of the rubble will be limit to 2/3 of the
width of the formwork, in any case the thickness of the retaining wall less than 400mm.
During continuous concrete pouring, fresh concrete will be poured on already laid concrete is less
than 30 minutes old and where this gap is exceeded further placing will be subjected to testing the
already placed concrete surface to be live. In the event of surface is not live, it shall be treated as a
construction joint and to be allowed to set.
All concrete will be placed in layers not more than 300mm. No concrete dropped from height greater
than about 1.5m except with a prior approval from the Engineer.
The freshly laid concrete will be kept undisturbed and protected from effects of sun and rain and
from drying out until it hardens. After hardened concrete will be cured for 7 days.
4..3 Backfilling
4.3.1 Backfilling of retaining wall base excavation
After construction of the base of retaining wall, the slopes of excavation pit will be trimmed or
prepared the gradients mentioned in the drawings. The materials for the backfilling will be soil
except peat and organic clay and free from timber and any other degradable materials. The
backfilling will be carried out in 150mm thick compacted layers using light compaction equipments.
The requirement for the compaction is to form a firm surface.
Construction Flow Chart for C20 rubble concrete Gravity retaining wall
Preparatio
n
Setting
Out
Base Trench
Excavation
Sub grade
Bearing
Capacity Test
Pass
Base Formwork
Fail
Analysis and
Solution
Settlement Joint
Construction
Base Rubble
Concreting
Base Pit
Backfilling
6. 0 HSE Measurements
6.1. Deep base pit with less stable slope should be excavated section by section or with intervals
between two sections. Moreover, temporary support structure should be strengthened
6.2. The location and height of the stockpiles of wasted soil after excavation should not influence the
stability of the base pit
6.3. The construction procedure should be arranged reasonably, and slope protection will be done to
prevent landslide or collapse;
6.4. Information about rainfall ought to be known timely to take protective measures preventing
newly constructed soil surface from being washed directly by raining.